ID Task Task Name Duration December


Start 2023 January 2024 February 2024 March 2024 April 2024
Mode 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2 7 12 17 22 27 1 6
1 ADAMJEE INSURANCE M.S STRUCTURE WORK 90 days? 1/1/2024
2 Mobilization 6 days 1/1/2024
3 Site Clearance 4 days 1/1/2024
4 Site office 2 days 1/5/2024
5 As-Built 16 days? 1/1/2024
6 Existing Detail & Dimensioning 3 days 1/1/2024
7 Dismantling of Existing Structure 5 days 1/4/2024
8 Inspection of work 1 day? 1/9/2024
9 Hidden Elements 2 days 1/10/2024
10 Removal of Existing False Ceiling 5 days 1/12/2024
11 Material Submittals 8 days 1/17/2024
12 Transportation for Hot Rolled section to Site of 2 days 1/17/2024
Work
13 Shifting Section @ 10th Floor 6 days 1/19/2024
14 Installation of Buil-up Section 40 days 1/6/2024
15 Fixing of Angels & Plates 13 days 1/6/2024
16 Cleaning, Cutting & Straightening Sections 7 days 1/19/2024
17 Fixing in Position 14 days 1/26/2024
18 Two Coats of Epoxy Zinc Phosphate Primer 3 days 2/9/2024
19 Two Coats of Anti Rust Enamel Paint 3 days 2/12/2024
20 MS Foundation Platform for Fibre Tank 15 days 2/15/2024
21 Dismantle of Existing Tank 2 days 2/15/2024
22 MS Foundation Platform for Fibre Tanks over 1 day 2/17/2024
column pedestal
23 Ms Corrugated Structure 3 days 2/18/2024
24 Connection with Existing Shed 2 days 2/21/2024
25 Fixing of Plate 2 days 2/23/2024
26 welding angles with section 3 days 2/25/2024
27 Fixing Corrugated sheet 2 days 2/28/2024
28 Shop Drawings 30 days 3/1/2024
29 Detail & Dimensioning 30 days 3/1/2024

Page 1
Engineeric Construction Services

2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 3 8 13 18 23 28 3 8 13 18 23 28

Page 2
Engineeric Construction Services

Task Project Summary Manual Task Start-only Deadline

Project: MS Split Inactive Task Duration-only Finish-only Progress


Date: 11/21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone