Quiz 4 CMPM 1 PDF
Quiz 4 CMPM 1 PDF
Instructions
Please choose the BEST answer. You only have 90 minutes to finish this quiz.
You need to get at least 50% (50 points) correct answers on this Quiz to have a passing grade.
“I affirm that I shall not give or receive any unauthorized help on this exam and that all work shall be my
own.”
Attempt History
Attempt Time Score
LATEST Attempt 1 42 minutes 100 out of 100
Question 1 3 / 3 pts
The predecessor activity must finish before the successor activity can
finish.
Start to Finish
Finish to Finish
Finish to Start
Start to Start
Question 2 3 / 3 pts
PDM - AON
GERT
None of these
Question 3 3 / 3 pts
CPM
None of these
PERT
GERT
Question 4 3 / 3 pts
Outlines a project and the logical order in which different activities must
be completed. It provides a clear sequence of events for the efficient
completion of a project.
CPM
PERT
Question 5 3 / 3 pts
None of these
Leads
Delay
Lag
Question 6 3 / 3 pts
None of these
PDM - AON
Question 7 3 / 3 pts
The predecessor activity must start before the successor activity can start.
Start to Start
Start to Finish
Finish to Finish
Finish to Start
Question 8 3 / 3 pts
A method that determines the longest path through the network diagram.
CPM
None of these
CMPM
PERT
Question 9 3 / 3 pts
Pessimistic Estimate
Optimistic Estimate
None of these
Question 10 3 / 3 pts
Pessimistic Estimate
None of these
Optimistic Estimate
Question 11 3 / 3 pts
The cost/duration of the activity, based on a realistic effort assessment for
the required work and any predicted expenses.
Optimistic Estimate
None of these
Pessimistic Estimate
Question 12 3 / 3 pts
Float
Duration
None of these
Activity
Question 13 3 / 3 pts
Lag
Delay
None of these
Leads
Question 14 3 / 3 pts
The predecessor activity must start before the successor activity can
finish.
Finish to Start
Start to Finish
Finish to Finish
Start to Start
Question 15 3 / 3 pts
The predecessor activity must finish before the successor activity can
start.
Finish to Finish
Finish to Start
Start to Start
Start to Finish
Question 16 5 / 5 pts
Determine the no. of slack of Activity C, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed
3 days
0 day
7 days
None of these
Question 17 5 / 5 pts
Determine the no. of slack of Activity A, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed
0 day
None of these
5 days
7 days
Question 18 5 / 5 pts
Determine the no. of slack of Activity G, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed
5 days
0 day
None of these
7 days
Question 19 5 / 5 pts
Given the following the precedence diagram table, determine the critical
path.
X-B-E-F-J-K-M
None of these
X-D-L-K-M
X-C-G-L-K-M
Question 20 5 / 5 pts
Given the following the precedence diagram table, by using Critical Path
Method, determine the duration of the project that is must be completed.
58 days
68 days
None of these
56 days
Question 21 5 / 5 pts
Using Critical Path Method, determine the duration of the project that is
must be completed.
22 days
24 days
17 days
None of these
Question 22 5 / 5 pts
Given the following the precedence diagram table, determine the no. of
slack of Activity B, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed
0 day
25 days
23 days
2 days
Question 23 5 / 5 pts
Given the following the precedence diagram table, determine the no. of
slack of Activity D, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed
0 day
8 days
10 days
13 days
Question 24 5 / 5 pts
Given the following the precedence diagram table, determine the no. of
slack of Activity G, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed
13 days
2 days
7 days
0 days
Question 25 5 / 5 pts
Determine the no. of slack of Activity D, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed.
3 days
8 days
10 days
0 day
Question 26 5 / 5 pts
Find the Critical Path on the given activity network diagram below.
1-2-4-9-10
1-3-4-9-10
1-3-5-6-8-10
None of these
Quiz #4
Due Dec 20 at 11:59pm Points 100 Questions 26
Available Dec 18 at 12am - Dec 20 at 11:59pm 3 days Time Limit 90 Minutes
Instructions
Please choose the BEST answer. You only have 90 minutes to finish this quiz.
You need to get at least 50% (50 points) correct answers on this Quiz to have a passing grade.
“I affirm that I shall not give or receive any unauthorized help on this exam and that all work shall be my
own.”
Attempt History
Attempt Time Score
LATEST Attempt 1 42 minutes 100 out of 100
Question 1 3 / 3 pts
The predecessor activity must finish before the successor activity can
finish.
Start to Start
Finish to Finish
https://tip.instructure.com/courses/27221/quizzes/334845 1/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
Start to Finish
Finish to Start
Question 2 3 / 3 pts
The predecessor activity must start before the successor activity can start.
Finish to Start
Start to Finish
Finish to Finish
Start to Start
Question 3 3 / 3 pts
Lag
Leads
None of these
Delay
Question 4 3 / 3 pts
https://tip.instructure.com/courses/27221/quizzes/334845 2/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
The predecessor activity must finish before the successor activity can
start.
Start to Start
Start to Finish
Finish to Finish
Finish to Start
Question 5 3 / 3 pts
PDM - AON
None of these
GERT
Question 6 3 / 3 pts
Float
Activity
https://tip.instructure.com/courses/27221/quizzes/334845 3/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
Duration
None of these
Question 7 3 / 3 pts
PDM - AON
GERT
None of these
Question 8 3 / 3 pts
PERT
GERT
CPM
None of these
https://tip.instructure.com/courses/27221/quizzes/334845 4/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
Question 9 3 / 3 pts
The predecessor activity must start before the successor activity can
finish.
Start to Finish
Finish to Finish
Start to Start
Finish to Start
Question 10 3 / 3 pts
None of these
Optimistic Estimate
Pessimistic Estimate
Question 11 3 / 3 pts
Outlines a project and the logical order in which different activities must
be completed. It provides a clear sequence of events for the efficient
https://tip.instructure.com/courses/27221/quizzes/334845 5/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
completion of a project.
PERT
CPM
Question 12 3 / 3 pts
Optimistic Estimate
None of these
Pessimistic Estimate
Question 13 3 / 3 pts
A method that determines the longest path through the network diagram.
CPM
CMPM
PERT
https://tip.instructure.com/courses/27221/quizzes/334845 6/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
None of these
Question 14 3 / 3 pts
PDM - AON
None of these
GERT
Question 15 3 / 3 pts
Leads
None of these
Delay
Lag
Question 16 5 / 5 pts
https://tip.instructure.com/courses/27221/quizzes/334845 7/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
Given the following the precedence diagram table, by using Critical Path
Method, determine the duration of the project that is must be completed.
68 days
None of these
56 days
58 days
Question 17 5 / 5 pts
Given the following the precedence diagram table, determine the no. of
slack of Activity G, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed
https://tip.instructure.com/courses/27221/quizzes/334845 8/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
13 days
0 days
7 days
2 days
Question 18 5 / 5 pts
Given the following the precedence diagram table, determine the no. of
slack of Activity D, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed
https://tip.instructure.com/courses/27221/quizzes/334845 9/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
8 days
0 day
13 days
10 days
Question 19 5 / 5 pts
Determine the no. of slack of Activity G, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed
https://tip.instructure.com/courses/27221/quizzes/334845 10/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
7 days
0 day
None of these
5 days
Question 20 5 / 5 pts
https://tip.instructure.com/courses/27221/quizzes/334845 11/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
Find the Critical Path on the given activity network diagram below.
1-2-4-9-10
None of these
1-3-5-6-8-10
1-3-4-9-10
Question 21 5 / 5 pts
https://tip.instructure.com/courses/27221/quizzes/334845 12/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
Given the following the precedence diagram table, determine the no. of
slack of Activity B, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed
0 day
2 days
25 days
23 days
Question 22 5 / 5 pts
Determine the no. of slack of Activity D, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed.
https://tip.instructure.com/courses/27221/quizzes/334845 13/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
8 days
10 days
3 days
0 day
Question 23 5 / 5 pts
https://tip.instructure.com/courses/27221/quizzes/334845 14/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
Determine the no. of slack of Activity H, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed
7 days
0 day
3 days
None of these
https://tip.instructure.com/courses/27221/quizzes/334845 15/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
Question 24 5 / 5 pts
Determine the no. of slack of Activity A, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed
0 day
None of these
7 days
5 days
https://tip.instructure.com/courses/27221/quizzes/334845 16/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
Question 25 5 / 5 pts
Using Critical Path Method, determine the duration of the project that is
must be completed.
24 days
17 days
22 days
https://tip.instructure.com/courses/27221/quizzes/334845 17/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
None of these
Question 26 5 / 5 pts
Determine the no. of slack of Activity C, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed
None of these
3 days
https://tip.instructure.com/courses/27221/quizzes/334845 18/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management
7 days
0 day