GUIDELINE
A. GENERAL
1. Architectural (passive) and M&E (active) plan must be endorsed and approved by Bomba.
2. Passive (Architecture)
a. Installation on site according to approved Bomba drawing.
b. External access road work must meet with bomba requirement
c. Tagging on fire door must be installed along with self-closing device
d. Tagging and labeling for all lift motor room, hose reel/wet riser compartment, service duct, pump room, electrical
room, and etc.
e. All electrical and mechanical risers at floor level and wall penetration must be sealed up with approved fire seal
material.
f. Water supply must be available for all firefighting water tank.
g. Water supply must be available for testing of Fire Hydrants.
h. All signage on fire system related rooms (pump/genset/MSB/transformer/main control) must be installed.
i. Tower Crane and Gondola to be dismantled.
j. External window and facade to be closed
3. Active (Mechanical)
a. Standby generator shall be tested for cranking test and change over mode.
b. Electrical testing (fireman isolating switch, essential power supply for emergency light and Keluar Sign).
c. Electrical supply must be in operation to all firefighting panels and pumps, fireman lift and fire alarm panels.
d. Affix mimic floor plan at lift lobby.
e. Smoke Spill/Pressurization system must be operation and functional
f. Tagging on each jockey, duty, standby pump for sprinkler, wet riser and hosereel systems must be installed.
4. Other services
a. Fireman lift and lift must be inspected and operational.
b. Power supply must be permanent.
c. Water supply must be permanent.
5. Please prepare tables, chairs and light refreshments on the day of inspection.
6. Please make sure all the doors are unlocked and all the keys for any firefighting related equipment are available on the day
of the inspection.
7. Please make sure at least one volunteer from maincon, architect and M & E consultant to closely follow the Bomba officers
during the inspection.
8. Please prepare sufficient walkie-talkie and prepare enough people to standby at main control room, genset room, rooftop
(wet riser) and pump room.
B. BOMBA FORMS & LETTERS
4. C1 C2 C3 FORM
- Title & JBPM reference number as per blue form
- Each form must come with valid Bomba certificate: ‘Sijil Perakuan Bahan or Sijil Pepasangan Keselamatan Kebakaran’
- Materials that required C1 C2 C3 form are as listed in below table:
ITEM RESPONSIBLE CONTRACTOR SIGNED & STAMPED BY
C1 C2 C3
1. MAIN CONTRACTOR
1. Fire Door Manufacturer/Supplier Installer Architect
2. Fire Roller Shutter Manufacturer/Supplier Installer Architect
3. Cement Sand Brick Manufacturer/Supplier Installer Architect
4. Class O Material Manufacturer/Supplier Installer Architect
5. Drywall Construction Manufacturer/Supplier Installer Architect
6. Hollow Concrete Block Manufacturer/Supplier Installer Architect
2. ELECTRICAL CONTRACTOR
1. Emergency Light Manufacturer/Supplier Installer Architect or M&E Consultant
2. KELUAR Sign Manufacturer/Supplier Installer Architect or M&E Consultant
3. Fire Rated Cable Manufacturer/Supplier Installer M&E Consultant
3. ACMV CONTRACTOR
1. Fire Damper Manufacturer/Supplier Installer M&E Consultant
2. Smoke Extraction System Manufacturer/Supplier Installer M&E Consultant
3. Fire Rated Duct Manufacturer/Supplier Installer M&E Consultant
4. Smoke Curtain Manufacturer/Supplier Installer M&E Consultant
4. LIFT CONTRACTOR
1. Fire Rated Lift Landing Door Manufacturer/Supplier Installer M&E Consultant
6. FIRE CONTRACTOR
1. Smoke Detector Manufacturer/Supplier Installer M&E Consultant
2. Heat Detector Manufacturer/Supplier Installer M&E Consultant
3. Alarm Bell or Sounder Manufacturer/Supplier Installer M&E Consultant
4. Breakglass Manufacturer/Supplier Installer M&E Consultant
5. Hosereel Drum Manufacturer/Supplier Installer M&E Consultant
6. Sprinkler Head Manufacturer/Supplier Installer M&E Consultant
7. Fire Alarm Panel Manufacturer/Supplier Installer M&E Consultant
8. Gas Suppression System Manufacturer/Supplier Installer M&E Consultant
9. Dry Powder Fire Extinguisher Manufacturer/Supplier Installer M&E Consultant
10. CO2 Fire Extinguisher Manufacturer/Supplier Installer M&E Consultant
11. Fireman Intercom** Manufacturer/Supplier Installer M&E Consultant
12. Fire Rated Cable Manufacturer/Supplier Installer M&E Consultant
13. Fire Curtain Manufacturer/Supplier Installer Architect or M&E Consultant
14. Fire Stop/Fire Seal
- For site that will be inspected by Bomba Putrajaya HQ, C1 & C2 form must be signed by the same person/company.
5. FORM A (PERAKUAN PEMASANGAN SISTEM SEMBURAN AUTOMATIK)
- Form to be filled up by Fire Contractor / M&E Consultant
- Form to be signed & stamped by Ir M&E Consultant
9. WATER AUTHORITY (SYABAS/SAINS/PAIP/SAJ) CLEARANCE LETTER OR ANY DOCUMENT THAT CAN PROVE WATER SUPPLY IS
PERMANENT
- To be provided by Developer or M&E Consultant
10. TNB CLEARANCE LETTER OR HANDOVER LETTER OR ANY DOCUMENT THAT CAN PROVE ELECTRICAL POWER SUPPLY IS
PERMANENT
- To be provided by M&E Consultant or Electrical Contractor
11. JKKP (DOSH) LIFT CLEARANCE LETTER OR LIFT INSPECTION LETTER OR PMA CERTIFICATE
- To be provided by Lift Contractor
NOTES:
i) Main contractor to pay all fees first in lump sum & claim the cost later from each sub-contractor.
ii) ** The C1C2C3 from & fee will be provided & paid by responsible contractor if the system is not covered by Fire
Contractor
iii) NA - quantity is required for Bomba record only, no need to pay any Bomba inspection fee