Expressions of Interest (EOI) are invited from the reputed organizations having relevant
experience, for
“Engineering, Procurement and Construction Management (EPCM) services for the proposed
pipelines in Golaghat/Jorhat districts of Assam..
Interested parties are requested to submit their EOI in the prescribed format along with all
supporting documents/ credentials.
EOI No AGCL/Tender/Khoraghat/BD/2018/01
Venue of EOI Conference Assam Gas Company Limited,
1st Floor, Adams Plaza, Christian Basti
Guwahati-781005 (Assam)
Date and time of EOI Conference 18th May 2018 at 11.00 AM
Last date of Submission of documents 14th May 2018 before 2:00 pm IST
Address for Correspondence Deputy General Manager (TS),
Assam Gas Company Limited
P.O. Duliajan, Dist: Dibrugarh,
Assam, PIN-786602
Page 1 of 11
I.INTRODUCTION
Assam Gas Company Ltd. (AGCL), is an ISO 9001 : 2008 certified, 56 years old Natural
Gas transmission and distribution company , wholly owned by the Govt. of Assam with its
registered office at Duliajan, Dist : Dibrugarh, Assam 786 602. The company transports
Natural Gas through its integrated pipeline infrastructure to several market segments i.e.
Power, Fertilizer, petrochemicals, Industrial, Commercial and Domestic consumers primarily
located in upper Assam.
The present infrastructure of the company has a transportation capacity of about 6.0
MMSCM of gas per day.
II. OBJECTIVE
Besides other sources, AGCL is collecting and transporting Natural Gas from the gas fields
of ONGCL in Khoraghat region of Golaghat District bordering Nagaland through its 4” NB x
46 km Uriumghat – Golaghat gas pipeline and distributing the same to the consumers of
Golaghat/Jorhat districts of Assam through its network of established pipeline infrastructure.
Page 2 of 11
In this regard, AGCL seeks to invite bona fide and resourceful ‘EPCM services rendering
organisations’ for executing the project right from detailed engineering to Commissioning &
project close out on total and single point responsibility basis.
Note: The terms bidder/ agency / party/ vendor / contractor (Singular / Plural) are used
interchangeably hereto.
III. DISCLAMER
All information contained in this Expression of Interest (EOI) and / or subsequently provided
/ clarified are in good faith and interest. This is not an agreement or contract and is not an
offer or invitation to enter into an agreement of any kind with any party.
Each bidder/consultant should conduct its own investigation and analysis and should check
the correctness, reliability and completeness of the information in this Expression of Interest.
Applicants should make their own independent investigation in relation to any additional
information that may be required.
Assam Gas Company Limited reserves the right to invite only short listed agencies to
participate in the EOI conference. It also reserves the right to accept or reject some or all the
Expressions of Interests without assigning any reason whatsoever.
Page 3 of 11
SN Parameter Description Supporting Documents
Note: The experience of the bidder for EPCM Consultancy Services as per the Technical
requirement above must be of their own and not with the support of another party/parent
company/subsidiary/ partner firm/group firm/Backup Consultant etc.
V SCOPE OF WORK
CONSULTANT’S SCOPE OF WORK
The scope of work is broadly defined under the following heads but not limited to:
A. Detail Engineering.
B. Planning & Scheduling
C. Preparation of all tender documents for all purchases of materials including
pipes as per approval of AGCL
D. Preparation of tender documents for selection of pipeline laying contractor.
E. Preparation of tender document for selection of contractor for installation
of Compressor on BOO basis
F. Issue of all purchase orders and work orders etc.
G. Inspection/ Expediting of equipment/Materials being manufactured by
vendors including contractors supplied items.
H. Management of Construction Stores and Stores Accounting
I. Construction & Supervision.
Page 4 of 11
J. Reporting system
K. Testing & Project Commissioning.
L. Any other work involved up to completion of Project.
The Project completion schedule is 18 (Eighteen) months from the date of issue of
LOI/WO..
4. The whole system needs to be completed considering the latest technology and
international standard, regulations and requirements under the appointed PMC by
AGCL.
Page 5 of 11
EOI conference. Each bidder shall be given 20 minutes time for presentation which shall be
divided as follows:
Sl. No. Items Duration(min)
1 Presentation on the Bidder’s organisation 5
2 Presentation on a completed similar EPCM project 5
3 Bidder is to give a detail presentation on the proposed AGCL 10
pipeline project considering 18 months completion schedule
showing the detail activities under the EPCM contract.
It may be noted that shortlisted bidders are required to send “Letter of Authorization”
permitting their personnel to attend the EOI conference through email at
agcl.projects@gmail.com. The representative also required to carry a hard copy of the
same.
Page 6 of 11
APPENDIX 1
NOTE
Golaghat
Khoraghat GGS, 8” NB, L -12 8” NB, L- 46 Km
Uriumghat
40,000 SCMD
8” NB, L- 5 Km
Nambar GGS,
60,000 SCMD
Page 7 of 11
ANNEXURE-1
Place: Signature :
Designation / Status:
Company Seal:
Page 8 of 11
ANNEXURE -2
Page 9 of 11
ANNEXURE-3
Page 10 of 11
Page 11 of 11