AAS DS with ECI file

1.-Waiting for MW starts.


2.-Download scripts from script release and verify if ECI file is available on ESI
portal.
3.-Perform and send Pre-checks to the market.
4.-When MW starts lock the cells on AAS node using "bls" command to lock the cells
corerctly.
5.-Once AAS is locked please load the ECI file to the AAS node using "cvput
$nodename_ECI_File.zip"
6.-Verify with "cvls" command if the ECI has been uploaded to the AAS node.
7.-Restart the AAS node with the new ECI file "acc+ backup + restore".
8.-When the AAS node came back again, please verify all the information with CIQ
"CLI part" and check if all match according to it.
9.-Enroll, set the Uri, check supervisions and Sync the AAS node.
10.Run interDU scrip on Legacy node.
11.-Lock the cells on Legacy node and perform a restart.
12.-Some times you also have InterDu scripts for anchors if this is the case please
also run it.
13.-According to the market you would have Call Test or not, if you have CT send
AAS to CT and FE must confirm if CT passed.
14.-After CT passed, each market decide if new Digital sectors must be leave locked
or unlocked.
15.-Perform integration charts.
16.-Check VSWR supervision on AAS node and NR or MMBB node.
17.-Perform and Send Post checks.
18.- Close the site.

AAS DS Manually.
1.-Waiting for MW starts.
2.-Download scripts from script release.
3.-Perform and send Pre-checks to the market.
4.-When MW starts lock the cells on AAS node using "bls" command to lock the cells
corerctly.
5.-Run the next script on AAS node
-00_$nodename_Feature_activation.mos
-01_$nodename_Add_L21_2nd_Cell.mos
-02_$nodename_1C2C_relation_noanr_create.mos
-03_$nodename_Cell_Parameter_preservation.mos
-05_$nodename_External_Neighbours.mos.
6.-Perform a restart on AAS node.
7.-When the AAS node came back again, please verify all the information with CIQ
"CLI part" and check if all match according to it.
8.-Run interDU scrip on Legacy node.
9.-Lock the cells on Legacy node and perform a restart.
10.-Some times you also have InterDu scripts for anchors if this is the case please
also run it.
11.-According to the market you would have Call Test or not, if you have CT send
AAS to CT and FE must confirm if CT passed.
12.-After CT passed, each market decide if new Digital sectors must be leave locked
or unlocked.
13.-Perform integration charts.
14.-Check VSWR supervision on AAS node and NR or MMBB node.
15.-Perform and Send Post checks.
16.- Close the site.