Professional Documents
Culture Documents
EC Final Book
EC Final Book
About CMTI
CONSTRUCTION MANAGEMENT TRAINING INSTITUTE (CMTI) is a leading
professional organisation working towards development of Constructional
professionals through Structured training programmes offline and online delivered by
Construction Experts
CMTI is training partner for Various Corporates like Larsen & Toubro, Shriram
Properties Limited, Naredco Karnataka, National Institute of Technical Teachers
Training Institute (MHRD India) Chennai and Civil Engineers Association of
Tamilnadu. CMTI is Proud Member of Association of Consulting Civil Engineers
India, Indian Concrete Institute and Indian Green Building Council
CMTI Civil Engg Connect App has 50+ Self Learning short free and paid courses,
those who don't have time for offline, can learn on your time anywhere at affordable
prices, CMTI Civil Engg Connect app is best rated App for Construction
Management & Interior Courses
CMTI, Bangalore
CMTI, Bangalore
ESTIMATION AND COSTING
CONTENTS
CMTI, Bangalore
ESTIMATION AND COSTING
18 Structural Plans 40 - 53
a Center Line Layout 40
b Excavation Plan 41
c Plinth Beam Layout 42
d Roof Beam Layout 43
e Floating Column C/S 44
f Column & Footing Schedule 45
g Plinth Beam Details 46 - 50
h Roof Beam Details 51 - 52
i Stair Case Details 53
j Joinery details 54
19 Detailed estimate 56 - 69
20 Abstract Estimate 70 - 72
21 Market Rates of Building Materials & Labour 73
22 Rate Analysis ( with Materials & only Labour) 74 - 85
23 Item Rate list ( with Materials & only Labour) 86 - 89
24 Total Costing with Materials & Labour 90 - 96
25 Total Costing with only Labour 97 - 103
26 Materials requirements calculation 104 - 109
27 Budget cost sheet (with materials & Labour) 110
28 Budget cost sheet only Labour 111
29 Abstract of Materials requirement 112
30 Break up cost mile stone wise 113
31 Bar Bending Schedule 114 - 147
a Footing 114 - 115
b Pedestal column 116 - 120
c Plinth Beam 121 - 131
d Roof Beam 132 -139
e Slab 140 - 143
CMTI, Bangalore
ESTIMATION AND COSTING
CMTI, Bangalore
ESTIMATION AND COSTING
Preface
This book consists of examples of estimate on residential buildings & method of preparing
estimate. This book contains bar bending schedule, rate analysis & specification of works.
Engineers & supervisors involved in the construction of building often require information
on planning & estimation in the discharge of work. The basic details and information
provided to help young engineers.
I would like to apologize for any mistakes left inadvertently and will welcome
comment/suggestion of the readers.
This book is general reference guide for normal building estimation work. However for
specialized job one must consult experts,
DISCLAIMER
The data, thumb rule, material methodologies etc., illustrated in this book with a view to for
engineers for checking of various aspects involved in building estimates. The ideologies
briefed in this text book should not be conceived as a complete replacement of actual
engineering design & theory text book.
The author has tried their best to incorporate the latest available information in this book.
This book is sold with the understanding the author is neither responsible for the result of
any action taken on the basis of this work nor any error of omission. Errors and omissions
may kindly be brought to the notice of Author.
Compiled by:
A.V.Muralidharan
Chennai
M.no: 9446591311
avm_20032002@yahoo.com
Visit at:
https://youtube.com/channel/UCGbG0XSmBDRSwQ0yAAG5DRg
https://www.facebook.com/Civil-Engineer-Guide-102976058429526/
No part of this book may be reproduced or transmitted in any form or by any means
electronic, photocopying without prior written permission.
1 CMTI, Bangalore
ESTIMATION AND COSTING
3 Concrete work. M³
4 Reinforcement. Kg
7 Plastering. M²
8 Painting. M²
9 Flooring. M²
10 Skirting. R.M
13 Grills M² or Kg
15 Pointing M²
16 Manholes, Chambers No
18 Retaining walls M³
19 Pointing M²
2 CMTI, Bangalore
ESTIMATION AND COSTING
1 Cement Bag
2 Sand M³ or ft³
3 Aggregates M³ or ft³
4 Earth/Gravel M³ or ft³
5 Stones M³ or ft³
6 Wood M³ or ft³
8 Bricks Nos
9 Reinforcement steel Kg
15 Hardware Nos
19 Wax polish Kg
3 CMTI, Bangalore
ESTIMATION AND COSTING
Abbreviations
4 CMTI, Bangalore
ESTIMATION AND COSTING
5 CMTI, Bangalore
ESTIMATION AND COSTING
RL : Reduced Level
STP : Sewerage Treatment plant
CBR : California Bearing Ratio
PPE’s : Personal Protective Equipments
SHE : Safety Health and Environment
FSI : Floor Space Index
EIA : Environment Impact Assessment
EC : Environment Clearence
CTE : Consent to Establish
CTO : Consent to operate
SPCB : State Pollution Control Board
DPR : Detailed Project Report
CGWA : Central Ground Water Authority
CPCB : Central Pollution Control Board
MB : Measurement Book
TM : Transit mixer
MIS : Management Information System
QC : Quality Control
WBS : Work Breakdown Structure
MOEF : Ministry of Environment and Forest
SEAC : State Environment Assessment Committee
IMS : Integrated Management System
MSL : Mean Sea Level
HFL : Highest Flood Level
R.A Bill : Running Account Bill
BG : Bank Guarantee
SCM : Supply Chain Management
NGL : Natural Ground Level
HSE : Health Safety and Environment
LPD : Litres per day
6 CMTI, Bangalore
ESTIMATION AND COSTING
TECHNICAL TERMS
1. Estimate:
An estimate is the anticipated or probable cost of work and is usually
prepared before the construction is taken up. It is indeed calculation or
computations of various items of engineering work.
The primary objective of the estimate is to enable one know beforehand,
the cost of work (building structure etc).
The estimate is the probable cost of work and is determined
theoretically by mathematical calculations based on drawings and
current rates.
2. Actual Cost:
The actual cost of work is known at the completion of work. Account of
all expenditure is maintained day –day during the execution of work.
And at the end of completion of work the actual cost is known. The
actual cost should not differ much from the estimated cost worked out
at the beginning.
3. Quantity Survey:
It is the preparation of Schedule of all items of work in a building. These
quantities are calculated from the drawing of the Building. It is the
Preparation of BOQ bill of quantity, rates and Cost. It is the
preparation of Budget cost of the building before its start.
4. Specifications:
Detailed specification gives the nature, quality and class of work,
materials to be used in the various parts of work, quality of the
materials, their proportion, workmanship and description of execution
of work of items.
5. Rates:
The rates of various Items of works, materials to be used in the
construction and the wages of different categories of labour (skilled &
unskilled) should be prepared / available for the preparation of estimate.
The Rates may be worked out by rate analysis method and schedule of
rates is to be prepared.
The rates of different items in the estimate are the current rates for the
completion of the item of work which include supply of materials,
transport, labour, scaffolding, T&P, over heads & profits etc..
7 CMTI, Bangalore
ESTIMATION AND COSTING
8 CMTI, Bangalore
ESTIMATION AND COSTING
This is basic tips for scheduling and can be planned between 6-8 months
depends on resources planning.
This is basic tips for scheduling and can be planned between 12-15 months
depends on resources planning.
9 CMTI, Bangalore
ESTIMATION AND COSTING
10 CMTI, Bangalore
ESTIMATION AND COSTING
11 CMTI, Bangalore
ESTIMATION AND COSTING
3. Give details information of drainage/Nala and basin details of base flow in the area.
4. Give details of water body name & capacity and their catchments nearby area.
6. Topo-sheet number, coordinates (latitude & longitude), Altitude with respect toMSL,
elevation difference at site. (attach the copy of relevant portion of topo-sheet and one
original full size topo sheet which are showing project area along with city).
7. Average annual rainfall and rainfall analysis of area (departure from normal),
Monsoon period, peak rainfall intensity in mm/hr.
11. Hydro-geological parameters in and around the proposed area including ground
water draft, stage of ground water development, etc..
12. Status of existing bore well/wells/tube wells in and around proposed area. (Format
table enclosed) Results of pumping tests to be included.
13. Details of existing water harvesting/water recharge structures present in the area
including location & distance.
14. Details of existing water structures (river, pond, dam ck.dam) present in the area
including location & distance.
16. Details of the Hydro-geological & Geo-physical study conducted including the basis
for pinpointing location of wells.
17. Results of the Geo- Physical investigations (attach field data, observations,
interpretations with graphs and curves for sounding and profiling or any othermethod0
provide the expected litho-log at each of the well point for around 300 m depth.
18. High flood level (HFL) near project site & its distance.
12 CMTI, Bangalore
ESTIMATION AND COSTING
PROJECT Date
Status of Existing Wells / Bore Wells / Tube wells in and around the proposed Area
I WeII No.
(Indicate on the map)
2 Location/'well owners
name
3 Survey number
4 Dimensions of 'well
a. Type
(Open well /BW'/TW)
b. Diameter
c. Depth
d. Curbing
e. Casing (attach details)
Static water level
a winter
h. Summer
6 Electrification Status
7 Pumping Device
a. Horse Power
b. Height of pump
8 Pumping Hours
a. Winter
h. Summer
9 Yields (LPD)
a. V\''inter
h. Summer
10 Drawdown
1 1 Lithology
c. Depth
d
e
f
12 Aquifers Type
13 Aquifers Thickness
l4 Constructed in the year
IS Performance over years
16 Abondonated / Servicahle
/maintenance required
17 Additional information
18 Remark
13 CMTI, Bangalore
ESTIMATION AND COSTING
14 CMTI, Bangalore
ESTIMATION AND COSTING
S.no Particulars
1 Site Plan
2 Contour Plan (for big Projects)
3 Architectural Plan/GFC/working drawings
a Floor Plan
b Center line plan with setting out details
c Floor Plan with Furniture Layout ( Helps to
plan Electrical Layout)
d Terrace Plan
e Brick work marking Plan (optional)
f Floor Tile Plan (optional)
g Sectional details
h Elevation details
(i) Front Elevation
(ii) Rear Elevation (optional)
(iii) Side Elevation (optional)
4 Structural Drawings
a Centerline Column Layout Plan
b Footing Plan/Excavation drawing
c Plinth Beam layout with RCC details
d Column Schedule with RCC details
e Footing Schedule with RCC details
f Roof Beam Layout with RCC details
g Staircase Details
h Roof Slab details
5 Road Level details
6 Foundation level details
7 High Flood level details (as applicable)
8 Plinth level/Floor level
15 CMTI, Bangalore
ESTIMATION AND COSTING
PROCEDURE OF ESTIMATING
Introduction:
In framing correct estimate care should be taken to find out the dimensions of
all item correctly, and to avoid omissions of any kind of work or part thereof.
Importance of Estimating:
1. Estimate gives an idea of the cost of work and hence its feasibility can be
determined.
2. Estimate gives an idea of time, manpower, resources required for the
completion of work.
3. Estimate is required to prepare BOQ, invite quotation/tenders and to
arrange contract & award of work.
4. Estimate is required to control the expenditure during execution of
work.
5. Estimate decides whether the proposed plan, specification matches with
the funds available or not.
6. Estimate helps to monitor works & proper cash flow management.
16 CMTI, Bangalore
ESTIMATION AND COSTING
Sequence in Estimating
Project Costing:
ProjectCosting
Land Cost:
1. Cost of land.
2. Brokerage.
3. Stamp duty &Registration cost.
4. Legal fees.
5. Incidental expenses.
17 CMTI, Bangalore
ESTIMATION AND COSTING
Pre-Construction cost:
1. Consultancy charges.
2. Approval Fees.
3. Liaison Expenses.
4. EB connection.
5. Bore well.
6. Pipes, Pump & Motor.
Construction Cost:
1. Building Cost.
2. External development cost/infrastructure cost.
Construction Cost:
1. Structure (Excavation + Foundation + Super Structure Brick work +
column + Beams + Slab and Plastering)
2. Tiling (flooring)
3. Doors & Windows(Joinery)
4. Painting work
5. Electrical work
6. Plumbing work
7. Grills & railing work (fabrication)
8. Elevation work
9. Water Proofing work
10. Contingency
External Development:
1. Under Ground Sump.
2. Septic Tank/STP
3. Plinth Protection
4. Paving
5. Compound Wall
6. Min Gate
18 CMTI, Bangalore
ESTIMATION AND COSTING
SPECIFICATION
19 CMTI, Bangalore
ESTIMATION AND COSTING
ASTRAL or Equivalent.
PVC Rain water, Sanitary, Waste and
water line.
PVC. Pipeline of Supreme / Prince or
Equivalent for underground drainage.
Bathroom and Kitchen with water
provision.
Separate Motors for Sump and Bore
wells.
Florentine/ESSESS or Equivalent CP
Fixtures
Parryware/Equivalent white Sanitary
Fixtures.
20 CMTI, Bangalore
ESTIMATION AND COSTING
SPECIFICATION DETAILS
8 Electrical work:
Switches Orbit/Anchor Rs.20 each
Concealed electrical Pipe Roof – Rs.60
Wall – 50
Metal Box Anchor
Wires Orbit/Anchor/Finolex/Kundhan
Fan Box As per requirements
Light Point 3nos each room
AC point 2nos
Heater Point 1no
9 Plumbing work
Concealed CPVC Pipes Rs. 320
1” PVC pipe Rs.300
2.5” Pvc pipe Rs.480
4” Pipe Rs.970
SS Tap Rs.600 each (Bath room tap 2nos Kitchen
Tap 1no)
21 CMTI, Bangalore
ESTIMATION AND COSTING
SPECIFICATION DETAILS
Shower SS Rs.1200
Rain water Pipe 2nos 4” pipe
Western Closet Rs.4500
Wash Basin
SS sink in Kitchen 1500
10 Painting work
Ceiling 02 coat Putty + 01 Primer+ 02Interior
Interior walls Emulsion
Exterior Walls 02 coat Putty+ 01Primer+ 02Interior
Varnish Emulsion
Internal Door 01 coat Primer + 02 coat Emulsion.
Grills Main Door
Enamel Paint
Enamel Paint
11 Wood Work:
Main Door and Frame Good quality teak wood
Hinges & Screw Brass
Main door lock Godrej Lock
Handle 2 nos
Tower Bolt 2 nos
Door Stopper 1 no
Cost of Main door frame & Rs.35000
fittings
Bedroom door frame Teak wood
Bed room door Rs.3800
Hinges & screw SS
Bedroom door lock Aldrop 1n0
Handle 2 nos SS
Tower Bolt 2 nos SS
Bedroom door Frame, door & 1 no
fittings Rs.15000
Bathroom PVC door Rs.2500
12 Staircase Handrail SS Hand Rail
13 Terrace Weathering Course using Lime brick jelly
red tile cost 12/-per no
14 Cement Dalmiya/Ramco/Zuvari/Chettinad
15 Steel TMT rods
22 CMTI, Bangalore
ESTIMATION AND COSTING
RATES:
The rates of various items of work, materials to be used in the construction
and the wages of different categories of labour (skilled and unskilled) should
be available for preparing an estimate. The cost of transportation charges
should also be known. The rate analysis may be worked out by the rate
analysis method.
Basic Rates of Building Materials:
S.no Materials Unit Rate
1 Cement Bag 430
2 M.Sand CFT 50
3 20mm Aggregates CFT 32
4 Gravel CFT 20
5 Bricks Nos 8.50
6 Reinforcement Steel Kg 58
7 Cement Primer Ltrs 125
8 Cement Putty Kg 25
9 Acrylic Putty Kg 20
10 Internal Acrylic Emulsion Ltrs 200
11 External Acrylic Emulsion Ltrs 250
12 Enamel Paint Ltrs 160
13 Hard wood door frames 4” X 3”/4” each 8000/6500
X 2.5”
14 African Teak wood shutters Each 15000 -20000
15 30 mm thick pressed door Each 3500-5000
16 Vitrified Tiles SFT 45-60
17 Ceramic Floor Tiles Sft 35-45
18 Ceramic wall Tiles Sft 35-45
19 Kitchen Granite Counter SFT 140
20 Door Hardware’s Set 1500
The rates may vary from place to place and from time to time.
23 CMTI, Bangalore
ESTIMATION AND COSTING
SEQUANCE OF ACTIVITIES
S.no Activities Remarks
A. Sub Structure
1 EW Excavation
2 Sand Filling
3 PCC Footing
4 Fixing reinforcement for footing and column
5 RCC Concreting for footing
6 Ant termite treatment
7 Short Column concreting (up to Plinth beam bottom)
8 Back Filling & consolidation
9 EW Excavation
10 PCC for Tie beam
11 Fixing reinforcement for tie beam
12 Shuttering for tie beams
13 RCC concreting for tie beam
14 Plinth BW
15 Plinth plastering work
16 Back Filling & consolidation
17 PCC at Plinth
18 Completion of Sub Structure Mile Stone
B. Super Structure
1 Providing & Fixing reinforcement
2 Shuttering Work
3 RCC Concreting Work ( M30)Column
4 RCC Concreting Work ( M25 ) Roof beam & Slab Mile Stone
5 Stair case work
6 Brick work
7 Lintel & Sunshade
8 Plastering
9 Completion of Structure work Mile Stone
C. Finishing work
1 Joinery Doors & Windows
2 Tiling work
3 Services Electrical & Plumbing work
4 Grills & Railing Work
5 Painting work
6 Completion of Finishing work Mile Stone
24 CMTI, Bangalore
ESTIMATION AND COSTING
The BOQ is the list of the various components of a building in a logical order.
Interim & Final valuation – use to value the progress of work on site.
Contents of a BOQ:
Preliminaries
Preambles
Measured quantities.
Provisional sums.
Classification of Costs:
25 CMTI, Bangalore
ESTIMATION AND COSTING
Gross Pricing:
Thumb Rule for estimating Concrete Volume with respect Area: The volume of Concrete
requires is about = 0.038M³/SFT area. If the Plan area is 40 x 25 = 1000 Sqm . Then volume
of concrete required is 1000 x 0.038 = 38 M³.
Thumb Rule for Steel quantity required for slab, beam, footing, & column etc:
Shuttering costs is taken as 15 – 18% of the total construction of the Building. The
Shuttering area is about 2.4 times plinth area per floor.
26 CMTI, Bangalore
ESTIMATION AND COSTING
D
A
O
R
27 CMTI, Bangalore
ESTIMATION AND COSTING
W1
D1
LIVING ROOM
4368 X 3046
D2
D
D2
A
W2
O
R
D3
W2
28 CMTI, Bangalore
ESTIMATION AND COSTING
W1
LIVING ROOM D1
4368 X 3046
WARDROBES
D2
D
D2
A
W2
O
R
D3
W2
29 CMTI, Bangalore
ESTIMATION AND COSTING
30 CMTI, Bangalore
ESTIMATION AND COSTING
12192
952 3492 4585 3162
1257
3
15
340
77
3163
B
4762
328
876
94
12 1
1 2
31 CMTI, Bangalore
ESTIMATION AND COSTING
8306
230
230
1889 1219
2863
2862
2862
184
300
300
8153
4461
4532
1910
TOILET
2300 X 1219
72
230
2047 914 230 300 652
3191 300 4285 300
32 CMTI, Bangalore
ESTIMATION AND COSTING
Safari stone Tiles
300mm x 300mm size
(or) cement floor finish
as per requirement
W1
LIVING ROOM D1
4368 X 3046
Verified Tiles
600mm x 600mm
size
Verified Tiles
600mm x 600mm
size
DESIGNER PARKING
TILES
D2
ANTI - SKID
CERAMIC Tiles
300mm x 300mm
V size
D2
W2 Verified Tiles
600mm x 600mm
size
D3
W2
33 CMTI, Bangalore
ESTIMATION AND COSTING
34 CMTI, Bangalore
ESTIMATION AND COSTING
35 CMTI, Bangalore
ESTIMATION AND COSTING
36 CMTI, Bangalore
ESTIMATION AND COSTING
RCC SLAB
1461
+2350 LVL
4877
3495
SITE BOUNDARY
LINE
2164
COMPOUND WALL
1524
1141
305
37 CMTI, Bangalore
ESTIMATION AND COSTING
38 CMTI, Bangalore
ESTIMATION AND COSTING
3505
39 CMTI, Bangalore
ESTIMATION AND COSTING
9
3
6
184
C2
3491 4585
2
9
6
3082
2050 735
1675
1556
1557
184
1246
2950
6773
1907
3212
3183
3184
C2/F2
681
C3/F1
1
1936 2988
41
EXCAVATION DRAWING CMTI, Bangalore
4461
2863
3191
3249
3108
PVB3(230 X 300)
PVB1(230 X 300)
PHB2(230 X 300)
4533 2861
42
4298
4367
4355
PHB4(230 X 300)
PVB1(230 X 300)
PVB2(230 X 300)
2861
4532
1836
1835
1835
PVB1(230 X 300)
7692
CMTI, Bangalore
ESTIMATION AND COSTING
ESTIMATION AND COSTING
43 CMTI, Bangalore
ESTIMATION AND COSTING
230
2-12ST
04-T16+
04-T12
125
RVB3(230x425)
125
FLOTING
COLUMN(230x375)
2-12ST
152
SECTION A-A
44 CMTI, Bangalore
ESTIMATION AND COSTING
COLUMN SCHEDULE :-
C2 04-T16
230 X 300 1,5,8 + 8T @175 C/C 375 X 450
(03 NOS)
2-T12
C3
(02 NOS) 230 X 382 10,11 08-T12 8T @175 C/C
375 X 532
COLUMNS
TOTAL NO. OF COLUMNS 11
GROUND LEVEL
PLINTH BEAM
PEDESTAL
FOOTING
100MM Thk.
P.C.C
LENGTH
45 CMTI, Bangalore
PVB3(230 X 300)
PVB1(230 X 300)
PHB2(230 X 300)
PLINTH
PHB4(230 X 300)
PVB1(230 X 300)
PVB2(230 X 300)
46 BEAM LAYOUT
PHB5(230 X 300) PHB5(230 X 300)
PVB1(230 X 300)
8 T @ 225 C/C
8T@225 C/C
1448
2- T 12 ST
2- T 12 ST
PHB2(230 X 300)
3075 2250
8 T @ 225 C/C
1447
1- T 16+1-12 EXT 2- T 16+1-12 EXT 1- T 12 EXT
2- T 12 ST
1200 800 800
PVB2 PVB3
2- T 12 ST
3075 2250
47 CMTI, Bangalore
ESTIMATION AND COSTING
8 T @ 225 C/C
8 T @ 225 C/C
2- T 12 ST
2- T 12 ST
3075 2250
3075 2250
48 CMTI, Bangalore
ESTIMATION AND COSTING
49 CMTI, Bangalore
ESTIMATION AND COSTING
1
2064 4598 3478
1-16 EXT
4762 3163
RHB1(230X425)
RHB2(230X425)
RVB1
1-12 EXT
2055
RHB4(230X425)
2-12 ST
1-12 EXT 1-12 EXT
2985 2215
430
2139 4586 3415
RVB1(230X425)
3B 1B
8T@100 C/C 8T@175 C/C
2-16T 2-12 ST
1-12 EXT
2985
430
2139 4586 3415
RVB2(230X425)
3C 1C
8T@100 C/C 8T@175 C/C
2-12 ST 2-12 ST
1-12 EXT
2985
430
2139 4586 3415
RVB3(230X425)
0.65x L1
52 CMTI, Bangalore
ESTIMATION AND COSTING
53 CMTI, Bangalore
ESTIMATION AND COSTING
Joinery Details:
S.no Particulars Nos Size in Mtrs Size in feet Qty in SFT
DOORS
1 D1 1 1.067 x 2.134 3’ 6” x 7’ 24.5
2 D2 2 0.916 x 2.134 3’ x 7’ 42
3 D3 3 0.787 x 2.134 2’6” x 7’ 52.5
Windows
4 W1 2 1.14 x 1.219 3’9” x 4’ 30
5 W2 3 0.914 x 1.219 3’ x 4’ 36
6 W3 1 1.219 x 1.219 4’ x 4’ 16
Total 82
Ventilators
7 V 2 0.61 x 0.61 2’ x 2’ 8
54 CMTI, Bangalore
ESTIMATION AND COSTING
Notes:
55 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
1 Earth work excavation for Footing
F1 3 1.450 1.385 1.500 9.037 Working Space
F2 3 1.650 1.585 1.500 11.769 0.15 allround
F3 3 1.750 1.685 1.500 13.269 (please refer footing
F4 2 1.850 1.785 1.500 9.907 schedule)
3
Total Qty M 43.982
Excavation for Plinth Beam
Extra 0.075 m for
Horizontal Direction A1-C1 1 4.287 0.38 0.400 0.652 Shuttering rest
2 & 3 Grid 2 4.130 0.38 0.400 1.256
A4-C4 1 6.470 0.38 0.400 0.983
1 1.219 0.38 0.400 0.185
1 1.104 0.38 0.400 0.168
Vertical Direction A grid 1 4.706 0.38 0.400 0.715
C grid 1 4.967 0.38 0.400 0.755
B Grid 1 5.622 0.38 0.400 0.855
1 3.098 0.38 0.400 0.471
1 4.218 0.38 0.400 0.641
Total Qty M3 6.681
Grand Total M³ 50.662
56 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
57 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
8 R.C.C Footing
F1 3 1.150 1.085 0.300 1.123
F2 3 1.350 1.285 0.300 1.561
F3 3 1.450 1.385 0.375 2.259
F4 2 1.550 1.485 0.375 1.726
58 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
Total Qty M3 6.670
14 R.C.C. Staircase
Grid A3 to B3 & A4 to B4
59 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
st Including mid
1 Flight 1 5.192 0.920 0.127 0.607
nd
2 Flight 1 5.054 0.920 0.127 0.591 landing
Staircase bottom Beam 1 it's starts from PB
Staircase Mid Landing Beam 1 2.065 0.230 0.305 0.145
Total Qty M3 1.342
17 Joineries
Window 01 2 1.181 1.219 2.879
Window 02 3 0.914 1.219 3.342
Window 03 1 1.219 1.219 1.486
Ventilator 2 0.610 0.610 0.744
Door 01 1 1.067 2.134 2.277
Door 02 2 0.916 2.134 3.909
Door 03 3 0.787 2.134 5.038
Total Qty M2 19.677
60 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
Grid B 1 9.450 0.230 0.700 1.521
Grid C1 - C3 1 7.406 0.230 0.700 1.192
Grid C3 -C4 1.834 0.230 0.300 0.127
Total Qty M3 8.430
Deductions
Door 02 -2 0.916 2.133 -3.908
61 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
Door 03 -2 0.787 2.133 -3.357
Open Living to Dining -1 1.714 2.133 -3.656
Open Dining to Bed room -1 1.217 2.133 -2.596
R.C.C. Lintel in G.Floor
Door 02 -2 1.376 0.115 -0.316
Door 03 -2 1.247 0.115 -0.287
Open Living to Dining -1 2.174 0.115 -0.250
Open Dining to Bed room -1 1.677 0.115 -0.193
Total Qty M2 85.358
62 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
Kitchen 1.953 1.334 2.605
Bed room 1 1 3.363 3.046 10.244
Bed room 2 1 3.363 3.198 10.755
Toilet 1 1 2.134 1.219 2.601
Toilet 2 1 2.300 1.219 2.804
Way to Bed 1 1.242 1.219 1.514
Portico 1 2.064 3.545 7.317
2
Total Qty M 65.118
Sunshade Plastering
Window 01 2 1.681 0.457 1.536
Window 02 2 1.414 0.457 1.292
Door 03 1 1.287 0.457 0.588
Sunshade Side 10 0.457 0.089 0.407
Parapet Wall
1 8.153 1.182 9.637
8.307 1.182 9.819
2 10.063 0.914 18.395
2
Total Qty M 237.677
63 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
29 PAINTING
A Interior walls
02 Coat Putty SQM SAME AS PLASTERING QTY 221.455
01 Coat Primer SQM SAME AS PLASTERING QTY 221.455
02 Coat Acralic Emulsion SQM SAME AS PLASTERING QTY 221.455
B Ceiling
02 Coat Putty SQM SAME AS PLASTERING QTY 65.118
01 Coat Primer SQM SAME AS PLASTERING QTY 65.118
02 Coat Acralic Emulsion SQM SAME AS PLASTERING QTY 65.118
64 CMTI, Bangalore
ESTIMATION AND COSTING
Sl. Quantity (
No. Description of work No's. L (M) B (M) H (M) M2 / M3) Remarks
Ventilator 2 0.610 1.600 0.610 1.191
Door Painting Co
efficient 1.3 on
Door 01 1 1.067 2.600 2.134 5.920 both side
Door 02 2 0.916 2.600 2.134 10.165
Door 03 3 0.787 2.600 2.134 13.100
Total Qty M2 42.708
65 CMTI, Bangalore
ESTIMATION AND COSTING
66 CMTI, Bangalore
ESTIMATION AND COSTING
67 CMTI, Bangalore
ESTIMATION AND COSTING
68 CMTI, Bangalore
ESTIMATION AND COSTING
69 CMTI, Bangalore
ESTIMATION AND COSTING
3
12 R.C.C. Roof beam M 5.960
3
13 R.C.C. Roof Slab M 7.779
70 CMTI, Bangalore
ESTIMATION AND COSTING
2
32 Anti Skid Ceramic Tiles in Toilet M 5.405
71 CMTI, Bangalore
ESTIMATION AND COSTING
72 CMTI, Bangalore
ESTIMATION AND COSTING
MARKET RATES
S.no Items Unit Rate Remarks
A - Labour
1 Mason No 900
2 Carpenter No 800
3 Bar bender No 800
4 MC No 700
5 FC No 550
6 Painter No 800
7 Plumber No 800
8 Electrician No 800
B - Materials
1 Cement Bag 420
2 M Sand Cft 50
3 P Sand Cft 55
4 Blue Metal Cft 32
5 Bricks nos 8.5
8 Steel kg 58
9 Gravel Cft 20
10 Cement Primer Ltrs 125
11 Cement Putty Kg 25
12 Acrylic Putty 20
13 Internal Acrylic Emulsion Ltrs 200
14 External Acrylic Emulsion Ltrs 250
15 Enamel Paint Ltrs 160
Hard wood door frames 4” X
16 3”/4” X 2.5” Nos 8000 - 6500
17 African Teak wood shutters Nos 15000 - 20000
18 30 mm thick pressed door Nos 3500 - 5000
19 Vitrified Tiles Sft 45 - 60
20 Ceramic Floor Tiles Sft 35 - 45
21 Ceramic wall Tiles Sft 36 - 45
22 Kitchen Granite Counter Sft 140
23 Door Hardware’s Set 1500 -2000
Note: Market rates of Labour & Materials will vary from place to place and time to time. Necessary
adjustments to be effected accordingly
73 CMTI, Bangalore
ESTIMATION AND COSTING
RATE ANALYSIS
CIVIL WORKS
S.no Description Unit Quantity Rate Amount Labour
Earth work excavation in all types of soils,
including manual dressing & levelling
including all leads upto 50 mts & lift 1.5
1 mts.
Details of Cost for 10 Cum
Average output of hydralic excavator per
Machinery
Hydralic excavator JCB day 0.041 8000 328.00
Hire & running charges of loader day 0.041 2500 102.50
Labour
Male day 0.32 700 224.00
Cooliie day 1.2 550 660.00
Total 1314.50
Add 1% water 13.15
Total 1327.65
Add for contractor profit & OH @ 11.6% 154.01
Total for 10 Cum 1481.65
Total for 1 Cum 148.17
Only with Labour
For 1CUM
Labour
Male Each 0.367 700 256.90 256.90
Add T & P @ 1.5% 3.85 3.85
Add water charges 1% 2.57 2.57
Total 263.32 263.32
Add Contractor Profit @ 11.6% 30.55 30.55
Total Rate for 1 Cum 293.87 293.87
74 CMTI, Bangalore
ESTIMATION AND COSTING
75 CMTI, Bangalore
ESTIMATION AND COSTING
76 CMTI, Bangalore
ESTIMATION AND COSTING
77 CMTI, Bangalore
ESTIMATION AND COSTING
9 CEMENT MORTAR
a Cement Mortar1:3
For 1 Cum
Materials
Cement Bag 10.2 420 4284.00
Fine Sand (M.sand) Cum 1.07 1765 1888.55
Total Materials 6172.55
Labour No
MC No 0.3 700 210.00 210.00
Fc No 0.6 550 330.00 330.00
Total Labour 540.00 540.00
Grand Total 6712.55
Add T & P @ 1.5% 100.69 8.10
Add Water @ 1% 67.13 5.40
6880.36 553.50
Rate per 1 Cum 6985.00 553.50
b Cement Mortar1:4
For 1 Cum
Materials
78 CMTI, Bangalore
ESTIMATION AND COSTING
c Cement Mortar1:5
For 1 Cum
Materials
Cement Bag 6.2 420 2604.00
Fine Sand (M.sand) Cum 1.07 1765.5 1889.09
Total Materials 4493.09
Labour No
MC No 0.3 700 210.00 210.00
Fc No 0.6 550 330.00 330.00
Total Labour 540.00 540.00
Grand Total 5033.09
Add T & P @ 1.5% 75.50 8.10
Add Water @ 1% 50.33 5.40
5158.91 553.50
Rate per 1 Cum 5158.91 553.50
d Cement Mortar1:6
For 1 Cum
Materials
Cement Bag 5 420 2100.00
Fine Sand (M.sand) Cum 1.07 1765.5 1889.09
Total Materials 3989.09
Labour No
MC No 0.3 700 210.00 210.00
Fc No 0.6 550 330.00 330.00
Total Labour 540.00 540.00
Grand Total 4529.09
Add T & P @ 1.5% 67.94 8.10
Add Water @ 1% 45.29 5.40
4642.31 553.50
Rate per 1 Cum 4642.31 553.50
79 CMTI, Bangalore
ESTIMATION AND COSTING
80 CMTI, Bangalore
ESTIMATION AND COSTING
81 CMTI, Bangalore
ESTIMATION AND COSTING
82 CMTI, Bangalore
ESTIMATION AND COSTING
83 CMTI, Bangalore
ESTIMATION AND COSTING
84 CMTI, Bangalore
ESTIMATION AND COSTING
85 CMTI, Bangalore
ESTIMATION AND COSTING
86 CMTI, Bangalore
ESTIMATION AND COSTING
87 CMTI, Bangalore
ESTIMATION AND COSTING
88 CMTI, Bangalore
ESTIMATION AND COSTING
89 CMTI, Bangalore
ESTIMATION AND COSTING
2 M.SAND FILLING
Filling with approved good quality of Quary
dust in foundation & Plinth, area
developementetc whereever specified in
layers not exceeeding 200mm thick
watering compacting each layer cost shall
includes all material tools & plant.
a Supplying and filling of M.Sand for Bed M³ 2.932 1291.46 3,786.73
Supplying and filling of M.Sand for Bed in
b basement M³ 6.322 1291.46 8,164.88
11,951.61
3 CONCRETING
Providing and laying P.C.C 1:4:8 bed in
foundations, raft slab, column footing etc..
Where ever specified using M.sand 40mm
and down grade size aggregates including
machine mixing tamping curing etc..
Complete with all lead & lifts at level.
3
a P.C.C. 1;4:8 for foundation M 2.932 5168.61 15,155.02
b P.C.C. 1;4:8 in Plinth Beam M3 2.463 5168.61 12,730.43
c P.C.C. 1;4:8 in Basement M3 6.343 5168.61 32,784.01
60,669.47
4 Earth Filling
Filling with approved good quality of earth
(with excavated earth avilable at site) in
foundation & Plinth, area developementetc
whereever specified in layers not
exceeeding 200mm thick watering
compacting each layer cost shall includes
all material tools & plant.
90 CMTI, Bangalore
ESTIMATION AND COSTING
91 CMTI, Bangalore
ESTIMATION AND COSTING
st
Providing and laying well burnt 1 class
stock bricks (of approved quality) 9”
thick in cement mortar 1:5 in superstruct-
ure of all floors including scaffolding,
b racking out joints, curing, etc., complete:
0.23 m tk wall Brick work using C.M.1:5 in
Super Structure M3 16.726 7793.65 1,30,359.38
92 CMTI, Bangalore
ESTIMATION AND COSTING
94 CMTI, Bangalore
ESTIMATION AND COSTING
Ceiling
02 Coat Putty SQM 65.118 141.21 9,195.60
b 01 Coat Primer SQM 65.118 67.20 4,376.20
02 Coat Acralic Emulsion SQM 65.118 117.82 7,672.31
95 CMTI, Bangalore
ESTIMATION AND COSTING
OTHER WORKS
Weathering course using brick coba laying
17 hydralic Pressed tiles in cm 1:3 M2 80.360 1250 1,00,449.38
Break Up
Rate per Sft including plumbing &
A electricals 18,07,715.61 = 1,977.81
914
B Contingency ( Misc.) 9140 = 10.00
914
C Other works/Extra work 3,63,552.98 = 397.76
914
Total Cost 2,385.57
96 CMTI, Bangalore
ESTIMATION AND COSTING
4 Earth Filling
Filling with approved good quality of earth
(with excavated earth avilable at site) in
foundation & Plinth, area developementetc
whereever specified in layers not
exceeeding 200mm thick watering
compacting each layer cost shall includes
all material tools & plant.
a Back filling in Foundation M3 29.685 150.98 4,481.97
b Filling in Basemant M3 25.572 150.98 3,860.87
1 of7
97 CMTI, Bangalore
ESTIMATION AND COSTING
4 R.C.C.
Providing and laying Reinfoced cement
concrete of grade as specified M20 using
M.sand and 20mm down aggregates
necessary admixtures approved including
all lead and lifts vibrating and finishing the
surfaces, scaffolding whereever necessary
curing as directed.
a R.C.C Footing M3 6.670 1435.59 9,575.19
b R.C.C Pedestal Column M3 1.087 1435.59 1,561.02
c R.C.C. in Plinth beam M3 4.893 1435.59 7,023.96
d R.C.C Column up to G.Roof M3 2.793 1435.59 4,008.90
e R.C.C. Roof beam M3 5.960 1435.59 8,555.88
f R.C.C. Roof Slab M3 7.779 1435.59 11,166.78
g R.C.C. Staircase M3 1.342 1435.59 1,926.57
h R.C.C. Lintel in G.Floor M3 0.597 1435.59 857.22
i R.C.C. Sunshade in G.Floor M3 0.296 1435.59 424.90
45,100.43
5 STEEL WORK
Providing fabricating reinforced steel of
various diameters for reinforced concrete
work . The work includes strightining
cutting bending and placing in position etc..
Cost include supply of 18 G binding wire
and PVC cover block.
Reinforcement steel in all R.C.C works KG 3339.532 17.12 57,178.12
6 FOAM WORK
Supply ,fixing ,Removing Shuttering &
Stagging M2 247.431 175.00 43,300.45
7 BRICK WORK
Providing and laying well burnt 1st class
bricks (of approved quality) 9”
thick in cement mortar 1:4 in foundation
and basement including racking out joints,
a curing, etc., complete.
2 of7
98 CMTI, Bangalore
ESTIMATION AND COSTING
3 of7
99 CMTI, Bangalore
ESTIMATION AND COSTING
5 of7
Ceiling
02 Coat Putty SQM 65.118 96.09 6,257.03
01 Coat Primer SQM 65.118 54.91 3,575.44
b 02 Coat Acralic Emulsion SQM 65.118 88.08 5,735.61
6 of7
OTHER WORKS
Weathering course using brick coba laying
17 hydralic Pressed tiles in cm 1:3 M2 80.360 326.01 26,198.12
Break Up:
Structure Labour cost ( Founadtion +
column + beam + slab + brick work &
A plaster) = 3,56,321.21 389.85
Finishing Labour Cost (Flooring + joinery
B + painting) = 1,57,974.20 172.84
C Plumbing Labour cost = 36,560.00 40
D Electrical Labour Cost = 36,560.00 40
642.69
E Other works = 1,00,828.92 110.32
GRANDTOTAL 753.00
7 of7
Total Qty
Quantity per of
S.no Description Unit Cum Est.Qty materials
Total Qty
Quantity per of
S.no Description Unit Cum Est.Qty materials
bricks (of approved quality) 115
mm thick in cement mortar 1:4 with 40
mm wide 15 guage hoop iron (or) 2 nos.
6mm diameter m.s. bars placed at every
76cm vertical intervals, including
scaffolding, racking out joints, curing,
etc., complete in all floors:
For 1 Sqm
I class Brick No 56.5 85.36 4822.73
Cement Bag 0.21 85.36 18.10
M.sand Cum 0.03 85.36 2.56
Cement for band Bag 0.48 85.36 40.97
Total Qty
Quantity per of
S.no Description Unit Cum Est.Qty materials
11 Vetrified Tiles CM 1:4 Total Estimate Qty 59.14
Providing and laying 605 x 605 size
polished vitrified tiles Plain Series (John-
son/Equivalent) of approved quality,
colour and design set in cement mortar
1:4 including
grouting with Bal Endura/Laticrete or
equivalent grouting material, etc.,
complete in all floors:
Details of cost for 1 Sqm
Vertified tile add breakages 2.5% Sqm 1.025 59.14 60.61
Cement for slurry over Bed 3.3 Kg perBag Sqm 0.2 59.14 11.83
M.sand Cum 0.03 59.14 1.77
Total Qty
Quantity per of
S.no Description Unit Cum Est.Qty materials
Materials
Cement primer 01 coat Litre 0.07 286.57 20.06
Interior Emulsion
Details of cost per 1Sqm
Materials
Interior Emulsion 02 coat Litre 0.12 286.57 34.39
15 Doors
Joinery
D1 Frames 5" x 3" No 1
D2 & D3 Frames 4" x 2.5" No 5
Shutters D1 No 1 21.00 SFT
ShuttersD2 No 2 36.17 SFT
Shutters D3 No 3 43.75 SFT
Total Qty
Quantity per of
S.no Description Unit Cum Est.Qty materials
S.no Items Unit OTY
2 M.Sand Cum 33.68
P.Sand Cum 10.69
3 Agg 40 mm Cum 10.45
Agg 20 mm Cum 27.96
4 Brick Nos 17149.43
5 Steel
8mm Kg 1307.39
10mm Kg 502.30
12mm Kg 1070.90
16mm Kg 386.78
25mm for Spacer rod Kg 72.16
6 Binding Wire Kg 33.40
7 Vertified Tiles Sqm 60.61
8 Designer Tiles Sqm 21.66
9 Ceramic tiles Sqm 55.94
10 Cement putty Kg 438.70
11 Primer Ltrs 20.06
12 Interior Emulsion Ltrs 34.39
13 Exterior Primer Ltrs 52.29
14 Exterior Emulsion Ltrs 33.99
Construction Cost
Type: Independfent House
Built up Area (BUA) : 914 SFT
S.no Details Amount Cost /Sft
Structure (Excavation +
Foundation + Super Structure Brick
work + Columns + beams + slab
1 and Plastering) 12,06,050.77 1319.53
2 Tiling 1,41,245.84 154.54
3 Doors & Windows 1,42,307.69 155.70
4 Painting work 1,45,018.40 158.66
5 Grills & Railling 5,920.59 6.48
6 Water proofing work 2,834.52 3.10
7 Plumbing work 82,168.89 89.90
8 Electrical work 82,168.89 89.90
9 Contingency 9140 10.00
Grand Total 18,16,855.61 1987.81
OTHER WORKS
Weathering course using brick
coba laying hydralic Pressed tiles
1 in cm 1:3 1,00,449.38 109.90
Break Up
Rate per Sft including plumbing &
A electricals 18,16,855.61 = 1987.81
914
B Other works/Extra work 363552.975 = 397.7603665
914
C Total Cost 2385.57
Construction Cost
Type: Independfent House
Built up Area (BUA) : 914 SFT
S.no Details Amount Cost /Sft
Break Up
Rate per Sft including plumbing &
A electricals 5,87,415.40 = 642.69
914
B Other works/Extra work 1,00,828.92 = 110.32
914
C Total Cost 753.00
MATERIAL REQUIREMENTS
Type: Independfent House
Break Up BUA 914 SFT
S.no Items Unit OTY
1 Cement Bag 486.63
Quarry dust for filling Cum 9.25
2 M.Sand Cum 33.68
P.Sand Cum 10.69
3 Agg 40 mm Cum 10.45
Agg 20 mm Cum 27.96
4 Brick Nos 17149.43
5 Steel
8mm Kg 1307.39
10mm Kg 502.30
12mm Kg 1070.90
16mm Kg 386.78
25mm for Spacer rod Kg 72.16
6 Binding Wire Kg 33.19
7 Vertified Tiles Sqm 60.61
8 Designer Tiles Sqm 21.66
9 Ceramic tiles Sqm 55.94
10 Cement putty Kg 438.70
11 Primer Ltrs 20.06
12 Interior Emulsion Ltrs 34.39
13 Exterior Primer Ltrs 52.29
14 Exterior Emulsion Ltrs 33.99
Note: Other works not considered.
With
S.no Particulars With Matrials Only Labour Matrials
1 Sub Structure (Foundations) 4,01,071.99 88,448.52 438.81
CMTI, Bangalore
115
ESTIMATION AND COSTING
Up to Ground
lvl (1.8 m
Assume)
1.5 1.5 - - - - - -
Plinth Beam
0.23 0.3 - - - - - -
Nominal
Cover 0.04 0.04 - - - - - -
CMTI, Bangalore
116
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
Nominal Cover 0.04 0.04 - - - - - -
Main Rod 0.012 0.016 - - - - - -
Column Size 0.23 0.3 0.008 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
Main Rod 1.500 0.381 12 3 4 1.857 - - 22.284 - - -
16 3 2 1.857 - - - 11.142 - -
- - - - - -
Stirrups 0.150 0.220 8 3 8 0.804 19.30 - - - - -
- - - - - -
Pedestal
Column 03 Column ID's 10 & 11 - - - - - -
Up to Ground
lvl 1.5 1.5 - - - - - -
Plinth Beam 0.23 0.3 - - - - - -
Nominal
Cover 0.04 0.04 - - - - - -
Main Rod 0.012 - - - - - -
Column Size 0.23 0.382 0.008 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
Main Rod 1.500 0.381 12 2 8 1.857 - - 29.712 - - -
- - - - - -
- - - - - -
Stirrups 0.150 0.302 8 2 8 0.968 15.49 - - - - -
CMTI, Bangalore
117
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
Total Weight in Kg 28.99 0.00 125.45 17.58 0.00 0.00
Total Weight in MT 0.17
Column
Column 01 Column ID's 2,3,4,6,7 & 9 - - - - - -
From G.Lvl to
F.F roof Top
3.81 3.81 - - - - - -
Roof Beam
Size 0.23 0.425 - - - - - -
Nominal Cover 0.04 0.04 - - - - - -
Main Rod 0.012 - - - - - -
Column Size 0.23 0.3 0.008 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
Main Rod 3.810 12 6 8 3.810 - - 182.880 - - -
- - - - - -
Laps 12 6 8 0.600 - - 28.800 - - -
- - - - - -
Stirrups 0.150 0.220 8 6 20 0.804 96.48 - - - - -
- - - - - -
Column 02 Column ID's 1,5 & 8 - - - - - -
From G.Lvl to
F.F roof Top
3.81 3.81 - - - - - -
Roof Beam
Size 0.23 0.425 - - - - - -
CMTI, Bangalore
118
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
Nominal Cover 0.04 0.04 - - - - - -
Main Rod 0.012 - - - - - -
Column Size 0.23 0.3 0.008 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
Main Rod 3.810 12 3 4 3.810 - - 45.720 - - -
16 3 2 3.810 - - - 22.860 - -
12 3 4 0.600 - - 7.200 - - -
Laps
16 3 2 0.800 - - - 4.800 - -
- - - - - -
Stirrups 0.150 0.220 8 3 20 0.804 48.24 - - - - -
- - - - - -
Column 03 Column ID's 10 & 11 - - - - - -
From G.Lvl to
Floting Column
F.F roof Top
3.81 3.81 - - - - - -
Roof Beam
Size 0.23 0.425 - - - - - -
Nominal Cover 0.04 0.04 - - - - - -
Main Rod 0.012 0.016 - - - - - -
Column Size 0.23 0.382 0.008 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
Main Rod 3.810 12 2 4 3.810 - - 30.480 - - -
- - - - - -
3.810 16 2 4 3.810 - - - 30.480 - -
CMTI, Bangalore
119
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
16 2 4 0.800 - - - 6.400 - -
- - - - - -
Stirrups 0.150 0.302 8 2 20 0.968 38.72 - - - - -
- - - - - -
Total Rmt 183.44 0.00 299.88 64.54 0.00 0.00
Unit Weight 0.395 0.617 0.889 1.58 2.47 3.85
Total Weight in Kg 72.47 0.00 266.56 101.84 0.00 0.00
Total Weight in MT 0.44
CMTI, Bangalore
120
ESTIMATION AND COSTING
CMTI, Bangalore
121
ESTIMATION AND COSTING
Top Extra
Rod Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
0.250 - - - - - -
- - - - - -
- - - - - -
3.075 12 1 1 3.075 - - 3.075 - - -
Bottom
- - - - - -
Extra Rod
2.250 12 1 1 2.250 - - 2.250 - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.250 8 1 35 0.924 32.34 - - - - -
- - - - - -
- - - - - -
Center
1.629 12 1 2 2.081 - - 4.162 - - -
Beam Top
0.250 0.250 - - - - - -
Rod
- - - - - -
- - - - - -
1.629 12 1 2 2.081 - - 4.162 - - -
Bottom Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.250 8 1 5 0.924 4.62 - - - - -
- - - - - -
Plinth
Horizonal
Beam 03 Grid A2 TO C2 - - - - - -
Bay 4.461 2.863 - - - - - -
Plinth Beam
0.008
Size 0.23 0.3 - - - - - -
CMTI, Bangalore
122
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.225 0.225 - - - - - -
- - - - - -
8.101 12 1 2 8.553 - - 17.106 - - -
Top Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
8.101 12 1 2 8.553 - - 17.106 - - -
Bottom Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
1.475 16 1 1 1.693 - - - 1.693 - -
0.250 12 1 1 1.693 - - 1.693 - - -
- - - - - -
Top Extra 2.300 16 1 2 2.300 - - - 4.600 - -
Rod 12 1 1 2.300 - - 2.300 - - -
- - - - - -
1.075 12 1 1 1.301 - - 1.301 - - -
0.250 - - - - - -
- - - - - -
- - - - - -
3.075 12 1 1 3.075 - - 3.075 - - -
Bottom
- - - - - -
Extra Rod
2.250 12 1 1 2.250 - - 2.250 - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.250 8 1 35 0.924 32.34 - - - - -
CMTI, Bangalore
123
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
Stirrups metre
- - - - - -
- - - - - -
Center
1.514 12 1 2 1.966 - - 3.932 - - -
Beam Top
0.250 0.250 - - - - - -
Rod
- - - - - -
- - - - - -
1.514 12 1 2 1.966 - - 3.932 - - -
Bottom Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.250 8 1 5 0.924 4.62 - - - - -
- - - - - -
Plinth
Horizonal
Beam 05 Grid A3 TO C3 - - - - - -
Bay 4.461 2.863 - - - - - -
Plinth Beam
0.008
Size 0.23 0.3 - - - - - -
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.225 0.225 - - - - - -
- - - - - -
8.101 12 1 2 8.553 - - 17.106 - - -
Top Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
8.101 12 1 2 8.553 - - 17.106 - - -
Bottom Rod
0.250 0.250 - - - - - -
CMTI, Bangalore
124
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Bottom Rod Member
metre
- - - - - -
- - - - - -
1.475 16 1 2 1.693 - - - 3.386 - -
0.250 - - - - - -
- - - - - -
Top Extra 2.300 16 1 2 2.300 - - - 4.600 - -
Rod 12 1 1 2.300 - - 2.300 - - -
CMTI, Bangalore
125
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
- - - - - -
8.101 12 1 2 8.553 - - 17.106 - - -
Top Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
8.101 12 1 2 8.553 - - 17.106 - - -
Bottom Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
1.546 16 1 3 1.764 - - - 5.292 - -
0.250 - - - - - -
Top Extra - - - - - -
Rod 1.075 16 1 2 1.301 - - - 2.602 - -
0.250 12 1 1 1.301 - - 1.301 - - -
- - - - - -
- - - - - -
- - - - - -
3.075 16 1 2 3.075 - - - 6.150 - -
Bottom
- - - - - -
Extra Rod
2.250 16 1 1 2.250 - - - 2.250 - -
- - - - - -
- - - - - -
Stirrups 0.180 0.250 8 1 35 0.924 32.34 - - - - -
- - - - - -
Plinth
Vertical
Beam 01 Grid A1 TO A4 - - - - - -
Bay 3.178 4.298 1.767 - - - - - -
CMTI, Bangalore
126
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
Plinth Beam
0.008
Size 0.23 0.3 - - - - - -
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.225 0.225 - - - - - -
- - - - - -
10.320 12 1 2 10.772 - - 21.544 - - -
Top Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
10.320 12 1 2 10.772 - - 21.544 - - -
Bottom Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
1.080 12 1 1 1.298 - - 1.298 - - -
0.250
- - - - - -
2.325 16 1 2 2.325 - - - 4.650 - -
Top Extra
- - - - - -
Rod
1.950 16 1 2 1.950 - - - 3.900 - -
- - - - - -
0.705 12 1 1 2.881 - - 2.881 - - -
0.250 - - - - - -
- - - - - -
- - - - - -
2.260 12 1 1 2.260 - - 2.260 - - -
Bottom
- - - - - -
Extra Rod
2.980 12 1 1 2.980 - - 2.980 - - -
CMTI, Bangalore
127
ESTIMATION AND COSTING
Bottom Length of
No of
SlExtra
No Rod Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
- - - - - -
- - - - - -
Stirrups 0.180 0.250 8 1 44 0.924 40.66 - - - - -
- - - - - -
- - - - - -
Center
4.778 12 1 2 5.230 - - 10.460 - - -
Beam Top
0.250 0.250 - - - - - -
Rod
- - - - - -
- - - - - -
4.778 12 1 2 5.230 - - 10.460 - - -
Bottom Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.250 8 1 20 0.924 18.48 - - - - -
- - - - - -
Plinth
Vertical
Beam 04 Grid B1 TO B4 - - - - - -
Bay 3.248 4.368 1.837 - - - - - -
Plinth Beam Size 0.23 0.3 0.008 - - - - - -
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.225 0.225 - - - - - -
- - - - - -
10.320 12 1 2 10.772 - - 21.544 - - -
Top Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
Bottom Rod
CMTI, Bangalore
128
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
10.320 12 1 2 10.772 - - 21.544 - - -
Bottom Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
1.080 12 1 1 1.298 - - 1.298 - - -
0.250 - - - - - -
Top Extra - - - - - -
Rod 2.255 16 1 1 2.255 - - - 2.255 - -
- - - - - -
1.880 16 1 4 1.880 - - - 7.520 - -
- - - - - -
- - - - - -
2.260 12 1 1 2.260 - - 2.260 - - -
Bottom
- - - - - -
Extra Rod
2.980 12 1 1 2.980 - - 2.980 - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.250 8 1 44 0.924 40.66 - - - - -
- - - - - -
- - - - - -
Center
3.658 12 1 2 4.110 - - 8.220 - - -
Beam Top
0.250 0.250 - - - - - -
Rod
- - - - - -
- - - - - -
3.658 12 1 2 4.110 - - 8.220 - - -
Bottom Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
Stirrups
CMTI, Bangalore
129
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
Stirrups 0.180 0.250 8 1 15 0.924 13.86 - - - - -
- - - - - -
Plinth
Vertical
Beam 05 Grid C1 TO C4 - - - - - -
Bay 3.108 4.228 1.837 - - - - - -
Plinth Beam
0.008
Size 0.23 0.3 - - - - - -
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.225 0.225 - - - - - -
- - - - - -
10.320 12 1 2 10.772 - - 21.544 - - -
Top Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
10.320 12 1 2 10.772 - - 21.544 - - -
Bottom Rod
0.250 0.250 - - - - - -
- - - - - -
- - - - - -
1.150 12 1 1 1.368 - - 1.368 - - -
0.250 - - - - - -
- - - - - -
2.325 16 1 2 2.325 - - - 4.650 - -
Top Extra
- - - - - -
Rod
1.950 16 1 2 1.950 - - - 3.900 - -
- - - - - -
0.755 12 1 1 0.755 - - 0.755 - - -
CMTI, Bangalore
130
Top Extra ESTIMATION AND COSTING
Rod
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
0.250 - - - - - -
- - - - - -
- - - - - -
2.260 12 1 1 2.260 - - 2.260 - - -
Bottom
- - - - - -
Extra Rod
2.980 12 1 1 2.980 - - 2.980 - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.250 8 1 44 0.924 40.66 - - - - -
CMTI, Bangalore
131
ESTIMATION AND COSTING
Stirrups c/c
0.175 0.175 - - - - - -
- - - - - -
8.101 12 1 2 8.803 - - 17.606 - - -
Top Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
8.101 12 1 2 8.803 - - 17.606 - - -
Bottom Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
1.470 - - - - - -
Top Extra 0.375 12 1 2 1.821 - - 3.642 - - -
Rod - - - - - -
2.290 16 1 2 2.290 - - - 4.580 - -
- - - - - -
CMTI, Bangalore
132
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
- - - - - -
Bottom Extra 3.095 16 1 1 3.095 - - - 3.095 - -
Rod - - - - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.375 8 1 43 1.174 50.48 - - - - -
- - - - - -
Roof Beam
02
Horizontal Grid A2 TO C2 - - - - - -
Bay 4.461 2.863 - - - - - -
Roof Beam
0.008
Size 0.23 0.425 - - - - - -
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
8.101 12 1 2 8.803 - - 17.606 - - -
Top Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
8.101 12 1 2 8.803 - - 17.606 - - -
Bottom Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
2.290 12 1 2 2.633 - - 5.266 - - -
Top Extra 0.375 - - - - - -
Rod - - - - - -
CMTI, Bangalore
133
ESTIMATION AND COSTING
Length of
No of
Sl Top
No Extra Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
Rod metre
3.045 16 1 3 3.045 - - - 9.135 - -
- - - - - -
- - - - - -
Bottom Extra 3.095 16 1 2 3.095 - - - 6.190 - -
Rod - - - - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.375 8 1 43 1.174 50.48 - - - - -
- - - - - -
Roof Beam
03
Horizontal Grid A3 TO C3 - - - - - -
Bay 4.461 2.863 - - - - - -
Roof Beam
0.008
Size 0.23 0.425 - - - - - -
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
8.101 12 1 2 8.803 - - 17.606 - - -
Top Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
8.101 12 1 2 8.803 - - 17.606 - - -
Bottom Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
1.400 12 1 2 1.743 - - 3.486 - - -
CMTI, Bangalore
Top Extra 134
Rod
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
0.375 - - - - - -
- - - - - -
Top Extra 2.290 16 1 2 2.290 - - - 4.580 - -
Rod 12 1 1 2.290 - - 2.290 - - -
- - - - - -
1.000 16 1 1 1.351 - - - 1.351 - -
0.375 - - - - - -
- - - - - -
- - - - - -
Bottom Extra 3.095 12 1 2 3.095 - - 6.190 - - -
Rod - - - - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.375 8 1 43 1.174 50.48 - - - - -
- - - - - -
Roof Beam
04
Horizontal Grid A4 TO C4 - - - - - -
Bay 7.464 - - - - - -
Roof Beam
0.008
Size 0.23 0.425 - - - - - -
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
8.101 12 1 2 8.803 - - 17.606 - - -
Top Rod
0.375 0.375 - - - - - -
- - - - - -
CMTI, Bangalore
135
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
- - - - - -
8.101 12 1 2 8.803 - - 17.606 - - -
Bottom Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
3.095 12 1 1 3.095 - - 3.095 - - -
Bottom Extra
- - - - - -
Rod
2.055 12 1 1 2.055 - - 2.055 - - -
- - - - - -
- - - - - -
Stirrups 0.180 0.375 8 1 45 1.174 52.83 - - - - -
- - - - - -
Roof Beam
01 Vertical Grid A1 TO A3 - - - - - -
Bay 3.178 4.298 1.834 - - - - - -
Roof Beam
0.008
Size 0.23 0.425 - - - - - -
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
10.320 12 1 2 11.022 - - 22.044 - - -
Top Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
10.320 12 1 2 11.022 - - 22.044 - - -
Bottom Rod
0.375 0.375 - - - - - -
- - - - - -
CMTI, Bangalore
136
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
- - - - - -
2.300 16 1 2 2.300 - - - 4.600 - -
12 1 1 2.300 - - 2.300 - - -
Top Extra
- - - - - -
Rod
3.484 16 1 3 3.484 - - - 10.452 - -
0.375 - - - - - -
- - - - - -
- - - - - -
2.215 12 1 1 2.215 - - 2.215 - - -
Bottom Extra
- - - - - -
Rod
2.985 12 1 1 2.985 - - 2.985 - - -
- - - - - -
- - - - - -
0.180 0.375 8 1 43 1.174 50.48 - - - - -
Stirrups
0.180 0.375 8 1 19 1.174 22.31 - - - - -
- - - - - -
Roof Beam
02 Vertical Grid B1 TO B3 - - - - - -
Bay 3.248 4.368 1.837 - - - - - -
Plinth Beam
0.008
Size 0.23 0.425 - - - - - -
Nominal
Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
- - - - - -
10.320 12 1 2 11.022 - - 22.044 - - -
Top Rod
0.375 0.375 - - - - - -
CMTI, Bangalore
137
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Top Rod Member
metre
- - - - - -
- - - - - -
10.320 12 1 2 11.022 - - 22.044 - - -
Bottom Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
- - - - - -
2.230 16 1 1 2.230 - - - 2.230 - -
Top Extra
- - - - - -
Rod
3.484 16 1 4 5.714 - - - 22.856 - -
0.375 - - - - - -
- - - - - -
- - - - - -
Bottom Extra 2.985 12 1 1 2.985 - - 2.985 - - -
Rod - - - - - -
- - - - - -
- - - - - -
0.180 0.375 8 1 44 1.174 51.66 - - - - -
Stirrups
0.180 0.375 8 1 19 1.174 22.31 - - - - -
- - - - - -
Roof Beam
03 Vertical Grid C1 TO C3 - - - - - -
Bay 3.108 4.228 1.834 - - - - - -
Roof Beam
0.008
Size 0.23 0.425 - - - - - -
Nominal Cover 0.025 0.025 - - - - - -
Stirrups c/c 0.175 0.175 - - - - - -
CMTI, Bangalore
138
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
- - - - - -
10.320 12 1 2 11.022 - - 22.044 - - -
Top Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
10.320 12 1 2 11.022 - - 22.044 - - -
Bottom Rod
0.375 0.375 - - - - - -
- - - - - -
- - - - - -
- - - - - -
2.300 16 1 2 2.300 - - - 4.600 - -
Top Extra
- - - - - -
Rod
3.484 16 1 3 5.784 - - - 17.352 - -
0.375 - - - - - -
- - - - - -
- - - - - -
Bottom Extra
2.985 12 1 1 2.985 - - 2.985 - - -
Rod
- - - - - -
- - - - - -
0.180 0.375 8 1 46 1.174 54.00 - - - - -
Stirrups
0.180 0.375 8 1 19 1.174 22.31 - - - - -
CMTI, Bangalore
139
ESTIMATION AND COSTING
CMTI, Bangalore
140
ESTIMATION AND COSTING
Length
Dia of No of No of
Sl No Description of bar in 8mm 10mm
bar Member rod
X - direction metre
2.245 - -
- -
Cut rod in Crank portion 8 1 10 2.094 20.94 -
2.094 - -
0.817 - -
X - direction 0.115 8 1 11 3.177 34.94 -
2.245 - -
- -
Cut rod in Crank portion 8 1 10 0.963 9.63 -
0.963 - -
- -
X - direction Distributor 8 2 5 3.353 33.53 -
3.353 - -
0.862 - -
Y - direction 8 1 8 3.485 27.88 -
0.115 2.508 - -
- -
Cut rod in Crank portion 8 1 8 1.043 8.34 -
1.043 - -
1.971 - -
Y - direction 0.115 8 1 8 4.593 36.74 -
2.508 - -
- -
Cut rod in Crank portion 8 1 8 2.131 17.05 -
2.131 - -
- -
Y - direction Distributor 8 2 4 3.651 29.21 -
3.651 - -
S2 Two way slab Grid : A2B2 -A3B3 L R T B - -
Clear span 4.532 4.354 0 2.933 3.261 0.000 - -
Bearing 0.23 0.23 0.23 - -
Bay c/c Distance 4.762 4.584 0.000 3.393 3.261 0.000 - -
c/c Spacing rod 0.15 0.125 - -
1.116 - -
X - direction 0.115 8 1 15 4.756 71.33 -
3.525 - -
- -
Cut rod in Crank portion 8 1 16 1.361 21.77 -
1.361 - -
1.870 - -
X - direction 0.115 8 1 15 5.509 82.63 -
3.525 - -
- -
Cut rod in Crank portion 8 1 16 2.096 33.54 -
2.096 - -
- -
X - direction Distributor
CMTI, Bangalore
141
ESTIMATION AND COSTING
Length
Dia of No of No of
Sl No Description of bar in 8mm 10mm
bar Member rod
metre
X - direction Distributor 8 2 7 4.952 69.33 -
4.952 - -
1.896 - -
Y - direction 8 1 19 5.393 102.46 -
0.115 3.382 - -
- -
Cut rod in Crank portion 8 1 19 2.131 40.49 -
2.131 - -
1.101 - -
Y - direction 0.115 8 1 18 4.598 82.76 -
3.382 - -
- -
Cut rod in Crank portion 8 1 19 1.316 25.00 -
1.316 - -
- -
Y - direction Distributor 8 2 8 4.744 75.90 -
4.744 - -
S1 Two way slab Grid : B2C2 -B3C3 L R T B - -
Clear span 2.933 4.354 4.532 0.000 0.000 4.354 - -
Bearing 0.23 0.23 0.23 0.23 - -
Bay c/c Distance 3.163 4.584 4.762 0.000 0.000 4.584 - -
c/c Spacing rod 0.175 0.2 - -
1.930 - -
X - direction 0.115 8 1 12 4.290 51.47 -
2.245 - -
- -
Cut rod in Crank portion 8 1 13 2.094 27.22 -
2.094 - -
0.817 - -
X - direction 0.115 8 1 14 3.177 44.47 -
2.245 - -
- -
Cut rod in Crank portion 8 1 13 0.963 12.52 -
0.963 - -
- -
X - direction Distributor 8 2 6 3.353 40.24 -
3.353 - -
1.081 - -
Y - direction 8 1 8 4.578 36.62 -
0.115 3.382 - -
- -
Cut rod in Crank portion 8 1 8 1.316 10.53 -
1.316 - -
2.189 - -
Y - direction 0.115 8 1 8 5.686 45.49 -
3.382 - -
CMTI, Bangalore
142
ESTIMATION AND COSTING
Length
Dia of No of No of
Sl No Description of bar in 8mm 10mm
bar Member rod
metre
- -
Cut rod in Crank portion 8 1 8 2.405 19.24 -
2.405 - -
- -
Y - direction Distributor 8 2 4 4.744 37.95 -
4.744 - -
S1 Two way slab Grid : B3C3 -B4C4 L R T B - -
Clear span 2.933 1.835 0 0.000 4.354 0.000 - -
Bearing 0.23 0.23 0.23 - -
Bay c/c Distance 3.163 2.065 0.000 0.000 4.584 0.000 - -
c/c Spacing rod 0.2 0.175 - -
0.797 - -
X - direction 0.115 8 1 5 3.157 15.78 -
2.245 - -
- -
Cut rod in Crank portion 8 1 6 0.961 5.76 -
0.961 - -
0.817 - -
X - direction 0.115 8 1 5 3.177 15.88 -
2.245 - -
- -
Cut rod in Crank portion 8 1 6 0.963 5.78 -
0.963 - -
- -
X - direction Distributor 8 2 3 3.353 20.12 -
3.353 - -
1.666 - -
Y - direction 8 1 9 3.147 28.32 -
0.115 1.367 - -
- -
Cut rod in Crank portion 8 1 9 1.775 15.97 -
1.775 - -
0.597 - -
Y - direction 0.115 8 1 9 2.079 18.71 -
1.367 - -
- -
Cut rod in Crank portion 8 1 9 0.686 6.18 -
0.686 - -
- -
Y - direction Distributor 8 2 4 2.225 17.80 -
2.225 - -
Chair rod 10 72 1 1 - 72.00
Total Rmt 1815.17 72.00
Unit Weight 0.395 0.617
Total Weight in Kg 717.10 44.44
Total Weight in MT 0.76
CMTI, Bangalore
143
ESTIMATION AND COSTING
Pore 1
1 S2 4.532 14 3.261 2
2 S1 2.933 8 3.261 4
3 S2 4.532 14 4.354 6
5 S1 2.933 8 4.354 8
6 S1 2.933 8 1.835 0
Total No's 72
CMTI, Bangalore
144
Stair Case details Residential Building
ESTIMATION AND COSTING
BUA: 914 sft
Length of
Dia of No of No of
Description Shape of Bar bar in 8mm 10mm 12mm
bar Member rod
metre
Staircase
All Dimensions are in metre
Waist Slab Grid : A3B3 -A4B4 L R T B - - -
Clear span 4.532 1.865 2.933 4.354 - - -
Bearing 0.23 0.23 0.23 0.23 - - -
Bay c/c Distance 4.762 2.095 3.163 4.584 - - -
Width 0.914
c/c Spacing rod 0.1 0.15 - - -
First Flight
Main Reinforcement in
10 1 10 2.14 21.37
Double Mat in Going
Distributor
Reinforcement in Double 8 1 13 0.86 11.23
Mat in Going
Main Reinforcement in
Double Mat in Mid 10 1 10 2.73 27.34
Landing
Distributor
Reinforcement in Double 8 1 16 0.86 13.82
Mat in Mid Landing
Second Flight
Main Reinforcement in
10 1 10 2.64 26.36
Double Mat in Going
Distributor
Reinforcement in Double 8 1 17 0.86 14.69
Mat in Going
Main Reinforcement in
Double Mat in Mid 10 1 10 2.73 27.34
Landing
Distributor
Reinforcement in Double 8 1 16 0.86 13.82
Mat in Mid Landing
Bottom Beam & Mid
Landing Beam Grid B3 to B4 & A3 to A4
CMTI, Bangalore
145
Length of ESTIMATION AND COSTING
Dia of No of No of
Description Shape of Bar bar in 8mm 10mm 12mm
bar Member rod
metre
Bay 1.835 1.837
Beam Size 0.23 0.305 0.008
Nominal Cover 0.025
Stirrups c/c 0.15
CMTI, Bangalore
146
LINTEL & SUNSHADE Residential Building
ESTIMATION AND COSTING
BUA: 914 sft
Length of
Dia of No of No of
Item Reinforcement Shape bar in 8mm
bar Member rod
metre
Lintel
All Dimensions are in metre
CMTI, Bangalore
147
Length of
Dia of No of No ofESTIMATION AND COSTING
Item Reinforcement Shape bar in 8mm
Door 03 bar Member rod
metre
Stirrups 0.23 m c/c 0.100 0.180 8 1 7 0.640 4.48
-
CMTI, Bangalore
148
ESTIMATION AND COSTING
CMTI, Bangalore
149
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT ESTIMATION AND COSTING
150
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
CMTI, Bangalore
ESTIMATION AND COSTING
CMTI, Bangalore
151
ESTIMATION AND COSTING
132
CMTI, Bangalore
152
ESTIMATION AND COSTING
134
CMTI, Bangalore
153
ESTIMATION AND COSTING
135
CMTI, Bangalore
154
ESTIMATION AND COSTING
136
CMTI, Bangalore
155
ESTIMATION AND COSTING
137
CMTI, Bangalore
156
ESTIMATION AND COSTING
138
CMTI, Bangalore
157
ESTIMATION AND COSTING
W3 W3
9"
MD
3'-3" 3'-3" 7'-0" 16'-0"
17'-6"
6'-0"
W2 ser.ver. o.t.s 6'-3"
6'-0"
10'-0"
bed slab at +3.05m lvl foyer
1'-0"
12'-6" bal KW W
wr D2
D2
12'-6" 17'-6"
20'-421"
4'-0"
22'-721"
10'-0"
1" kitchen
42
9"
15'-1021"
FLAT - 1A,2A,3A,4A
V D2
5'-1021"
2'-0" toi living
11'-6" duct
2'-0"
5'-6" D1
10'-0"
39'-6"
11'-6"
5'-6"
5'-6"
6'-0"
toi
4'-421"
2'-0" dress
14'-1021"
V 10'-0" dining wr
1" D2
2'-3" 17'-6"
42
5'-0"
9"
wr D dress
D
4'-0" D2
master bed 12'-6"
15'-0"
12'-6"
bed
FD
9'-721"
W2
10'-0"
eq eq toi
1'-0"
bal
6'-0"
bal
D2 3'-9" 3'-9"
9"
2'-0"
2'-0"
2'-0"
W3 W3 duct V W1
duct
4'-0" 7'-6"
1"
42 1"
11'-12
9" 17'-6" 9" 11'-9" 9" 6'-0"
158
FLOOR PLAN (PART)
CMTI, Bangalore
ESTIMATION AND COSTING
133
CMTI, Bangalore
159
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT ESTIMATION AND COSTING
160
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
CMTI, Bangalore
ESTIMATION AND COSTING
NOTES:
1. The drawings is S+4 Structure of 03 units in each floor.
2. Only part drawing of 01 unit is considered for this exercise.
3. In stilt floor only column sizes are 300mm or 1’ sizes.
4. Upper floor it’s 230mm or 9” thick.
5. For Excavation 6” extra considered on all sides.
6. Here excavation GL is considered flat. But actual site it may vary.
7. PCC thickness 5”.
8. Tie Beam/Plinth top is laid at GL .
9. Height of short column varies ( footing top to Tie beam bottom) due to
different depth of footing. (16” – 27”)
10.Basement height considered 2’.
11.PCC considered 1:4:8.
12.All calculation restricted including BBS up to plinth level for only sample
study.
13.Rates of materials are highly varying in 2021. Hence the rates have to
checked from place to place also time to time.
14.The market rates of building materials & wages of labour varies from
place to place and time to time.
15. The coefficients can be tuned as per local practice & PWD standard.
CMTI, Bangalore
161
ESTIMATION AND COSTING
FOOTING CALCULATION:
S.no Details Size in Feet Size in Metre Size in feet Size in metre
Bottom Bottom Top Top
1 F1 5’ x 5’ 1.52 x 1.52 1’ 4” x 1’ 10” 0.41 x 0.56
2 F2 5’6” x 5’6” 1.68 x 1.68 1’ 4” x 1’ 10” 0.41 x 0.56
3 F3 6’6” x 6’6” 1.98 x 1.98 1’ 4” x 1’ 10” 0.41 x 0.56
4 F4 7’ x 7’ 2.13 x 2.13 1’ 4” x 1’ 10” 0.41 x 0.56
5 F5 8’ x 8’ 2.44 x 2.44 1’ 4” x 1’ 10” 0.41 x 0.56
6 F6 10’ x 10’ 3.05 x 3.05 1’ 4” x 2’ 04” 0.41 x 0.71
(1) = Lx B x D
= 5’ X 5’ X 8”(0.667’)
=16.675 CFT
(2) = H/3 (A1 + A2 +√A1xA2)
A1 – Top Area & A2 – Bottom Area
A1 = 1’4” x 1’10” = 2.44 SFT
A2 = 5’ x 5’ = 25 SFT
(2) = H/3 (A1 + A2 +√A1xA2)
= 0.667/3 (2.44 + 25 +√2.44 x 25)
= 7.84 CFT
Total Volume = 16.675 + 7.84 = 24.515 CFT
CMTI, Bangalore
162
ESTIMATION AND COSTING
FOOTING - 2
(1) = 5’6” x 5’6” x 0.667’
= 20.18 CFT
(2) = H/3 (A1 + A2 +√A1xA2)
A1 – Top Area & A2 – Bottom Area
A1 = 1’4” x 1’10” = 2.44 SFT
A2 = 5’6” x 5’6”
= 30.25 SFT
FOOTING – 3
(1) =6’6” x 6’6” x 0.667
= 28.18 CFT
(2)= H/3 (A1 + A2 +√A1xA2)
= 18.28 CFT
FOOTING – 4
(1) = 7’ x 7’ x 0.667
= 32.683 CFT
(2) = H/3 (A1 + A2 +√A1xA2)
A1 – Top Area & A2 – Bottom Area
A1 = 1’4” x 1’10” = 2.44 SFT
A2 = 7’ x 7’ = 49 SFT
CMTI, Bangalore
163
ESTIMATION AND COSTING
FOOTING - 5
(1) = 8’ X 8 X 0.667
= 42.688 CFT
A1 = 2.44 SFT
A2 = 8’ X 8’ = 64 SFT
= 35.074 CFT
FOOTING – 6
A1 – 1’ 4” X 2’ 4”
= 3.11 SFT
A2 = 10’ x 10’ = 100 SFT
(2) = 1.583/3 ( 3.11 + 100 + √3.11x100 )
= 63.713 CFT
Total volume = 66.67 + 63.713 = 130.383 CFT
CMTI, Bangalore
164
ESTIMATION AND COSTING
CMTI, Bangalore
165
ESTIMATION AND COSTING
CMTI, Bangalore
166
ESTIMATION AND COSTING
CMTI, Bangalore
167
ESTIMATION AND COSTING
CMTI, Bangalore
168
ESTIMATION AND COSTING
L PCC 1:4:8
Plinth level CFT 1461.43 0.333 486.65 13.786 CUM
CMTI, Bangalore
169
ESTIMATION AND COSTING
CMTI, Bangalore
170
ESTIMATION AND COSTING
CMTI, Bangalore
171
ESTIMATION AND COSTING
CMTI, Bangalore
172
ESTIMATION AND COSTING
Break Up:
Substructure Cost Rs. 8,73,425.68
Rate per SFT Rs. 444.46
CMTI, Bangalore
173
ESTIMATION AND COSTING
CMTI, Bangalore
174
ESTIMATION AND COSTING
Total Qty
Quantity per of
S.no Description Unit Cum Est.Qty materials
1 Material
Cement Bag 0.14 34.80 4.87
CMTI, Bangalore
175
ESTIMATION AND COSTING
Total Qty
Quantity per of
S.no Description Unit Cum Est.Qty materials
CMTI, Bangalore
176
ESTIMATION AND COSTING
BILL OF MATERIALS
BUA: 1965.13 SFT Structure is: S+4 Floors
Part drawing study done for one house up to plinth level:
S.no Items Unit OTY Rate Amount
1 Cement Bag 411.09 420 172658.76
2 Quarry dust for filling Cum 31.97 1059.00 33857.78
3 M.Sand Cum 33.67 1765.5 59451.25
4 P.Sand Cum 0.84 1765.5 1475.07
5 Gravel Cum 1.43 706.2 1008.96
6 Agg 40 mm Cum 26.66 1129.92 30122.86
7 Agg 20 mm Cum 31.57 1129.92 35677.02
8 Brick Nos 5301.16 8.5 45059.87
Steel
9 8mm Kg 395.91 58 22962.78
10 10mm Kg 742.06 58 43039.76
11 12mm Kg 306.45 58 17773.87
12 16mm Kg 453.98 58 26331.07
13 20mm Kg 259.35 58 15042.30
14 25mm Kg 161.70 58 9378.60
15 Binding Wire Kg 19.50 70 1365.13
TOTAL 515205.09
Break up :
1 Materials Cost = 515205.094
Total cost with
contract (Materials + Rate per
2 Labour) = 8,73,425.68 444.46 SFT
CMTI, Bangalore
177
ESTIMATION AND COSTING
CMTI, Bangalore
178
ESTIMATION AND COSTING
- - - - - -
Y - direction 0.200 1.550 0.200 10 2 11 1.950 - 42.90 - - - -
- - - - - -
Footing 3 - - - - - -
Clear span 1.85 1.85 - - - - - -
Nominal Cover 0.05 0.05 - - - - - -
Over all Length 1.95 1.95 - - - - - -
c/c Distance 0.15 0.15 - - - - - -
- - - - - -
X - direction 0.100 1.850 0.100 10 3 13 2.050 - 79.95 - - - -
- - - - - -
- - - - - -
Y - direction 0.100 1.850 0.100 10 3 13 2.050 - 79.95 - - - -
- - - - - -
Footing 4 Column ID's 5 & 8 - - - - - -
Clear span 2.1 2.1 - - - - - -
Nominal Cover 0.05 0.05 - - - - - -
Over all Length 2.2 2.2 - - - - - -
c/c Distance 0.15 0.15 - - - - - -
- - - - - -
X - direction 0.100 2.100 0.100 10 6 15 2.300 - 207.00 - - - -
- - - - - -
- - - - - -
Y - direction
CMTI, Bangalore
179
ESTIMATION AND COSTING
CMTI, Bangalore
180
ESTIMATION AND COSTING
CMTI, Bangalore
181
ESTIMATION AND COSTING
From footing.Lvl
to plinth Top
2.2 2.2 - - - - -
Nominal Cover 0.04 0.04 - - - - -
Main Rod 0.012 - - - - -
Column Size 0.3 0.45 0.008 - - - - -
Stirrups c/c 0.2 0.2 - - - - -
- - - - -
Main Rod 2.200 0.300 12 1 8 2.500 - - 20.000 - -
- - - - -
Laps - - -
- - - - - -
Stirrups 0.220 0.370 8 1 12 1.244 14.93 - - - - -
- - - - - -
- - - - - -
Stirrups 0.150 0.370 8 1 12 1.104 13.25 - - - - -
- - - - - -
0.150 - - - - - -
0.080 0.080 8 1 12 0.278 3.34 - - - - -
Links
Column F2 - - - - - -
CMTI, Bangalore
182
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
From G.Lvl to Column
Plinth Top 2.2 2.2 - - - - - -
Nominal Cover 0.04 0.04 - - - - - -
Main Rod 0.012 0.016 - - - - - -
Column Size 0.3 0.45 0.008 - - - - - -
Stirrups c/c 0.2 0.2 - - - - - -
- - - - - -
Main Rod 2.200 0.300 12 2 2 2.500 - - 10.000 - - -
16 2 4 2.500 - - - 20.000 - -
- -
Laps
- -
- - - - - -
Stirrups 0.220 0.370 8 2 12 1.244 29.86 - - - - -
- - - - - -
- - - - - -
Stirrups 0.150 0.370 8 2 12 1.104 26.50 - - - - -
- - - - - -
0.150 - - - - - -
0.080 0.080 8 2 12 0.278 6.67 - - - - -
Links
Column F3 - - - - - -
From G.Lvl to
Plinth Top 2.2 2.2 - - - - - -
Nominal Cover 0.04 0.04 - - - - - -
Main Rod 0.016 - - - - - -
Column Size 0.3 0.45 0.008 - - - - - -
Stirrups c/c 0.2 0.2 - - - - - -
- - - - - -
Main Rod
CMTI, Bangalore
183
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
Main Rod Column
2.200 0.300 16 3 6 2.500 - - - 45.000 - -
12 3 2 2.500 - - 15.000 - - -
Laps -
- - - - - -
Stirrups 0.220 0.370 8 3 12 1.244 44.78 - - - - -
- - - - - -
-
Stirrups 0.150 0.370 8 3 12 1.104 39.74
-
0.150 -
Links 0.080 0.080 8 3 12 0.278 10.01
Column 4
From G.Lvl
toPlinth Top 2.2 2.2 - - - - - -
Nominal Cover 0.04 0.04 - - - - - -
Main Rod 0.02 0.016 - - - - - -
Column Size 0.3 0.45 0.008 - - - - - -
Stirrups c/c 0.2 0.2 - - - - - -
- - - - - -
Main Rod 2.200 0.300 20 6 4 2.500 - - - - 60.000 -
16 6 2 2.500 - - - 30.000 - -
12 6 2 2.500 - - 30.000 - - -
Laps - - -
- - - - - -
Stirrups 0.220 0.370 8 6 12 1.244 89.57 - - - - -
Stirrups
CMTI, Bangalore
184
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
Stirrups 0.150 Column
0.370 8 6 12 1.104 79.49 - - - - -
- - - - - -
0.150 - - - - - -
0.080 0.080 8 6 12 0.278 20.02 - - - - -
Links
Column F5 - - - - - -
From G.Lvl to
F.F Plinth Top 2.2 2.2 - - - - - -
Nominal Cover 0.04 0.04 - - - - - -
Main Rod 0.02 - - - - - -
Column Size 0.3 0.45 0.008 - - - - - -
Stirrups c/c 0.2 0.2 - - - - - -
- - - - - -
Main Rod 2.200 0.300 20 2 8 2.500 - - - - 40.000 -
12 2 2 2.500 - - 10.000 - - -
Laps - - -
- - - - - -
Stirrups 0.220 0.370 8 2 12 1.244 29.86 - - - - -
- - - - - -
- - - - - -
Stirrups 0.150 0.370 8 2 12 1.104 26.50 - - - - -
- - - - - -
- - - - - -
Stirrups 0.120 0.150 8 2 12 0.604 14.50 - - - - -
- - - - - -
- - - - - -
Column F6 - - - - - -
CMTI, Bangalore
185
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm 25mm
Member
metre
From G.Lvl to Column
PlinthF.F roof
Top 2.2 2.2 - - - - - -
Nominal Cover 0.04 0.04 - - - - - -
Main Rod 0.02 - - - - - -
Column Size 0.3 0.6 0.008 - - - - - -
Stirrups c/c 0.2 0.2 - - - - - -
- - - - - -
Main Rod 2.200 0.300 25 2 8 2.500 - - - - - 40.000
12 2 3 2.500 - - 15.000 - - -
Laps - - -
- - - - - -
Stirrups 0.220 0.520 8 2 12 1.544 37.06 - - - - -
- - - - - -
- - - - - -
Stirrups 0.150 0.520 8 2 12 1.404 33.70 - - - - -
- - - - - -
- - - - - -
Stirrups 0.170 0.150 8 2 12 0.704 16.90 - - - - -
CMTI, Bangalore
186
ESTIMATION AND COSTING
CMTI, Bangalore
187
ESTIMATION AND COSTING
Length of
Top No of
Sl NoExtra Rod Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm
Member
metre
- - - - -
- - - - -
Stirrups 0.180 0.325 8 1 73 1.074 78.40 - - - -
- - - - -
Plinth
Horizonal
Beam Grid D1 TO D4 - - - - -
Bay TB3 TB3 - - - - -
Plinth Beam
0.008
Size 0.23 0.375 - - - - -
Nominal
Cover 0.025 0.025 - - - - -
Stirrups c/c 0.2 0.2 - - - - -
- - - - -
8.790 12 1 2 9.392 - - 18.784 - -
Top Rod
0.325 0.325 - - - - -
- - - - -
- - - - -
8.790 16 1 2 9.392 - - - 18.784 -
Bottom Rod
0.325 0.325 - - - - -
- - - - -
- - - - -
- - - - -
Top Extra Rod 2.740 16 1 1 2.740 - - - 2.740 -
- - - - -
- - - - -
- - - - -
- - - - -
Stirrups
CMTI, Bangalore
188
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm
Member
metre
Stirrups 0.180 0.325 8 1 44 1.074 47.26 - - - -
- - - - -
Plinth
Horizonal
Beam Grid C5 TO C7 - - - - -
Bay TB4 - - - - -
Plinth Beam
0.008
Size 0.23 0.375 - - - - -
Nominal
Cover 0.025 0.025 - - - - -
Stirrups c/c 0.2 0.2 - - - - -
- - - - -
5.820 12 1 2 6.422 - - 12.844 - -
Top Rod
0.325 0.325 - - - - -
- - - - -
- - - - -
5.820 16 1 3 6.422 - - - 19.266 -
Bottom Rod
0.325 0.325 - - - - -
- - - - -
- - - - -
Stirrups 0.180 0.325 8 1 31 1.074 33.29 - - - -
- - - - -
Plinth
Horizonal
Beam Grid F5 TO F7 - - - - -
Bay TB 4 - - - - -
Plinth Beam
0.008
Size 0.23 0.375 - - - - -
CMTI, Bangalore
189
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm
Member
metre
Nominal
Cover 0.025 0.025 - - - - -
Stirrups c/c 0.2 0.2 - - - - -
- - - - -
5.820 12 1 2 6.422 - - 12.844 - -
Top Rod
0.325 0.325 - - - - -
- - - - -
- - - - -
5.820 16 1 3 6.422 - - - 19.266 -
Bottom Rod
0.325 0.325 - - - - -
- - - - -
- - - - -
Stirrups 0.180 0.325 8 1 31 1.074 33.29 - - - -
- - - - -
Plinth
Vertical Beam
Grid H1 TO H6 - - - - -
Bay TB4 TB1 TB1 - - - - -
Plinth Beam
0.008
Size 0.23 0.375 - - - - -
Nominal
Cover 0.025 0.025 - - - - -
Stirrups c/c 0.2 0.2 - - - - -
- - - - -
10.850 12 1 2 11.452 - - 22.904 - -
Top Rod
0.325 0.325 - - - - -
- - - - -
- - - - -
Bottom Rod
CMTI, Bangalore
190
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm
Member
metre
0.325 16 1 3 6.368 - - - 19.104 -
Bottom Rod
6.075 - - - - -
- - - - -
- - - - -
5.235 12 1 2 5.536 - - 11.072 - -
Bottom Rod
0.325 - - - - -
- - - - -
- - - - -
5.640 12 1 1 5.640 - - 5.640 - -
- - - - -
- - - - -
- - - - -
Stirrups 0.180 0.325 8 1 54 1.074 58.00 - - - -
- - - - -
Plinth
Vertical Beam
Grid A1 TO H1 - - - - -
Bay TB3 TB3 TB2 - - - - -
Plinth Beam
0.008
Size 0.23 0.375 - - - - -
Nominal
Cover 0.025 0.025 - - - - -
Stirrups c/c 0.2 0.2 - - - - -
- - - - -
11.990 12 1 2 12.592 - - 25.184 - -
Top Rod
0.325 0.325 - - - - -
- - - - -
- - - - -
Bottom Rod
CMTI, Bangalore
191
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm
Member
metre
7.975 16 1 2 12.592 - - - 25.184 -
Bottom Rod
0.325 - - - - -
- - - - -
Bottom Rod 4.315 0.325 12 1 3 4.616 - - 13.848 - -
- - - - -
- - - - -
Top extra 2.740 12 1 1 2.740 - - 2.740 - -
- - - - -
Top Extra 2.740 12 1 1 2.740 - - 2.740 - -
- - - - -
- - - - -
Stirrups 0.180 0.325 8 1 54 1.074 58.00 - - - -
- - - - -
Plinth
Vertical Beam
Grid A5 TO H5 - - - - -
Bay TB3 TB2 TB3, TB1 - - - - -
Plinth Beam
0.008
Size 0.23 0.375 - - - - -
Nominal
Cover 0.025 0.025 - - - - -
Stirrups c/c 0.2 0.2 - - - - -
- - - - -
11.990 12 1 2 12.592 - - 25.184 - -
Top Rod
0.325 0.325 - - - - -
- - - - -
Bottom Rod 11.990 16 1 2 12.592 - - - 25.184 -
0.325 0.325 - - - - -
CMTI, Bangalore
192
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm
Member
metre
- - - - -
- - - - -
5.030 12 1 1 5.030 - - 5.030 - -
- - - - -
Top Extra Rod - - - - -
2.890 16 1 1 2.890 - - - 2.890 -
- - - - -
- - - - -
- - - - -
Stirrups 0.180 0.325 8 1 60 1.074 64.44 - - - -
Plinth
Vertical Beam
Grid A7 TO F7
Bay TB3 TB2 - - - - -
Plinth Beam
0.008
Size 0.23 0.375 - - - - -
Nominal
Cover 0.025 0.025 - - - - -
Stirrups c/c 0.2 0.2 - - - - -
- - - - -
8.330 12 1 2 8.932 - - 17.864 - -
Top Rod
0.325 0.325 - - - - -
- - - - -
Bottom Rod 0.325 4.895 16 1 2 5.188 - - - 10.376 -
- - - - -
3.900 0.325 12 1 3 4.201 - - 12.603 - -
CMTI, Bangalore
193
ESTIMATION AND COSTING
Length of
No of
Sl No Description Dia of bar No of rod bar in 8mm 10mm 12mm 16mm 20mm
Member
metre
- - - - -
- - - - -
2.890 12 1 1 2.890 - - 2.890 - -
- - - - -
- - - - -
- - - - -
Stirrups 0.180 0.325 8 1 42 1.074 45.11 - - - -
CMTI, Bangalore
194
ESTIMATION AND COSTING
CMTI, Bangalore
195
ESTIMATION AND COSTING
CMTI, Bangalore
196