Departmental labour (Amani labour)

[1] Sunita devi labour contractor civil work curring material shifting Housekeeping tower s2 s3 s4 non Tower T4 .68

[2] Kanhaiya labour contractor material shifting non Tower .7


[3] Munir alam chiper cont S3 .3
Total=78

Peti contractor solitarrian city


[1] Imran shuttering non tower T4 .0
[2] Ranjeet shuttering non tower villa. 8
[3] Arun Kumar folding 5
[4]Azahar pop s5 T1 .14
[5] Taushif Ansari plaster s5. 12
[6] M.d. shakil plaster t1.24
[7]Ashraf steel. Non Tower T4 .24
[8] Pankaj elect. T1 S5 S2.11
9[9] Hitesh fabricator. 01
[10] faith tech infra painter panter.S2 S3.T1.basment .32
[11] Sanjana construction brick wor k Tower S5 T1 .8
[12] Pinku KumarTower S5 B/W . 10
[13] Sharfuddin carpenter s2 .04
[14] Sher Singh tile S2.4
[15] Pramod Tile S3 S4.18
[16] Kamna Railing S5.T1.5
[17] Vishnu pipe line .4
[18] Sonu Kumar chaukhat . T1.0
[19] Neetu Kumari Stone work S3.T 1.06
[20] Juhi Kumari water Proof Tower S4.N.T .05
[21]. Craitive glass. U.P.V.C.S2.02
[22] Rohit Yadav core cutting T1.2
[23] raj Kumar fire S3 .04
[24] Chandrasila waterproof NT .S2.05
(25) Anamika parvat Tower S5 plumber work.
(26) Ram Tomar remix basement Steel binding .03
Total .209

Grand total manpower at site (287)


s3 s4 non Tower T4 .68