Quiz #4

Due Dec 20 at 11:59pm Points 100 Questions 26


Available Dec 18 at 12am - Dec 20 at 11:59pm 3 days Time Limit 90 Minutes

Instructions
Please choose the BEST answer. You only have 90 minutes to finish this quiz.

You need to get at least 50% (50 points) correct answers on this Quiz to have a passing grade.

Reminder: Honor Pledge for Exams

“I affirm that I shall not give or receive any unauthorized help on this exam and that all work shall be my
own.”

Attempt History
Attempt Time Score
LATEST Attempt 1 42 minutes 100 out of 100

 Correct answers will be available on Dec 21 at 12am.

Score for this quiz: 100 out of 100


Submitted Dec 18 at 4:12pm
This attempt took 42 minutes.

Question 1 3 / 3 pts

The predecessor activity must finish before the successor activity can
finish.

Start to Finish

Finish to Finish
Finish to Start

Start to Start

Question 2 3 / 3 pts

A network diagram method of drawing wherein circles are used to show


dependencies, and arrows represent activity.

PDM - AON

GERT

None of these

Arrow Diagramming Method

Question 3 3 / 3 pts

A three point activity estimating technique that considers estimation


uncertainty and risk by using three estimates to define an approximate
probability for an activity’s cost or duration.

CPM

None of these

PERT

GERT
Question 4 3 / 3 pts

Outlines a project and the logical order in which different activities must
be completed. It provides a clear sequence of events for the efficient
completion of a project.

None of the above

Project Schedule Network Diagram

CPM

PERT

Question 5 3 / 3 pts

Inserted waiting time between activities.

None of these

Leads

Delay

Lag

Question 6 3 / 3 pts

A network diagram method of drawing wherein boxes are used to


represent activities, and arrows show activity dependence.
GERT

None of these

PDM - AON

Arrow Diagramming Method

Question 7 3 / 3 pts

The predecessor activity must start before the successor activity can start.

Start to Start

Start to Finish

Finish to Finish

Finish to Start

Question 8 3 / 3 pts

A method that determines the longest path through the network diagram.

CPM

None of these

CMPM

PERT
Question 9 3 / 3 pts

The activity cost/duration based on an analysis of the best-case scenario


for the activity.

Pessimistic Estimate

Optimistic Estimate

None of these

Most Likely Estimate

Question 10 3 / 3 pts

The activity cost/duration based on an analysis of the worst-case scenario


for the activity.

Pessimistic Estimate

Most Likely Estimate

None of these

Optimistic Estimate

Question 11 3 / 3 pts
The cost/duration of the activity, based on a realistic effort assessment for
the required work and any predicted expenses.

Optimistic Estimate

None of these

Pessimistic Estimate

Most Likely Estimate

Question 12 3 / 3 pts

The amount of time by which the start of an activity may be delayed


without affecting the overall completion of the project.

Float

Duration

None of these

Activity

Question 13 3 / 3 pts

An overlap between activities that have a dependency.

Lag
Delay

None of these

Leads

Question 14 3 / 3 pts

The predecessor activity must start before the successor activity can
finish.

Finish to Start

Start to Finish

Finish to Finish

Start to Start

Question 15 3 / 3 pts

The predecessor activity must finish before the successor activity can
start.

Finish to Finish

Finish to Start

Start to Start

Start to Finish
Question 16 5 / 5 pts

Determine the no. of slack of Activity C, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed

3 days

0 day

7 days

None of these
Question 17 5 / 5 pts

Determine the no. of slack of Activity A, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed

0 day

None of these

5 days

7 days
Question 18 5 / 5 pts

Determine the no. of slack of Activity G, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed

5 days

0 day

None of these

7 days

Question 19 5 / 5 pts
Given the following the precedence diagram table, determine the critical
path.

X-B-E-F-J-K-M

None of these

X-D-L-K-M

X-C-G-L-K-M

Question 20 5 / 5 pts

Given the following the precedence diagram table, by using Critical Path
Method, determine the duration of the project that is must be completed.
58 days

68 days

None of these

56 days

Question 21 5 / 5 pts

Using Critical Path Method, determine the duration of the project that is
must be completed.
22 days

24 days

17 days

None of these

Question 22 5 / 5 pts

Given the following the precedence diagram table, determine the no. of
slack of Activity B, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed
0 day

25 days

23 days

2 days

Question 23 5 / 5 pts

Given the following the precedence diagram table, determine the no. of
slack of Activity D, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed
0 day

8 days

10 days

13 days

Question 24 5 / 5 pts

Given the following the precedence diagram table, determine the no. of
slack of Activity G, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed
13 days

2 days

7 days

0 days

Question 25 5 / 5 pts

Determine the no. of slack of Activity D, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed.
3 days

8 days

10 days

0 day

Question 26 5 / 5 pts
Find the Critical Path on the given activity network diagram below.

1-2-4-9-10

1-3-4-9-10

1-3-5-6-8-10

None of these

Quiz Score: 100 out of 100


12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Quiz #4
Due Dec 20 at 11:59pm Points 100 Questions 26
Available Dec 18 at 12am - Dec 20 at 11:59pm 3 days Time Limit 90 Minutes

Instructions
Please choose the BEST answer. You only have 90 minutes to finish this quiz.

You need to get at least 50% (50 points) correct answers on this Quiz to have a passing grade.

Reminder: Honor Pledge for Exams

“I affirm that I shall not give or receive any unauthorized help on this exam and that all work shall be my
own.”

Attempt History
Attempt Time Score
LATEST Attempt 1 42 minutes 100 out of 100

 Correct answers will be available on Dec 21 at 12am.

Score for this quiz: 100 out of 100


Submitted Dec 18 at 3:28pm
This attempt took 42 minutes.

Question 1 3 / 3 pts

The predecessor activity must finish before the successor activity can
finish.

Start to Start

Finish to Finish

https://tip.instructure.com/courses/27221/quizzes/334845 1/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Start to Finish

Finish to Start

Question 2 3 / 3 pts

The predecessor activity must start before the successor activity can start.

Finish to Start

Start to Finish

Finish to Finish

Start to Start

Question 3 3 / 3 pts

Inserted waiting time between activities.

Lag

Leads

None of these

Delay

Question 4 3 / 3 pts

https://tip.instructure.com/courses/27221/quizzes/334845 2/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

The predecessor activity must finish before the successor activity can
start.

Start to Start

Start to Finish

Finish to Finish

Finish to Start

Question 5 3 / 3 pts

A network diagram method of drawing wherein boxes are used to


represent activities, and arrows show activity dependence.

PDM - AON

None of these

GERT

Arrow Diagramming Method

Question 6 3 / 3 pts

The amount of time by which the start of an activity may be delayed


without affecting the overall completion of the project.

Float

Activity

https://tip.instructure.com/courses/27221/quizzes/334845 3/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Duration

None of these

Question 7 3 / 3 pts

A network diagram method of drawing wherein circles are used to show


dependencies, and arrows represent activity.

Arrow Diagramming Method

PDM - AON

GERT

None of these

Question 8 3 / 3 pts

A three point activity estimating technique that considers estimation


uncertainty and risk by using three estimates to define an approximate
probability for an activity’s cost or duration.

PERT

GERT

CPM

None of these

https://tip.instructure.com/courses/27221/quizzes/334845 4/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Question 9 3 / 3 pts

The predecessor activity must start before the successor activity can
finish.

Start to Finish

Finish to Finish

Start to Start

Finish to Start

Question 10 3 / 3 pts

The cost/duration of the activity, based on a realistic effort assessment for


the required work and any predicted expenses.

Most Likely Estimate

None of these

Optimistic Estimate

Pessimistic Estimate

Question 11 3 / 3 pts

Outlines a project and the logical order in which different activities must
be completed. It provides a clear sequence of events for the efficient

https://tip.instructure.com/courses/27221/quizzes/334845 5/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

completion of a project.

None of the above

Project Schedule Network Diagram

PERT

CPM

Question 12 3 / 3 pts

The activity cost/duration based on an analysis of the worst-case scenario


for the activity.

Optimistic Estimate

None of these

Most Likely Estimate

Pessimistic Estimate

Question 13 3 / 3 pts

A method that determines the longest path through the network diagram.

CPM

CMPM

PERT

https://tip.instructure.com/courses/27221/quizzes/334845 6/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

None of these

Question 14 3 / 3 pts

A computer simulation that allows loops between activities.

PDM - AON

None of these

Arrow Diagramming Method

GERT

Question 15 3 / 3 pts

An overlap between activities that have a dependency.

Leads

None of these

Delay

Lag

Question 16 5 / 5 pts

https://tip.instructure.com/courses/27221/quizzes/334845 7/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Given the following the precedence diagram table, by using Critical Path
Method, determine the duration of the project that is must be completed.

68 days

None of these

56 days

58 days

Question 17 5 / 5 pts

Given the following the precedence diagram table, determine the no. of
slack of Activity G, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed

https://tip.instructure.com/courses/27221/quizzes/334845 8/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

13 days

0 days

7 days

2 days

Question 18 5 / 5 pts

Given the following the precedence diagram table, determine the no. of
slack of Activity D, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed

https://tip.instructure.com/courses/27221/quizzes/334845 9/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

8 days

0 day

13 days

10 days

Question 19 5 / 5 pts

Determine the no. of slack of Activity G, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed

https://tip.instructure.com/courses/27221/quizzes/334845 10/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

7 days

0 day

None of these

5 days

Question 20 5 / 5 pts

https://tip.instructure.com/courses/27221/quizzes/334845 11/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Find the Critical Path on the given activity network diagram below.

1-2-4-9-10

None of these

1-3-5-6-8-10

1-3-4-9-10

Question 21 5 / 5 pts

https://tip.instructure.com/courses/27221/quizzes/334845 12/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Given the following the precedence diagram table, determine the no. of
slack of Activity B, if the duration of the project will be determined by its
Critical Path, and no other activities on its path will be delayed

0 day

2 days

25 days

23 days

Question 22 5 / 5 pts

Determine the no. of slack of Activity D, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed.

https://tip.instructure.com/courses/27221/quizzes/334845 13/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

8 days

10 days

3 days

0 day

Question 23 5 / 5 pts

https://tip.instructure.com/courses/27221/quizzes/334845 14/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Determine the no. of slack of Activity H, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed

7 days

0 day

3 days

None of these

https://tip.instructure.com/courses/27221/quizzes/334845 15/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Question 24 5 / 5 pts

Determine the no. of slack of Activity A, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed

0 day

None of these

7 days

5 days

https://tip.instructure.com/courses/27221/quizzes/334845 16/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

Question 25 5 / 5 pts

Using Critical Path Method, determine the duration of the project that is
must be completed.

24 days

17 days

22 days

https://tip.instructure.com/courses/27221/quizzes/334845 17/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

None of these

Question 26 5 / 5 pts

Determine the no. of slack of Activity C, if the duration of the project will
be determined by its Critical Path, and no other activities on its path will
be delayed

None of these

3 days

https://tip.instructure.com/courses/27221/quizzes/334845 18/19
12/18/21, 3:28 PM Quiz #4: CE 434-CE31S5 - Construction Methods and Project Management

7 days

0 day

Quiz Score: 100 out of 100