DAILY PROGRESS REPORT

Client : Jindal Paradip Port Ltd. Project No :

Vessel : M.L. Chandrama Date : 2/21/2024


Location : Paradip DPR No : 6
Party Chief: Mr. Manoranjan Rath (Project Manager) Client Rep.: Mr. Debashish
Project Title Bathymetric and Geophysical Survey at Paradip Port, Odisha

Survey Personnel :
1. Mr. Amit Jurel 2. Mr. Vishtasp Mehta 3. Shubham Sutrakar 4. Dhanasekaran Narayan

1. Norbit MBES with 2. Norbit Positioning 3. Geopulse Sub- 4. Geometrics G882 5. Hypack and
backscatter System bottom Profiler Magnetometer Hysweep software
Equipment
6. CODA DA4G
7. Maglog software 8. Valeport SVP
acquisition

Time (hrs) Activities


From To
23:59 6:00 Standby at hotel in Paradip
6:00 6:30 Team transit to jetty
6:30 7:00 Switched on MBES and Magnetometer equipment and cast off to survey area
7:00 7:15 Collection of Sound Velocity Profile data
Carried out Magnetometer and MBES survey (with backscatter) inside the harbour as well as outer channel
7:15 17:30
(approx. 43.5 line km) at line spacing of 30m as instructed by client rep.
17:30 17:45 Collection of Sound Velocity Profile data in deeper area
17:45 18:00 All raw data of MBES including backscatter, SVP files and magnetometer data handed over to client rep.
18:00 18:15 Survey team transit to hotel
18:15 23:59 Team standby at hotel

Survey Details Cumulative details


Magnetometer and MBES 43.5 Magnetometer and MBES 55
Sub-bottom Profiler Survey 0 Sub-bottom Profiler Survey 0

Plan for next 24 hours: Continue with magnetometer and MBES survey

Remarks:
Safety Statistics Weather Conditions
Daily Cumulative
Tool Box Talk 1 6 Calm inside the harbour (inner channel)
Safety Meetings 0
Remarks (if any):

Party Chief Client Representative