Lps-01-Hti-Mst-Me-032 - Method Statement For Foam Fire Fire Supression System
Lps-01-Hti-Mst-Me-032 - Method Statement For Foam Fire Fire Supression System
Revision History
1. PURPOSE .......................................................................................................................... 3
2. SCOPE ............................................................................................................................... 3
3. REFERENCES ................................................................................................................... 3
4. ABBREVIATIONS .............................................................................................................. 3
5. RESOURCES ..................................................................................................................... 3
6. RESPONSIBILITIES .......................................................................................................... 4
7. SEQUENCE OF ACTIVITIES ............................................................................................. 5
8. QUALITY .......................................................................................................................... 18
9 HSE ISSUES, RISK ASSESSMENT AND HAZARD ANALYSIS .................................... 19
10 ATTACHMENTS .............................................................................................................. 19
1. PURPOSE
The Purpose of this Method Statement is to establish the necessary guidelines for the
Deluge Foam Fire Suppression System installation, testing, and commissioning in
accordance with the contract requirements.
This Method Statement will also ensure that the materials are installed safely.
2. SCOPE
This method statement is for the Deluge Foam Fire Suppression System Installation,
Testing, and Commissioning for 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS project
3. REFERENCES
Project Specification.
Qatar Construction Specification and QCDD
NFPA 16 & 25 Standard
Approved System Design Calculations
Approved Material Submittal for Deluge Foam Fire Suppression System
Approved Deluge Foam Fire Suppression System Plan Layout and Shop Drawing
4. ABBREVIATIONS
5. RESOURCES
5.1 Equipment
5.2 Manpower
Project Manager
Project Engineer
HSE Officer
Foreman
5.3 Material
All materials and equipment of the Foam Fire Suppression System shall be in
accordance with the approved material submittal.
6. RESPONSIBILITIES
6.1 Project Manager
In overall, the Project manager will be responsible in project execution and ensuring
quality and safety in all the activities. Also, maintaining the planning progress and
coordination of works with the main contractor.
Project Engineer is responsible for ensuring the project is fit for the purpose and
adheres to the project budget and schedule. Ensuring all relevant safety objectives
and legal requirements are observed and accounting for engineering tasks to ensure
they meet the contract requirements. project Engineer will develop project specific
procedures for the work to be carried out. Interpreting client’s requirements,
identifying and addressing design parameters and engineering problems and
ensuring solutions are implemented. Ensuring all justifications for contractual
variations during project is maintained to support subsequent commercial claim.
Evaluating, organizing and prioritizing work within the overall project schedule.
Project Engineer will be directly reporting to project manager.
6.3 HSE Officer
HSE Officer is responsible for the overall Health and Safety aspects on site as per
managing contractor requirements.
6.4 Foreman
7. SEQUENCE OF ACTIVITIES
b. Check the project documents like materials submittal, Method of statement, ITP,
Shop drawings, Calculation, etc. are approved by the Engineer / Consultant.
c. All installation materials are available and have been inspected and approved by
the Engineer/consultant.
e. Check and confirm that the plinths were cast in accordance with the approved
construction drawings.
f. Scaffolding required for installations is correctly built, safe, and appropriate for the
purpose.
g. The location has temporary lighting and a power source, and the protection settings
are correct.
j. Check to see if pipe sleeves are installed or if a pipe sleeve is intact or inserted in
the Deluge Foam Fire Suppression Pipe where a wall is expected to cross.
Ensure that the cutter, reamer, and die head are all swung to the UP position.
Turn the carriage hand wheel to bring dies against the end of a pipe. Continue
applying pressure to the hand wheel to start dies.
When the desired thread length is reached, depress the release handle to
discharge the latch, and the Die head will open automatically.
Release the footswitch and turn the carriage hand wheel clockwise to back
the die head off.
Lift the pipe with your hands or other equipment, such as a pulley block or
chain block, and place it on one side of the stand, inserting it between the
grooving upper and lower rollers.
Apply the hydraulic pressure to the grooved wheel until it reaches the
specified depth.
Pipe Preparation
Check pipe end for proper groove dimensions and assure that pipe end is
free of indentations and projections that would prevent correct sealing.
Lubricate Gasket
Check the gasket to be sure it’s compatible with the intended service
Apply thin lubricant to the outside and seal the lips of the gasket.
Gasket Installation
Slip the gasket over one pipe, and make sure the gasket lip does not
overhang the pipe end.
Alignment
After aligning two pipe ends, pull the gasket into position, centering
between the grooves on each pipe.
The gasket should not extend into the groove on either pipe.
Housing Installation
Remove one bolt & nut and loosen the other nut. Place one housing over the
gasket, and make sure the housing keys fit into the pipe grooves.
Swing the other housing over the gasket and into the grooves on both pipes.
Tighten Nuts
Firstly, hand tighten nuts and ensure that the bolts are completely fit into the
bolt hole.
Then securely tighten the nuts alternatively and equally to the specified bolt
torque using a spanner.
CAUTION:
Proper torque of the bolts is required to obtain specified performance.
Overtightening the bolts may cause damage to the bolt and/or casting,
resulting in pipe joint separation.
Warning: Do not make adjustment to grooved products while the piping system
is under pressure
Pipe Preparation
The preparation of the pipe is the first step in the installation process. Pipe
preparation is essential for sealing and performance.
During the outlet hole cutting process, the pipe must be supported. Make
a mark on the pipe at the location of the specified outlet hole.
Check to ensure that the proper hole saw is being used to cut the proper
sized outlet hole at the specified location on the pipe.
The outlet hole must be drilled in the center and perpendicular to the pipe's
centerline. Improperly cut outlet holes may prevent the locating collar from
being fully inserted and the product from sealing on the pipe surface.
Remove any burrs and sharp edges from the outlet hole. Leftover burrs or
sharp edges could affect the engagement of the locating collar, flow from
the outlet, or sealing of the gasket.
Verify that the pipe surface within 5/8 inch / 16mm of the outlet hole is
clean, smooth, and generally free from indentations and/or projections that
could affect gasket sealing.
Gasket Installation
Insert the gasket into the outlet housing and ensure the tab in the gasket
line up with the tab recesses in the housing.
Align outlet housing over the pipe hole and ensure that the locating collar
is in the pipe hole.
Alignment
Align the strap around the pipe, insert the bolts and tighten the nuts finger
tight.
Tighten Nuts
Firstly, hand tighten nuts and ensure that the bolts are completely fit into
the bolt hole.
Then securely tighten the nuts alternatively and equally to the specified
bolt torque using a spanner.
Assembly Completed
There should be even gaps on two sides between upper and lower
housings.
CAUTION:
Proper torque of the bolts is required to obtain specified performance.
Overtightening the bolts may cause damage to the bolt and/or casting,
resulting in pipe joint separation.
Identify the actual location of the hanger based on the approved shop drawing.
Mark the position for installing the drop-in anchor.
Check the hanger size to confirm the depth of the hole to be drilled based on
approved shop drawings and the manufacturer’s specifications. Adjust the
depth gauge so the anchor will be flush with the base material surface.
Check the hanger size to select the right drill bit. Then drill the hole according
to the manufacturer’s specification on the marked position.
Clean the drilled hole to ensure it is free of dust.
Hammer down the conical plug inside the anchor with a setting punch.
Identify the actual location of the hanger based on the approved shop drawing.
Mark the position for installing the drop-in anchor.
Install Hanger Rod based on the pipe size. Install the hanger rod to the drop-
in anchor.
Tight the bolts and nuts that hold the hanger rod and hanger evenly.
Confirm the valve size and location based on the shop drawings. Ensure that
the selected valve is screw-type.
Place the valve between the pipes and make sure the threads are free of dust.
Guide one of the pipe ends into the valve’s thread, slowly run pipe in clock-
wise direction.
Hold the valve firmly by a spanner on the flat nearest joint and then rotate the
pipe with a plumbing wrench. Rotate the pipe until the end of the spindle-
operating joint. Repeat the above steps for the other pipe.
Confirm the valve size and location based on the shop drawings. Ensure that
the selected valve is flanged type.
Place the valve between the pipe flanges. Make sure the flange and adjacent
pipework are clean of dirt.
Choose the gasket size based on the valve size and associated pipe size as
specified in the approved shop drawings, so that it can fit the pipe work flange.
Connecting the valve with the pipe flange. The pipe flange shall be square with
the associated pipeline.
Install the bolts into the holes once the valve is in the proper position. Tighten
the nuts one at a time, evenly. Repeat the previous steps for the other joint.
Check the pipe length required based on the approved shop drawing.
Mark and cut the pipe to the desired length with a hacksaw or pipe cutting
machine. Check that the pipe is parallel to the hacksaw or machine blade cut.
Thread the pipe in the threading machine as directed. Check that the pipe
thread is in good condition.
After threading, remove the oil from the pipe end and wrap it in jute.
a. Check that the sprinkler head is in accordance with the approved materials list and
that the sprinkler head location, positions, and spacing are consistent with the
approved shop drawing.
b. Sprinklers shall be positioned to provide area protection consistent with the overall
objectives of this standard by controlling sprinkler positioning and allowable area of
coverage.
e. Make sure the threaded fitting and sprinkler tee joint are dust-free.
f. To prevent leaking, wrap Teflon tape around the sprinkler head's threaded joint.
g. Install the sprinkler head and dropper pipe threaded joint. Then, using a wrench,
tighten the sprinkler head into the threaded fitting.
b. Check the tank system connection to be sure nothing is obstructing the inlet passage
way.
c. Set tank in place and pipe system connection to system. Be sure to include isolation
valves and drain.
d. Ensure the isolation valves, drain, bolt & nuts are properly fixed.
a. Examine and confirm that the area is ready for the installation of devices and
equipment.
b. Based on the shop drawings, confirm the valve size and location.
c. Fabricate the Pipe to the desired length and the appropriate connection.
d. Place the valve into the grooved/flanged end pipes. And ensure that the
grooved/flanged and adjacent pipe work is dirt-free.
e. Select the rubber coupling size based on the valve size and associated pipe size as
specified on approved shop drawings, so that it can fit the grooved pipe.
b. The alarm valve must be installed in a readily visible and accessible location
and provision to be made in such a way that alarm line drain is visible and
accessible.
c. Where water pressure fluctuates, the variable pressure trim with retard
chamber must be used. Under non-fluctuating water pressure condition, the
constant pressure trim, which does not include retard chamber, may be used.
d. The valve must be installed with trim in accordance with the trim data. Failure
to follow the appropriate trim connection guidelines may prevent the device
from functioning properly as well as void listing, approval and the
manufacturer’s warranty.
e. Care must be exercised while installing the check valve in the trim to ascertain
that they are located with the arrow mark on the check valve body and pointed
in proper direction.
g. The ball valve provided on the alarm line must be kept open and strapped in
set position.
h. Pipe connecting the retard chamber and sprinkler alarm bell must be
supported properly to avoid loading on the retard chamber.
i. All the newly installed system pipes must be flushed properly before alarm
valve is put into service.
7.5.2 Installation of Sprinkler Water Motor Gong
a. Locate and cut a hole through the building wall to accommodate a 20NB
(3/4”) pipe with coupling (galvanized pipe to be supplied by the installer). The
required length of support pipe is equal to the thickness of the wall minus 30
millimeters. The pipe is to be threaded with standard 20NB (3/4”) pipe
threading on both the ends to a length of 20 millimeters. Cut the drive shaft
length, equal to the wall thickness plus 43 millimeters.
b. Insert one end of the drive shaft into the square hole provided in the impeller
of the Sprinkler Alarm gong assembly. One end of 20NB (3/4”) support pipe
is to be screwed to the coupling provided with the assembly and the other
end of the pipe is to be screwed to the housing of the Sprinkler Alarm motor
assembly as shown in the figure. Position this assembly against the building
wall through a washer with the support pipe extending through the wall.
c. Connect the alarm port of the Alarm Valve or Deluge Valve to the inlet of the
Sprinkler Alarm assembly with 20NB (3/4”) pipe, with proper support. A 20NB
(3/4”) strainer is to be provided as close as possible to the Sprinkler Alarm
assembly.
d. Move to the other side of the wall, place protection cover on to the pipe
coupling (screwed to the pipe) and hold against the wall. Insert the bush
(assembly with drive shaft adaptor) into the hole provided in the protection
cover and thereby hand tighten the coupling extending through the wall.
Make sure that the drive shaft is properly fitted in the square hole of impeller
and drive shaft adaptor. This can be ensured by rotating the drive shaft
adaptor. The drive shaft adaptor should rotate without any binding while
tightening the bush. If any binding is noticed then unscrew the bush and refit.
After ensuring that the drive shaft is properly placed in the square holes at
both ends, wrench tight the bush.
e. Place the gong over the gong post with washers as shown in the cross-
sectional drawing and hand tighten the dome nut, rotate the gong until the
lettering is properly originated. Wrench tighten the dome nut.
f. Connect the 25NB (1”) open drain pipe to the motor housing, taking due care
that the drain discharge is running to a safe location and keep it free from
obstruction.
a. Special Note: For system protection, on valve sizes 1-1/2" thru 8" a minimum
1/2" pressure relief valve is to be installed downstream (system side) of the
Pressure Reducing Valve. Adequate drainage of the relief valve discharge
must be provided. The relief valve should be set above the “no flow” or “dead
end” shutoff pressure which is recommended at 5 to 10 psi higher than the
PRV set pressure for 1-1/2" thru 8" valve sizes and 2 psi for 10" and 12"
valve sizes.
b. Allow sufficient room around the valve assembly to make adjustments and
for disassembly.
c. It is recommended that isolation valves be installed on both ends of the PRV
valve to facilitate isolating the valve for start-up, testing and preventative
maintenance.
1. Upon initial start-up and after any valve servicing, it is necessary to follow
these steps.
4. Slowly open the upstream isolation valve enough to allow the valve and
pilot control system to fill with liquid.
5. Bleed air from the main valve (1) cover and pilot system by slightly
loosening fittings or plugs at all high points until a steady flow of water is
observed retighten. It may be necessary to do this more than once.
7. Slowly open the downstream isolation valve part way to establish a low
flow rate.
Optimum valve performance occurs when pressure setting is done with flow
rate as low as practical.
8. Adjust the CRD Control (3) to desired pressure. To change pressure set-
ting, turn the adjusting screw in (clockwise) to increase delivery pressure.
Turn the adjusting screw out (counter-clockwise) to decrease delivery
pressure. The pressure should change approximately 27 psi per turn.
Only slight changes in adjustment should be made to avoid damage to
equipment. When the desired setting has been made, tighten jam nut and
replace cover.
9. For 1-1/2" thru 8" Pressure Reducing Valves the downstream pressure
relief control recommended set point is 2-8 psi above the CRD (3) set
point. For 10" and 12" Pressure Reducing Valves the recommended set
point is 2 psi above the CRD (3) set point. The relief valve for the 10" and
12" PRV should be installed a recommended minimum 6 pipe diameters
downstream of the PRV.
NOTE: The “no flow” or “dead end” shutoff pressure will be 5 to 11 psi
above the set pressure.
a. Examine and confirm that the area is ready for the installation of devices
and equipment.
b. Confirm the valve size and location based on the shop drawings.
c. Fabricate the Pipe to the desired length and the appropriate connection.
d. Place the valve between the grooved pipes. Make sure the grooved and
adjacent pipe work is clean of dirt.
e. Select the rubber coupling size based on the valve size and associated pipe
size as specified on approved shop drawings, so that it can fit the grooved
pipe.
f. Join the valve and the grooved pipe. The grooved pipe must be parallel to
the associated pipeline
Test Instruments
To carry out the required tests, the following test instruments must be used:
1. Pressure Gauges
2. Manifolds
3. Pressure Pump (for pressure test)
Safety will be a major factor during pressure testing to ensure a safe working
environment for all the site personnel and to safeguard plant and equipment.
Prior to commencement of test, toolbox talk will be given to all personnel
identifying the potential dangers of pressure testing and to make everyone
aware that testing is ongoing in the area.
7.6.2 Testing Procedure
c. All test equipment’s (test pumps, manifolds, gauges etc.) will be inspected
prior to use to make sure they comply with the site safety requirements. All
gauges shall have a valid calibration certificate available for inspection.
Generally, two gauges will be provided per test, one at the high point possible
and one at the lowest point possible.
e. Prior to introducing water into the system, all piping installations shall be
checked thoroughly for tightness.
g. The piping shall be hydrostatic tested in a closed circuit for a period of 2 hours
at 200 psi (13.8 bar) in excess of the system working pressure, whichever is
greater, and shall maintain that pressure without loss for 2 hours.
i. Prior to testing, a demarcation area will be taped off and warning signs placed
prominently, stating that hydrostatic testing is in progress.
j. These demarcation areas will be on entry areas for all personnel with the
exception of testing inspectors and test personnel. The demarcation area
limits may vary greatly in relation to hydrostatic testing that is in progress.
Ensure all work permit and tools needed for the required piping flushing are
ready.
Flushing of pipe network shall proceed once the preparation is clear and the
site is satisfactory.
Upon conducting the flushing for any pipe portion ensure that the isolation
valve of the designated pipe is in open position and all other portion is isolated.
Start the flushing by continuously discharge out the clear water starting from
the existing line to the flushing point by maintaining the required flow.
Ensure that the system shall be flushed until the water is visually clear and
ensure that the flushed water is free from foreign objects/debris.
Close the flushing valve of the completed pipe portion then proceed the next
one and conduct flushing for all the remaining designated flushing point as per
the same procedure.
Ensure that the discharge water is being drained properly to the nearest
drainage available in the area.
Ensure proper housekeeping before leaving the activity area, all tools and
equipment’s are on proper place.
Enough draining points will be left for this purpose. These points will be the
lowest point of the area/zone and the water supply point.
The water will be pumped into the water supply point using the existing fire
pumps and/or any external adequate water supply meeting the flow
requirement as stated in the below table and the lowest points will be
connected to the nearest drainage facility via hose.
The pipe network will be flushed to ensure that the pipes are clear from debris
and other residual materials. Flushing will be continued until clear water at the
drainage side is observed.
Pipeline flushing should preferably be done from the highest to the lowest
elevation.
Flushing should be performed through fully open flanges/ open pipe ends and
never be carried out through smaller openings such as drains or vents.
The proper capacity of the pump and/or adequate water supply shall be
selected for pipe flushing activity.
All required temporary fittings like a hose, blind flange, strainer, gasket, etc
must be fitted before flushing and shall be removed immediately after
completion of pipe flushing.
1) Visual Inspection
A. Main Riser
Ensure that the Piping layout and size are as per the approved design.
Ensure that the hanger and support space intervals are in accordance
with the approved design.
Ensure that the Mains and cross mains have one hanger between each
branch line at the end of the main.
Ensure that the Pipes are painted are in accordance with the approved
design.
C. Foam System Sprinkler
Ensure that the proper sprinkler type and temperature are used.
Ensure that the minimum distance of sprinkler head from wall are as
per approved design.
FIRST STEP:
Collect a little amount of water from the Test Valve in a small cup and insert
the Conductivity Meter into it and get the reading.
Determine the conductivity of the water at 2% of foam. For this you have to get
98-gram water and
2 grams of foam from the foam tank and mix well (5 to 10 seconds)
In that mixture insert the Conductivity Meter and get the reading/result
Determine the conductivity of the water at 3% of foam. For this you have to get
97-gram water and 3 grams of foam from the foam tank and mix well.
In that mixture insert the Conductivity Meter and get the reading/result
8. QUALITY
All inspection requested must be properly documented for future references and to be
witnessed and approved by main contractor qa/qc engineer.
Installation activities will follow as per the approved Inspection Test Plan.
9 HSE ISSUES, RISK ASSESSMENT AND HAZARD ANALYSIS
Responsible Health, Safety and Environment Officer of the project will conduct
routine HSE inspections.
Safe access and egress to and from the work place shall be provided by the main
contractor.
Risk assessments for the installation of Fire Fighting System have been attached to this
method statement and related to the risks and associated hazards related to the activity.
10 ATTACHMENTS
10.3 Checklist
10.1 Risk Assessment
Project Name: 2B+G+6 LA PLAGE SOUTH 1 RESIDENTIAL BUILDINGS
Document Title Risk Assessment for Installation, Testing & Commissioning of Foam system Date 21/05/2023
Document No. LPS-01-HTI-MST-ME-032 Rev. No. 0
Contractor: HBK Contracting Company Employer: Sheik Ali Bin Hamad Bin Khalid Al-Thani
Note: Where the Hazard Rating remains High after control measures have been identified the work must not
RISK / IMPACT ASSESSMENT
be started and the HSE department contacted for further advice.
MATRIX
Where the Hazard Rating remains High after any additional control
HAZARD RATING measures have been identified the work must not be started and the
HSE department must be contacted for further advice.
Likelihood
Severity
Rating 15 – 25 High -H 3 – Likely 3 - > 3 days 3 – Minor impact 3 3 6 9 12 15
Contractor
Assessed by: Reviewed by: Approved by:
Name: Name: Name:
Construction Project HSE Manager Project Manager
Signature: Signature: Signature:
11 Painting of Pipes Hazard such as: Discuss the hazards of the 3 4 12 Make sure the floor is 3 1 3
Fume Exposure chemical in the toolbox talk; even and stable. Avoid
Working at Height refer to MSDS. wet and slippery
Provide additional ventilation surfaces.
to direct the fumes away to Always support the
Risk such as: the painter. ladder at four points.
Respiratory, eye and Wear the appropriate gloves, Keep your shoulders
skin irritation solvent-resistant chemical between the rails and do
Serious physical injury and anti-fume mask and not over-reach – move
or fatality due to Fall goggles. the ladder instead.
from height Inspect the ladder; take time Be prepared for an
to check the condition of the unforeseen vertigo attack
ladder both before and after – do not look down,
use. breath slowly and
Check that the ladder is steadily, and go back
sufficiently robust to support down systematically.
your weight. Ladders should be used
Make sure the steps are free for short duration-low risk
of oil, wet paint, mud or any activities only. Otherwise,
other potentially slippery safe working platform
substance. shall be provided.
If the ladder needs to be in Clear the area around the
the front of the door, ladder from any clutter.
consider locking the door to
prevent surprise opening.
Foam System Installation Hazard such as: Ensure that the scaffolding is 3 4 12 Secure all the tools and 2 1 2
Working at Height properly erect and inspect by materials in the working
competent personnel. platform.
Risk such as: Fall prevention must be in Maintain the orderliness
Fall from height can place prior commencing of in the platform, avoid
cause serious physical activities. loose material that can
injury or fatality Alteration on the scaffolding fall when tap.
Falling object can must only be execute by Provide rope when
cause serious physical competent scaffolding bringing up or lowering
injury or fatality erectors. tools or materials.
Caster wheel of mobile Barricading the working
scaffold must always be area and do not allowed
locked especially on an even anyone to pass beneath
ground. the working platform.
Ladders should be used for
short duration-low risk
activities only. Otherwise,
safe working platform shall
be provided.
12 Installation of Fire Alarm & Hazard such as: Inspect the ladder; take time 3 4 12 Always support the 3 1 3
other devices Working at Height to check the condition of the ladder at four points.
Working on Ladder ladder both before and after Keep your shoulders
use. between the rails and do
Risk such as: Check that the ladder is not over-reach – move
Fall from height sufficiently robust to support the ladder instead.
Fall from Ladder can your weight. Be prepared for an
cause Minor to Serious Make sure the steps are free unforeseen vertigo attack
Physical Injury of oil, wet paint, mud or any – do not look down,
other potentially slippery breath slowly and
substance. steadily, and go back
down systematically.
Clear the area around the
ladder from any clutter.
13 Cable Pulling Hazard such as: Ensure that the scaffolding is 3 4 12 Caster wheel of mobile 3 1 3
Working at Height properly erected and scaffold must always be
inspected by competent locked especially on an
Risk such as: personnel. even ground.
Fall from height Fall prevention must be in If using ladder, ensure
place prior commencing of that the ladders are
activities. appropriate for the work
Alteration on the scaffolding and erected rigidly.
must only be execute by
competent scaffolding
erectors.
Installation of Foam Hazard such as: Lorry truck operator, lifting 3 4 12 Ensure that the 2 1 2
Generator Lifting gears and truck certified by scaffolding is properly
Tip-over third party. erected and inspected by
Working at Height Lifting plan permit must be competent personnel.
Working on Ladder acquired prior the activity. Fall prevention must be in
Position the lorry truck in a place prior the
Risk such as: manner to avoid striking any commencing of activities.
Fall from Ladder can objects or person. Alteration on the
cause Minor to Serious Ensure barriers to prevent scaffolding must only be
Physical Injury people entering swing executed by competent
Falling object can radius. scaffolding erectors.
cause serious physical Installation of generator shall Caster wheel of mobile
injury or fatality be in accordance of scaffold must always be
manufacturer’s locked especially on an
recommendation. even ground.
Strictly implement the pre- Ladders should be used
inspection of the plant and for short duration-low risk
equipment prior to using, activities only. Otherwise,
make sure third-party safe working platform
certification copies are with shall be provided.
the operator.
Set the brakes, position the
outriggers devices on pads
or similar solid surface and
install the wheel chocks prior
lifting.
TESTING AND COMMISSIONING
14 Cable continuity and Hazard such as: Permit to work system is 4 3 12 Isolate the item being 4 1 4
Resistance Exposure to Electricity secured. (advance notice to checked from the
the permit issuer) circuitry, if possible
Risk such as: Toolbox talk is conducted to Ensure proper PPE are
Electrocution or shock operatives involved prior to provided to all operatives
starting the activity. Never touch the test lead
De-energize and discharge while the megger is being
the circuit completely before used.
connecting a megger.
15 Activation of Any Detection Hazard such as: Permit to work system 3 3 9 Ensure that the water 3 1 3
System in Crossed Zone Exposure to high levels should is secured. (advance coming from the system
Circuit of Noise notice to the permit issuer) will be collected in an
Toolbox talk regularly appropriate container if
Risk such as: conducted to operatives the drain is not available.
Hearing Loss involved prior to starting the Activities must be
Physiological effects activity. coordinated to all
Work related stress Segregating the devices subcontractors that may
Property damaged. under test. be affected by this
Person who doing the activity.
task i.e. Supervisor, All operatives should be
provided by suitable
PPEs.
16 Pneumatic Testing Hazard such as: Permit to work system 4 3 12 Conduct testing possibly 3 2 6
(Puff Test) Exposure to High should be secured. (advance at night or in a weekend
Pressure notice to the permit issuer) when few people are
Toolbox talk should be near the test site..
Risk such as: conducted to operatives Conduct testing possibly
Serious physical injury involved prior to starting the at night or in weekend
and damage to activity. when few people are
property Maintaining test connectors, near the test site.
ensure that it is well secured
or tightened.
Assign personnel from
exclusion zone (an area
where unauthorized
personnel are prohibited to
enter) surrounding the piping
system under test.
COVID-19
17 Transportation of Hazard such as: Vehicle seat capacity 3 3 9 Ensure “Etheraz” status 2 2 4
Personnel at Site Failure to follow reduced to 50 % to get is green prior to entering
physical distancing enough spacing to follow the vehicle and the site.
protocol physical distance protocol. Cover cough or sneeze
Personnel maintaining a by tissue paper or cloth.
Risk such as: distance of 1.5 meters. Sanitize your hands
Symptoms related to All personnel must wear wherever possible,
COVID-19 (fever, colds mask while travelling to site. including entering and
and respiratory Ensure the windows are leaving buildings.
problems) open to allow proper
ventilation.
18 Working at Site Hazard such as: Temperature monitoring in 3 3 9 Regularly clean and 2 2 4
Failure to follow place. disinfect surfaces that
COVID-19 safety Adequate supervision to many people touch.
precautions at the site monitor the personnel. Limit food handling and
Stop integrating with other sharing of food in the
company personnel. workplace.
Risk such as: Stay at home unless going Eat healthy! Bring your
Symptoms related to out is absolutely necessary. lunch to work and eat at
COVID-19 (fever, colds Stop visiting others rest your desk, or away from
and respiratory areas. others.
problems) Stop shaking hands to greet Ensure “Etheraz” status
others. is green prior to entering
Hold essential meetings the vehicle and the site.
outside in the open air if
possible.
Promote good hand, sneeze
and cough hygiene.
OTHERS
19 General Hazard such as: Check all Tools, don’t issue 3 2 6 Employees shall be 2 1 2
Usage of Defective defective Tools ensured that their tools
Tools and Greasy Keep the Tools clean and are in good condition and
Tools free from any lubricants, like if a defect is observed,
Oil, Grease etc. then it must be replaced.
Risk such as:
Physical injury No Improvised tools shall be All Tools and Equipment
use. must be properly stored.
20 Working under unfavorable Hazards such as: Hot Season 4 4 16 Hot Season 4 1 4
weather conditions Working under hot Strict monitoring and Provide intermittent rest
weather / high humidity. supervision during extreme hot
Working under foggy Heat index chart / MOL climate and procedure of
weather, regulation to be maintained. work in confined space
Exposure of materials Adequate rest and rotation will be ensured.
to extreme weather to be maintained. Report physical unwell to
Activities to be scheduled as immediate supervisor/first
Risk such as per prevailing weather aider/male nurse.
Heat stress / condition. Communication of site
exhaustion / stroke Weather monitoring chart to emergency procedure
Hypothermia be monitored effectively. and heat stress
Faintness / dizziness Emergency procedures and prevention management
Heat rash preparedness to be through tool box talk.
Discomfort (nausea/ communicated to all Materials to be protected
vomiting workers. (Emergency from UV rays
contacts to be displayed) Cold Season
Hourly monitoring of heat Wear a hat, mittens or
stress and recording. insulated gloves.
Provision of adequate Keep your face warm
drinking water/ice/glucose in with a scarf, neck tube or
working location. facemask.
Personnel body temperature Wear warm and
to be monitored. waterproof footwear.
Winter jackets to be When it is very cold, or
provided if work is to be when the wind chill is
executed under extremely significant, cover as
Cold Season much exposed skin as
Workers to be advised to possible.
take warm water when Moisturizing your skin
necessary. with a cold cream or
Strict monitoring of health petroleum jelly.
condition of workers.
21 Housekeeping Hazards such as: Train and inform the 3 3 9 Remind the concerned 3 1 3
Exposure to Sharp operatives the content of the operatives to segregate
Objects dust generated in the work waste collected in
Exposure to Dust and site and the diseases that it assigned bins or skips
Chemicals
will cause if it enters the (labeled the bins or
Risk such as: body. skips).
Cut, laceration or Wetting the dust or ground Use appropriate tools and
amputation before sweeping. equipment for collecting
Respiratory, eye, skin Use vacuum instead of waste.
irritation broom. Ensure that the
Controlled disposal of temporary collected
dangerous waste. wastes are regularly
Provide appropriate mask to removed in the
all operatives. workplace.
Provide appropriate
gloves to all operatives.
All preventive action must be taken as per legal requirements, Activity in charge is responsible to ensure that all control measures are in place as per
international standards and client procedure. He has the authority to stop any activity if observed any potential HSE issues that lead to accident, incident or
potential Near Miss.
10.2 Inspection & Test Plan
Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
INSPECTION AND TEST PLAN FOR INSTALLATION
Document Title Date
TESTING & COMMISSIONING FOR FOAM SYSTEM 21/May/2023
LPS-01-HTI-MST-ME-032
Document No Rev. No. 0
Revision History
Contractor
Contractor
Checking
3rd Party
# Works Tolerances (if applicable) Responsible Required
Sub-
CSC
Activity to Job Function Frequency
be
Performed
1.0 DOCUMENTATION
1.1 Review Project Specification Approved Method statement. Site Engineer For Review and R R R N/A Project
Verify the QCS-2014 Specifications
Approval before
approval of NFPA Standards Material
proceeding the
method Material Submittal Submittal
works NFPA Standards
statement
QCS
Specifications
2.0 STORAGE CONDITION OF MATERIAL
2.1 Review/ Project Specification Stored in accordance with QC During Material H H W N/A Material
Foam System QCS-2014
Visual manufacturer's Material Safety Storage delivery note
Materials NFPA Standards Data Sheet Material
Material Submittal Certificates,
Material
safety data
sheet
2.2 Review/ Project Specification Visual Inspection/ Delivery Store-in- After material H H W N/A Material
Material Delivery QCS-2014
Visual storage and handling as per Charge / arrived at site Inspection
Inspection NFPA Standards Manufacturer’s Instructions QC Engineer Request (MIR)
Material Submittal
3.0 MOCK UP
3.1 Visual Project Specification Verify the substrate, must Project At the time of H H W N/A WIR shall be
Conduct mock
QCS-2014 match with the UL system / Engineer/Site Mock up
For foam system raised.
Manufacturer Instruction / installation
NFPA Standards Engineer Subcontractor
Engineering Judgement (EJ)
Material Submittal Inspection
Reports.
4 Installation
4.1 Installation of Visual Project Specification Approved Method statement. Site After installation H H W N/A Checklist
Pipes and inspection QCS-2014 And Approved Shop Drawings Engineer/QAQC
Fittings NFPA Standards Engineer
Material Submittal
Approved Shop Drawings
4.2 Installation of Visual Project Specification Approved Method statement. Site After installation H H W N/A Installation
Sprinkler inspection QCS-2014 And Approved Shop Drawings Engineer/QAQC Checklist
NFPA Standards Engineer
Material Submittal
Approved Shop Drawings
4.3 Installation of Visual Project Specification Approved Method statement. Site After installation H H W N/A Installation
Mechanical inspection QCS-2014 And Approved Shop Drawings Engineer/QAQC Checklist
Equipment’s NFPA Standards Engineer
Material Submittal
Approved Shop Drawings
4.6 Installation of Visual Project Specification Approved Method statement. Site After installation H H W N/A Installation
Electrical inspection QCS-2014 And Approved Shop Drawings Engineer/QAQC Checklist
Equipment’s NFPA Standards Engineer
Material Submittal
Approved Shop Drawings
Material Submittal
Approved Shop Drawings
5.4 Foam Conductivity Visual Project Specification As per Approved Method Site Engineer / After Installation of H H H N/A Testing &
Test Inspection / QCS-2014 Statement QAQC Engineer System and Commissioning
Testing NFPA Standards requested for Checklist
Material Submittal
Approved Shop Drawings
Inspection
6 FINAL INSPECTION
6.1 Inspection for Visual Project Specification Contractor /consultant Project Manager/ After completion R R R N/A WIR Shall be
the completed Inspection/ QCS-2014 Inspection Control Sheet QAQC Engineer of Testing & raised.
Foam System as Document NFPA Standards completed for the foam System Commissioning Subcontractor
Material Submittal
per the selected Verification Approved Shop Drawings
works Installation, testing & of the System Inspection
system Commissioning should comply Reports,
/Engineering with QCD Standards and NFPA Approved
Judgement Specifications Drawings,
inspection
standard as
per project
specification
7 COLLATE RECORDS/DOCUMENTS FOR FINAL HANDOVER
7.1 Collation of all Document Project Specification Collect all compliance RFI for all QAQC Engineer During Handing R R R N/A Inspection
Quality Verification QCS-2014 inspected areas and documented Over of the Reports, UL
NFPA Standards for final hand over.
Documents system systems /EJs.
Material Submittal
Approved Shop Drawings
7.2 Inspections from Contractor Project Specification Contractor is responsible for Project During Final H R R N/A Copies of WIR,
authorities Rep. QCS-2014 approval /Inspection from manager Inspection from Work
NFPA Standards authorities and Sub-contractor Authorized completion
Material Submittal shall arrange all required
letter, UL
Approved Shop Drawings documents for this process of the
handing over systems
, QCDD
product
approvals.
10.3 Checklist
Project Name: 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM
Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
Contractor:
Remarks :
21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM
Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
LOCATION:
PIPELINE LOCATION:
MATERIAL TYPE:
NOMINAL DIAMETER:
TYPE OF SERVICE:
TEST
HOLDING TIME:
Remarks
21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM
Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
FLUSHING REPORT
LOCATION:
PIPELINE LOCATION:
MATERIAL TYPE:
NOMINAL DIAMETER:
TYPE OF SERVICE:
TEST:
How flushing flow was obtained: Public Water Tank or reservoir Fire Pump
Through what type opening: Y connection to flange and spigot Open pipe
Remarks:
21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM
Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
1) Visual Inspection
A Main Riser
21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM
Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
Remarks
21/May/20
Document Title CHECKLIST FOR INSTALLATION Date 23
TESTING & COMMISSIONING FOR FOAM SYSTEM
Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
Status
Item No. Inspection / Check Point Not Remarks
Accepted
Accepted
Remarks:
21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM
Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
INSTALLATION CHECKLIST
Project : 2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
Request For Inspection / Testing No. Date:
Contractor:
Status
Item No. Inspection / Check Point Remarks
Not
Accepted
Accepted
REMARKS:
Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
Location /Area:
Status
Item No. Inspection / Check point Not Remarks
Accepted
Accepted
Remarks
21/May/2023
Document Title CHECKLIST FOR INSTALLATION Date
TESTING & COMMISSIONING FOR FOAM SYSTEM
Document No LPS-01-HTI-MST-ME-032
Rev. No. 0
SPRINKLER HEAD INSTALLATION CHECKLIST
Project:2B+G+6 LA PLAGE SOUTH-1 RESIDENTIAL BUILDINGS
Request for Inspection / Testing No.
Date:
Location /Area:
Status
Item No. Inspection / Check point Not Remarks
Accepted
Accepted