Professional Documents
Culture Documents
Tunnel Engineering
Tunnel Engineering
The Underground passages which are constructed without removing or disturbing the
ground surface are known as Tunnels.
Necessity of Tunnels
1. When the surface route of railway tracks reaching the outside the hill is much longer and
costlier in construction than tunnel.
2. When the depth of open cut is more than 20m. It is costlier to construct and maintain than
a tunnel.
3. When the provision of a bridge across the river or sea is inconvenient.
4. When two terminal stations, separated by a mountain are to be connected by shortest
route.
5. When holding up of traffic for long periods is to be avoided.
6. When the route of railway track is to be protected from blockage.
7. When there is necessity of water for generating power.
8. When damage to transportation system is to be avoided and safety is to be provided
against aerial welfare.
2. Advantages of Tunnels
1. Tunnels are more economical than open cuts
2. Tunnels avoid disturbing the surface traffic during construction.
3. In case of aerial bombing tunnels provide protection.
4. They connect two terminal stations by shortest route.
5. They avoid acquisition of costly land.
6. Proves to be cheaper than bridges and open cuts.
3. Disadvantages of Tunnels
1. They may be costlier in construction than open cut.
2. They require more time for construction.
3. They require special equipments for construction.
4. They may cause suffocation if not ventilated.
Size of Tunnel: The size of the tunnel depends primarily on the purpose for which the
tunnel is to be used such as for carrying traffic, water, sewage etc.
2. The Size of Clear Opening Required: In case of a railway tunnel for single track a
clear space of at least 75 cm on each side should be allowed between the side of the
tunnel and side of the largest locomotive.
In such a tunnel minimum head clearance of 1 meter is allowed between the roof and the
top of the locomotive.
In case of a double line track the minimum centre to centre distance between both the
track should be 4.3 meters.
3. Thickness and allowance of lining: The thickness of lining varies with the material to
be penetrated in lining, an allowance of 5 to 7.5 cm for inward movement of side walls
without endangering the side walls should be given,
Similarly allowance for setting down of the tunnel roof must be given to 20 to 60 cm.
4. Drainage facilities required: The type of drainage system to be provided also affect
the size of the tunnel.
6. Construction of Shaft
7. Tunneling
The art of constructing a tunnel is known as tunneling.
Tunneling is done by a suitable method which depends on following factors:
1. Shape and size of tunnel
2. Type of ground
3. Equipment available
4. The extent of timbering required
5. The scheme of mucking
Tunneling in Soft Rocks
It is comparatively cheap.
In this case timbering is to be provided soon after excavation is started but supporting
the rocks requires complicated structure.
These temporary supports are then replaced by tunnel lining.
The sequence of operation is as follows:
1. Excavation
2. Timbering or shuttering
3. Removal of excavated material
4. Lining of tunnel.
Methods of Tunneling In Soft Rock
1. Needle Beam Method.
The needle beam consists of stout timber beam or Composite flinched beam which
forms the main support during excavation.
The length of the beam is usually 5 to 6m.
The construction procedure is as follows:
1. A monkey drift for a short distance of 1m is driven beyond the day work on working
face.
2. The roof of the drift is supported by lagging carried on wooden segments, which are in
turn supported by two trench jack sets in hitches cut in side of the monkey drift.
3. After this drift is completed the needle beam is slowly skidded forward into the
monkey drift.
4. The front end of the needle beam rests on the plank on the floor of the drift, while the
rear end is carried on stout post resting on the floor lining of tunnel.
5. A trench jack is now placed along the centre line of the needle beam, to support the
segments, thus transferring the load to needle beam.
6.The other trench jack are removed and the drift is widened sideways and supported as
before by laggings, and trench jack supported on sides of needle beam.
Advantages:
This method is economical.
Brick lining can be easily done by this method.
Disadvantages:
A large numbers of trench jacks are required which interfere with labour gang’s
efficient working.
The concrete lining with mechanical method is difficult.
Tunneling in Hard Rock
The sequence of operation followed in Tunneling in hard rocks is as follows:
1. Setting up and drilling
2. Loading holes and firing the explosives
3. Ventilation and removing dust of explosion
4. Mucking
5. Removing ground water if any
6. Timbering for sides and roofs if necessary
7. Grouting and Lining
The methods for tunneling in hard rocks are as follows:
1. Full Face Method
This method is so called because in this method the whole section of the tunnel is
attacked at the same time.
In this method drilling is done on the whole section and drilled holes are charged
with explosives.
After completing one round the tunnel drilling for the next round is started and
repeated until the entire tunnel is drilled.
Advantages:
The progress of work is fast as compared to other methods.
It facilitates laying and mucking progressively.
Disadvantages:
Heavy mechanical equipment are required to execute the work
This method is not suitable for unstable rocks.
Unexpected problem may crop in the water bearing strata.
This method involves driving the top portion in advance to the bottom portion.
If the rock is hard and self supporting the top driving advances ahead so that it
follows heading and benching method.
In case of broken rock the top heading will need support and bench will afford
platform for this.
Advantages:
In this method drilling and mucking are done simultaneously.
It requires less labour.
It requires less explosives.
Disadvantages:
Use of machinery for mucking becomes difficult.
Removal of muck from heading is difficult
3. Drift Method
Telescopic Forms
The main ribs are made up of sections hinged together so that a back unit could be
collapsed and moved under form units erected and in use without disturbing concreting.
This is suitable for tunnels of 20 to 25 ft diameter.
As the tunnel size increases the hinged section becomes too heavy to handle.
Placing of Concrete
For small tunnels (4-10 ft dia) hand placing is quite satisfactory.
The laggings are arranged waist high and sides are concreted first.
Gradually the concrete is lifted to the area under crown.
The gap in the crown section is concreted in the longitudinal direction or by Pressure
method.
For bigger jobs the modern practice is to place concrete by the help of pneumatic
concrete placers.
Compaction: It is done with the help of vibrators.
Curing: If the tunnel provides enough humidity there is no need for curing.
Otherwise perforated pipes are fixed to the roof of tunnel.
If water is not available the best method is to paint the concrete surface with bituminous
paint.
2. By Exhausting
In this method air is sucked by one or two exhaust fans.
This creates vaccum due to which fresh air enters inside the tunnel.
It is also known as vaccum method.
In this method a central drain is provided between the two railway tracks or road
pavement.
It should handle the maximum flow of water.
It should be well designed to facilitate inspection and cleaning.
For this man holes should be provided at 30 to 50 m along the drain.
It is used when a huge quantity of water does not come through roofs and side of
tunnel.
In this method a continuous corrugated shed is provided along with side drains.
The iron shed is so placed that it facilitates shedding of water leaking through the roofs or
sides of the tunnels into the tunnel without dropping on communication route.
It is used when huge quantity of water falls through roof and side of tunnel.
Heavy expenditure is involved since iron sheds are subjected to corrosion.
3. Side Drains