DAILY PROGRESS REPORT

Client : Jindal Paradip Port Ltd. Project No :

Vessel : M.L. Chandrama Date : 2/18/2024


Location : Paradip DPR No : 3
Party Chief: Mr. Manoranjan Rath (Project Manager) Client Rep.: Mr. Debashish
Project Title Bathymetric and Geophysical Survey at Paradip Port, Odisha

Survey Personnel :
1. Mr. Amit Jurel 2. Mr. Vishtasp Mehta 3. Shubham Sutrakar 4. Dhanasekaran Narayan

1. Norbit MBES with 2. Norbit Positioning 3. Geopulse Sub- 4. Geometrics G882 5. Hypack and
backscatter System bottom Profiler Magnetometer Hysweep software
Equipment
6. CODA DA4G
7. Maglog software 8. Valeport SVP
acquisition

Time (hrs) Activities


From To
23:59 7:00 Standby at hotel in Paradip
7:00 7:30 Team transit to jetty
Mobilization continued, interfacing of computer systems and deck equipment inside boat cabin completed. Carried
7:30 17:00 out DGPS observation at known point provided by client for 2 hours using Norbit system. The results were found
to be within the tolerable limts.
17:00 19:00 Installation of Geopulse SBP tranducer, ladder and pole completed. Inclination of ladder checked.
19:00 19:30 Survey team transit to hotel
19:30 23:59 Team standby at hotel

Survey Details Cumulative details


Geophysical and Bathymetric Survey 0 0

Plan for next 24 hours: Commence function tests of survey equipment and carry out patch test for MBES and calibration of MBES with
reference to SBES.

Remarks:
Safety Statistics Weather Conditions
Daily Cumulative
Tool Box Talk 1 3
Safety Meetings 0
Remarks (if any):