BOMBA INSPECTION GENERAL

GUIDELINE
A. GENERAL

1. Architectural (passive) and M&E (active) plan must be endorsed and approved by Bomba.

2. Passive (Architecture)
a. Installation on site according to approved Bomba drawing.
b. External access road work must meet with bomba requirement
c. Tagging on fire door must be installed along with self-closing device
d. Tagging and labeling for all lift motor room, hose reel/wet riser compartment, service duct, pump room, electrical
room, and etc.
e. All electrical and mechanical risers at floor level and wall penetration must be sealed up with approved fire seal
material.
f. Water supply must be available for all firefighting water tank.
g. Water supply must be available for testing of Fire Hydrants.
h. All signage on fire system related rooms (pump/genset/MSB/transformer/main control) must be installed.
i. Tower Crane and Gondola to be dismantled.
j. External window and facade to be closed

3. Active (Mechanical)
a. Standby generator shall be tested for cranking test and change over mode.
b. Electrical testing (fireman isolating switch, essential power supply for emergency light and Keluar Sign).
c. Electrical supply must be in operation to all firefighting panels and pumps, fireman lift and fire alarm panels.
d. Affix mimic floor plan at lift lobby.
e. Smoke Spill/Pressurization system must be operation and functional
f. Tagging on each jockey, duty, standby pump for sprinkler, wet riser and hosereel systems must be installed.

4. Other services
a. Fireman lift and lift must be inspected and operational.
b. Power supply must be permanent.
c. Water supply must be permanent.

5. Please prepare tables, chairs and light refreshments on the day of inspection.

6. Please make sure all the doors are unlocked and all the keys for any firefighting related equipment are available on the day
of the inspection.

7. Please make sure at least one volunteer from maincon, architect and M & E consultant to closely follow the Bomba officers
during the inspection.

8. Please prepare sufficient walkie-talkie and prepare enough people to standby at main control room, genset room, rooftop
(wet riser) and pump room.
B. BOMBA FORMS & LETTERS

1. COVER LETTER TO CALL FOR BOMBA INSPECTION


- To be prepared by architect
- For site that will be inspected by Bomba Putrajaya HQ, then this letter has to be submitted to OSC first to obtain
OSC acknowledgement receipt before it can be submitted to Bomba

2. BORANG SENARAI SEMAK PERMOHONAN PEMERIKSAAN KESELAMATAN KEBAKARAN


- Form to be filled up by Fire Contractor & signed by Architect

3. BLUE FORM (PERAKUAN PEMASANGAN, SISTEM KEBOMBAAN & ELEMEN STRUKTUR)


- Title to be provided by Architect
- JBPM reference number to be obtained from approved Bomba passive or active plan
- Form to be signed & stamped by Ar Architect (2 copies)
- Form to be signed & stamped by Ir M&E Consultant (2 copies)

4. C1 C2 C3 FORM
- Title & JBPM reference number as per blue form
- Each form must come with valid Bomba certificate: ‘Sijil Perakuan Bahan or Sijil Pepasangan Keselamatan Kebakaran’
- Materials that required C1 C2 C3 form are as listed in below table:
ITEM RESPONSIBLE CONTRACTOR SIGNED & STAMPED BY
C1 C2 C3
1. MAIN CONTRACTOR
1. Fire Door Manufacturer/Supplier Installer Architect
2. Fire Roller Shutter Manufacturer/Supplier Installer Architect
3. Cement Sand Brick Manufacturer/Supplier Installer Architect
4. Class O Material Manufacturer/Supplier Installer Architect
5. Drywall Construction Manufacturer/Supplier Installer Architect
6. Hollow Concrete Block Manufacturer/Supplier Installer Architect
2. ELECTRICAL CONTRACTOR
1. Emergency Light Manufacturer/Supplier Installer Architect or M&E Consultant
2. KELUAR Sign Manufacturer/Supplier Installer Architect or M&E Consultant
3. Fire Rated Cable Manufacturer/Supplier Installer M&E Consultant
3. ACMV CONTRACTOR
1. Fire Damper Manufacturer/Supplier Installer M&E Consultant
2. Smoke Extraction System Manufacturer/Supplier Installer M&E Consultant
3. Fire Rated Duct Manufacturer/Supplier Installer M&E Consultant
4. Smoke Curtain Manufacturer/Supplier Installer M&E Consultant
4. LIFT CONTRACTOR
1. Fire Rated Lift Landing Door Manufacturer/Supplier Installer M&E Consultant
6. FIRE CONTRACTOR
1. Smoke Detector Manufacturer/Supplier Installer M&E Consultant
2. Heat Detector Manufacturer/Supplier Installer M&E Consultant
3. Alarm Bell or Sounder Manufacturer/Supplier Installer M&E Consultant
4. Breakglass Manufacturer/Supplier Installer M&E Consultant
5. Hosereel Drum Manufacturer/Supplier Installer M&E Consultant
6. Sprinkler Head Manufacturer/Supplier Installer M&E Consultant
7. Fire Alarm Panel Manufacturer/Supplier Installer M&E Consultant
8. Gas Suppression System Manufacturer/Supplier Installer M&E Consultant
9. Dry Powder Fire Extinguisher Manufacturer/Supplier Installer M&E Consultant
10. CO2 Fire Extinguisher Manufacturer/Supplier Installer M&E Consultant
11. Fireman Intercom** Manufacturer/Supplier Installer M&E Consultant
12. Fire Rated Cable Manufacturer/Supplier Installer M&E Consultant
13. Fire Curtain Manufacturer/Supplier Installer Architect or M&E Consultant
14. Fire Stop/Fire Seal
- For site that will be inspected by Bomba Putrajaya HQ, C1 & C2 form must be signed by the same person/company.
5. FORM A (PERAKUAN PEMASANGAN SISTEM SEMBURAN AUTOMATIK)
- Form to be filled up by Fire Contractor / M&E Consultant
- Form to be signed & stamped by Ir M&E Consultant

6. FORM B (PERAKUAN PEMASANGAN TETAP & SISTEM PENGGERA KEBAKARAN)


- Form to be filled up by Fire Contractor / M&E Consultant
- Form to be signed & stamped by Ir M&E Consultant

7. BORANG BAYARAN PU (A) 207


- Refer ‘C. MATERIAL QUANTITY & BOMBA FEE’ section

8. E-FEIS EXTINGUISHER PAYMENT RECEIPT & QUANTITY


- To be prepared by Fire Contractor

9. WATER AUTHORITY (SYABAS/SAINS/PAIP/SAJ) CLEARANCE LETTER OR ANY DOCUMENT THAT CAN PROVE WATER SUPPLY IS
PERMANENT
- To be provided by Developer or M&E Consultant

10. TNB CLEARANCE LETTER OR HANDOVER LETTER OR ANY DOCUMENT THAT CAN PROVE ELECTRICAL POWER SUPPLY IS
PERMANENT
- To be provided by M&E Consultant or Electrical Contractor

11. JKKP (DOSH) LIFT CLEARANCE LETTER OR LIFT INSPECTION LETTER OR PMA CERTIFICATE
- To be provided by Lift Contractor

12. BUKU OPERASI BOMBA


- To be prepared by Architect or Fire Contractor (3 Hard Copies + 1 Softcopy in DVD)
- Final mimic graphic floor plan, site plan, and side elevation plan to be provided by architect
C. MATERIAL QUANTITY & BOMBA FEE

ITEM RESPONSIBLE CONTRACTOR QUANTITY BOMBA FEE (RM)


1. MAIN CONTRACTOR
1. First Bomba Inspection _______ Inspection 1.00 Per Inspection
2. Second, 3rd, 4th ,…. Bomba Inspection _______ Inspection 100.00 Per Inspection
2. HYDRANT CONTRACTOR
3. Hydrant Pillar _______ Nos NA
4. Hydrant System _______ System 100.00 Per System
3. MAIN CONTRACTOR
1. Fire Door (Single Leaf) _______ Nos 1.00 Per Nos
2. Fire Door (Double Leaf) _______ Nos 1.00 Per Nos
3. Fire Roller Shutter _______ Nos NA
4. ELECTRICAL CONTRACTOR
1. Emergency Light _______ Nos NA
2. KELUAR Sign _______ Nos NA
3. Fireman Isolation Switch _______ Nos NA
5. PA SYSTEM CONTRACTOR
1. PA System _______ System 50.00 Per System
6. ACMV CONTRACTOR
1. Fire Damper (Motorised) _______ Nos 5.00 Per Nos
2. Fire Damper (Fusible Link) _______ Nos 5.00 Per Nos
3. Smoke Extraction System _______ System 50.00 Per System
4. Staircase Pressurization System _______ System 100.00 Per System
5. Lobby Pressurization System _______ System 100.00 Per System
6. Corridor Pressurization System _______ System 100.00 Per System
7. LIFT CONTRACTOR
1. Bomba Lift _______ Nos 50.00 Per Nos
8. FIRE CONTRACTOR
15. Dry Powder Fire Extinguisher _______ Nos NA (E-Feis)
16. CO2 Fire Extinguisher _______ Nos NA (E-Feis)
17. Dry Riser System _______ System 50.00 Per System
18. Wet Riser System _______ System 100.00 Per System
19. Wet Riser Pump _______ Set 50.00 Per Set
20. Breakglass & Alarm Bell _______ Nos 2.00 Per Nos
21. Smoke Detector _______ Nos 1.00 Per Nos
22. Heat Detector _______ Nos 1.00 Per Nos
23. Hosereel Drum _______ Nos 5.00 Per Nos
24. Hosereel Pump _______ Set 50.00 Per Set
25. Fireman Intercom** _______ System 50.00 Per System
26. Sprinkler Head _______ Nos 0.50 Per Nos
27. Sprinkler Pump _______ Set 50.00 Per Set
28. Fire Alarm Panel _______ Nos 20.00 Per Nos
29. CO2/Inert/Clean Agent Fixed Gas _______ System 100.00 Per System
Suppression System _______ System 100.00 Per System

NOTES:
i) Main contractor to pay all fees first in lump sum & claim the cost later from each sub-contractor.
ii) ** The C1C2C3 from & fee will be provided & paid by responsible contractor if the system is not covered by Fire
Contractor
iii) NA - quantity is required for Bomba record only, no need to pay any Bomba inspection fee