Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

Document Title METHOD STATEMENT FOR INSTALLATION Date 21/May/23


TESTING & COMMISSIONING FOR FOAM SYSTEM
Document No. LPS-01-HTI-MST-ME-032 Rev. No. 0

Method Statement for Installation, Testing


& Commissioning of Foam System

Project : 2B+G+6 La Plage South-1 Residential Buildings

Employer : Ali Hamad K Al Thani

Project Design & Construction: Qatar Design Consortium

Supervision Service Consultant: Neo Spectrum

Main Contractor : HBK Contracting Company W.L.L.

Revision History

LPS-01-HTI-MST-032 0 21/MAY/23 Issued for Review and


Approval

Prep. By Rev by Approved by


Doc. no. Purpose of Proj. QA QC Project Manager
Rev. no. Date
submission Manager
CONTENTS

1. PURPOSE .......................................................................................................................... 3
2. SCOPE ............................................................................................................................... 3
3. REFERENCES ................................................................................................................... 3
4. ABBREVIATIONS .............................................................................................................. 3
5. RESOURCES ..................................................................................................................... 3
6. RESPONSIBILITIES .......................................................................................................... 4
7. SEQUENCE OF ACTIVITIES ............................................................................................. 5
8. QUALITY .......................................................................................................................... 18
9 HSE ISSUES, RISK ASSESSMENT AND HAZARD ANALYSIS .................................... 19
10 ATTACHMENTS .............................................................................................................. 19
1. PURPOSE

 The Purpose of this Method Statement is to establish the necessary guidelines for the
Deluge Foam Fire Suppression System installation, testing, and commissioning in
accordance with the contract requirements.
 This Method Statement will also ensure that the materials are installed safely.

2. SCOPE

This method statement is for the Deluge Foam Fire Suppression System Installation,
Testing, and Commissioning for 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS project

3. REFERENCES

 Project Specification.
 Qatar Construction Specification and QCDD
 NFPA 16 & 25 Standard
 Approved System Design Calculations
 Approved Material Submittal for Deluge Foam Fire Suppression System
 Approved Deluge Foam Fire Suppression System Plan Layout and Shop Drawing

4. ABBREVIATIONS

QCS - Qatar Construction Specifications


HSE - Health, Safety and Environment
QA/ QC - Quality Assurance and Quality Control
ITP - Inspection and Test Plan
ERP - Emergency Response Plan
WIR - Work Inspection Request
MIR - Material Inspection Request
QCDD - Qatar Civil Defense Department

5. RESOURCES

5.1 Equipment

5.1.1 Testing Tools / Equipment


a. Socket Wrenches Set & adjustable wrenches
b. Chain Block / Rope Pulley
c. Lever Bar
d. Hammer
e. Combination Wrenches
f. Threading and Grooving Machine
g. Pipe cutter
h. Hole saw cutter
i. Portable Grinder
j. Calibrated Pressure Gauge
k. Electric Drill and Impact drill
l. Measuring Tape
m. Marker Pen
n. Screw Drivers
o. Test Pump

5.1.2 Standard Safety PPE for all the Labours

a. Helmet / Hard Hat


b. Safety Shoes
c. Gloves
d. Safety Harness
e. Other PPE’s depending on the scope of work

5.2 Manpower

 Project Manager
 Project Engineer
 HSE Officer
 Foreman

5.3 Material

All materials and equipment of the Foam Fire Suppression System shall be in
accordance with the approved material submittal.

6. RESPONSIBILITIES
6.1 Project Manager

In overall, the Project manager will be responsible in project execution and ensuring
quality and safety in all the activities. Also, maintaining the planning progress and
coordination of works with the main contractor.

6.2 Project Engineer

Project Engineer is responsible for ensuring the project is fit for the purpose and
adheres to the project budget and schedule. Ensuring all relevant safety objectives
and legal requirements are observed and accounting for engineering tasks to ensure
they meet the contract requirements. project Engineer will develop project specific
procedures for the work to be carried out. Interpreting client’s requirements,
identifying and addressing design parameters and engineering problems and
ensuring solutions are implemented. Ensuring all justifications for contractual
variations during project is maintained to support subsequent commercial claim.
Evaluating, organizing and prioritizing work within the overall project schedule.
Project Engineer will be directly reporting to project manager.
6.3 HSE Officer

HSE Officer is responsible for the overall Health and Safety aspects on site as per
managing contractor requirements.

6.4 Foreman

Foreman is responsible to assist the project engineer in implementing the installation as


per approved drawing and monitor all the project execution and installation works.
Attend inspection, testing and commissioning work together with Engineer.

7. SEQUENCE OF ACTIVITIES

7.1 Pre-Installation Requirements

a. The main contractor has given permission to begin installation.

b. Check the project documents like materials submittal, Method of statement, ITP,
Shop drawings, Calculation, etc. are approved by the Engineer / Consultant.

c. All installation materials are available and have been inspected and approved by
the Engineer/consultant.

d. All preceding trades have finished their works.

e. Check and confirm that the plinths were cast in accordance with the approved
construction drawings.

f. Scaffolding required for installations is correctly built, safe, and appropriate for the
purpose.

g. The location has temporary lighting and a power source, and the protection settings
are correct.

h. Installation details and manufacturer recommendations, if any, should be available


on-site.

i. Inspect all materials to ensure they are not damaged.

j. Check to see if pipe sleeves are installed or if a pipe sleeve is intact or inserted in
the Deluge Foam Fire Suppression Pipe where a wall is expected to cross.

7.2 Fabrication of pipe

7.2.1 Threading (50mmØ & below shall be threaded type)

 Ensure that the cutter, reamer, and die head are all swung to the UP position.

 If the pipe is being cut to length, make it the desired length.


 Insert the pipe into the machine and cut it with a cutter. Clear the edge with a
reamer.

 Place the die head on the position.

 Turn the carriage hand wheel to bring dies against the end of a pipe. Continue
applying pressure to the hand wheel to start dies.

 When the desired thread length is reached, depress the release handle to
discharge the latch, and the Die head will open automatically.

 Release the footswitch and turn the carriage hand wheel clockwise to back
the die head off.

 Swing dies head to the UP position.

 After threading, provide jute for elbow and pipe assembly.

7.2.2 Grooving (65mmØ & above shall be grooved type)

 Lift the pipe with your hands or other equipment, such as a pulley block or
chain block, and place it on one side of the stand, inserting it between the
grooving upper and lower rollers.

 Adjust the rollers to hold the pipe.

 Start the Grooving Machine.

 Apply the hydraulic pressure to the grooved wheel until it reaches the
specified depth.

 Stop the machine and remove the pipe.


 Check the grooved width and finish.

 If found OK, send for installation.

7.2.3 Mechanical Grooved Coupling Installation

 Pipe Preparation
 Check pipe end for proper groove dimensions and assure that pipe end is
free of indentations and projections that would prevent correct sealing.

 Lubricate Gasket
 Check the gasket to be sure it’s compatible with the intended service
 Apply thin lubricant to the outside and seal the lips of the gasket.

 Gasket Installation
 Slip the gasket over one pipe, and make sure the gasket lip does not
overhang the pipe end.
 Alignment
 After aligning two pipe ends, pull the gasket into position, centering
between the grooves on each pipe.

 The gasket should not extend into the groove on either pipe.

 Housing Installation
 Remove one bolt & nut and loosen the other nut. Place one housing over the
gasket, and make sure the housing keys fit into the pipe grooves.

 Swing the other housing over the gasket and into the grooves on both pipes.

 Re-insert the bolt and connect the two housings.

 Tighten Nuts
 Firstly, hand tighten nuts and ensure that the bolts are completely fit into the
bolt hole.

 Then securely tighten the nuts alternatively and equally to the specified bolt
torque using a spanner.

 Assembly Completed - Rigid Coupling


 For Rigid Coupling, keep the gaps at the bolt pads evenly spaced. And the
gaskets must not be seen visually.

 Assembly Completed - Flexible Coupling


 For Flexible Coupling, two housings shall be connected iron-to-iron. And the
gaskets must not be seen visually.

CAUTION:
 Proper torque of the bolts is required to obtain specified performance.

 Overtightening the bolts may cause damage to the bolt and/or casting,
resulting in pipe joint separation.

Warning: Do not make adjustment to grooved products while the piping system
is under pressure

7.2.4 Threaded & Grooved Mechanical Tee Installation

 Pipe Preparation
 The preparation of the pipe is the first step in the installation process. Pipe
preparation is essential for sealing and performance.

 During the outlet hole cutting process, the pipe must be supported. Make
a mark on the pipe at the location of the specified outlet hole.
 Check to ensure that the proper hole saw is being used to cut the proper
sized outlet hole at the specified location on the pipe.

 The outlet hole must be drilled in the center and perpendicular to the pipe's
centerline. Improperly cut outlet holes may prevent the locating collar from
being fully inserted and the product from sealing on the pipe surface.
 Remove any burrs and sharp edges from the outlet hole. Leftover burrs or
sharp edges could affect the engagement of the locating collar, flow from
the outlet, or sealing of the gasket.

 Verify that the pipe surface within 5/8 inch / 16mm of the outlet hole is
clean, smooth, and generally free from indentations and/or projections that
could affect gasket sealing.

 Don’t drill the hole on weld line.

 Gasket Installation
 Insert the gasket into the outlet housing and ensure the tab in the gasket
line up with the tab recesses in the housing.

 Align outlet housing over the pipe hole and ensure that the locating collar
is in the pipe hole.

 Alignment
 Align the strap around the pipe, insert the bolts and tighten the nuts finger
tight.

 Tighten Nuts
 Firstly, hand tighten nuts and ensure that the bolts are completely fit into
the bolt hole.

 Then securely tighten the nuts alternatively and equally to the specified
bolt torque using a spanner.

 Assembly Completed
 There should be even gaps on two sides between upper and lower
housings.

CAUTION:
 Proper torque of the bolts is required to obtain specified performance.

 Overtightening the bolts may cause damage to the bolt and/or casting,
resulting in pipe joint separation.

Warning: Do not make adjustment to grooved products while the piping


system is under pressure

7.2.5 Drop in Anchor Installation

 Identify the actual location of the hanger based on the approved shop drawing.
Mark the position for installing the drop-in anchor.

 Check the hanger size to confirm the depth of the hole to be drilled based on
approved shop drawings and the manufacturer’s specifications. Adjust the
depth gauge so the anchor will be flush with the base material surface.

 Check the hanger size to select the right drill bit. Then drill the hole according
to the manufacturer’s specification on the marked position.
 Clean the drilled hole to ensure it is free of dust.

 Insert the drop-in anchor into the hole.

 Hammer down the conical plug inside the anchor with a setting punch.

 Install the hanger rod into the drop-in anchor.

7.2.6 Pipe Hanger Installation

 Identify the actual location of the hanger based on the approved shop drawing.
Mark the position for installing the drop-in anchor.

 Install drop-in anchor.

 Install the pipe either by screw fitting or welding.

 Install Hanger Rod based on the pipe size. Install the hanger rod to the drop-
in anchor.

 Install the Hanger to the pipe and the hanger rod.

 Tight the bolts and nuts that hold the hanger rod and hanger evenly.

7.2.7 Valve Screw Connection Installation

 Confirm the valve size and location based on the shop drawings. Ensure that
the selected valve is screw-type.

 Fabricate the Pipe to the required length and thread it accordingly.

 Place the valve between the pipes and make sure the threads are free of dust.

 Guide one of the pipe ends into the valve’s thread, slowly run pipe in clock-
wise direction.

 Hold the valve firmly by a spanner on the flat nearest joint and then rotate the
pipe with a plumbing wrench. Rotate the pipe until the end of the spindle-
operating joint. Repeat the above steps for the other pipe.

7.2.8 Valve with Flanged End Connection Installation

 Confirm the valve size and location based on the shop drawings. Ensure that
the selected valve is flanged type.

 Place the valve between the pipe flanges. Make sure the flange and adjacent
pipework are clean of dirt.

 Choose the gasket size based on the valve size and associated pipe size as
specified in the approved shop drawings, so that it can fit the pipe work flange.
 Connecting the valve with the pipe flange. The pipe flange shall be square with
the associated pipeline.

 Install the bolts into the holes once the valve is in the proper position. Tighten
the nuts one at a time, evenly. Repeat the previous steps for the other joint.

7.2.9 Threaded Fittings Installation

 Check the pipe length required based on the approved shop drawing.

 Mark and cut the pipe to the desired length with a hacksaw or pipe cutting
machine. Check that the pipe is parallel to the hacksaw or machine blade cut.

 Thread the pipe in the threading machine as directed. Check that the pipe
thread is in good condition.

 After threading, remove the oil from the pipe end and wrap it in jute.

 Install the threaded fitting to the pipe.

7.3 Installation of Foam Sprinkler Heads

a. Check that the sprinkler head is in accordance with the approved materials list and
that the sprinkler head location, positions, and spacing are consistent with the
approved shop drawing.

b. Sprinklers shall be positioned to provide area protection consistent with the overall
objectives of this standard by controlling sprinkler positioning and allowable area of
coverage.

c. Ensure the ceiling tee is being installed and levelled.

d. Install the dropper pipe to the sprinkler range pipe.

e. Make sure the threaded fitting and sprinkler tee joint are dust-free.

f. To prevent leaking, wrap Teflon tape around the sprinkler head's threaded joint.

g. Install the sprinkler head and dropper pipe threaded joint. Then, using a wrench,
tighten the sprinkler head into the threaded fitting.

h. Ensure the sprinkler head is level with the ceiling board.

7.4 Installation of Bladder Tank

a. Installation of Bladder Tank shall be in accordance of approved material submittal,


approved drawing, manufacturer’s instruction and NFPA Standard.

b. Check the tank system connection to be sure nothing is obstructing the inlet passage
way.
c. Set tank in place and pipe system connection to system. Be sure to include isolation
valves and drain.
d. Ensure the isolation valves, drain, bolt & nuts are properly fixed.

7.5 Valves and Accessories

a. Examine and confirm that the area is ready for the installation of devices and
equipment.

b. Based on the shop drawings, confirm the valve size and location.

c. Fabricate the Pipe to the desired length and the appropriate connection.

d. Place the valve into the grooved/flanged end pipes. And ensure that the
grooved/flanged and adjacent pipe work is dirt-free.

e. Select the rubber coupling size based on the valve size and associated pipe size as
specified on approved shop drawings, so that it can fit the grooved pipe.

7.5.1 Installation of Alarm Check Valve

a. Alarm Check Valve, must be installed vertically.

b. The alarm valve must be installed in a readily visible and accessible location
and provision to be made in such a way that alarm line drain is visible and
accessible.

c. Where water pressure fluctuates, the variable pressure trim with retard
chamber must be used. Under non-fluctuating water pressure condition, the
constant pressure trim, which does not include retard chamber, may be used.

d. The valve must be installed with trim in accordance with the trim data. Failure
to follow the appropriate trim connection guidelines may prevent the device
from functioning properly as well as void listing, approval and the
manufacturer’s warranty.

e. Care must be exercised while installing the check valve in the trim to ascertain
that they are located with the arrow mark on the check valve body and pointed
in proper direction.

f. The contraction and expansion associated with an excessive volume of


trapped air could cause the waterway clapper to cycle open and shut. This
may result in false alarm or an intermittent alarm. To avoid these, it is
recommended to have breather valve in the system piping network and a vent
valve at the extreme end of the system to bleed-off the air.

g. The ball valve provided on the alarm line must be kept open and strapped in
set position.

h. Pipe connecting the retard chamber and sprinkler alarm bell must be
supported properly to avoid loading on the retard chamber.

i. All the newly installed system pipes must be flushed properly before alarm
valve is put into service.
7.5.2 Installation of Sprinkler Water Motor Gong

a. Locate and cut a hole through the building wall to accommodate a 20NB
(3/4”) pipe with coupling (galvanized pipe to be supplied by the installer). The
required length of support pipe is equal to the thickness of the wall minus 30
millimeters. The pipe is to be threaded with standard 20NB (3/4”) pipe
threading on both the ends to a length of 20 millimeters. Cut the drive shaft
length, equal to the wall thickness plus 43 millimeters.

b. Insert one end of the drive shaft into the square hole provided in the impeller
of the Sprinkler Alarm gong assembly. One end of 20NB (3/4”) support pipe
is to be screwed to the coupling provided with the assembly and the other
end of the pipe is to be screwed to the housing of the Sprinkler Alarm motor
assembly as shown in the figure. Position this assembly against the building
wall through a washer with the support pipe extending through the wall.

c. Connect the alarm port of the Alarm Valve or Deluge Valve to the inlet of the
Sprinkler Alarm assembly with 20NB (3/4”) pipe, with proper support. A 20NB
(3/4”) strainer is to be provided as close as possible to the Sprinkler Alarm
assembly.

d. Move to the other side of the wall, place protection cover on to the pipe
coupling (screwed to the pipe) and hold against the wall. Insert the bush
(assembly with drive shaft adaptor) into the hole provided in the protection
cover and thereby hand tighten the coupling extending through the wall.
Make sure that the drive shaft is properly fitted in the square hole of impeller
and drive shaft adaptor. This can be ensured by rotating the drive shaft
adaptor. The drive shaft adaptor should rotate without any binding while
tightening the bush. If any binding is noticed then unscrew the bush and refit.
After ensuring that the drive shaft is properly placed in the square holes at
both ends, wrench tight the bush.

e. Place the gong over the gong post with washers as shown in the cross-
sectional drawing and hand tighten the dome nut, rotate the gong until the
lettering is properly originated. Wrench tighten the dome nut.

f. Connect the 25NB (1”) open drain pipe to the motor housing, taking due care
that the drain discharge is running to a safe location and keep it free from
obstruction.

7.5.3 Installation of Pressure Reducing Valve

a. Special Note: For system protection, on valve sizes 1-1/2" thru 8" a minimum
1/2" pressure relief valve is to be installed downstream (system side) of the
Pressure Reducing Valve. Adequate drainage of the relief valve discharge
must be provided. The relief valve should be set above the “no flow” or “dead
end” shutoff pressure which is recommended at 5 to 10 psi higher than the
PRV set pressure for 1-1/2" thru 8" valve sizes and 2 psi for 10" and 12"
valve sizes.

b. Allow sufficient room around the valve assembly to make adjustments and
for disassembly.
c. It is recommended that isolation valves be installed on both ends of the PRV
valve to facilitate isolating the valve for start-up, testing and preventative
maintenance.

BEFORE THE VALVE IS INSTALLED, PIPE LINES SHOULD BE FLUSHED


OF ALL CHIPS, SCALE, AND FOREIGN MATTER.
d. Place the PRV valve in the line with flow through the valve in the direction
indicated on the inlet nameplate mounted on inlet flange or by arrow on
nameplate mounted on side of threaded ends valves. Check all fittings and
hardware for proper makeup and that no apparent dam-age is evident.

e. PRV valves operate with maximum efficiency when mounted in horizontal


piping with the cover UP; however, other positions are accept-able. Due to
size and weight of cover and internal components of six inch and larger
valves, installation with the cover up is advisable. This makes periodic
inspection of internal parts readily accessible.

Start-Up and Adjustment

1. Upon initial start-up and after any valve servicing, it is necessary to follow
these steps.

2. Prior to pressurizing the valve make sure the necessary gauges to


measure pressure are installed. Gauges should be installed upstream
(inlet) and downstream (outlet) of the valve. Unused ports on main valve
body can be used for this purpose.

Caution: During start-up and test procedures a large volume of water


may be discharged downstream. Check to make sure that the down-
stream venting is adequate to prevent damage to personnel and
equipment.

3. Close upstream and downstream isolation valves.

4. Slowly open the upstream isolation valve enough to allow the valve and
pilot control system to fill with liquid.

5. Bleed air from the main valve (1) cover and pilot system by slightly
loosening fittings or plugs at all high points until a steady flow of water is
observed retighten. It may be necessary to do this more than once.

6. Open fully the upstream isolation valve.

7. Slowly open the downstream isolation valve part way to establish a low
flow rate.

There must be liquid flowing through the valve during pressure


adjustments.

Optimum valve performance occurs when pressure setting is done with flow
rate as low as practical.
8. Adjust the CRD Control (3) to desired pressure. To change pressure set-
ting, turn the adjusting screw in (clockwise) to increase delivery pressure.
Turn the adjusting screw out (counter-clockwise) to decrease delivery
pressure. The pressure should change approximately 27 psi per turn.
Only slight changes in adjustment should be made to avoid damage to
equipment. When the desired setting has been made, tighten jam nut and
replace cover.

9. For 1-1/2" thru 8" Pressure Reducing Valves the downstream pressure
relief control recommended set point is 2-8 psi above the CRD (3) set
point. For 10" and 12" Pressure Reducing Valves the recommended set
point is 2 psi above the CRD (3) set point. The relief valve for the 10" and
12" PRV should be installed a recommended minimum 6 pipe diameters
downstream of the PRV.

NOTE: The “no flow” or “dead end” shutoff pressure will be 5 to 11 psi
above the set pressure.

7.5.4 Installation of Butterfly Valve

a. Examine and confirm that the area is ready for the installation of devices
and equipment.
b. Confirm the valve size and location based on the shop drawings.

c. Fabricate the Pipe to the desired length and the appropriate connection.

d. Place the valve between the grooved pipes. Make sure the grooved and
adjacent pipe work is clean of dirt.

e. Select the rubber coupling size based on the valve size and associated pipe
size as specified on approved shop drawings, so that it can fit the grooved
pipe.

f. Join the valve and the grooved pipe. The grooved pipe must be parallel to
the associated pipeline

7.6 TESTING AND COMMISSIONING

Test Instruments

To carry out the required tests, the following test instruments must be used:
1. Pressure Gauges
2. Manifolds
3. Pressure Pump (for pressure test)

7.6.1 PIPE INSTALLATION HYDROSTATIC TEST

Safety will be a major factor during pressure testing to ensure a safe working
environment for all the site personnel and to safeguard plant and equipment.
Prior to commencement of test, toolbox talk will be given to all personnel
identifying the potential dangers of pressure testing and to make everyone
aware that testing is ongoing in the area.
7.6.2 Testing Procedure

a. Test limits will be indicated on drawings. Test may comprise a complete


system or a section of piping within a system. Test limits shall be at flanged
or similar mechanical joints.

b. All in line instruments (pressure gauges, thermometers, etc.) shall be


removed during testing. Temporary spreads/blinds will be installed where
necessary at the test limits points.

c. All test equipment’s (test pumps, manifolds, gauges etc.) will be inspected
prior to use to make sure they comply with the site safety requirements. All
gauges shall have a valid calibration certificate available for inspection.
Generally, two gauges will be provided per test, one at the high point possible
and one at the lowest point possible.

d. Before testing commences, the client will be advised twenty-four hours in


advance, by request for inspection (RFI) of the intention to proceed with such
testing and the intended location of any such test. Testing will be coordinated
through the main contractor so as not to affect construction schedules of other
contractors at site.

e. Prior to introducing water into the system, all piping installations shall be
checked thoroughly for tightness.

f. Testing shall be in accordance with the project specifications and guidelines


in NFPA 16.

g. The piping shall be hydrostatic tested in a closed circuit for a period of 2 hours
at 200 psi (13.8 bar) in excess of the system working pressure, whichever is
greater, and shall maintain that pressure without loss for 2 hours.

h. Equipment shall be omitted from tests and bypass arrangements shall be


tested. Temporary spades/blinds will be installed where necessary at the test
limit points.(bladder tanks shall not be included in pressure test)

i. Prior to testing, a demarcation area will be taped off and warning signs placed
prominently, stating that hydrostatic testing is in progress.

j. These demarcation areas will be on entry areas for all personnel with the
exception of testing inspectors and test personnel. The demarcation area
limits may vary greatly in relation to hydrostatic testing that is in progress.

k. Pressurizing of the system will proceed on an incremental basis in the interest


of safety.

l. Test pressure results will be recorded on a pressure test certificate.

m. Test pressure results will be assessed on a test-by test basis to be agreed on


the site and shall be carried out without environmental contamination. When
all aspects of testing are completed, the demarcation area will be removed
and all barriers and signs stored in a safe / tidy manner.
7.6.3 Flushing Procedure

 Ensure all work permit and tools needed for the required piping flushing are
ready.

 Ensure that proper drainage is connected to the discharge side of flushing.

 Flushing of pipe network shall proceed once the preparation is clear and the
site is satisfactory.

 Upon conducting the flushing for any pipe portion ensure that the isolation
valve of the designated pipe is in open position and all other portion is isolated.

 Start the flushing by continuously discharge out the clear water starting from
the existing line to the flushing point by maintaining the required flow.

 Ensure that the system shall be flushed until the water is visually clear and
ensure that the flushed water is free from foreign objects/debris.

 Close the flushing valve of the completed pipe portion then proceed the next
one and conduct flushing for all the remaining designated flushing point as per
the same procedure.

 Ensure that the discharge water is being drained properly to the nearest
drainage available in the area.

 Ensure proper housekeeping before leaving the activity area, all tools and
equipment’s are on proper place.

 Flushing of the firefighting piping system will be after successful completion of


the pressure testing. This will be done during the sectional installations of the
system and after the completion of the whole work assembly.

 Enough draining points will be left for this purpose. These points will be the
lowest point of the area/zone and the water supply point.

 The water will be pumped into the water supply point using the existing fire
pumps and/or any external adequate water supply meeting the flow
requirement as stated in the below table and the lowest points will be
connected to the nearest drainage facility via hose.

 The pipe network will be flushed to ensure that the pipes are clear from debris
and other residual materials. Flushing will be continued until clear water at the
drainage side is observed.

 Pipe flushing should be done using normal operation flow direction.

 Pipeline flushing should preferably be done from the highest to the lowest
elevation.
 Flushing should be performed through fully open flanges/ open pipe ends and
never be carried out through smaller openings such as drains or vents.

 The proper capacity of the pump and/or adequate water supply shall be
selected for pipe flushing activity.

 All required temporary fittings like a hose, blind flange, strainer, gasket, etc
must be fitted before flushing and shall be removed immediately after
completion of pipe flushing.

Table: Flow Required to Produce Velocity of 10ft/sec (3.0 m/sec) in pipes

7.6.4 Sprinkler System

1) Visual Inspection

Before performing functional testing on the Sprinkler System, a visual


inspection must be performed. The following must be included in the test:

A. Main Riser

 Ensure that the hydrostatic test has been completed.

 Each control valve has a permanent system identification sign.

B. Foam System Piping

 Ensure that the hydrostatic test has been completed.

 Ensure that the Piping layout and size are as per the approved design.

 Ensure that the hanger and support space intervals are in accordance
with the approved design.

 Ensure that the Mains and cross mains have one hanger between each
branch line at the end of the main.

 Ensure that the Pipes are painted are in accordance with the approved
design.
C. Foam System Sprinkler

 Ensure that the hydrostatic test has been completed.

 Ensure that the proper sprinkler type and temperature are used.

 Ensure that the minimum distance of sprinkler head from wall are as
per approved design.

7.6.5 Foam Conductivity Test

FIRST STEP:

 Collect a little amount of water from the Test Valve in a small cup and insert
the Conductivity Meter into it and get the reading.

SECOND STEP: Conductivity@ 2%

 Determine the conductivity of the water at 2% of foam. For this you have to get
98-gram water and

 2 grams of foam from the foam tank and mix well (5 to 10 seconds)

 In that mixture insert the Conductivity Meter and get the reading/result

THIRD STEP: Conductivity@ 3%

 Determine the conductivity of the water at 3% of foam. For this you have to get
97-gram water and 3 grams of foam from the foam tank and mix well.

 In that mixture insert the Conductivity Meter and get the reading/result

8. QUALITY

In process, works shall be monitored for quality of workmanship and it should be in


accordance to approved shop drawings, specifications, code and standard.

All inspection requested must be properly documented for future references and to be
witnessed and approved by main contractor qa/qc engineer.

9.1 Inspection Test Plan.

Installation activities will follow as per the approved Inspection Test Plan.
9 HSE ISSUES, RISK ASSESSMENT AND HAZARD ANALYSIS

 Implementation of Health, Safety and Environment mechanisms must be check


thoroughly as per contract agreement and the approved Health and Safety Manual.

 Responsible Health, Safety and Environment Officer of the project will conduct
routine HSE inspections.

 Safe access and egress to and from the work place shall be provided by the main
contractor.

 Risk assessments for the installation of Fire Fighting System have been attached to this
method statement and related to the risks and associated hazards related to the activity.

10 ATTACHMENTS

10.1 Risk Assessment

10.2 Inspection & Test Plan

10.3 Checklist
10.1 Risk Assessment
Project Name: 2B+G+6 LA PLAGE SOUTH 1 RESIDENTIAL BUILDINGS
Document Title Risk Assessment for Installation, Testing & Commissioning of Foam system Date 21/05/2023
Document No. LPS-01-HTI-MST-ME-032 Rev. No. 0

Risk Assessment for Installation, Testing &


RA Description: MST Ref. No.: LPS-01-HTI-MST-ME-032 Rev. No.: 0 Date: 21/05/2023
Commissioning of Foam system
Project Name: 2B+G+6 LA PLAGE SOUTH 1 RESIDENTIAL BUILDINGS

Contractor: HBK Contracting Company Employer: Sheik Ali Bin Hamad Bin Khalid Al-Thani

Note: Where the Hazard Rating remains High after control measures have been identified the work must not
RISK / IMPACT ASSESSMENT
be started and the HSE department contacted for further advice.
MATRIX
Where the Hazard Rating remains High after any additional control
HAZARD RATING measures have been identified the work must not be started and the
HSE department must be contacted for further advice.
Likelihood

Hazard Rating Likelihood Severity Environment 1 2 3 4 5

Rating 1 – 6 Low -L 1 -Unlikely 1 - First aid 1 - No impact 1 1 2 3 4 5

Rating 7 – 14 Medium - M 2 –May Happen 2 –Hosp. Treatment 2 – Local impact 2 2 4 6 8 10

Severity
Rating 15 – 25 High -H 3 – Likely 3 - > 3 days 3 – Minor impact 3 3 6 9 12 15

4 - Very likely 4 –Major Injuries 4 – Moderate impact 4 4 8 12 16 20


5 - Almost certain 5 – Fatal 5 – Major impact 5 5 10 15 20 25
Severity x Likelihood = Hazard Rating

Contractor
Assessed by: Reviewed by: Approved by:
Name: Name: Name:
Construction Project HSE Manager Project Manager
Signature: Signature: Signature:

Date: Date: Date:


Risk Rating Residual Rating
Item Activity Hazard & Risks Existing Control Additional Controls
S L RR S L RR
01 Preparation of the activity Hazard such as:  Arrangement and provision 3 4 12  Provide suitable & 3 1 3
/General requirements / Unfamiliarity / for the required tools, sufficient signage.
Site Preparation negligence to site rules equipment and working  Check/ make awareness
 Incompetency of the platform required for the job. about the surrounding
work crew.  Obtain permit UDC to activities before
 Obstructed access / work priorto the activity. commencing the tasks.
egress.  All workers and staff  All personnel to get
 No / insufficient safety Involved in activities of accustomed with site
signage. Installation of wall & floor emergency response
 Unaware of tiles activity should undergo procedures.
surrounding activities. site induction.  Comply PPE policy and
 Damage to tools /  Approved method statement wear task specified PPE.
equipment and and risk assessment and  Comply corporate
incorrect. drawings should be in place policies and procedures
 Unfamiliarity with site and briefed to all individuals to prevent or resolve
emergency procedures prior to work commencing. unacceptable behavior.
 No PPE compliance  Trained and competent  Systems are in place to
 Workload. personnel to be deployed for enable and encourage
 Manual handling the activity. mangers to deal with un-
 Lack of Communication  Keep clear all access/ acceptable behavior.
/Coordination egress always. Provide  Following proven health
proper access and egress to measures is still the best
the work location. way to keep everyone,
 Only fit to use and safe (TP including workers and
Risk such as: certified if applicable) staffs, safe from COVID-
 Human Injury, Human equipment and tools to be 19. This includes keeping
error, Hand injury, deployed to site. hands clean, practicing
Abrasion, Ill health and  Agreed performance targets. sneezing and coughing
sickness.  Regular workload meetings. into bent elbows, opening
 Review and monitor of staff windows, wearing a mask
working hours. if age-appropriate, and
 Work life balance policies continuing physical
implemented. distancing
02 Mobilization of manpower, Hazard such as:  Pre-start talks to be carried 3 4 12  Ensure you provide 3 1 3
materials,  Unsecured load. out to all work force exclusion zone around
 Slips, trips and falls. involved. working area with
 Falling material.  Make sure all new suitable warning zone
 Flammable substance employees undergone HSE posted.
 Smoking induction training.  Estimate the work area
 Poor behavior  RAMS Shall be discussed and should be barricaded
 Overturning with work force before off to ensure
 Overloading of starting the works. unauthorized personnel
materials Competent and Authorized do not enter the area.
 Inclement weather Supervision present at all  All area should be well
times to ensure illuminated at all time.
 Poor lifting Technique
employees/workers are  Appropriate PPE to be
 No PPE inside site
adhering to manual handling worn by all personnel
premises.
safe working procedures  Train workers on manual
 Provided proper path way handling techniques.
Risk such as:
 Hand injury, human
and lighting for safe access  In case of transporting
to all material. flammable hazardous
injury
 Priority shall be given to the substances, transporting
 Abrasion, cut injury
use of mechanical devices. section in MSDS should
 Ill health and sickness
 Maintain proper handling be strictly followed.
 Property damage. procedure while handling the  Make sure all employees
materials. use site mandatory PPE
 Deploy only fit and safe and task related PPE
equipment/tools for the such as Helmet, Safety
activity. Glass, Safety Shoe, High
Visible Vest, Hand gloves
etc.
03 Material Delivery Hazard such as  Ensure that employees do 3 3 9  Should include pre-trip 3 1 3
 Collision with Another not drive any vehicles unless vehicles inspections.
Vehicle they have VALID Qatar  Immediate withdrawal
 Vehicle Breakdown driver’s license and are from service for vehicles
familiar with traffic rules and with mechanical
regulations. problems.
Risk such as:  Conduct effective drivers  Periodic withdrawal from
 Legal obligation/ training and communication service for
penalties system. comprehensive
 Property damage and  Work with regulatory inspection and scheduled
or physical injury agencies to ensure maintenance.
 Oil spill can cause regulatory compliance is  Each driver should
environmental achieved. prepare a report in writing
contamination  Drivers should adhere to all at the completion of each
traffic laws and regulations day’s work on each
when operating company vehicle operated
vehicles. regarding the vehicle
 Safely stopping and securing conditions.
the vehicle and load.  Securing the vehicle and
 Safely placing the warning placing the appropriate
devices. warning devices suitably.
 Ensure that all the drivers  Provide appropriate oil
understand how to use the spill kit or alike to all
spill kit provided. vehicles.
 Used kit must be properly
secured and disposed
according to the local
municipality procedures.
Panel Delivery Hazard such as:  Strictly implement the pre- 3 4 12  Lorry truck operator, 3 1 3
 Lifting inspection of the plant and lifting gears and truck
 Tip-over equipment prior using, make certified by third party.
sure third-party certification  Lifting plan permit must
Risk such as: copies are with the operator. be acquired prior the
 Caught in between or  Set the brakes, position the activity.
struck by falling object, outriggers devices on pads  Position the lorry truck in
bone fracture, serious or similar solid surface and a manner to avoid striking
physical injury install the wheel chocks prior any objects or person.
 Property damaged, lifting.  Ensure barriers to
physical injury  Position the lorry truck in a prevent people entering
manner that the boom will swing radius.
maintain a minimum of 10
feet from the power lines.
 Position the boom truck in a
manner in which to secure
stability
 Know the ground condition.
04 Material Storage and Stack Hazard such as:  Avoid the need for manual 3 3 9  Ensure that heavy 3 1 3
Pilling  Manual Handling handling as far as it is objects will be assisted
 Falling Object reasonably practicable. by lifting or transporting
 Assess the weight of the equipment.
Risk such as: object to be lifted before  Take care to ensure that
 Back pain and muscle lifting, ask help from others manual handling activities
strain when lifting heavy objects. do not put others at risk.
 Struck by  Follow appropriate safe  Handling equipment such
system of work for manual as forklift truck that is
lifting. suitable for the job is
 Securing the objects/pipes properly inspected and
from falling by providing operated by competent
barriers. and qualified persons as
 Stocking properly, ensuring required.
shelving systems are  Making sure the load is
properly secured and balanced and secured
maintained. when load is lifted.
 Inspecting pallets each time  Loading on pallets
before use to make sure correctly. To ensure load
they are in a safe condition. stability; banding with
shrink or stretch wrap can
help with this.
05 Inspection Prior to Hazard such as:  Check the Foam and its 3 2 6  Before any materials are 2 1 2
Installation  Using Defective accessories if properly installed, ensure that
Materials, Tools / labelled and received at site these have been
Equipment and in accordance with inspected at the site and
Improper Storage specification and correct have been approved by
dimension as per approved consultant.
Risk such as: drawings.  Check all proper
 Property damage and  Materials shall be moved to materials, tools and
or physical injury the work in a safe manner equipment are available
and shall not block to carry out the work and
access/egress from the site. in compliance with
 Thorough coordination with contract specification.
other subcontractors (e.g.
structural, architectural etc.)
must be implemented before
and during installation work
06 Threading/ Grooving of Hazard such as:  Only authorized and 3 4 12  Remove loose clothing 3 1 3
Pipes  Exposure to Moving competent workers will be and jewelries to avoid
Parts and Sharp allowed to use the threading entanglement to moving
Objects and grooving machines. parts.
 Falling Object  Ensure that the threading  Stand support rigidly
 Oil Spill and grooving machine are in erected in a firm ground.
good condition and erected  Remove the
Risk such as: in a rigid position. contaminated sand in the
 Laceration, amputation  While grooving long pipes, drip tray regularly and
 Struck by ensure that the pipes are dispose in accordance to
 Pollution local regulations.
supported properly to avoid  Machine with oil leak
falling. must be removed in the
 Remind helper to be more workplace and scheduled
attentive and vigilant while for maintenance.
grooving is going-on.  Place the newly threaded
pipes in the empty pale to
drain the excess oil.
07 Drilling Hazard such as:  Only authorized and 3 3 9  Ensure that the 3 1 3
 Exposure to Sharp competent workers will be scaffolding is properly
Object allowed to use the drilling erected and inspected by
 Dust Exposure machine. competent personnel.
 Working at Heights  Ensure that the drill bit is  Fall prevention must be in
sharp and correctly mounted place prior to
Risk such as: to the chuck of the drill and commencing of activities.
 Serious physical injury fitted properly.  Alteration on the
or fatality due to Fall  Ensure that the switches are scaffolding must only be
from height working in good condition. executed by competent
 Respiratory, eye and  Ensure that you have scaffolding erectors.
skin irritation enough space while drilling.  Caster wheel of mobile
 Physical injury  Require the management to scaffold must always be
provide drill with a built-in locked especially on un-
dust collection system. even ground.
 Provide induced fan to  Ladders should be used
modulate the dust for short duration-low risk
generated. activities only. Otherwise,
 Re-shuffle the operatives safe working platform
who are drilling in the ceiling. shall be provided.
 Barricading the workplace
area and put signage.
 Provide appropriate personal
protective equipment.
08 Installation of Pipes and Hazard such as:  Avoid the manual lifting as 3 3 9  Avoid the manual lifting 3 1 3
Hoisting of Pipes to Ceiling  Working at Height far as it is reasonably as far as it is reasonably
Level  Manual Lifting practicable. practicable.
 Only use the pipe lifter in the  Only use the pipe lifter in
Risk such as: level ground and install a the level ground and
 Fall from height can hard barricade appropriate install a hard barricade
cause serious physical to the length of the pipes appropriate to the length
injury or fatality lifted. of the pipes lifted.
 Falling object can  Lifting assisted with chain  Lifting assisted with chain
cause serious physical block; ensure that third party block; ensure that third
injury or fatality certificate is provided.
 Back pain, muscle pain  Follow appropriate safe party certificate is
and fracture due to system of work for manual provided.
manual lifting a heavy lifting.  Follow appropriate safe
load  Take care to ensure that system of work for
manual lifting activities do manual lifting.
not put others at risk.  Take care to ensure that
manual lifting activities do
not put others at risk.
09 Installation of Hanger, Hazard such as:  Alteration on the scaffolding 3 4 12  Ensure that the 3 1 3
Support and Pipes  Working at Heights must be executed by scaffolding is properly
competent scaffolding erected and inspected by
Risk such as: erectors. competent personnel.
 Serious physical injury  Caster wheel of mobile  Fall prevention must be in
or fatality due to Fall scaffold must always be place prior to
from height locked especially on un-even commencing of activities.
ground.  Barricading the working
 Ladders should be used for area and do not allow
short duration-low risk anyone to pass beneath
activities only. Otherwise, the working platform.
safe working platform shall
be provided.
10 Hot Works Hazard such as:  Hot works permit is required 3 4 12  Do not weld on 3 1 3
(Welding, Grinding and  Electrocution before the job will start. To containers that have held
Cutting)  Welding Fumes and ensure that all the combustible materials
Gasses precautions has been unless procedures for
 Sparks, Fire and applied before doing the safe welding and cutting
Explosion task. of such containers are
 Ark Ray, Spatter  Operators to be competent carefully followed.
 Exposure of Cutting or given practical  Remove flammable
Equipment demonstration. materials from welding
 (Grinder)  Ensure grinding disc and area or shield from
Risk such as: guards are not damaged. sparks and heat.
 Expose to live wires  Ensure power cord and  Deploy certified
 Exposure to fumes and motor are not damaged. firewatcher before, during
gasses causing  Appropriate PPE`s should and after the welding
(occupational ill health) be worn while executing the jobs.
pulmonary diseases or task.  Keep appropriate fire
even fatalities  Keep others clear of the extinguishers in welding
 Property damage, work area and erect a area.
severe injury or barricade or fire-resistant  Remind operatives the
fatalities cloth if necessary. hazard generated from
welding (SDS for the
 Exposure to sparks and  Make sure work piece is fumes) in the toolbox talk
ark ray of welding secured and use appropriate / pre-briefing / STARTT.
works can cause burn, disc as per the manufacturer  Provide additional
eye and skin irritation advice. ventilation and exhaust
 Failed cutting disc while  Always use insulated handle where it is needed or if
using it can cause for the grinder. welding in confined
laceration, amputation  Always turn off and remove space.
or even fatality the power supply of the  Know what the base
power tools after using it. metal is and determine if
 Select proper filter lens that there is any paint, plating
is comfortable while welding. or coating, and remove it
 Wear flame resistant from metal being welded,
clothing that provides full if possible.
coverage for skin.  Position (welder) head
 Use earplug to keep spark away from the fumes, to
and spatter from entering keep the amount of fume
ears. breathed as low as
 Cover the welding workplace possible.
with non-flammable screen  Use adequate ventilation
to protect others nearby. and/or exhaust to keep
 Use respirator if exposure to the air breathed clear and
welding fumes cannot be comfortable. Work area
controlled or if natural air should have enough
movement is not enough to ventilation and/or local
keep the welding fumes out exhaust at the arc to
of your breathing zone. control from exposure.

11 Painting of Pipes Hazard such as:  Discuss the hazards of the 3 4 12  Make sure the floor is 3 1 3
 Fume Exposure chemical in the toolbox talk; even and stable. Avoid
 Working at Height refer to MSDS. wet and slippery
 Provide additional ventilation surfaces.
to direct the fumes away to  Always support the
Risk such as: the painter. ladder at four points.
 Respiratory, eye and  Wear the appropriate gloves,  Keep your shoulders
skin irritation solvent-resistant chemical between the rails and do
 Serious physical injury and anti-fume mask and not over-reach – move
or fatality due to Fall goggles. the ladder instead.
from height  Inspect the ladder; take time  Be prepared for an
to check the condition of the unforeseen vertigo attack
ladder both before and after – do not look down,
use. breath slowly and
 Check that the ladder is steadily, and go back
sufficiently robust to support down systematically.
your weight.  Ladders should be used
 Make sure the steps are free for short duration-low risk
of oil, wet paint, mud or any activities only. Otherwise,
other potentially slippery safe working platform
substance. shall be provided.
 If the ladder needs to be in  Clear the area around the
the front of the door, ladder from any clutter.
consider locking the door to
prevent surprise opening.
Foam System Installation Hazard such as:  Ensure that the scaffolding is 3 4 12  Secure all the tools and 2 1 2
 Working at Height properly erect and inspect by materials in the working
competent personnel. platform.
Risk such as:  Fall prevention must be in  Maintain the orderliness
 Fall from height can place prior commencing of in the platform, avoid
cause serious physical activities. loose material that can
injury or fatality  Alteration on the scaffolding fall when tap.
 Falling object can must only be execute by  Provide rope when
cause serious physical competent scaffolding bringing up or lowering
injury or fatality erectors. tools or materials.
 Caster wheel of mobile  Barricading the working
scaffold must always be area and do not allowed
locked especially on an even anyone to pass beneath
ground. the working platform.
 Ladders should be used for
short duration-low risk
activities only. Otherwise,
safe working platform shall
be provided.
12 Installation of Fire Alarm & Hazard such as:  Inspect the ladder; take time 3 4 12  Always support the 3 1 3
other devices  Working at Height to check the condition of the ladder at four points.
 Working on Ladder ladder both before and after  Keep your shoulders
use. between the rails and do
Risk such as:  Check that the ladder is not over-reach – move
 Fall from height sufficiently robust to support the ladder instead.
 Fall from Ladder can your weight.  Be prepared for an
cause Minor to Serious  Make sure the steps are free unforeseen vertigo attack
Physical Injury of oil, wet paint, mud or any – do not look down,
other potentially slippery breath slowly and
substance. steadily, and go back
down systematically.
 Clear the area around the
ladder from any clutter.
13 Cable Pulling Hazard such as:  Ensure that the scaffolding is 3 4 12  Caster wheel of mobile 3 1 3
 Working at Height properly erected and scaffold must always be
inspected by competent locked especially on an
Risk such as: personnel. even ground.
 Fall from height  Fall prevention must be in  If using ladder, ensure
place prior commencing of that the ladders are
activities. appropriate for the work
 Alteration on the scaffolding and erected rigidly.
must only be execute by
competent scaffolding
erectors.
Installation of Foam Hazard such as:  Lorry truck operator, lifting 3 4 12  Ensure that the 2 1 2
Generator  Lifting gears and truck certified by scaffolding is properly
 Tip-over third party. erected and inspected by
 Working at Height  Lifting plan permit must be competent personnel.
 Working on Ladder acquired prior the activity.  Fall prevention must be in
 Position the lorry truck in a place prior the
Risk such as: manner to avoid striking any commencing of activities.
 Fall from Ladder can objects or person.  Alteration on the
cause Minor to Serious  Ensure barriers to prevent scaffolding must only be
Physical Injury people entering swing executed by competent
 Falling object can radius. scaffolding erectors.
cause serious physical  Installation of generator shall  Caster wheel of mobile
injury or fatality be in accordance of scaffold must always be
manufacturer’s locked especially on an
recommendation. even ground.
 Strictly implement the pre-  Ladders should be used
inspection of the plant and for short duration-low risk
equipment prior to using, activities only. Otherwise,
make sure third-party safe working platform
certification copies are with shall be provided.
the operator.
 Set the brakes, position the
outriggers devices on pads
or similar solid surface and
install the wheel chocks prior
lifting.
TESTING AND COMMISSIONING
14 Cable continuity and Hazard such as:  Permit to work system is 4 3 12  Isolate the item being 4 1 4
Resistance  Exposure to Electricity secured. (advance notice to checked from the
the permit issuer) circuitry, if possible
Risk such as:  Toolbox talk is conducted to  Ensure proper PPE are
 Electrocution or shock operatives involved prior to provided to all operatives
starting the activity.  Never touch the test lead
 De-energize and discharge while the megger is being
the circuit completely before used.
connecting a megger.
15 Activation of Any Detection Hazard such as:  Permit to work system 3 3 9  Ensure that the water 3 1 3
System in Crossed Zone  Exposure to high levels should is secured. (advance coming from the system
Circuit of Noise notice to the permit issuer) will be collected in an
 Toolbox talk regularly appropriate container if
Risk such as: conducted to operatives the drain is not available.
 Hearing Loss involved prior to starting the  Activities must be
 Physiological effects activity. coordinated to all
 Work related stress  Segregating the devices subcontractors that may
 Property damaged. under test. be affected by this
 Person who doing the activity.
task i.e. Supervisor,  All operatives should be
provided by suitable
PPEs.

16 Pneumatic Testing Hazard such as:  Permit to work system 4 3 12  Conduct testing possibly 3 2 6
(Puff Test)  Exposure to High should be secured. (advance at night or in a weekend
Pressure notice to the permit issuer) when few people are
 Toolbox talk should be near the test site..
Risk such as: conducted to operatives  Conduct testing possibly
 Serious physical injury involved prior to starting the at night or in weekend
and damage to activity. when few people are
property  Maintaining test connectors, near the test site.
ensure that it is well secured
or tightened.
 Assign personnel from
exclusion zone (an area
where unauthorized
personnel are prohibited to
enter) surrounding the piping
system under test.
COVID-19
17 Transportation of Hazard such as:  Vehicle seat capacity 3 3 9  Ensure “Etheraz” status 2 2 4
Personnel at Site  Failure to follow reduced to 50 % to get is green prior to entering
physical distancing enough spacing to follow the vehicle and the site.
protocol physical distance protocol.  Cover cough or sneeze
 Personnel maintaining a by tissue paper or cloth.
Risk such as: distance of 1.5 meters.  Sanitize your hands
 Symptoms related to  All personnel must wear wherever possible,
COVID-19 (fever, colds mask while travelling to site. including entering and
and respiratory  Ensure the windows are leaving buildings.
problems) open to allow proper
ventilation.

18 Working at Site Hazard such as:  Temperature monitoring in 3 3 9  Regularly clean and 2 2 4
 Failure to follow place. disinfect surfaces that
COVID-19 safety  Adequate supervision to many people touch.
precautions at the site monitor the personnel.  Limit food handling and
 Stop integrating with other sharing of food in the
company personnel. workplace.
Risk such as:  Stay at home unless going  Eat healthy! Bring your
 Symptoms related to out is absolutely necessary. lunch to work and eat at
COVID-19 (fever, colds  Stop visiting others rest your desk, or away from
and respiratory areas. others.
problems)  Stop shaking hands to greet  Ensure “Etheraz” status
others. is green prior to entering
 Hold essential meetings the vehicle and the site.
outside in the open air if
possible.
 Promote good hand, sneeze
and cough hygiene.

OTHERS
19 General Hazard such as:  Check all Tools, don’t issue 3 2 6  Employees shall be 2 1 2
 Usage of Defective defective Tools ensured that their tools
Tools and Greasy  Keep the Tools clean and are in good condition and
Tools free from any lubricants, like if a defect is observed,
Oil, Grease etc. then it must be replaced.
Risk such as:
 Physical injury  No Improvised tools shall be  All Tools and Equipment
use. must be properly stored.

20 Working under unfavorable Hazards such as:  Hot Season 4 4 16  Hot Season 4 1 4
weather conditions  Working under hot  Strict monitoring and  Provide intermittent rest
weather / high humidity. supervision during extreme hot
 Working under foggy  Heat index chart / MOL climate and procedure of
weather, regulation to be maintained. work in confined space
 Exposure of materials  Adequate rest and rotation will be ensured.
to extreme weather to be maintained.  Report physical unwell to
 Activities to be scheduled as immediate supervisor/first
Risk such as per prevailing weather aider/male nurse.
 Heat stress / condition.  Communication of site
exhaustion / stroke  Weather monitoring chart to emergency procedure
 Hypothermia be monitored effectively. and heat stress
 Faintness / dizziness  Emergency procedures and prevention management
 Heat rash preparedness to be through tool box talk.
 Discomfort (nausea/ communicated to all  Materials to be protected
vomiting workers. (Emergency from UV rays
contacts to be displayed)  Cold Season
 Hourly monitoring of heat  Wear a hat, mittens or
stress and recording. insulated gloves.
 Provision of adequate  Keep your face warm
drinking water/ice/glucose in with a scarf, neck tube or
working location. facemask.
 Personnel body temperature  Wear warm and
to be monitored. waterproof footwear.
 Winter jackets to be  When it is very cold, or
provided if work is to be when the wind chill is
executed under extremely significant, cover as
 Cold Season much exposed skin as
 Workers to be advised to possible.
take warm water when  Moisturizing your skin
necessary. with a cold cream or
 Strict monitoring of health petroleum jelly.
condition of workers.
21 Housekeeping Hazards such as:  Train and inform the 3 3 9  Remind the concerned 3 1 3
 Exposure to Sharp operatives the content of the operatives to segregate
Objects dust generated in the work waste collected in
 Exposure to Dust and site and the diseases that it assigned bins or skips
Chemicals
will cause if it enters the (labeled the bins or
Risk such as: body. skips).
 Cut, laceration or  Wetting the dust or ground  Use appropriate tools and
amputation before sweeping. equipment for collecting
 Respiratory, eye, skin  Use vacuum instead of waste.
irritation broom.  Ensure that the
 Controlled disposal of temporary collected
dangerous waste. wastes are regularly
 Provide appropriate mask to removed in the
all operatives. workplace.
 Provide appropriate
gloves to all operatives.
All preventive action must be taken as per legal requirements, Activity in charge is responsible to ensure that all control measures are in place as per
international standards and client procedure. He has the authority to stop any activity if observed any potential HSE issues that lead to accident, incident or
potential Near Miss.
10.2 Inspection & Test Plan
Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
INSPECTION AND TEST PLAN FOR INSTALLATION
Document Title Date
TESTING & COMMISSIONING FOR FOAM SYSTEM 21/May/2023
LPS-01-HTI-MST-ME-032
Document No Rev. No. 0

INSPECTION AND TEST PLAN


FOR
FOAM SYSTEM

Project : 2B+G+6 LA Plage South-1 Residential Buildings

Employer : Ali Hamad K Al Thani

Project Design & Construction : Qatar design consortium

Supervision Service Consultant: Neo-spectrum

Main Contractor : HBK Contracting Company W.L.L.

Revision History

LPS-01-HTI-MST-ME-032 0 21/May/2023 Issued for Review and ALEEM AHMED


Approval
Doc. no. Rev. Date Purpose of Submission Prep. By Rev. by Appr. By
no. Proj. QA/QC Project
Manager Manager
Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
INSPECTION AND TEST PLAN FOR INSTALLATION
Document Title Date
TESTING & COMMISSIONING FOR FOAM SYSTEM 21/May/2023
Document No LPS-01-HTI-MST-ME-032 Rev. No. 0
Legend: H=Hold Point, WIR to be issued and work shall not proceed without acceptance from the responsible party; W=Witness Point- WIR to be issued and work may proceed if the
responsible party does not attend; S=random surveillance, no signature or IRW required; R=“Record/ Document Review”(submitted separately as necessary);TRR=Test Report Review
Checks Intervention Points Verification
Documents
Control Documents Acceptance Criteria/

Contractor
Contractor
Checking

3rd Party
# Works Tolerances (if applicable) Responsible Required

Sub-

CSC
Activity to Job Function Frequency
be
Performed
1.0 DOCUMENTATION
1.1 Review Project Specification Approved Method statement. Site Engineer For Review and R R R N/A Project
Verify the QCS-2014 Specifications
Approval before
approval of NFPA Standards Material
proceeding the
method Material Submittal Submittal
works NFPA Standards
statement
QCS
Specifications
2.0 STORAGE CONDITION OF MATERIAL
2.1 Review/ Project Specification Stored in accordance with QC During Material H H W N/A Material
Foam System QCS-2014
Visual manufacturer's Material Safety Storage delivery note
Materials NFPA Standards Data Sheet Material
Material Submittal Certificates,
Material
safety data
sheet
2.2 Review/ Project Specification Visual Inspection/ Delivery Store-in- After material H H W N/A Material
Material Delivery QCS-2014
Visual storage and handling as per Charge / arrived at site Inspection
Inspection NFPA Standards Manufacturer’s Instructions QC Engineer Request (MIR)
Material Submittal
3.0 MOCK UP
3.1 Visual Project Specification Verify the substrate, must Project At the time of H H W N/A WIR shall be
Conduct mock
QCS-2014 match with the UL system / Engineer/Site Mock up
For foam system raised.
Manufacturer Instruction / installation
NFPA Standards Engineer Subcontractor
Engineering Judgement (EJ)
Material Submittal Inspection
Reports.

4 Installation
4.1 Installation of Visual Project Specification Approved Method statement. Site After installation H H W N/A Checklist
Pipes and inspection QCS-2014 And Approved Shop Drawings Engineer/QAQC
Fittings NFPA Standards Engineer
Material Submittal
Approved Shop Drawings
4.2 Installation of Visual Project Specification Approved Method statement. Site After installation H H W N/A Installation
Sprinkler inspection QCS-2014 And Approved Shop Drawings Engineer/QAQC Checklist
NFPA Standards Engineer
Material Submittal
Approved Shop Drawings
4.3 Installation of Visual Project Specification Approved Method statement. Site After installation H H W N/A Installation
Mechanical inspection QCS-2014 And Approved Shop Drawings Engineer/QAQC Checklist
Equipment’s NFPA Standards Engineer
Material Submittal
Approved Shop Drawings
4.6 Installation of Visual Project Specification Approved Method statement. Site After installation H H W N/A Installation
Electrical inspection QCS-2014 And Approved Shop Drawings Engineer/QAQC Checklist
Equipment’s NFPA Standards Engineer
Material Submittal
Approved Shop Drawings

5 TESTING AND COMMISSIONING


5.1 Cable Test: Visual Project Specification Test voltage as 250V DC and Site After installation H H H N/A TESTING &
Inspection QCS-2014 minimum resistance value is Engineer/QAQC And requested Commissioning
- Cable /Testing NFPA Standards 0.5 M ohms. If the test result is Engineer for Inspection Checklist
Continuity, Material Submittal more than 0.5 M ohms the
Loop Approved Shop Drawings cable passed the test.
Resistance and
Polarity Test
Cable Insulation
Resistance Test
5.2 Visual Project Specification All piping and attached Site After installation H H H N/A TESTING &
Pressure Test QCS-2014 Commissioning
Inspection appurtenances subjected to Engineer/QAQC And requested
/Testing NFPA Standards Engineer for Inspection Checklist
system working pressure shall
Material Submittal
be hydrostatically tested at 200
Approved Shop Drawings
psi ( 13.8 bar) or 50 psi (3.5
bar) in excess of the system
working pressure, whichever is
greater, and shall maintain that
pressure without loss for 2
hours.
5.3 Flushing of Foam Visual Project Specification As per Approved Method Site After installation H H H N/A TESTING &
System Statement
Inspection QCS-2014 Engineer/QAQC And requested Commissioning

/Testing NFPA Standards Engineer for Inspection Checklist

Material Submittal
Approved Shop Drawings
5.4 Foam Conductivity Visual Project Specification As per Approved Method Site Engineer / After Installation of H H H N/A Testing &
Test Inspection / QCS-2014 Statement QAQC Engineer System and Commissioning
Testing NFPA Standards requested for Checklist
Material Submittal
Approved Shop Drawings
Inspection
6 FINAL INSPECTION
6.1 Inspection for Visual Project Specification Contractor /consultant Project Manager/ After completion R R R N/A WIR Shall be
the completed Inspection/ QCS-2014 Inspection Control Sheet QAQC Engineer of Testing & raised.
Foam System as Document NFPA Standards completed for the foam System Commissioning Subcontractor
Material Submittal
per the selected Verification Approved Shop Drawings
works Installation, testing & of the System Inspection
system Commissioning should comply Reports,
/Engineering with QCD Standards and NFPA Approved
Judgement Specifications Drawings,
inspection
standard as
per project
specification
7 COLLATE RECORDS/DOCUMENTS FOR FINAL HANDOVER
7.1 Collation of all Document Project Specification Collect all compliance RFI for all QAQC Engineer During Handing R R R N/A Inspection
Quality Verification QCS-2014 inspected areas and documented Over of the Reports, UL
NFPA Standards for final hand over.
Documents system systems /EJs.
Material Submittal
Approved Shop Drawings
7.2 Inspections from Contractor Project Specification Contractor is responsible for Project During Final H R R N/A Copies of WIR,
authorities Rep. QCS-2014 approval /Inspection from manager Inspection from Work
NFPA Standards authorities and Sub-contractor Authorized completion
Material Submittal shall arrange all required
letter, UL
Approved Shop Drawings documents for this process of the
handing over systems
, QCDD
product
approvals.
10.3 Checklist
Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM

Document No LPS-01-HTI-MST-ME-032
Rev. No. 0

Material Inspection Checklist

Project :2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

Request For Inspection / Testing No. Date:

Contractor:

Discipline: Mechanical Electrical


Status
Item No. Inspection / Check Point Not
Remarks
Accepted
Accepted
Ensure that the equipment is packed for protection against
1. damage during handling, transport, warehousing and
installation.

2. Check the Pipes, Fittings and Equipment’s are not damaged

Verify that the material is within accordance of approved


3.
material submittal and drawing.

4. Check whether the delivery note is provided.

5. Check whether the quantity of material is correct.

Remarks :

HBK/FG Site Engineer HBK Inspector CSC (Dar Al Handasa) TWC/TPL/Others

Name Name Name Name

Position Position Position Position

Signature Signature Signature Signature


Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM

Document No LPS-01-HTI-MST-ME-032
Rev. No. 0

PRESSURE TEST REPORT


Project:2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
Request for Inspection / Testing No. Date:

REFERENCE ITP NO.:

LOCATION:

ROOM NO. OR DESCRIPTION:

REFERENCE DRAWING NO.:

PIPELINE LOCATION:

MATERIAL TYPE:

NOMINAL DIAMETER:

TYPE OF SERVICE:

CALIBRATED PRESSURE GUAGE SERIAL NO:

TEST

ACTUAL TIME START: ACTUAL READING: DATE:

ACTUAL TIME FINISH: FINAL READING: DATE:

HOLDING TIME:

RESULT: Accepted Rejected

Remarks

HBK/FG Site Engineer HBK Inspector CDC HEXATECH QA/AC

Name Name Name Name

Position Position Position Position

Signature Signature Signature Signature


Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM

Document No LPS-01-HTI-MST-ME-032
Rev. No. 0

FLUSHING REPORT

Project:2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS


Request for Inspection / Testing No. Date:

REFERENCE ITP NO.:

LOCATION:

ROOM NO. OR DESCRIPTION:

REFERENCE DRAWING NO.:

PIPELINE LOCATION:

MATERIAL TYPE:

NOMINAL DIAMETER:

TYPE OF SERVICE:
TEST:

Piping flushed according to standard by (Company) Yes No


If no, explain

How flushing flow was obtained: Public Water Tank or reservoir Fire Pump

Through what type opening: Y connection to flange and spigot Open pipe

RESULT: Accepted Rejected

Remarks:

HBK/FG Site Engineer HBK Inspector CDC HEXATECH QA/AC

Name Name Name Name

Position Position Position Position

Signature Signature Signature Signature


Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM

Document No LPS-01-HTI-MST-ME-032
Rev. No. 0

SYSTEM OPERATIONAL TEST FOR SPRINKLER SYSTEM


Project: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
Request for Inspection / Testing No. Date:
Location /Area:
Status
Item No. Activities / Items to be inspected Not Remarks
Accepted
Accepted

1) Visual Inspection

A Main Riser

Ensure that the hydrostatic Test has been successfully


a
completed
Check for Permanent system identification signs for each
b
control valve
Verify that the main riser has an air release valve fitted at
c
the highest point

B Foam System Piping

Ensure that hydrostatic test has been successfully


a
completed
Ensure that Piping layout and size are as per approved
b
design
Ensure that Hanger and support space interval are as per
c
approved design
Ensure that Mains and cross mains have one hanger
d
between each branch lines at the end of the main

e Ensure that Pipes painted are as per approved design

C Foam System Sprinkler

Ensure that hydrostatic test has been successfully


a
completed
Ensure that Proper type and temperature sprinklers are
b
used
Check that the minimum distance of sprinkler head from
c
wall are as per approved design
Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM

Document No LPS-01-HTI-MST-ME-032
Rev. No. 0

SYSTEM OPERATIONAL TEST FOR SPRINKLER SYSTEM


Project: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
Request for Inspection / Testing No. Date:
Location /Area:
Status
Item No. Activities / Items to be inspected Not Remarks
Accepted
Accepted

Check that the Sprinkler heads are not painted or


d
covered
Ensure that Cover plates and retainer assembly are fitted
e
to concealed pendant sprinkler

Remarks

HBK/FG Site Engineer HBK Inspector CDC HEXATECH QA/AC

Name Name Name Name

Position Position Position Position

Signature Signature Signature Signature


Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

21/May/20
Document Title CHECKLIST FOR INSTALLATION Date 23
TESTING & COMMISSIONING FOR FOAM SYSTEM

Document No LPS-01-HTI-MST-ME-032
Rev. No. 0

INSTALLATION OF PIPES & FITTINGS


Project: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
Request for Inspection / Testing No. Date:

Contractor: Discipline: Mechanical Electrical

Status
Item No. Inspection / Check Point Not Remarks
Accepted
Accepted

Check the material used for installation as per approved material


1.
submittal, project specification, code & standard

Check the installations and location are as per approved detail


2.
shop drawings.

3. Ensure that all fins and burrs are removed.

4. Ensure that lubricant is applied only for male threads.

5. Check the elevation, orientation, alignments are correct.

Check that the installation of pipes & fittings is securely


6.
supported.

7. Check the installation and quality of workmanship is acceptable

Remarks:

HBK/FG Site Engineer HBK Inspector CDC HEXATECH QA/AC

Name Name Name Name

Position Position Position Position

Signature Signature Signature Signature


Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM

Document No LPS-01-HTI-MST-ME-032
Rev. No. 0

INSTALLATION CHECKLIST
Project : 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
Request For Inspection / Testing No. Date:

Contractor:

Discipline: Mechanical Electrical

Status
Item No. Inspection / Check Point Remarks
Not
Accepted
Accepted

Ensure that the equipment’s, materials size and schedule are


1.
within accordance of approved material submittal.

2. Ensure that the installation of pipes is securely supported.

Ensure that the installation of pipes, fittings and supports as


3.
per approved drawing.

Ensure that the Electrical Equipment for Foam Fire Suppression


4. System is installed as per approved drawing and manufacturer
instruction.

REMARKS:

HBK/FG Site Engineer HBK Inspector CDC OTHERS

Name Name Name Name

Position Position Position Position

Signature Signature Signature Signature


Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

Document Title CHECKLIST FOR INSTALLATION Date


TESTING & COMMISSIONING FOR FOAM SYSTEM

Document No LPS-01-HTI-MST-ME-032
Rev. No. 0

ALARM CHECK VALVE ASSEMBLY INSTALLATION CHECKLIST

Project: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS


Request for Inspection / Testing No.
Date:

Location /Area:
Status
Item No. Inspection / Check point Not Remarks
Accepted
Accepted

Check the material used for installation as per approved


1. material submittal, project specification ,code and standard

Check if the installation and location are as per approved detail


2. shop drawing and method statement.

Check the elevation, orientation, alignment are correct.


3.

Check that the installation of pipes is fixed properly.


4.
Check the installation is free from any clashing with other
5. services.

Check the installation and quality of workmanship is


acceptable.
6.

Remarks

HBK/FG Site Engineer HBK Inspector CDC

Name Name Name Name

Position Position Position Position

Signature Signature Signature Signature


Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS

21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM

Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
SPRINKLER HEAD INSTALLATION CHECKLIST
Project:2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
Request for Inspection / Testing No.
Date:

Location /Area:
Status
Item No. Inspection / Check point Not Remarks
Accepted
Accepted

Check the material used for installation as per approved


1. material submittal, project specification ,code and
standard

Check the installations and location of sprinkler heads


2. are as per approved detail shop drawings and method
statement.

Check if the elevation, orientation, alignment are


3.
correct.

Check that the installation of pipes is securely


4.
supported.

Check the hanger and support shall be spaced at


5.
interval as per approved drawing.

Check the installation is free from any clashing with


6.
other services.

Check the installation and quality of workmanship is


7.
acceptable.
Remarks:

HBK/FG Site Engineer HBK Inspector CDC OTHERS

Name Name Name Name

Position Position Position Position

Signatur Signature Signature Signature


e