RESTRICTED

Multi Role Light Frigate

WBS 4100

OEM No. TP 3541

CWCS Harbour Acceptance Trial Equipment


Volume 1

Command and Weapon Control System

September 2002

RESTRICTED
UK RESTRICTED TP 3541

CONDITIONS OF RELEASE

This information is released by the UK Government for defence purposes only.

This information must be afforded the same degree of security protection as


that afforded to information of an equivalent security marking originated by the
recipient Government or as required by the recipient Government’s security
regulations.

The information may be disclosed only within the Defence Departments of the
recipient Government, except as authorised by the issuing department of the
Ministry of Defence (Navy).

This information may be subject to privately-owned rights.

 2002 Alenia Marconi Systems Limited

The copyright in this document is the property of Alenia Marconi Systems


Limited. The document is supplied by Alenia Marconi Systems Limited with the
express terms that it is to be treated as confidential and that it may not be
copied, used or disclosed to others for any purpose except as authorised in
writing by this company.

Any person, other than the authorised holder, who finds or otherwise obtains
possession of the document, should post it, together with their name and
address, to the Registrar, Alenia Marconi Systems, Lyon Way, Frimley,
Camberley, Surrey, GU16 7EX UK. Postage will be refunded.

UK RESTRICTED Page (iii)/(iv)


UK RESTRICTED TP 3541

AMENDMENT RECORD

Amdt Incorporated by Date Amdt Incorporated by Date


1 35
2 36
3 37
4 38
5 39
6 40
7 41
8 42
9 43
10 44
11 45
12 46
13 47
14 48
15 49
16 50
17 51
18 52
19 53
20 54
21 55
22 56
23 57
24 58
25 59
26 60
27 61
28 62
29 63
30 64
31 65
32 66
33 67
34 68

UK RESTRICTED Page (v)/(vi)


COVERING UK RESTRICTED

CONDITIONS OF RELEASE
1 This information is released by the UK Government for Defence purposes only.
2 This information must be afforded the same degree of security protection as that afforded
to information of an equivalent security marking originated by the recipient Government or as
required by the recipient Government’s security regulations.
3 This information may be disclosed only within the Defence Department of the recipient
Government, except as otherwise authorised by the Ministry of Defence (Navy).
4 This information may be subject to privately owned rights.

TP 3541 VOLUME 1

ROYAL BRUNEI ARMED FORCES


OFFSHORE PATROL VESSEL COMMAND AND CONTROL SYSTEM

HARBOUR ACCEPTANCE TRIAL (EQUIPMENT) (HAT(E))

Amendment 1 / October 2003

1 Summary of Changes

a To amend HAT(E) Schedule to clarify input syntax and the procedure.


b To amend the results in Annex A in accordance to the changes in the schedule.
c To correct other observed errors.

2 Removal and Insertion Amendments

REMOVE INSERT

Pages (vii) and (viii) (1 leaf) Pages (vii) and (viii) (1 leaf)
Chap 2 Pages 1 to 40 (20 leaves) Chap 2 Pages 1 to 40 (20 leaves)
Chap 2 Pages 53 to 62 (5 leaves) Chap 2 Pages 53 to 62 (5 leaves)
Annex A Pages 1 to 25/26 (13 leaves) Annex A Pages 1 to 25/26 (13 leaves)
Annex R Page 1/2 (1 leaf) Annex R Page 1/2 (1 leaf)
Annex S Pages 1 to 7/8 (4 leaves Annex S Pages 1 to 7/8 (4 leaves)

3 Superseded Material. Destroy all superseded material. Abide by the local arrangements for disposal
of classified waste

4 Record the incorporation of this amendment on the Amendment Record at the beginning of the
publication. File this Amendment Instruction Sheet in the publication.

Lyon Way, Frimley, Camberley


Surrey GU16 7EX, England, United Kingdom
Telephone: +44 (0) 1276 63311 Facsimile: +44 (0) 1276 695498
www.aleniamarconisystems.com

COVERING UK RESTRICTED Page 1/2


UK RESTRICTED TP 3541

BRUNEI OFFSHORE PATROL VESSEL CWCS HANDBOOKS

TP 3530 System Handbook

Section 1 Purpose and Planning


Section 2 System Technical Description
Section 3 Equipment Technical Description
Section 4 Maintenance Instructions – Diagnostic
Section 5 Maintenance Schedules
Section 6 Spares Catalogue

TP 3531 Operator’s Handbook

Volume 1 Sections 1, 2 and 3 – CWCS Functionality


Volume 2 Section 4 – Manual Injection Guide

TP 3532 Software Facilities and Support Handbook

Section 1 Technical Description


Section 2 Equipment Testing

TP 3533 System PEC Handbook

Chapters (21) PEC Technical Descriptions

TP 3534 Ethernet Adaptor Unit Handbook

Section 1 Purpose and Planning


Section 2 System Technical Description
Section 3 Hardware Technical Description
Section 4 Maintenance Instructions – Corrective
Section 5 Maintenance Instructions – Preventive
Section 6 Spares Catalogue

TP 3535 Navigation Radar Track Extractor Handbook

Section 1 Purpose and Planning


Section 2 System Technical Description
Section 3 Hardware Technical Description
Section 4 Maintenance Instructions – Corrective
Section 5 Maintenance Instructions – Preventive
Section 6 Spares Catalogue

TP 3536 Console Handbook

Section 1 Purpose and Planning


Section 2 System Technical Description
Section 3 Hardware Technical Description
Section 4 Maintenance Instructions – Corrective
Section 5 Maintenance Instructions – Preventive
Section 6 Spares Catalogue

(Continued)

Oct 03 (Amdt 1) UK RESTRICTED Page (vii)


TP 3541 UK RESTRICTED

BRUNEI OFFSHORE PATROL VESSEL CWCS HANDBOOKS (continued)

TP 3537 Gunfire Control Predictor Handbook

Section 1 Purpose and Planning


Section 2 System Technical Description
Section 3 Hardware Technical Description
Section 4 Maintenance Instructions – Corrective
Section 5 Maintenance Instructions – Preventive
Section 6 Spares Catalogue

TP 3538 Weapon Auxiliary Switching Panel Handbook

Section 1 Purpose and Planning


Section 2 System Technical Description
Section 3 Hardware Technical Description
Section 4 Maintenance Instructions – Corrective
Section 5 Maintenance Instructions – Preventive
Section 6 Spares Catalogue

TP 3539 Installation Handbook

Chapters (6) Installation Information

TP 3540 Setting to Work

Volume 1 CWCS Equipment


Volume 2 CWCS Linking and Integration

TP 3541 Harbour Acceptance Trials

Volume 1 Harbour Acceptance Trial (Equipment) (HAT(E))


Volume 2 Harbour Acceptance Trial (System) (HAT(S))

TP 3542 Sea Acceptance Trials

Section 1 CWCS Tracking Sensors and Directors (Test Groups 1 to 9)


Section 2 Position Fixing (Test Group 10)
Section 3 CWCS Weapons Systems (Test Groups 11 to 15)
Section 4 Navigation and Tactical Calculations (Test Groups 16 to 18)

For a complete list of associated CWCS Handbooks, refer to TP 3530, Sect 1, Chap 1, Table 2.

Page (viii) UK RESTRICTED


UK RESTRICTED TP 3541

CONTENTS

VOLUME 1

Page

Preliminary material

Title Page (i)/(ii)


Conditions of Release (iii)/(iv)
Amendment Record (v)/(vi)
Brunei OPV CWCS Handbooks (vii)–(viii)
Contents (this List) (ix)–(x)
Hazard Warnings (xi)–(xii)
Cautions (xiii)/(xiv)
Notes to Readers (xv)/(xvi)
References (xvii)/(xviii)

HARBOUR ACCEPTANCE TRIAL (EQUIPMENT)

Chapter

1 Harbour Acceptance Trial (Equipment) – Introduction


2 HAT(E) Schedule of Tests

Annex

A Test Records
B SES Running Instructions
C Console BIST List
D EAU/010 (ASYNC) BIST List
E EAU/011 (SYNC) BIST List
F EAU/013 (EOTS) BIST List
G NRTE BIST List
H GCP (76mm) BIST List
I GCP (30mm) BIST List
J Console Operator-Controlled Extended BIST List
K EAU/010 (ASYNC) Operator-Controlled Extended BIST List
L EAU/011 (SYNC) Operator-Controlled Extended BIST List
M EAU/013 (EOTS) Operator-Controlled Extended BIST List
N NRTE Operator-Controlled extended BIST List
O GCP 76mm Operator-Controlled extended BIST List
P GCP 30mm Operator-Controlled extended BIST List
Q SES Test 022 TV External Test picture description
R Equipment Designations within the CWCS
S List of Abbreviations

UK RESTRICTED Page (ix)


TP 3541 UK RESTRICTED

CONTENTS (Continued)

VOLUME 2

Page

Preliminary material

Title page (i)/(ii)


Conditions of release (iii)/(iv)
Amendment record (v)/(vi)
Brunei OPV CWCS handbooks (vii)–(viii)
Contents (this list) (ix)–(x)
Hazard warnings (xi)–(xii)
Cautions (xiii)/(xiv)
Notes to readers (xv)/(xvi)
References (xvii)/(xviii)

HARBOUR ACCEPTANCE TRIAL (SYSTEM)

Chapter

1 Harbour Acceptance Trial (System) – Introduction

Annex

A System Modes and Console States


B Operator Display Facilities
C Tracking Sensors and Directors
D Position Estimating
E Weapons Systems
F Navigation
G Recording, Replay and Training
H List of Abbreviations

Appendix

1 Test Record Sheets

Page (x) UK RESTRICTED


UK RESTRICTED TP 3541

HAZARD WARNINGS

(1) DC VOLTAGES

UNITS WITHIN THE CWCS CONTAIN VOLTAGES UP TO 50 V dc. DO NOT REMOVE OR


REPLACE ANY UNIT OR ASSEMBLY WITHOUT FIRST SWITCHING OFF THE AC
POWER, I.E., MAINS AND ACH SUPPLIES (WHERE APPLICABLE) AND
DISCONNECTING THE AC SUPPLY CABLE(S) FROM THE UNIT, RELEVANT MODULE
OR POWER SOURCE.

(2) AC MAINS AND ACH VOLTAGES

AC MAINS VOLTAGES ARE PRESENT WITHIN UNITS OF THE CWCS. DO NOT


REMOVE OR REPLACE ANY UNIT OR ASSEMBLY WITHOUT FIRST SWITCHING OFF
THE AC POWER, I.E., MAINS AND ACH SUPPLIES (WHERE APPLICABLE) AND
DISCONNECTING THE AC SUPPLY CABLE(S) FROM THE UNIT, RELEVANT MODULE
OR POWER SOURCE.

(3) RASTER COLOUR MODULE HIGH VOLTAGE WARNING

THE EHT VOLTAGE PRODUCED IN THIS UNIT IN THE CONSOLES IS IN EXCESS OF


29 kV. THE UNIT PRODUCES UP TO 10 kV d.c. AND ± 600 V PULSES.

(4) PRIMARY CELL BATTERY HAZARDS

THE REAL TIME CLOCK IN THE SINGLE BOARD COMPUTER (SBC) PEC 419/7/67500/
005 WHICH IS IN ALL CWCS UNITS, AND ALSO THE 419/7/67501/002 (SBC TRACKER)
PRESENTS A POTENTIAL FIRE OR EXPLOSION HAZARD WHICH COULD CAUSE
SERIOUS INJURY TO PERSONNEL. ALL NECESSARY PRECAUTIONS MUST BE
TAKEN DURING HANDLING, STORAGE AND DISPOSAL, IN PARTICULAR:

a. DO NOT INCINERATE OR HEAT ABOVE 150 °C (302 °F).

b. DO NOT DISASSEMBLE, CRUSH OR PUNCTURE THE BATTERY OR


EXPOSE ITS CONTENTS TO WATER.

(5) WEAPON AUXILIARY SWITCHING PANEL (WASP)

THE WASP USED IN THE CWCS CONTAINS SAFETY CRITICAL CIRCUITS. CHANGES
MUST NOT BE MADE TO THESE CIRCUITS WITHOUT AN OFFICIAL SAFETY REVIEW
BEING CARRIED OUT TO ASSESS THE EFFECTS OF ANY CHANGES ON THE WASP
AND ANY OTHER ELEMENTS OF THE CWCS.

UK RESTRICTED Page (xi)


TP 3541 UK RESTRICTED

(6) SYNCHRO VOLTAGES

115 V 400 Hz ac VOLTAGES ARE PRESENT WITHIN THE GCP AND ON THE
TERMINATIONS (TAPER PIN BLOCKS). DO NOT PERFORM ANY OPERATIONS IN
THESE AREAS WITHOUT ENSURING THAT THE RELEVANT EXTERNAL
CONNECTORS TO THESE POINTS ARE SWITCHED OFF. IN ADDITION, ENSURE
THAT THE REFERENCE SUPPLY CABLE TO THE GCP IS REMOVED.

Page (xii) UK RESTRICTED


UK RESTRICTED TP 3541

CAUTIONS

ELECTROSTATIC SENSITIVE DEVICES

CAUTIONS

(1) The equipment described in this handbook contains electrostatic discharge


sensitive devices (ESDs) which require protection from electrostatic discharges and
fields.

(2) The general requirements for the protection of such devices are specified in
British Standard BS EN 100015-1 Part 1 (Basic specification: Protection of electrostatic
sensitive devices – Part 1. General requirements) which includes details of storage,
handling, training and quality requirements.

UK RESTRICTED Page (xiii)/(xiv)


UK RESTRICTED TP 3541

NOTES TO READERS

1 The following cross reference between Alenia Marconi Systems (AMS) Limited and BAE
Systems Marine (BSM) Limited equipment nomenclature is included for clarification:

AMS BSM

EAU SAP F EAU(S) 1802(F)


EAU SAP A EAU(S) 1802(A)

LAN A or Highway A Highway Port


LAN B or Highway B Highway Stbd
LAN Monitor or Highway Monitor Highway Centre

2 On block and signal interconnection diagrams, PEC slot locations are shown by the number
in the right-hand corner and sub-assembly references by a letter.

8 A

PEC SLOT LOCATION SUB-ASSEMBLY REFERENCE

UK RESTRICTED Page (xv)/(xvi)


UK RESTRICTED TP 3541

REFERENCES

The following documents or items are quoted as references within this Harbour Acceptance Trial.
They are referred to using only the Reference Number:
r

Ref.
Document Title Document No.
No.
1 SYSTEM SPECIFICATION FOR THE BRUNEI COMMAND 380/AA/35003/000
AND WEAPON CONTROL SYSTEM
2 MAN MACHINE INTERFACE SPECIFICATION FOR THE 380/AJ/32952/000
BRUNEI COMMAND AND WEAPON CONTROL SYSTEM
3 SYSTEM ACCEPTANCE TEST PLAN FOR BRUNEI BBR I PM 0007
COMMAND AND WEAPON CONTROL SYSTEM
4 BRUNEI SETTING TO WORK HANDBOOK TP 3540
5 SYSTEM SPECIFICATION FOR THE BRUNEI COMMAND 380/SG/35835/000
AND WEAPON CONTROL SYSTEM – CONFIGURATION
DATA
6 SCREEN LAYOUT DATA FILE CONFIGURATION 380/HE/35835/000
7 BRUNEI MESSAGE CATALOGUE LINK Y Mk1 AND Mk2. 9501 075 097
8 BRUNEI CWCS ALARMS, WARNINGS, NOTIFICATIONS AND 380/HE/35913/000
OPERATOR INPUT ACKNOWLEDGEMENTS
9 RVG HANDBOOK BOPVRVG/HB/001 - 004
10 BAE SYSTEMS PROFILES REFERENCE COMSYSCONDATA (CDSA 05)
11 BRUNEI SYSTEM SOFTWARE VERSION DESCRIPTION 380/HA/35000/000)
DOCUMENT

UK RESTRICTED Page (xvii)/(xviii)


UK RESTRICTED TP 3541

Chapter 1

HARBOUR ACCEPTANCE TRIAL (EQUIPMENT) – INTRODUCTION

CONTENTS

Para

1 INTRODUCTION
3 Objective
4 Authorities
5 Requirements
6 Limitations
7 Acceptance criteria
11 Safety precautions
14 Recording and analysis
TRIAL PREREQUISITES
15 Trial preconditions
Test readiness review
16 Timescale
17 Objectives
18 Pre-requisites
20 Agenda
21 Meeting minutes
22 Preparation of test equipment
24 Availability of services
27 Preparation of CWCS equipment
29 Functional configuration audit
33 Physical configuration audit
37 Preparation of documents
TRIAL REQUIREMENTS
41 Venue and facilities required
43 Provision of test equipment, power supplies and test software
44 Provision of CWCS equipment
46 Provision of ship services equipment
47 Trial equipment configuration
49 Personnel requirements
TRIAL CONDUCT AND DURATION
50 Commencement
51 During the trial
52 Completion of the trial
53 Duration of the trial
TRIAL RECORDS
54 Test results
56 Observations

HAT(E) Chap 1
UK RESTRICTED Page 1
TP 3541 UK RESTRICTED

HAT(E) SCHEDULE OF TESTS

Test Group Page

1 Console ............................................................................................................... 1
2 EAU (ASYNC) ..................................................................................................... 8
3 EAU (SYNC) ........................................................................................................ 13
4 EAU (EOTS) ........................................................................................................ 18
5 NRTE ................................................................................................................... 23
6 GCP 76mm .......................................................................................................... 28
7 GCP 30mm .......................................................................................................... 33
8 WASP .................................................................................................................. 38
9 DATALINK Y ....................................................................................................... 39
10 RTVDU ................................................................................................................ 41
11 Radar video generator.......................................................................................... 43
12 Gun footpush ....................................................................................................... 46
13 System ................................................................................................................ 50

Annexes

A Test records
B SES running instructions
C Console BIST list
D EAU/010 (ASYNC) BIST list
E EAU/011 (SYNC) BIST list
F EAU/013 (EOTS) BIST list
G NRTE BIST list
H GCP (76mm) BIST list
I GCP (30mm) BIST List
J Console operator-controlled extended BIST list
K EAU/010 (ASYNC) operator-controlled extended BIST list
L EAU/011 (SYNC) operator-controlled extended BIST list
M EAU/013 (EOTS) operator-controlled extended BIST list
N NRTE operator-controlled extended BIST list
O GCP 30mm operator-controlled extended BIST list
P GCP 76mm operator-controlled extended BIST list
Q SES test 022 TV external test picture description
R Equipment designations within CWCS
S List of abbreviations

HAT(E) Chap 1
Page 2 UK RESTRICTED
UK RESTRICTED TP 3541

INTRODUCTION

1 This Harbour Acceptance Trial (Equipment) (HAT(E)) Schedule is applicable to the


Command and Weapon Control System (CWCS) supplied to BAE Systems Marine (BSM) for the
Royal Brunei Armed Forces by Alenia Marconi Systems (AMS) Limited, Integrated Systems
Division, under contract 98/4253/1055-1057. The major unit tests and system tests are defined in
HAT(E) Schedule of Tests.

2 The definition of the items of equipment covered by this schedule is contained in the Minimum
Build Document, but excludes Carried On Board Spares.

OBJECTIVE

3 The objective of HAT(E) is to demonstrate that the CWCS hardware functions correctly as
individual units and when linked as a complete system via the Ethernet Highway after installation
and setting to work on board ship.

AUTHORITIES

4 For the purposes of this Trial, the following roles are identified:

(1) Preparation of CWCS for Trial: Presenting Authority.

(2) Trial Programming: Accepting Authority.

(3) Trial Presentation: Presenting Authority

(4) Trial Conduct: Accepting Authority.

(5) Trial Acceptance: Accepting Authority.

REQUIREMENTS

5 Requirements for the trial are as follows:

5.1 Equipment for the Trial is to be prepared ensuring that all pre-conditions are satisfied
and that all pre-requisites are met.

5.2 Ensure all documents required are produced or referenced during the Trial, these
include records of Observations recorded during previous Trials and actions taken.

5.3 Complete the requisite records during the Trial.

5.4 Raise an Observation wherever a departure from the expected result is noted during
the Trial.

5.5 At the completion of the Trial, agree the validity and assess the results of the Trial,
together with the categorization of any Observations raised during the Trial..

5.6 Sign the Observation Reports in confirmation that the content provides an accurate
record of the Trial.

5.7 Conduct pre-Trial and post-Trial briefings and wash-up meetings.

HAT(E) Chap 1
UK RESTRICTED Page 3
TP 3541 UK RESTRICTED

5.8 Conduct the Trial.

5.9 At the daily wash-up meeting, and in any event no later than the completion of the Trial,
agree the categorization of any recorded observations in accordance with the provisions of
this schedule.

5.10 At the completion of the Trial, agree the validity and the assessed result of the Trial.

LIMITATIONS

6 The tests performed within the HAT(E) are aimed at establishing the correct operation of each
major unit of the CWCS when connected via the Ethernet Highway and internal interconnecting
Ship’s Cables. There is no connectivity to external Combat Systems Interfaces.

ACCEPTANCE CRITERIA

7 The result of each numbered test sequence is to be assessed against the following criteria:

7.1 The test is to be recorded as complete and satisfactory when the test steps have been
carried out and the expected results have been observed without the raising of a Failing
Observation.

7.2 The test result is accepted as correct when the result observed falls within the tolerance
permitted in that test for the measurement of the respective parameter.

8 An Observation is to be raised wherever the result observed during a test serial does not
match that defined in the expected result column of that test serial. Observations may be raised
to record comments pertaining to the test documentation.

9 An Observation is to be placed in an agreed category. The Observations are then further


classified as Non-Failing or Failing Observation.

10 The result of the Trial must be agreed between all parties at the final post-trial meeting at the
completion of the Trial taking into consideration all recorded Observations and information
contained in the Trial Report.

SAFETY PRECAUTIONS

11 No special safety precautions are applicable during normal operation of the equipment under
test and its associated test equipment during this Trial other than acknowledgement of normal
personnel safety precautions when working with electronic equipment.

12 Procedures for the commissioning and maintenance of the CWCS equipment are contained
in the Technical Documentation. Since equipment operates from a.c. power supplies and
generates high voltages to drive a Cathode Ray Tube display, appropriate Hazard Notices are
contained within the equipment and in the Documentation.

13 Full Anti-static procedures are to be used when handling PECs.

RECORDING AND ANALYSIS

14 There is no requirement for recording and analysis.

HAT(E) Chap 1
Page 4 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL PRE-REQUISITES

TRIAL PRE-CONDITIONS

15 Prior to commencement of the HAT(E) and, to ensure that the correct conditions required for
the Trial are achieved, a number of actions are required to be complete:

15.1 At least 30 calendar days notice of the intended commencement of the Trial.

15.2 At least ten days notice of the names and status of the intended attendees (or
nominated representatives) is required.

15.3 Trial Schedule presentation five months prior to the Trial.

15.4 A Test Readiness Review (TRR) not less than ten working days prior to each defined
trial phase.

TEST READINESS REVIEW

Timescale

16 The Test Readiness Review meeting is to be held at least two weeks prior to each
Acceptance Trial.

Objectives

17 The objectives of the The Test Readiness Review meeting is to:

(1) Agree the Acceptance Trial Plan.

(2) Agree the progress towards the Functional Configuration Audit (FCA) and the Physical
Configuration Audit (PCA).

(3) Ensure that the necessary resources are identified and in place.

(4) Agree the compatibility between VCRI and schedules.

(5) Agree that the Acceptance Trial may proceed.

Pre-requisites

18 The following items to be reviewed and confirmed:

(1) Daily Test or Trial Plan.

(2) Statement of acceptance documentation status.

(3) Statement of equipment status.

(4) Version Description Document and Design Certificate.

(5) PCA/FCA status reports.

HAT(E) Chap 1
UK RESTRICTED Page 5
TP 3541 UK RESTRICTED

(6) Status Report on Observations raised in previous Acceptance Test or Trials.

(7) Status Report on outstanding Observations.

(8) Summary of Concessions

19 Personnel designated by the RBAF or their authorised representatives, are to be in


attendance.

Agenda

20 The agenda for the meeting follows the following format:

(1) Summary of Purpose of Meeting

(2) Acceptance Trial Plan

(3) Status of Trials Schedules

(4) Status of Equipment

(5) Status of Software against Acceptance Criteria

(6) Status of Observations raised at Previous Acceptance Trial

(7) Status of outstanding Observations

(8) Summary of Actions raised.

(9) Any Other Business

(10) Recommendation to proceed (or otherwise)

Meeting minutes

21 The minutes of the meeting are to be recorded.

PREPARATION OF TEST EQUIPMENT

22 The test equipment defined within this schedule as being required to support the Test
configuration of the CWCS equipment must be prepared for use during the Test in accordance
with the appropriate procedures.

23 Test equipment (with serial numbers) provided for the simulation, stimulation or measurement
of interface parameters must be in date for calibration.

AVAILABILITY OF SERVICES

24 The availability of services such as power supplies, ventilation, cooling, etc., is to be


confirmed prior to the Test. Availability is to be considered against the requirements of the
equipment under test.

25 There are no special requirements for services from other Contractors or Authorities.

HAT(E) Chap 1
Page 6 UK RESTRICTED
UK RESTRICTED TP 3541

26 There are no special precautions required to ensure non-interference by or with other


activities during this Test.

PREPARATION OF CWCS EQUIPMENT

27 Prior to HAT(E) each CWCS Console, each EAU, the NRTE, both 30mm and the 76mm
Gunfire Control Predictor, the WASP, RVG, RTVDU, Datalink Y, Bridge Display and the Gun
Footpushes must have been previously accepted against the Factory Acceptance Test
(Equipment) Schedule.

28 All CWCS hardware and software presented for Trial must be formally released and its build
state recorded and any deficiencies declared.

FUNCTIONAL CONFIGURATION AUDIT

29 The Functional Configuration Audit (FCA) is a formal Design Assurance audit to validate that
the development of a configuration item (hardware) has been completed satisfactorily and that the
configuration item has achieved the performance and functional characteristics specified in the
functional or allocated configuration identification. In addition, the completed operation and
support documents must be reviewed.

30 The FCA is to be progressed using all test results.

31 A sample inspection of the requirement trail is to be carried out immediately prior to the TRR.

32 The following documentation is to be presented for the FCA:

(1) NAUTIS:

a. Main Assembly Design Certificates.

b. Main Assembly Design Reports.

c. Hardware Requirement Specification VCRI.

d. Procurement Specification VCRI (21 in. Bridge Display, etc.).

e. Design Assurance certified PTS Results.

(2) RTVDU:

a. Design Certificate.

b. Design Reports (PEC).

(3) RVG:

a. Design Certificate.

b. Design Reports.

HAT(E) Chap 1
UK RESTRICTED Page 7
TP 3541 UK RESTRICTED

(4) DATALINK Y:

a. Design Certificate

PHYSICAL CONFIGURATION AUDIT

33 A Physical Configuration Audit (PCA) is a technical examination of the first of a designated


configuration item to verify that the configuration item “As Built” conforms to the technical
documentation which defines it.

34 Hardware configuration items are defined by the Hardware Build State Definition document
and comply with the Hardware Minimum Build State Definition Document.

35 In preparation for the first applicable test or trial of the System, a PCA is to be prepared and,
for subsequent tests or trials, the PCA is to be updated to reflect any hardware changes.

36 An inspection of the requirement trial is to be carried out immediately prior to the TRR.

PREPARATION OF DOCUMENTS

37 The HAT(E) schedule must be confirmed as being at the latest amendment issue before
authorisation of its use in the conduction of the Test.

38 A Build State Document is to be prepared and formally issued. It defines the Build State of all
items of equipment subject to Test. These definitions include the firmware and hardware of the
CWCS at the date of commencement of the Test.

39 Records of tests performed prior to the Test, and which may be cited as evidence as required
by one or more of the Test schedules, are to be endorsed and made available for reference.

40 All Observations raised prior to the start of the Test relating to the CWCS or any part of its
equipment or BIST and SES software are to be available for inspection at the Test.

HAT(E) Chap 1
Page 8 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL REQUIREMENTS

VENUE AND FACILITIES REQUIRED

41 The HAT(E) Trial is to be carried out on-board Ship berthed alongside.

42 Unrestricted access to all equipment comprising the CWCS is required for the personnel
presenting and conducting the Trial.

PROVISION OF TEST EQUIPMENT, POWER SUPPLIES AND TEST SOFTWARE

43 The following items are required to be provided:

(1) Blank DAT Tape DG-90MA SONY.

(2) System Software Tape No: 380/FU/35000/000.

(3) Link Y Software CD No.: 380/FU/36062/000.

(4) RVG Software CD No.: 364/FU/35911/000.

(5) Test Scenario Software No.: 380/FU/35075/00.

PROVISION OF CWCS EQUIPMENT

44 The minimum requirement for CWCS for this Trial is one complete CWCS, comprising:

(1) 8 in No. CWCS Display Consoles (No 678/1/42001/100).

(2) 8 in No. Ethernet Adaptor Unit (ASYNC) (No 678/1/42100/010).

(3) 5 in No. Ethernet Adaptor Unit (SYNC) (No 678/1/42100/011).

(4) 1 in No. Ethernet Adaptor Unit (EOTS) (No 678/1/42100/013).

(5) 1 in No. Navigation Radar Track Extractor (No 678/1/42080/010).

(6) 2 in No. 30mm Gunfire Control Predictors (No 678/1/42060/010).

(7) 1 in No. 76mm Gunfire Control Predictor (No 678/1/42060/011).

(8) 1 in No. Weapon Auxiliary Switching Panel (No 678/1/43910/000)

(9) 1 in No. 21 in. Bridge Display (No 678/1/43358/001).

(10) 1 in No. Radar Video Generator with Control Unit (612/7/50760/001) and Junction Box.

(11) 2 in No. Radar Television Video Distribution Units (678/7/41516/002).

(12) 1 in No. Datalink Y - including Remote Control Panel (612/7/50757/005).

(13) 1 in No RCP and Link Y Remote Switch Box (678/1/43979/000)

HAT(E) Chap 1
UK RESTRICTED Page 9
TP 3541 UK RESTRICTED

(14) Data Output Interface (Maintainer's PC) (678/1/42124/001).

(15) 4 in No. Gun FootPushes (No 408/4/58765/000).

(16) Magnetic Tape Cartridges/CD discs: Software System (No. 380/FU/35090/000)


Link Y Software (CD No. 380/FU/36062/000)
RVG Software (CD No. 364/FU/35911/004)
Test Scenario Software
(No. 380/FU/35075/000).

(17) Blank Magnetic Tape Cartridge (DAT) DG-90MA SONY

(18) 1 in No Maintainer’s Tool Kit (678/1/42152/101)

(19) Nautis II dual redundant Ethernet Highway

(20) Nautis II Monitoring Ethernet Highway

45 Any substitution of equipment during the Trial must be confined to equipment which is of the
same build standard as that recorded in the Trial Records and must have been subjected to the
defined pre-requisite tests. Such substitution must be recorded in the Trials Log.

PROVISION OF SHIP SERVICES EQUIPMENT

46 The following non-CWCS ship equipment is required for the trial when stated, and must be at
HAT standard and operational.

(1) All internal interconnecting cables and Local Area Network (LAN) cables.

(2) VCS21 (50 V a.c. for WASP).

TRIAL EQUIPMENT CONFIGURATION

47 All CWCS equipment is to be connected by the dual redundant Ethernet highway and the
monitor highway (where applicable) and all ‘internal’ interconnecting cables shall be connected to
the equipment Termination Panels for the Trial.

48 The configuration and set-up conditions for each group of tests within the Trial are defined in
HAT(E) Schedule of Tests contained in this chapter.

PERSONNEL REQUIREMENTS

49 The following staff are required to perform the roles and to carry out the responsibilities of the
Trial:

(1) Test Director

(2) Test Recorder / Reader

(3) Test Operator(s)

(4) Design Assurance Observer

HAT(E) Chap 1
Page 10 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL CONDUCT AND DURATION

COMMENCEMENT

50 At the commencement of the Trial, a meeting is to be convened to:

50.1 Brief all attendees as to the purpose of the Trial and the procedures to be followed.

50.2 Agree that all Trial pre-requisites have been met and that there are no circumstances
known which might lead to a judgement that the Trial conditions could be invalid.

50.3 Agree that the records prepared prior to the commencement of the Trial are accurate,
complete and reflect the conformity of the equipment with the requirements of this Schedule.

DURING THE TRIAL

51 The following may take place at any time during the trial:

51.1 A meeting may be convened at the start of each day's work during the Trial to
communicate changes in plans for the days work or to consider any other factors affecting
the progress of the Trial.

51.2 Test cables may be connected prior to the start of each main assembly test.

51.3 The tests to be carried out for each CWCS unit are defined in HAT(E) Schedule of Tests.
The Tests are grouped under suitable headings, but may be carried out in any order.

51.4 As each test serial is completed, a note of its completion is to be recorded in the
appropriate Record Sheet with a note of any Observations raised during the test.

51.5 Observations are to be raised according to the defined criteria.

51.6 Each Observation is to be assigned a sequential serial number within the series being
maintained until Final Acceptance.

51.7 An Observation can be raised at any time, which has the next number in the
Observation sequence. These Observations can be raised as a result of deviations from, or
deficiencies in each test.

51.8 The categorisation of Observations raised is to be carried out as soon as possible and,
in any event, no later than the end of the Trial.

51.9 At the end of each Trial day, a meeting may be held to agree the records obtained, i.e.,
Observations, test documentation errors, test validity, test results and recommendations.

COMPLETION OF THE TRIAL

52 At the completion of the Trial, a post-Trial meeting is to be convened. At this meeting, the
following matters are to be considered and agreed:

52.1 The records obtained.

52.2 The Observations to be recorded and their categorisation.

HAT(E) Chap 1
UK RESTRICTED Page 11
TP 3541 UK RESTRICTED

52.3 The errors noted in the test or trials documentation.

52.4 The validity of the Trial.

52.5 The result of the Trial.

52.6 The requirements for re-presentation, if any.

52.7 Any matters not resolved during the Trial.

52.8 The designated authority is to determine Acceptance.

DURATION OF THE TRIAL

53 The anticipated duration of the HAT(E) is expected to be five working days in total.

HAT(E) Chap 1
Page 12 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL RECORDS

TEST RESULTS

54 During the Trial, the Results Record for each group of tests in this schedule must be ticked,
initialled and dated to indicate the completion of each test in the test sequence. This Record is
intended for the convenience of the presenting and conducting authorities to record progress
through the Trial. A copy is to be included in the Test report.

55 Where any test to be applied to the CWCS in this Trial requires the taking of readings for
future use, the results produced by the respective test are to be recorded in the Results Record.

OBSERVATIONS

56 Where an Observation is raised during the conduct of a test, using the Combat System
Agency Work Instruction, a note of the Observation serial number is to be made against the
respective test in the Results Record Sheet. This acts as an aide memoire to the conducting
authority when reviewing the Trial.

HAT(E) Chap 1
UK RESTRICTED Page 13/14
TP 3541 UK RESTRICTED

HAT(E) SCHEDULE OF TESTS

Test Group Page

1 Console ............................................................................................................... 15
2 EAU (ASYNC) ..................................................................................................... 22
3 EAU (SYNC) ........................................................................................................ 27
4 EAU (EOTS) ........................................................................................................ 32
5 NRTE ................................................................................................................... 37
6 GCP 76mm .......................................................................................................... 42
7 GCP 30mm .......................................................................................................... 47
8 WASP .................................................................................................................. 52
9 DATALINK Y ....................................................................................................... 53
10 RTVDU ................................................................................................................ 55
11 Radar video generator.......................................................................................... 57
12 Gun footpush ....................................................................................................... 60
13 System ................................................................................................................ 64

Annexes

A Test records
B SES running instructions
C Console BIST list
D EAU/010 (ASYNC) BIST list
E EAU/011 (SYNC) BIST list
F EAU/013 (EOTS) BIST list
G NRTE BIST list
H GCP (76mm) BIST list
I GCP (30mm) BIST List
J Console operator-controlled extended BIST list
K EAU/010 (ASYNC) operator-controlled extended BIST list
L EAU/011 (SYNC) operator-controlled extended BIST list
M EAU/013 (EOTS) operator-controlled extended BIST list
N NRTE operator-controlled extended BIST list
O GCP 30mm operator-controlled extended BIST list
P GCP 76mm operator-controlled extended BIST list
Q SES test 022 TV external test picture description
R Equipment designations within CWCS
S List of abbreviations

HAT(E) Chap 1
Page 2 UK RESTRICTED
UK RESTRICTED TP 3541

INTRODUCTION

1 This Harbour Acceptance Trial (Equipment) (HAT(E)) Schedule is applicable to the


Command and Weapon Control System (CWCS) supplied to BAE Systems Marine (BSM) for the
Royal Brunei Armed Forces by Alenia Marconi Systems (AMS) Limited, Integrated Systems
Division, under contract 98/4253/1055-1057. The major unit tests and system tests are defined in
HAT(E) Schedule of Tests.

2 The definition of the items of equipment covered by this schedule is contained in the Minimum
Build Document, but excludes Carried On Board Spares.

OBJECTIVE

3 The objective of HAT(E) is to demonstrate that the CWCS hardware functions correctly as
individual units and when linked as a complete system via the Ethernet Highway after installation
and setting to work on board ship.

AUTHORITIES

4 For the purposes of this Trial, the following roles are identified:

(1) Preparation of CWCS for Trial: Presenting Authority.

(2) Trial Programming: Accepting Authority.

(3) Trial Presentation: Presenting Authority

(4) Trial Conduct: Accepting Authority.

(5) Trial Acceptance: Accepting Authority.

REQUIREMENTS

5 Requirements for the trial are as follows:

5.1 Equipment for the Trial is to be prepared ensuring that all pre-conditions are satisfied
and that all pre-requisites are met.

5.2 Ensure all documents required are produced or referenced during the Trial, these
include records of Observations recorded during previous Trials and actions taken.

5.3 Complete the requisite records during the Trial.

5.4 Raise an Observation wherever a departure from the expected result is noted during
the Trial.

5.5 At the completion of the Trial, agree the validity and assess the results of the Trial,
together with the categorization of any Observations raised during the Trial..

5.6 Sign the Observation Reports in confirmation that the content provides an accurate
record of the Trial.

5.7 Conduct pre-Trial and post-Trial briefings and wash-up meetings.

HAT(E) Chap 1
UK RESTRICTED Page 3
TP 3541 UK RESTRICTED

5.8 Conduct the Trial.

5.9 At the daily wash-up meeting, and in any event no later than the completion of the Trial,
agree the categorization of any recorded observations in accordance with the provisions of
this schedule.

5.10 At the completion of the Trial, agree the validity and the assessed result of the Trial.

LIMITATIONS

6 The tests performed within the HAT(E) are aimed at establishing the correct operation of each
major unit of the CWCS when connected via the Ethernet Highway and internal interconnecting
Ship’s Cables. There is no connectivity to external Combat Systems Interfaces.

ACCEPTANCE CRITERIA

7 The result of each numbered test sequence is to be assessed against the following criteria:

7.1 The test is to be recorded as complete and satisfactory when the test steps have been
carried out and the expected results have been observed without the raising of a Failing
Observation.

7.2 The test result is accepted as correct when the result observed falls within the tolerance
permitted in that test for the measurement of the respective parameter.

8 An Observation is to be raised wherever the result observed during a test serial does not
match that defined in the expected result column of that test serial. Observations may be raised
to record comments pertaining to the test documentation.

9 An Observation is to be placed in an agreed category. The Observations are then further


classified as Non-Failing or Failing Observation.

10 The result of the Trial must be agreed between all parties at the final post-trial meeting at the
completion of the Trial taking into consideration all recorded Observations and information
contained in the Trial Report.

SAFETY PRECAUTIONS

11 No special safety precautions are applicable during normal operation of the equipment under
test and its associated test equipment during this Trial other than acknowledgement of normal
personnel safety precautions when working with electronic equipment.

12 Procedures for the commissioning and maintenance of the CWCS equipment are contained
in the Technical Documentation. Since equipment operates from a.c. power supplies and
generates high voltages to drive a Cathode Ray Tube display, appropriate Hazard Notices are
contained within the equipment and in the Documentation.

13 Full Anti-static procedures are to be used when handling PECs.

RECORDING AND ANALYSIS

14 There is no requirement for recording and analysis.

HAT(E) Chap 1
Page 4 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL PRE-REQUISITES

TRIAL PRE-CONDITIONS

15 Prior to commencement of the HAT(E) and, to ensure that the correct conditions required for
the Trial are achieved, a number of actions are required to be complete:

15.1 At least 30 calendar days notice of the intended commencement of the Trial.

15.2 At least ten days notice of the names and status of the intended attendees (or
nominated representatives) is required.

15.3 Trial Schedule presentation five months prior to the Trial.

15.4 A Test Readiness Review (TRR) not less than ten working days prior to each defined
trial phase.

TEST READINESS REVIEW

Timescale

16 The Test Readiness Review meeting is to be held at least two weeks prior to each
Acceptance Trial.

Objectives

17 The objectives of the The Test Readiness Review meeting is to:

(1) Agree the Acceptance Trial Plan.

(2) Agree the progress towards the Functional Configuration Audit (FCA) and the Physical
Configuration Audit (PCA).

(3) Ensure that the necessary resources are identified and in place.

(4) Agree the compatibility between VCRI and schedules.

(5) Agree that the Acceptance Trial may proceed.

Pre-requisites

18 The following items to be reviewed and confirmed:

(1) Daily Test or Trial Plan.

(2) Statement of acceptance documentation status.

(3) Statement of equipment status.

(4) Version Description Document and Design Certificate.

(5) PCA/FCA status reports.

HAT(E) Chap 1
UK RESTRICTED Page 5
TP 3541 UK RESTRICTED

(6) Status Report on Observations raised in previous Acceptance Test or Trials.

(7) Status Report on outstanding Observations.

(8) Summary of Concessions

19 Personnel designated by the RBAF or their authorised representatives, are to be in


attendance.

Agenda

20 The agenda for the meeting follows the following format:

(1) Summary of Purpose of Meeting

(2) Acceptance Trial Plan

(3) Status of Trials Schedules

(4) Status of Equipment

(5) Status of Software against Acceptance Criteria

(6) Status of Observations raised at Previous Acceptance Trial

(7) Status of outstanding Observations

(8) Summary of Actions raised.

(9) Any Other Business

(10) Recommendation to proceed (or otherwise)

Meeting minutes

21 The minutes of the meeting are to be recorded.

PREPARATION OF TEST EQUIPMENT

22 The test equipment defined within this schedule as being required to support the Test
configuration of the CWCS equipment must be prepared for use during the Test in accordance
with the appropriate procedures.

23 Test equipment (with serial numbers) provided for the simulation, stimulation or measurement
of interface parameters must be in date for calibration.

AVAILABILITY OF SERVICES

24 The availability of services such as power supplies, ventilation, cooling, etc., is to be


confirmed prior to the Test. Availability is to be considered against the requirements of the
equipment under test.

25 There are no special requirements for services from other Contractors or Authorities.

HAT(E) Chap 1
Page 6 UK RESTRICTED
UK RESTRICTED TP 3541

26 There are no special precautions required to ensure non-interference by or with other


activities during this Test.

PREPARATION OF CWCS EQUIPMENT

27 Prior to HAT(E) each CWCS Console, each EAU, the NRTE, both 30mm and the 76mm
Gunfire Control Predictor, the WASP, RVG, RTVDU, Datalink Y, Bridge Display and the Gun
Footpushes must have been previously accepted against the Factory Acceptance Test
(Equipment) Schedule.

28 All CWCS hardware and software presented for Trial must be formally released and its build
state recorded and any deficiencies declared.

FUNCTIONAL CONFIGURATION AUDIT

29 The Functional Configuration Audit (FCA) is a formal Design Assurance audit to validate that
the development of a configuration item (hardware) has been completed satisfactorily and that the
configuration item has achieved the performance and functional characteristics specified in the
functional or allocated configuration identification. In addition, the completed operation and
support documents must be reviewed.

30 The FCA is to be progressed using all test results.

31 A sample inspection of the requirement trail is to be carried out immediately prior to the TRR.

32 The following documentation is to be presented for the FCA:

(1) NAUTIS:

a. Main Assembly Design Certificates.

b. Main Assembly Design Reports.

c. Hardware Requirement Specification VCRI.

d. Procurement Specification VCRI (21 in. Bridge Display, etc.).

e. Design Assurance certified PTS Results.

(2) RTVDU:

a. Design Certificate.

b. Design Reports (PEC).

(3) RVG:

a. Design Certificate.

b. Design Reports.

HAT(E) Chap 1
UK RESTRICTED Page 7
UK RESTRICTED TP 3541

TRIAL REQUIREMENTS

VENUE AND FACILITIES REQUIRED

41 The HAT(E) Trial is to be carried out on-board Ship berthed alongside.

42 Unrestricted access to all equipment comprising the CWCS is required for the personnel
presenting and conducting the Trial.

PROVISION OF TEST EQUIPMENT, POWER SUPPLIES AND TEST SOFTWARE

43 The following items are required to be provided:

(1) Blank DAT Tape DG-90MA SONY.

(2) System Software Tape No: 380/FU/35000/000.

(3) Link Y Software CD No.: 380/FU/36062/000.

(4) RVG Software CD No.: 364/FU/35911/000.

(5) Test Scenario Software No.: 380/FU/35075/00.

PROVISION OF CWCS EQUIPMENT

44 The minimum requirement for CWCS for this Trial is one complete CWCS, comprising:

(1) 8 in No. CWCS Display Consoles (No 678/1/42001/100).

(2) 8 in No. Ethernet Adaptor Unit (ASYNC) (No 678/1/42100/010).

(3) 5 in No. Ethernet Adaptor Unit (SYNC) (No 678/1/42100/011).

(4) 1 in No. Ethernet Adaptor Unit (EOTS) (No 678/1/42100/013).

(5) 1 in No. Navigation Radar Track Extractor (No 678/1/42080/010).

(6) 2 in No. 30mm Gunfire Control Predictors (No 678/1/42060/010).

(7) 1 in No. 76mm Gunfire Control Predictor (No 678/1/42060/011).

(8) 1 in No. Weapon Auxiliary Switching Panel (No 678/1/43910/000)

(9) 1 in No. 21 in. Bridge Display (No 678/1/43358/001).

(10) 1 in No. Radar Video Generator with Control Unit (612/7/50760/001) and Junction Box.

(11) 2 in No. Radar Television Video Distribution Units (678/7/41516/002).

(12) 1 in No. Datalink Y - including Remote Control Panel (612/7/50757/005).

(13) 1 in No RCP and Link Y Remote Switch Box (678/1/43979/000)

HAT(E) Chap 1
UK RESTRICTED Page 9
TP 3541 UK RESTRICTED

(14) Data Output Interface (Maintainer's PC) (678/1/42124/001).

(15) 4 in No. Gun FootPushes (No 408/4/58765/000).

(16) Magnetic Tape Cartridges/CD discs: Software System (No. 380/FU/35090/000)


Link Y Software (CD No. 380/FU/36062/000)
RVG Software (CD No. 364/FU/35911/004)
Test Scenario Software
(No. 380/FU/35075/000).

(17) Blank Magnetic Tape Cartridge (DAT) DG-90MA SONY

(18) 1 in No Maintainer’s Tool Kit (678/1/42152/101)

(19) Nautis II dual redundant Ethernet Highway

(20) Nautis II Monitoring Ethernet Highway

45 Any substitution of equipment during the Trial must be confined to equipment which is of the
same build standard as that recorded in the Trial Records and must have been subjected to the
defined pre-requisite tests. Such substitution must be recorded in the Trials Log.

PROVISION OF SHIP SERVICES EQUIPMENT

46 The following non-CWCS ship equipment is required for the trial when stated, and must be at
HAT standard and operational.

(1) All internal interconnecting cables and Local Area Network (LAN) cables.

(2) VCS21 (50 V a.c. for WASP).

TRIAL EQUIPMENT CONFIGURATION

47 All CWCS equipment is to be connected by the dual redundant Ethernet highway and the
monitor highway (where applicable) and all ‘internal’ interconnecting cables shall be connected to
the equipment Termination Panels for the Trial.

48 The configuration and set-up conditions for each group of tests within the Trial are defined in
HAT(E) Schedule of Tests contained in this chapter.

PERSONNEL REQUIREMENTS

49 The following staff are required to perform the roles and to carry out the responsibilities of the
Trial:

(1) Test Director

(2) Test Recorder / Reader

(3) Test Operator(s)

(4) Design Assurance Observer

HAT(E) Chap 1
Page 10 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL CONDUCT AND DURATION

COMMENCEMENT

50 At the commencement of the Trial, a meeting is to be convened to:

50.1 Brief all attendees as to the purpose of the Trial and the procedures to be followed.

50.2 Agree that all Trial pre-requisites have been met and that there are no circumstances
known which might lead to a judgement that the Trial conditions could be invalid.

50.3 Agree that the records prepared prior to the commencement of the Trial are accurate,
complete and reflect the conformity of the equipment with the requirements of this Schedule.

DURING THE TRIAL

51 The following may take place at any time during the trial:

51.1 A meeting may be convened at the start of each day's work during the Trial to
communicate changes in plans for the days work or to consider any other factors affecting
the progress of the Trial.

51.2 Test cables may be connected prior to the start of each main assembly test.

51.3 The tests to be carried out for each CWCS unit are defined in HAT(E) Schedule of Tests.
The Tests are grouped under suitable headings, but may be carried out in any order.

51.4 As each test serial is completed, a note of its completion is to be recorded in the
appropriate Record Sheet with a note of any Observations raised during the test.

51.5 Observations are to be raised according to the defined criteria.

51.6 Each Observation is to be assigned a sequential serial number within the series being
maintained until Final Acceptance.

51.7 An Observation can be raised at any time, which has the next number in the
Observation sequence. These Observations can be raised as a result of deviations from, or
deficiencies in each test.

51.8 The categorisation of Observations raised is to be carried out as soon as possible and,
in any event, no later than the end of the Trial.

51.9 At the end of each Trial day, a meeting may be held to agree the records obtained, i.e.,
Observations, test documentation errors, test validity, test results and recommendations.

COMPLETION OF THE TRIAL

52 At the completion of the Trial, a post-Trial meeting is to be convened. At this meeting, the
following matters are to be considered and agreed:

52.1 The records obtained.

52.2 The Observations to be recorded and their categorisation.

HAT(E) Chap 1
UK RESTRICTED Page 11
TP 3541 UK RESTRICTED

(4) DATALINK Y:

a. Design Certificate

PHYSICAL CONFIGURATION AUDIT

33 A Physical Configuration Audit (PCA) is a technical examination of the first of a designated


configuration item to verify that the configuration item “As Built” conforms to the technical
documentation which defines it.

34 Hardware configuration items are defined by the Hardware Build State Definition document
and comply with the Hardware Minimum Build State Definition Document.

35 In preparation for the first applicable test or trial of the System, a PCA is to be prepared and,
for subsequent tests or trials, the PCA is to be updated to reflect any hardware changes.

36 An inspection of the requirement trial is to be carried out immediately prior to the TRR.

PREPARATION OF DOCUMENTS

37 The HAT(E) schedule must be confirmed as being at the latest amendment issue before
authorisation of its use in the conduction of the Test.

38 A Build State Document is to be prepared and formally issued. It defines the Build State of all
items of equipment subject to Test. These definitions include the firmware and hardware of the
CWCS at the date of commencement of the Test.

39 Records of tests performed prior to the Test, and which may be cited as evidence as required
by one or more of the Test schedules, are to be endorsed and made available for reference.

40 All Observations raised prior to the start of the Test relating to the CWCS or any part of its
equipment or BIST and SES software are to be available for inspection at the Test.

HAT(E) Chap 1
Page 8 UK RESTRICTED
UK RESTRICTED TP 3541

Chapter 1

HARBOUR ACCEPTANCE TRIAL (EQUIPMENT) – INTRODUCTION

CONTENTS

Para

1 INTRODUCTION
3 Objective
4 Authorities
5 Requirements
6 Limitations
7 Acceptance criteria
11 Safety precautions
14 Recording and analysis
TRIAL PRE-REQUISITES
15 Trial pre-conditions
Test readiness review
16 Timescale
17 Objectives
18 Pre-requisites
20 Agenda
21 Meeting minutes
22 Preparation of test equipment
24 Availability of services
27 Preparation of CWCS equipment
29 Functional configuration audit
33 Physical configuration audit
37 Preparation of documents
TRIAL REQUIREMENTS
41 Venue and facilities required
43 Provision of test equipment, power supplies and test software
44 Provision of CWCS equipment
46 Provision of ship services equipment
47 Trial equipment configuration
49 Personnel requirements
TRIAL CONDUCT AND DURATION
50 Commencement
51 During the trial
52 Completion of the trial
53 Duration of the trial
TRIAL RECORDS
54 Test results
56 Observations

HAT(E) Chap 1
UK RESTRICTED Page 1
TP 3541 UK RESTRICTED

HAT(E) SCHEDULE OF TESTS

Test Group Page

1 Console ............................................................................................................... 1
2 EAU (ASYNC) ..................................................................................................... 8
3 EAU (SYNC) ........................................................................................................ 13
4 EAU (EOTS) ........................................................................................................ 18
5 NRTE ................................................................................................................... 23
6 GCP 76mm .......................................................................................................... 28
7 GCP 30mm .......................................................................................................... 33
8 WASP .................................................................................................................. 38
9 DATALINK Y ....................................................................................................... 39
10 RTVDU ................................................................................................................ 41
11 Radar video generator.......................................................................................... 43
12 Gun footpush ....................................................................................................... 46
13 System ................................................................................................................ 50

Annexes

A Test records
B SES running instructions
C Console BIST list
D EAU/010 (ASYNC) BIST list
E EAU/011 (SYNC) BIST list
F EAU/013 (EOTS) BIST list
G NRTE BIST list
H GCP (76mm) BIST list
I GCP (30mm) BIST List
J Console operator-controlled extended BIST list
K EAU/010 (ASYNC) operator-controlled extended BIST list
L EAU/011 (SYNC) operator-controlled extended BIST list
M EAU/013 (EOTS) operator-controlled extended BIST list
N NRTE operator-controlled extended BIST list
O GCP 30mm operator-controlled extended BIST list
P GCP 76mm operator-controlled extended BIST list
Q SES test 022 TV external test picture description
R Equipment designations within CWCS
S List of abbreviations

HAT(E) Chap 1
Page 2 UK RESTRICTED
UK RESTRICTED TP 3541

INTRODUCTION

1 This Harbour Acceptance Trial (Equipment) (HAT(E)) Schedule is applicable to the


Command and Weapon Control System (CWCS) supplied to BAE Systems Marine (BSM) for the
Royal Brunei Armed Forces by Alenia Marconi Systems (AMS) Limited, Integrated Systems
Division, under contract 98/4253/1055-1057. The major unit tests and system tests are defined in
HAT(E) Schedule of Tests.

2 The definition of the items of equipment covered by this schedule is contained in the Minimum
Build Document, but excludes Carried On Board Spares.

OBJECTIVE

3 The objective of HAT(E) is to demonstrate that the CWCS hardware functions correctly as
individual units and when linked as a complete system via the Ethernet Highway after installation
and setting to work on board ship.

AUTHORITIES

4 For the purposes of this Trial, the following roles are identified:

(1) Preparation of CWCS for Trial: Presenting Authority.

(2) Trial Programming: Accepting Authority.

(3) Trial Presentation: Presenting Authority

(4) Trial Conduct: Accepting Authority.

(5) Trial Acceptance: Accepting Authority.

REQUIREMENTS

5 Requirements for the trial are as follows:

5.1 Equipment for the Trial is to be prepared ensuring that all pre-conditions are satisfied
and that all pre-requisites are met.

5.2 Ensure all documents required are produced or referenced during the Trial, these
include records of Observations recorded during previous Trials and actions taken.

5.3 Complete the requisite records during the Trial.

5.4 Raise an Observation wherever a departure from the expected result is noted during
the Trial.

5.5 At the completion of the Trial, agree the validity and assess the results of the Trial,
together with the categorization of any Observations raised during the Trial..

5.6 Sign the Observation Reports in confirmation that the content provides an accurate
record of the Trial.

5.7 Conduct pre-Trial and post-Trial briefings and wash-up meetings.

HAT(E) Chap 1
UK RESTRICTED Page 3
TP 3541 UK RESTRICTED

5.8 Conduct the Trial.

5.9 At the daily wash-up meeting, and in any event no later than the completion of the Trial,
agree the categorization of any recorded observations in accordance with the provisions of
this schedule.

5.10 At the completion of the Trial, agree the validity and the assessed result of the Trial.

LIMITATIONS

6 The tests performed within the HAT(E) are aimed at establishing the correct operation of each
major unit of the CWCS when connected via the Ethernet Highway and internal interconnecting
Ship’s Cables. There is no connectivity to external Combat Systems Interfaces.

ACCEPTANCE CRITERIA

7 The result of each numbered test sequence is to be assessed against the following criteria:

7.1 The test is to be recorded as complete and satisfactory when the test steps have been
carried out and the expected results have been observed without the raising of a Failing
Observation.

7.2 The test result is accepted as correct when the result observed falls within the tolerance
permitted in that test for the measurement of the respective parameter.

8 An Observation is to be raised wherever the result observed during a test serial does not
match that defined in the expected result column of that test serial. Observations may be raised
to record comments pertaining to the test documentation.

9 An Observation is to be placed in an agreed category. The Observations are then further


classified as Non-Failing or Failing Observation.

10 The result of the Trial must be agreed between all parties at the final post-trial meeting at the
completion of the Trial taking into consideration all recorded Observations and information
contained in the Trial Report.

SAFETY PRECAUTIONS

11 No special safety precautions are applicable during normal operation of the equipment under
test and its associated test equipment during this Trial other than acknowledgement of normal
personnel safety precautions when working with electronic equipment.

12 Procedures for the commissioning and maintenance of the CWCS equipment are contained
in the Technical Documentation. Since equipment operates from a.c. power supplies and
generates high voltages to drive a Cathode Ray Tube display, appropriate Hazard Notices are
contained within the equipment and in the Documentation.

13 Full Anti-static procedures are to be used when handling PECs.

RECORDING AND ANALYSIS

14 There is no requirement for recording and analysis.

HAT(E) Chap 1
Page 4 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL PRE-REQUISITES

TRIAL PRE-CONDITIONS

15 Prior to commencement of the HAT(E) and, to ensure that the correct conditions required for
the Trial are achieved, a number of actions are required to be complete:

15.1 At least 30 calendar days notice of the intended commencement of the Trial.

15.2 At least ten days notice of the names and status of the intended attendees (or
nominated representatives) is required.

15.3 Trial Schedule presentation five months prior to the Trial.

15.4 A Test Readiness Review (TRR) not less than ten working days prior to each defined
trial phase.

TEST READINESS REVIEW

Timescale

16 The Test Readiness Review meeting is to be held at least two weeks prior to each
Acceptance Trial.

Objectives

17 The objectives of the The Test Readiness Review meeting is to:

(1) Agree the Acceptance Trial Plan.

(2) Agree the progress towards the Functional Configuration Audit (FCA) and the Physical
Configuration Audit (PCA).

(3) Ensure that the necessary resources are identified and in place.

(4) Agree the compatibility between VCRI and schedules.

(5) Agree that the Acceptance Trial may proceed.

Pre-requisites

18 The following items to be reviewed and confirmed:

(1) Daily Test or Trial Plan.

(2) Statement of acceptance documentation status.

(3) Statement of equipment status.

(4) Version Description Document and Design Certificate.

(5) PCA/FCA status reports.

HAT(E) Chap 1
UK RESTRICTED Page 5
TP 3541 UK RESTRICTED

(6) Status Report on Observations raised in previous Acceptance Test or Trials.

(7) Status Report on outstanding Observations.

(8) Summary of Concessions

19 Personnel designated by the RBAF or their authorised representatives, are to be in


attendance.

Agenda

20 The agenda for the meeting follows the following format:

(1) Summary of Purpose of Meeting

(2) Acceptance Trial Plan

(3) Status of Trials Schedules

(4) Status of Equipment

(5) Status of Software against Acceptance Criteria

(6) Status of Observations raised at Previous Acceptance Trial

(7) Status of outstanding Observations

(8) Summary of Actions raised.

(9) Any Other Business

(10) Recommendation to proceed (or otherwise)

Meeting minutes

21 The minutes of the meeting are to be recorded.

PREPARATION OF TEST EQUIPMENT

22 The test equipment defined within this schedule as being required to support the Test
configuration of the CWCS equipment must be prepared for use during the Test in accordance
with the appropriate procedures.

23 Test equipment (with serial numbers) provided for the simulation, stimulation or measurement
of interface parameters must be in date for calibration.

AVAILABILITY OF SERVICES

24 The availability of services such as power supplies, ventilation, cooling, etc., is to be


confirmed prior to the Test. Availability is to be considered against the requirements of the
equipment under test.

25 There are no special requirements for services from other Contractors or Authorities.

HAT(E) Chap 1
Page 6 UK RESTRICTED
UK RESTRICTED TP 3541

26 There are no special precautions required to ensure non-interference by or with other


activities during this Test.

PREPARATION OF CWCS EQUIPMENT

27 Prior to HAT(E) each CWCS Console, each EAU, the NRTE, both 30mm and the 76mm
Gunfire Control Predictor, the WASP, RVG, RTVDU, Datalink Y, Bridge Display and the Gun
Footpushes must have been previously accepted against the Factory Acceptance Test
(Equipment) Schedule.

28 All CWCS hardware and software presented for Trial must be formally released and its build
state recorded and any deficiencies declared.

FUNCTIONAL CONFIGURATION AUDIT

29 The Functional Configuration Audit (FCA) is a formal Design Assurance audit to validate that
the development of a configuration item (hardware) has been completed satisfactorily and that the
configuration item has achieved the performance and functional characteristics specified in the
functional or allocated configuration identification. In addition, the completed operation and
support documents must be reviewed.

30 The FCA is to be progressed using all test results.

31 A sample inspection of the requirement trail is to be carried out immediately prior to the TRR.

32 The following documentation is to be presented for the FCA:

(1) NAUTIS:

a. Main Assembly Design Certificates.

b. Main Assembly Design Reports.

c. Hardware Requirement Specification VCRI.

d. Procurement Specification VCRI (21 in. Bridge Display, etc.).

e. Design Assurance certified PTS Results.

(2) RTVDU:

a. Design Certificate.

b. Design Reports (PEC).

(3) RVG:

a. Design Certificate.

b. Design Reports.

HAT(E) Chap 1
UK RESTRICTED Page 7
TP 3541 UK RESTRICTED

(4) DATALINK Y:

a. Design Certificate

PHYSICAL CONFIGURATION AUDIT

33 A Physical Configuration Audit (PCA) is a technical examination of the first of a designated


configuration item to verify that the configuration item “As Built” conforms to the technical
documentation which defines it.

34 Hardware configuration items are defined by the Hardware Build State Definition document
and comply with the Hardware Minimum Build State Definition Document.

35 In preparation for the first applicable test or trial of the System, a PCA is to be prepared and,
for subsequent tests or trials, the PCA is to be updated to reflect any hardware changes.

36 An inspection of the requirement trial is to be carried out immediately prior to the TRR.

PREPARATION OF DOCUMENTS

37 The HAT(E) schedule must be confirmed as being at the latest amendment issue before
authorisation of its use in the conduction of the Test.

38 A Build State Document is to be prepared and formally issued. It defines the Build State of all
items of equipment subject to Test. These definitions include the firmware and hardware of the
CWCS at the date of commencement of the Test.

39 Records of tests performed prior to the Test, and which may be cited as evidence as required
by one or more of the Test schedules, are to be endorsed and made available for reference.

40 All Observations raised prior to the start of the Test relating to the CWCS or any part of its
equipment or BIST and SES software are to be available for inspection at the Test.

HAT(E) Chap 1
Page 8 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL REQUIREMENTS

VENUE AND FACILITIES REQUIRED

41 The HAT(E) Trial is to be carried out on-board Ship berthed alongside.

42 Unrestricted access to all equipment comprising the CWCS is required for the personnel
presenting and conducting the Trial.

PROVISION OF TEST EQUIPMENT, POWER SUPPLIES AND TEST SOFTWARE

43 The following items are required to be provided:

(1) Blank DAT Tape DG-90MA SONY.

(2) System Software Tape No: 380/FU/35000/000.

(3) Link Y Software CD No.: 380/FU/36062/000.

(4) RVG Software CD No.: 364/FU/35911/000.

(5) Test Scenario Software No.: 380/FU/35075/00.

PROVISION OF CWCS EQUIPMENT

44 The minimum requirement for CWCS for this Trial is one complete CWCS, comprising:

(1) 8 in No. CWCS Display Consoles (No 678/1/42001/100).

(2) 8 in No. Ethernet Adaptor Unit (ASYNC) (No 678/1/42100/010).

(3) 5 in No. Ethernet Adaptor Unit (SYNC) (No 678/1/42100/011).

(4) 1 in No. Ethernet Adaptor Unit (EOTS) (No 678/1/42100/013).

(5) 1 in No. Navigation Radar Track Extractor (No 678/1/42080/010).

(6) 2 in No. 30mm Gunfire Control Predictors (No 678/1/42060/010).

(7) 1 in No. 76mm Gunfire Control Predictor (No 678/1/42060/011).

(8) 1 in No. Weapon Auxiliary Switching Panel (No 678/1/43910/000)

(9) 1 in No. 21 in. Bridge Display (No 678/1/43358/001).

(10) 1 in No. Radar Video Generator with Control Unit (612/7/50760/001) and Junction Box.

(11) 2 in No. Radar Television Video Distribution Units (678/7/41516/002).

(12) 1 in No. Datalink Y - including Remote Control Panel (612/7/50757/005).

(13) 1 in No RCP and Link Y Remote Switch Box (678/1/43979/000)

HAT(E) Chap 1
UK RESTRICTED Page 9
TP 3541 UK RESTRICTED

(14) Data Output Interface (Maintainer's PC) (678/1/42124/001).

(15) 4 in No. Gun FootPushes (No 408/4/58765/000).

(16) Magnetic Tape Cartridges/CD discs: Software System (No. 380/FU/35090/000)


Link Y Software (CD No. 380/FU/36062/000)
RVG Software (CD No. 364/FU/35911/004)
Test Scenario Software
(No. 380/FU/35075/000).

(17) Blank Magnetic Tape Cartridge (DAT) DG-90MA SONY

(18) 1 in No Maintainer’s Tool Kit (678/1/42152/101)

(19) Nautis II dual redundant Ethernet Highway

(20) Nautis II Monitoring Ethernet Highway

45 Any substitution of equipment during the Trial must be confined to equipment which is of the
same build standard as that recorded in the Trial Records and must have been subjected to the
defined pre-requisite tests. Such substitution must be recorded in the Trials Log.

PROVISION OF SHIP SERVICES EQUIPMENT

46 The following non-CWCS ship equipment is required for the trial when stated, and must be at
HAT standard and operational.

(1) All internal interconnecting cables and Local Area Network (LAN) cables.

(2) VCS21 (50 V a.c. for WASP).

TRIAL EQUIPMENT CONFIGURATION

47 All CWCS equipment is to be connected by the dual redundant Ethernet highway and the
monitor highway (where applicable) and all ‘internal’ interconnecting cables shall be connected to
the equipment Termination Panels for the Trial.

48 The configuration and set-up conditions for each group of tests within the Trial are defined in
HAT(E) Schedule of Tests contained in this chapter.

PERSONNEL REQUIREMENTS

49 The following staff are required to perform the roles and to carry out the responsibilities of the
Trial:

(1) Test Director

(2) Test Recorder / Reader

(3) Test Operator(s)

(4) Design Assurance Observer

HAT(E) Chap 1
Page 10 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL CONDUCT AND DURATION

COMMENCEMENT

50 At the commencement of the Trial, a meeting is to be convened to:

50.1 Brief all attendees as to the purpose of the Trial and the procedures to be followed.

50.2 Agree that all Trial pre-requisites have been met and that there are no circumstances
known which might lead to a judgement that the Trial conditions could be invalid.

50.3 Agree that the records prepared prior to the commencement of the Trial are accurate,
complete and reflect the conformity of the equipment with the requirements of this Schedule.

DURING THE TRIAL

51 The following may take place at any time during the trial:

51.1 A meeting may be convened at the start of each day's work during the Trial to
communicate changes in plans for the days work or to consider any other factors affecting
the progress of the Trial.

51.2 Test cables may be connected prior to the start of each main assembly test.

51.3 The tests to be carried out for each CWCS unit are defined in HAT(E) Schedule of Tests.
The Tests are grouped under suitable headings, but may be carried out in any order.

51.4 As each test serial is completed, a note of its completion is to be recorded in the
appropriate Record Sheet with a note of any Observations raised during the test.

51.5 Observations are to be raised according to the defined criteria.

51.6 Each Observation is to be assigned a sequential serial number within the series being
maintained until Final Acceptance.

51.7 An Observation can be raised at any time, which has the next number in the
Observation sequence. These Observations can be raised as a result of deviations from, or
deficiencies in each test.

51.8 The categorisation of Observations raised is to be carried out as soon as possible and,
in any event, no later than the end of the Trial.

51.9 At the end of each Trial day, a meeting may be held to agree the records obtained, i.e.,
Observations, test documentation errors, test validity, test results and recommendations.

COMPLETION OF THE TRIAL

52 At the completion of the Trial, a post-Trial meeting is to be convened. At this meeting, the
following matters are to be considered and agreed:

52.1 The records obtained.

52.2 The Observations to be recorded and their categorisation.

HAT(E) Chap 1
UK RESTRICTED Page 11
TP 3541 UK RESTRICTED

52.3 The errors noted in the test or trials documentation.

52.4 The validity of the Trial.

52.5 The result of the Trial.

52.6 The requirements for re-presentation, if any.

52.7 Any matters not resolved during the Trial.

52.8 The designated authority is to determine Acceptance.

DURATION OF THE TRIAL

53 The anticipated duration of the HAT(E) is expected to be five working days in total.

HAT(E) Chap 1
Page 12 UK RESTRICTED
UK RESTRICTED TP 3541

TRIAL RECORDS

TEST RESULTS

54 During the Trial, the Results Record for each group of tests in this schedule must be ticked,
initialled and dated to indicate the completion of each test in the test sequence. This Record is
intended for the convenience of the presenting and conducting authorities to record progress
through the Trial. A copy is to be included in the Test report.

55 Where any test to be applied to the CWCS in this Trial requires the taking of readings for
future use, the results produced by the respective test are to be recorded in the Results Record.

OBSERVATIONS

56 Where an Observation is raised during the conduct of a test, using the Combat System
Agency Work Instruction, a note of the Observation serial number is to be made against the
respective test in the Results Record Sheet. This acts as an aide memoire to the conducting
authority when reviewing the Trial.

HAT(E) Chap 1
UK RESTRICTED Page 13/14
UK RESTRICTED TP 3541

Chapter 2

HAT(E) SCHEDULE OF TESTS

TEST GROUP 1: CONSOLE

Test Group 1 CONSOLE


OBJECTIVE OF TEST
Console Switch-On and Run-Up Confidence Checks: To demonstrate the Power-on, Run-up and correct
functioning of Console components. Power-up BIST and Operator-Controlled BIST, in Extended Mode, is
demonstrated.
This test group is to be repeated for all eight Consoles

Test 1.1 METHOD


Power Indicators, Dimmer switch and Elapsed Time Meter: Mains supply is connected to Termination
Panel and the Integrated Control Panel (ICP) is set to ON. Elapsed Time Meter incrementing is checked
over at least six minutes. The Console FAULT and OVERHEAT indicators are observed. The System
Monitor connection is observed. The Power Supply to the Console is observed.

PROCEDURE EXPECTED RESULTS


1.1.1 Connect 115 V 60 Hz a.c. MAINS and Observe, on the ICP, that the ACH ON LED and the
ACH supplies to PLV and PLW. MAINS AVAILABLE LED are extinguished.
1.1.2 On the ICP, set the ON/OFF switch to ON. Observe, on the ICP, that the ACH ON LED is
Record the reading indicated at the Console extinguished, the MAINS AVAILABLE LED remains
elapsed time indicator. Note the current time. lit and that the MAINS ON LED is lit.
1.1.3 On the ICP, view the Operator Control’s Observe, on the ICP, the FAULT LED is illuminated.
FAULT and OVERHEAT LEDs. NOTE
The FAULT LED is red until all Applications
Software is running when it changes to green.
Observe the OVERHEAT LED is illuminated green.
1.1.4 At the ICP, press the BRIGHT/DIM switch Observe that the LEDs are bright and dim as
to demonstrate the operation, and effect, of the selected at the switch.
switch upon the ICP illuminated LEDs.
1.1.5 After at least six minutes from Console Observe that the time has incremented.
power-up time noted above, view and record the
reading of the Elapsed Time Meter.
1.1.6 At the ICP, switch OFF the Console. Observe, on the ICP, the ACH ON LED is
illuminated, the MAINS AVAILABLE LED remains
illuminated and the MAINS ON LED is
extinguished.
1.1.7 Connect the Maintainer’s Terminal to the
Maintainer’s Terminal connector SKA 'MASTER’
connection on the Maintainer’s Bracket inside the
Electronics Module front door, and enter ‘Terminal
Mode’, at the Maintainer’s Terminal, by selecting
the ‘Terminal’ application from the DeskTop.
(Continued)

HAT(E) Chap 2
UK RESTRICTED Page 1
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


1.1.8 Switch the Console ON at the ICP. At the Maintainer’s Terminal, observe that the
Console BIST runs (in Quick mode), rapidly
displaying the Console BIST list.
On completion of the BIST run, observe that the
Operating System and Applications Software is
loaded.
(Continued)

Test 1.2 METHOD


All pec pass Power-up BIST and BIST indicators are correct. Console is switched ON, the BITE
indications are observed at the Console and the Start-Up menu is called at the Maintainer’s Terminal.
The SMF option and Slave Processor Control option are invoked.

PROCEDURE EXPECTED RESULTS


1.2.1 Ensure that the Console is switched OFF
at the ICP.
1.2.2 At the Console, raise the keyboard desk
assembly and open the front doors of the
Electronics Module to view the Console pec
indicators.
1.2.3 Connect the Maintainer’s Terminal to the
Maintainer’s Terminal connector SKA ‘MASTER’
below the Electronics Module, and enter ‘Terminal
mode’, at the Maintainer’s Terminal, by selecting
the ‘Terminal’ application from the DeskTop.
1.2.4 Switch the Console ON at the ICP. Observe that the Console FAULT LED is lit red
while BIST is running.
Observe that the LEDs: AC FAIL, SYSRESET,
TEMP 1, AIRFLOW and DC LOW 1 on the SIG pec
(Card Carrier slot 5) are extinguished,
NOTE
The SIG SYSFAIL LED remains illuminated until
such time as the Applications Software is loaded
and the Console achieves full operational state.
Observe that the front panel LEDs 0, 1, 2 and 3, on
the Master and Slave SBC pecs (Card Carrier slots
1 and 16) illuminate in a binary count sequence
whilst the BIST tests are running.
(The colour of the LEDs can be ignored).
1.2.5 At the Console ICP, press ‘RESTART’. At the Maintainer’s Terminal, observe that the
View the Maintainer’s Terminal screen. Console BIST runs, rapidly displaying the Console
BIST list.
Observe that BIST completes within approximately
30 seconds from restart.
1.2.6 During the Remainder BIST, press any At the Console, observe that LEDs 0, 1, 2 and 3 on
Maintainer’s Terminal key. the Master and Slave SBC pec are extinguished.
(Continued)

HAT(E) Chap 2
Page 2 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


1.2.8 View the Maintainer’s Terminal screen. At the Maintainer’s Terminal, observe that the Start
Up menu is displayed, thus:
START UP MENU
1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF)
Enter Selection 1–7:
1.2.8 Using the scroll bar, on the Maintainer’s Observe that the Console BIST List is as described
Terminal, review the displayed Console BIST list. in Annex C.
1.2.9 Using the scroll bar, on the Maintainer’s
Terminal, display the Start Up menu.
1.2.10 At the Maintainer’s Terminal, select option Observe that the Restricted System Management
7<CR> (Run SMF) from the Start Up Menu. Facilities (SMF) menu is displayed.
1.2.11 From the Restricted SMF menu select Observe that the operator is prompted for SMF
option U<CR> (Full SMF menu). User name.
1.2.12 Enter SMF User name: Observe that the operator is prompted for
maintainer1<CR> Password.

1.2.13 Enter Password: Observe that the password is accepted and the Full
password<CR> System Management Facilities (SMF) menu is
displayed.
NOTE
Observe that the Copy File (C), Install File (I) and
‘password’ is the default password only and
Install System (Z) options are available.
may be altered at a later date.
1.2.14 At the Console ICP, press ‘RESTART’. At the Maintainer’s Terminal, observe that the
View the Maintainer’s Terminal screen. Console BIST runs, rapidly displaying the Console
BIST list.
1.2.15 During the Remainder BIST, press any Observe that BIST completes and the Start Up
Maintainer’s Terminal key. menu is displayed.
1.2.16 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> (Slave Processor Control) from the Start Up NOTE
Menu and enter 02<CR> in response to the
While in Slave Processor Control mode, each
processor ID prompt.
displayed line is tagged with ‘<02>’ to indicate
that the Slave SBC is being accessed.
1.2.17 From the Slave Processor Start-up menu, Observe that ‘bist>’ is displayed on the
select option 3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
1.2.18 At the Maintainer’s Terminal, enter: Observe that the Slave SBC BIST tests only are
l<CR> (list). listed on the Maintainer’s Terminal, as defined in
Annex C.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 3
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


1.2.19 At the Console ICP, press ‘RESTART’. At the Maintainer’s Terminal, observe that the
View the Maintainer’s Terminal screen. Console BIST runs, rapidly displaying the Console
BIST list.
NOTE
The Slave SBC is no longer being accessed
directly by the Maintainer’s Terminal.
1.2.20 During the Remainder BIST, press any Observe that BIST completes and the Start Up
Maintainer’s Terminal key. menu is displayed.
1.2.21 At the Maintainer’s Terminal, select option Observe that the operating System and
1<CR> (Run Applications) from the Start Up Menu. Applications Software software is loaded in the
same manner as normal start-up.
(Continued)

Test 1.3 METHOD


All pec pass Operator-controlled BIST in both Quick and Extended Mode: Operator-controlled BIST is
selected at the Maintainer’s Terminal within the Start-Up menu where Quick and Extended mode is
selected.
NOTE
Running Extended BIST proves the Ethernet connection from the unit to the Transceiver and that the
Transceiver is connected to a correctly terminated Highway. Therefore, both Dual Redundant Highway
and Monitor Highway connections are proved.

PROCEDURE EXPECTED RESULTS


1.3.1 View the Console Termination panel. Observe that an ‘ENET MONITOR’ connector
(SKS) is provided, and suitable LAN drop cable is
in place to the Monitor Highway transceiver.
1.3.2 Connect the Maintainer’s Terminal to the
Maintainer’s Terminal connector SKA 'MASTER’
connection on the Maintainer’s Bracket inside the
Electronics Module front door, and enter ‘Terminal
Mode’ at the Maintainer’s Terminal, by selecting the
‘Terminal’ application from the Desk Top.
1.3.3 Ensure that the Start Up menu is displayed
on the Maintainer’s Terminal screen.
1.3.4 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
1.3.5 Select, all tests (a), one iteration (1), Quick Observe that the Console Quick BIST tests run,
mode (q), continue on failure (c). displaying the Console Operator-Controlled Quick
Type: a,1,q,c<CR>. BIST List.

1.3.6 Select all tests (a), through five iterations Observe that the Console Quick BIST tests run
(5), Quick mode (q), continue on failure (c). through five iterations, displaying the Console
Type: a,5,q,c<CR>. Operator-Controlled Quick BIST List.

(Continued)

HAT(E) Chap 2
Page 4 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


NOTE
During Serials 1.3.7 to 1.3.9, select each test
individually from the Console BIST through two
iterations in Quick mode with continue on
failure, on both Master and Slave PME68-42,
and also PME ENET-1
1.3.7 Type t,x,2,q,c<CR> to invoke test number Observe that tests 1 to 9 for the Master PME68-42
‘x’, (where x = 1 through 9 from the Master are executed, as invoked, through two iterations in
PME68-42 BIST Remainder list). Quick mode, and each displays the correct status
After completing test 9, type: <Cntl>e. from Annex C, without errors.

1.3.8 Use Slave Test Control option 5<CR> from Observe that tests 1 to 7 for the Slave PME68-42
the Start Up menu and enter 02<CR> in response are executed, as invoked, through two iterations in
to the processor ID prompt to verify the Slave Quick mode, and each displays the correct status
PME68-42. from Annex C, without errors.
From the Start-up menu, select option 3<CR>
(Operator-Controlled BIST).
Type t,x,2,q,c<CR> to invoke test number ‘x’,
(where x = 1 through 7 on the Slave PME68-42
BIST Remainder list through two iterations in
Quick mode with continue on failure).
After completing test 7, type: <Ctrl>e.
1.3.9 Use Slave Test Control option 5<CR> from Observe that tests 1 to 3 for the PME ENET-1 are
the Start Up menu and enter 01<CR> in response executed, as invoked, through two iterations in
to the processor ID prompt to verify PME ENET-1. Quick mode, and each displays the correct status
From the Start-up menu, select option 3<CR> from Annex C, without errors.
(Operator-Controlled BIST).
Type: t,x,2,q,c<CR> to invoke test number ‘x’,
(where x = 1 through 3 on the PME ENET-1
BIST Remainder list through two iterations in
Quick mode with continue on failure).
After completing test 3, type <Ctrl>e.
1.3.10 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST) Maintainer’s Terminal.
1.3.11 Using the Operator-Controlled BIST Observe that the Console Extended BIST tests run,
facility, (at the Master processor), select all tests displaying the Console Operator-Controlled
(a), one iteration (1), Extended mode (e), and Extended BIST List.
continue on failure (c) as follows: NOTE
Type: a,1,e,c<CR>. This test takes approximately 1.0 hour to
complete.
1.3.12 Wait for Extended BIST to complete. Observe that ‘BIST run completed’ is displayed on
the Maintainer’s Terminal screen and that the
Console master and Slave processor front panel
LEDs are all OFF, except for PR.
1.3.13 Using the scroll bar, on the Maintainer’s Observe that the Console Operator-Controlled
Terminal, review the displayed Console Extended BIST list, as defined in Annex J, is
Operator-Controlled Extended BIST list. displayed.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 5
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


NOTE
During Serials 1.3.14 to1.3.16, select and run
any individual test, at random, from the Console
BIST, through two iterations in Extended mode
with option to continue on error, on both Master
and Slave PME68-42, and also PME ENET-1.
1.3.14 Type t,x,2,e,c<CR> to invoke test number Observe that tests 1 to 9 for the Master PME68-42
‘x’ (where x = 1 through 9 from the Master are executed, as invoked, through two iterations in
PME68-42 BIST Remainder list). Extended mode, and each displays the correct
After completing test 9, type <Ctrl>e. status from Annex J, without errors.
1.3.15 Use Slave Test Control option 5<CR> from Observe that tests 1 to 7 for the Slave PME68-42
the Start Up menu and enter 02<CR> in response are executed, as invoked, through two iterations in
to the processor ID prompt to verify Slave PME68- Extended mode, and each displays the correct
42. status from Annex J, without errors.
From the Start-up menu, select option 3<CR>
(Operator-Controlled BIST).
Type t,x,2,e,c<CR> to invoke test number ‘x’,
(x = 1 through 7 on the Slave PME68-42 BIST
Remainder list through two iterations in
Extended mode with option to continue on
error).
After completing test 7, type <Ctrl>e.
1.3.16 Use Slave Test Control option 5<CR> from Observe that tests 1 to 3 for the PME ENET-1 are
the Start Up menu and enter 01<CR> in response executed, as invoked, through two iterations in
to the processor ID prompt to verify PME ENET-1. Extended mode, and each displays the correct
From the Start-up menu, select option 3 status from Annex J, without errors.
(Operator-Controlled BIST).
Type t,x,2,e,c<CR> to invoke test number ‘x’,
(and x = 1 through 3 on the PME ENET-1 BIST
Remainder list through two iterations in
Extended mode with option to continue on
error).
After completing test 3, type <Ctrl>e
1.3.17 On the Console ICP, set the ON/OFF
switch to OFF.
1.3.18 At the Console card carrier, remove one NOTE
end of the ribbon cable between the Vantage and This should induce a BIST non-fatal failure.
Virgo++ front panels, slots 19 and 20.
1.3.19 At the Console ICP, set the ON/OFF At the Maintainer’s Terminal, observe that the
switch to ON. Console BIST runs, rapidly displaying the Console
View the Maintainer’s Terminal screen. BIST list.
Observe that BIST test 008 (Slave Test Control)
reports a non-fatal failure due to the Vantage to
Virgo++ hardware disconnection.
Observe that the BIST completes the remaining
tests.
1.3.20 During the Remainder BIST, press any Observe that the Start Up menu is displayed.
Maintainer’s Terminal key.
(Continued)

HAT(E) Chap 2
Page 6 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


1.3.21 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 02<CR> NOTE
in response to the processor ID prompt.
While in Slave Processor Control mode, each
displayed line is tagged with ‘<02>’ to indicate
that the Slave SBC is being accessed.
1.3.22 From the Slave Start-up menu, select Observe that ‘bist>’ is displayed on the
option 3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
1.3.23 Select and run BIST test 007 (Virgo++) Observe that the selected test is executed, as
(t,7), from the Console BIST, through two (2) invoked, through only one iteration in Extended
iterations in Extended mode (e), with option to mode, and displays an error report for test ‘007’
abort (a) test on error. and a status ‘C00000FF’.
Type t,7,2,e,a<CR> to invoke test number ‘007’ Observe that the test run has been aborted.
(from the Slave BIST Remainder list).
1.3.24 Select and run BIST test 007 (Virgo++) Observe that the selected test is executed, as
(t,7), from the Console BIST, through two (2) invoked, through two iterations in Extended mode,
iterations in Extended (e) mode, with option to and displays an error report for test ‘007’ and a
continue testing on error (c). status ‘C00000FF’.
Type t,7,2,e,c<CR> to invoke test number ‘007’ Observe that the test run has continued through
(from the Slave BIST Remainder list). two iterations despite the error, and the following
message is displayed:
‘BIST run Completed’.
1.3.25 Exit Operator-Controlled BIST. Observe that the Slave Processor Start Up menu is
Type: e<CR>. displayed on the Maintainer’s Terminal screen.
1.3.26 Exit Slave Processor Control mode. Observe that the Master Processor Start Up menu
Type: <Ctrl>e. is displayed on the Maintainer’s Terminal screen.

1.3.27 On the Console ICP, set the ON/OFF


switch to OFF. Restore the ribbon connection
between the Vantage and Virgo++ front panels
slots 19 and 20.
1.3.28 At the Console ICP, set the ON/OFF At the Maintainer’s Terminal, observe that the
switch to ON. View the Maintainer’s Terminal Console BIST runs.
screen.
1.3.29 During the Remainder BIST, press any Observe that BIST completes and the Start Up
Maintainer’s Terminal key. menu is displayed.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 7
TP 3541 UK RESTRICTED

TEST GROUP 2: EAU (ASYNC)

Test Group 2 EAU (ASYNC)


OBJECTIVE OF TEST
Switch-On and Run-Up Confidence Checks – EAU (010 – ASYNC): To demonstrate the Power-ON,
Run-Up and correct functioning of EAU components. Power-ON components included are Power
Indicators, Power-up BIST and BITE indicators for all pec, BIST for all pec in Extended mode. These
procedures are to be repeated for all EAU (010 - ASYNC).
NOTE
Throughout this test section, the equipments are required to achieve ‘Operational’ state; this requires
a CWCS Console to be powered-up.

Test 2.1 METHOD


Power Indicators and Elapsed Time Meter. Mains supply is connected to the EAU and is switched to ON.
Elapsed Time Meter incrementation is checked over at least six minutes. The EAU FAULT and TEMP
indicators are observed.

PROCEDURE EXPECTED RESULTS


2.1.1 Set the MAINS and ACH ON/ISOLATION
switches, located on the top front panel, to
ISOLATION.
2.1.2 Ensure that the 115 V 60 Hz a.c. supplies Observe, at the Termination Panel, that the MAINS
are available to connectors PLK MAINS and PLL AVAIL and ACH AVAIL LEDs are illuminated.
ACH on the Termination Panel.
2.1.3 Set the ACH ISOLATION switch to ON. Observe, on the front panel, that the ACH ON LED
illuminates.
2.1.4 On the front panel, set the MAINS ON/ Observe, on the front panel, that the ACH ON LED
ISOLATION switch to ON. extinguishes and the MAINS ON LED illuminates
Note the reading on the Elapsed Time meter. and that the TEMP LED is illuminated green and
Note also the current time. the FAULT LED is illuminated red.
NOTE
The FAULT LED is red until all Applications
Software is running when it changes to green.
2.1.5 After at least six minutes from the noted Observe that the time has incremented.
current time above, record the reading of the
Elapsed Time Meter.
2.1.6 At the front panel, set the MAINS ON/ Observe, on the front panel that the ACH ON LED
ISOLATION switch to ISOLATION. is illuminated.

HAT(E) Chap 2
Page 8 UK RESTRICTED
UK RESTRICTED TP 3541

Test 2.2 METHOD


All pec pass Power-up BIST and BIST indicators are correct. EAU is switched ON, the BIST indications
are observed and the Start Up menu is called. The SMF and Slave Control facilities are selected.

PROCEDURE EXPECTED RESULTS


2.2.1 Ensure that the MAINS ON/ISOLATION
switch is set to ISOLATION.
2.2.2 Connect a Maintainer’s Terminal to
‘MASTER’ socket on the top front panel of the
EAU, and enter ‘Terminal Mode’, at the
Maintainer’s Terminal, by selecting the ‘Terminal’
application from the ‘DESKTOP’.
2.2.3 Switch ON the EAU. Observe that the EAU FAULT LED is lit red while
BIST is running.
Observe that the LEDs: AC FAIL, SYSRESET,
TEMP 1, AIRFLOW and DC LOW 1 on the SIG pec
(Card Carrier slot 7) are extinguished.
NOTE
The Sig SYSFAIL LED remains illuminated until
such time as the Applications Software is loaded
and the EAU achieves full operational state.
2.2.4 During the Remainder BIST, press any Observe that the front panel LEDs 0, 1 and 2, on
Maintainer’s Terminal key. the Master SBC pec (Card Carrier slot 1) illuminate
in a binary sequence while the BIST tests are
running.
(The colours can be ignored)
2.2.5 View the Maintainer’s Terminal screen. Observe that ‘PASSED’ is displayed as each test
completes. Observe that no error messages are
displayed.
Observe that ‘System BIST complete’ is displayed
on the Maintainer’s Terminal and LEDs 0, 1, 2 and
3 on the Master SBC pec are extinguished.
Observe that the Start Up menu is displayed, thus:
START UP MENU
1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF
Enter Selection 1 - 7:
2.2.6 Using the scroll bar on the Maintainer’s Observe that the EAU/010 BIST List is displayed,
Terminal, review the displayed EAU/010 BIST list. as defined in Annex D.
2.2.7 Using the scroll bar on the Maintainer’s Observe that the Start Up menu is displayed.
Terminal, display the Start Up menu.
2.2.8 At the Maintainer’s Terminal, select option Observe that the Restricted System Management
7<CR> from the Start Up Menu. Facilities menu is displayed.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 9
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


2.2.9 From the Restricted SMF menu, select Observe that the operator is prompted for SMF
option U<CR> (Full SMF menu). User name.
2.2.10 Enter SMF User name: Observe that the operator is prompted for
maintainer1<CR> password.
2.2.11 Enter Password: Observe that password is accepted and the Full
password<CR> System Management Facilities (SMF) menu is
displayed.
NOTE
Observe that the Copy File (C), Install File (I) and
‘password’ is the default password only and
Install System (Z) options are available.
may be altered at a later date.
2.2.12 At the EAU SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the EAU/
the Maintainer’s Terminal screen. 010 BIST runs to completion without error.
2.2.13 During the Remainder BIST, press any Observe that the Master Processor Start Up menu
Maintainer’s Terminal key. is displayed.
2.2.14 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 01<CR> NOTE
in response to the processor ID prompt.
While in Slave Processor Control mode, each
displayed line is tagged with ‘<01>’ to indicate
that the Slave SBC is being accessed.
2.2.15 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
2.2.16 At the Maintainer’s Terminal, enter l<CR>, Observe that the Slave BIST tests only are listed
(list). on the Maintainer’s Terminal as defined in
Annex D.
2.2.17 At the EAU SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the EAU/
the Maintainer’s Terminal screen. 010 BIST runs, rapidly displaying the EAU/010
BIST list.
NOTE
The Slave SBC is no longer being accessed
directly by the Maintainer’s Terminal.
2.2.18 During the Remainder BIST, press any Observe that BIST completes and that the Start Up
Maintainer’s Terminal key. menu is displayed.
2.2.19 At the Maintainer’s Terminal, select option Observe that the Operating System and
1<CR> (Run Applications) from the Start Up Menu. Applications Software is loaded in the same
manner as normal start-up (except that the COT
EAU Applications software is not loaded).
Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
2.2.20 Reset the EAU/010. At the Maintainer’s Terminal, observe that the EAU/
010 BIST runs in Quick mode, rapidly displaying
the EAU/010 BIST list.
On completion of the BIST run, observe that the
Operating System and Applications (except COT
EAU Applications) Software is loaded.
2.2.21 View the Maintainer’s Terminal screen. Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
(Continued)

HAT(E) Chap 2
Page 10 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test 2.3 METHOD


All pec pass Operator-controlled BIST in Quick and Extended Mode: Operator-controlled BIST is run
from the Start Up menu and Quick and Extended mode is selected. The System Monitor connection is
observed.
NOTE
Running Extended BIST proves the Ethernet connection from the unit to the Transceiver and that the
Transceiver is connected to a correctly terminated Highway. Therefore, both Dual Redundant Highway
and Monitor Highway connections are proved.

PROCEDURE EXPECTED RESULTS


2.3.1 At the Maintainer’s Terminal connected to
EAU/010, ensure that the Start Up menu is
displayed on the Maintainer’s Terminal screen.
2.3.2 Type 3<CR> to select Operator-Controlled Observe that ‘bist>’ is displayed on the
BIST. Maintainer’s Terminal.
2.3.3 Select all tests (a), one iteration (1), Quick Observe that the EAU/010 Quick BIST tests run,
mode (q), continue on failure (c). displaying the EAU/010 Operator-Controlled Quick
Type: a,1,q,c<CR>. BIST List.

2.3.4 Select all tests (a), through five iterations Observe that the EAU/010 Quick BIST tests run
(5), Quick mode (q), continue on failure (c). through five iterations, displaying the EAU/010
Type: a,5,q,c<CR>. Operator-Controlled Quick BIST List.

2.3.5 Select all tests (a), one iteration (1), Observe that the EAU/010 Extended BIST tests
Extended mode (e), continue on failure (c). run, displaying the EAU/010 Operator-Controlled
Type: a,1,e,c<CR>. Extended BIST List.
NOTE
This test takes approximately 40 minutes to
complete.
2.3.6 Extended BIST is completed. Observe that ‘BIST run completed’ is displayed on
the Terminal screen and the processor front panel
LEDs are all OFF except for PR.
2.3.7 Using the scroll bar, on the Maintainer’s Observe that the EAU/010 Operator-Controlled
Terminal, review the displayed EAU/010 BIST list. Extended BIST List, as defined in Annex K, is
displayed.
2.3.8 On the EAU, set the MAINS ON/
ISOLATION switch to ISOLATION.
2.3.9 At the EAU Card Carrier, remove cable
D/3J3 from the front of the PME ENET-1 pec,
located in slot 3. (This induces a BIST Slave
processor fatal failure in Extended mode only).
2.3.10 At the EAU, set the MAINS ON/ At the Maintainer’s Terminal, observe that the EAU/
ISOLATION switch to ON. 010 BIST runs, rapidly displaying the EAU/010
BIST list.
2.3.11 View the Maintainer’s Terminal screen. Observe that the EAU/010 Quick BIST tests run to
completion without error.
2.3.12 During the Remainder BIST, press any Observe that the Master Start Up menu is
Maintainer’s Terminal key. displayed.
(Continued)

HAT(E) Chap 2
UK RESTRICTED Page 11
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


2.3.13 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 01<CR> NOTE
(for PME ENET-1) in response to the processor ID
While in Slave Processor Control mode, each
prompt.
displayed line is tagged with ‘<01>’ to indicate
that the Slave PME ENET-1 is being accessed.
2.3.14 From the Slave Start-up menu, select Observe that ‘bist>’ is displayed on the
option 3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
2.3.15 Select and run BIST test 003 (APEX 100 Observe that the selected test is executed, as
Network controller), from the EAU/010 BIST, invoked, through only one iteration in Extended
through five iterations in Extended mode, with mode, and displays an error report for test ‘003’
option to abort test on error. and a status ‘C000001F’, followed by the message:
Type: t,3,5,e,a<CR> to invoke test number ‘BIST run aborted due to fatal failure’.
‘003’ (from the Slave BIST Remainder list).
2.3.16 Select and run BIST test 003 (APEX 100 Observe that the selected test is executed, as
Network Controller), from the EAU/010 BIST, invoked, through five iterations in Extended mode,
through five iterations in Extended mode, with and displays an error report for test ‘003’ and a
option to continue testing on error. status ‘C000001F’, which indicates that the test has
At the ‘bist>’ prompt, type: t,3,5,e,c<CR> to continued to run despite the error.
invoke test number ‘003’ (from the Slave BIST
Remainder list).
2.3.17 Exit Operator-Controlled BIST. Observe that the Slave Processor Start Up menu is
Type: e<CR>. displayed on the Maintainer’s Terminal screen.

2.3.18 Exit Slave Processor Control mode. Observe that the Master Processor Start Up menu
Type: <Ctrl>e. is displayed on the Maintainer’s Terminal screen.

2.3.19 On the EAU, set the MAINS ON/


ISOLATION switch to ISOLATION. Reconnect
cable D/3J3 at the front of the PME ENET-1 pec
located in slot 3.
2.3.20 On the EAU, set the MAINS ON/ Observe, on the Maintainer’s Terminal, that the
ISOLATION switch to ON. EAU/011 Quick BIST tests run to completion
without error.
2.3.21 During the Remainder BIST, press any
Maintainer’s Terminal key.
View the Maintainer’s Terminal screen. Observe that the Start Up menu is displayed.
(Continued)

HAT(E) Chap 2
Page 12 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

TEST GROUP 3: EAU (SYNC)

Test Group 3 EAU (SYNC)


OBJECTIVE OF TEST
Switch-On and Run-Up Confidence Checks – EAU (011 – SYNC): To demonstrate the Power-ON,
Run-Up and correct functioning of EAU components. Power-on components included are Power
Indicators, Power-up BIST and BITE indicators for all pec, BIST for all pec in Extended mode. These
procedures are to be repeated for all EAU (011 – SYNC).
NOTES
(1) Throughout this test section, the equipment is required to achieve ‘Operational’ state; this
requires a CWCS Console to be powered-up.
(2) Whilst running the following tests, on the SAP EAU(s), the relevant EAU-under-test is to be set
'active'; i.e., selected at the WASP.

Test 3.1 METHOD


Power Indicators and Elapsed Time Meter. Mains supply is connected to Front Top Panel and the EAU is
switched to 'ON'. Elapsed Time Meter incrementation is checked over at least six minutes. The EAU
FAULT and TEMP indicators are observed.

PROCEDURE EXPECTED RESULTS


3.1.1 Set the MAINS and ACH ON/ISOLATION
switches, located on top front panel, to
'ISOLATION'.
3.1.2 Ensure that the 115 V 60 Hz a.c. supplies Observe, at the EAU front top panel, that the
are available to connectors PLK MAINS and PLL MAINS AVAIL and ACH AVAIL LEDs are
ACH on the Termination Panel. illuminated.
3.1.3 Set the ACH ON/ISOLATION switch to Observe, on the front top panel, that the ACH ON
ON. LED illuminates.
3.1.4 On the front top panel, set the MAINS ON/ Observe, on the front top panel, that the ACH ON
ISOLATION switch to ON. LED extinguishes and the MAINS ON LED is now
Note the reading on the Elapsed Time meter. illuminated.
Note also the current time. Observe that the TEMP LED is illuminated green
and the FAULT LED is illuminated red.
NOTE
The FAULT LED is red until all Applications
Software is running when it changes green.
3.1.5 After at least six minutes from the noted Observe that the time has incremented.
time, above, record the reading of the Elapsed
Time Meter.
3.1.6 At the front top panel, set the MAINS ON/ Observe, on the front top panel, that the ACH ON
ISOLATION switch to ISOLATION. LED is illuminated.

HAT(E) Chap 2
UK RESTRICTED Page 13
TP 3541 UK RESTRICTED

Test 3.2 METHOD


All pec pass Power-up BIST and BIST indicators are correct: EAU is switched ON, the BIST indications
are observed and the Start Up menu is called. The SMF and Slave Control facilities are selected.

PROCEDURE EXPECTED RESULTS


3.2.1 Ensure that the MAINS ON/ISOLATION
switch is set to ISOLATION.
3.2.2 Connect a Maintainer’s Terminal to the
‘MASTER’ socket on the top front panel of the
Power Input Box (PIB), and enter ‘Terminal Mode’,
at the Maintainer’s Terminal, by selecting the
‘Terminal’ application from the ‘DESKTOP’.
3.2.3 Switch ON the EAU. Observe that the EAU FAULT LED is lit while BIST
is running.
Observe that the LEDs: AC FAIL, SYSRESET,
TEMP 1, AIRFLOW and DC LOW 1 on the SIG pec
(Card Carrier slot 7) are extinguished.
NOTE
The SIG SYSFAIL LED remains illuminated until
such time as the Applications Software is loaded
and the EAU achieves full operational state).
3.2.4 During the Remainder BIST, press any Observe that the front panel LEDs 0, 1 and 2, on
Maintainer’s Terminal key. the Master SBC pec (Card Carrier slot 1) illuminate
in a binary sequence while the BIST tests are
running.
(The colours can be ignored)
3.2.5 View the Maintainer’s Terminal screen. Observe that ‘PASSED’ is displayed as each test
completes. Observe that no error messages are
displayed.
Observe that LEDs 0, 1, 2 and 3 on the Master
SBC pec are extinguished. Observe that the Start
Up menu is displayed, thus:
START UP MENU
1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF)
Enter Selection 1 - 7:
3.2.6 Using the scroll bar on the Maintainer’s Observe that the EAU/011 BIST List is displayed as
Terminal, review the displayed EAU/011 BIST list. defined in Annex E.
3.2.7 Using the scroll bar on the Maintainer’s Observe that the Start Up menu is displayed.
Terminal, display the Start up menu.
3.2.8 At the Maintainer’s Terminal, select option Observe that the Restricted System Management
7<CR> from the Start Up Menu. Facilities menu is displayed in Annex E.
(Continued)

HAT(E) Chap 2
Page 14 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


3.2.9 From the Restricted SMF menu, select Observe that the operator is prompted for SMF
option U<CR> (Full SMF menu). User name.
3.2.10 Enter SMF User name: Observe that the operator is prompted for
maintainer1<CR> password.
3.2.11 Enter Password: Observe that password is accepted and the Full
password<CR> System Management Facilities (SMF) menu is
displayed.
NOTE
Observe that the Copy File (C), Install File (I) and
‘password’ is the default password only and
Install System (Z) options are available.
may be altered at a later date.
3.2.12 At the EAU SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the EAU/
the Maintainer’s Terminal screen. 011 BIST runs to completion without error.
3.2.13 During the Remainder BIST, press any Observe that the Master Processor Start Up menu
Maintainer’s Terminal key. is displayed.
3.2.14 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 01<CR> NOTE
in response to the processor ID prompt.
While in Slave Processor Control mode, each
displayed line is tagged with ‘<01>’ to indicate
Slave SBC is being accessed.
3.2.15 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
3.2.16 At the Maintainer’s Terminal, enter l<CR> Observe that the Slave BIST tests only are listed
(list). on the Maintainer’s Terminal, as defined in Annex
E.
3.2.17 At the EAU SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the EAU/
the Maintainer’s Terminal screen. 011 BIST runs, rapidly displaying the EAU/011
BIST list.
NOTE
The Slave SBC is no longer being accessed
directly by the Maintainer’s Terminal.
3.2.18 During the Remainder BIST, press any Observe that BIST completes and that the Start Up
Maintainer’s Terminal key. menu is displayed.
3.2.19 At the Maintainer’s Terminal, select option Observe that the operating System and
1<CR> (Run Applications) from the Start Up Menu. Applications Software is loaded in the same
manner as normal start-up.
Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
3.2.20 At the EAU SIG pec, press ‘RESET’. At the Maintainer’s Terminal, observe that the EAU/
011 BIST runs in Quick mode, rapidly displaying
the EAU/011 BIST list.
On completion of the BIST run, observe that the
operating System and Applications Software is
loaded.
3.2.21 View the Maintainer’s Terminal screen. Observe at the Maintainer’s Terminal that the
Restricted SMF menu is displayed.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 15
TP 3541 UK RESTRICTED

Test 3.3 METHOD


All pec pass Operator-controlled BIST in Quick and Extended Mode: Operator-controlled BIST is run
from the Start Up menu and Quick and Extended mode are selected.
NOTE
Running Extended BIST proves the Ethernet connection from the unit to the Transceiver and that the
Transceiver is connected to a correctly terminated Highway. Therefore both Dual Redundant Highway
and Monitor Highway connections are proved.

PROCEDURE EXPECTED RESULTS


3.3.1 At Maintainer’s Terminal connected to Observe that the Start Up menu is displayed, thus:
EAU/011, ensure that the Start Up menu is
START UP MENU
displayed on the Terminal screen. 1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF)
Enter Selection 1–7
3.3.2 Type 3<CR> to select Operator-Controlled Observe that ‘bist>’ is displayed on the
BIST. Maintainer’s Terminal.
3.3.3 Select all tests (a), one iteration (1), Quick Observe that the EAU/011 Quick BIST tests run,
mode (q), continue on failure (c). displaying the EAU/011 Operator-Controlled Quick
Type: a,1,q,c<CR>. BIST List.

3.3.4 Select all tests (a), through five iterations Observe that the EAU/011 Extended BIST tests run
(5), Quick mode (q), continue on failure (c). through five iterations, displaying the EAU/011
Type a,5,q,c<CR>. Operator-Controlled Extended BIST List.

3.3.5 Select all tests (a), one iteration (1), Observe that the EAU/011 Extended BIST tests
Extended mode (e), continue on failure (c). run, displaying the EAU/011 Operator-Controlled
Type: a,1,e,c<CR>. Extended BIST List.
NOTE
This test takes approximately 40 minutes to
complete.
3.3.6 Extended BIST is completed. Observe that ‘BIST run completed’ is displayed on
the Maintainer’s Terminal screen and the processor
front panel LEDs are all OFF except for PR.
3.3.7 Using the scroll bar on the Maintainer’s Observe that the EAU/011 Operator-Controlled
Terminal, review the displayed EAU/011 BIST list. Extended BIST List, as defined in Annex L, is
displayed.
3.3.8 On the EAU/011, set the MAINS ON/
ISOLATION switch to ISOLATION.
3.3.9 At the EAU card carrier, remove cable D/
3J3 from the front of the PME ENET-1 pec located
in slot 3. (This induces a BIST Slave Processor
fatal failure in Extended mode only).
(Continued)

HAT(E) Chap 2
Page 16 UK RESTRICTED
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


3.3.10 At the EAU, set the MAINS ON/ At the Maintainer’s Terminal, observe that the EAU/
ISOLATION switch to ON. 011 BIST runs, rapidly displaying the EAU/011
BIST list.
3.3.11 View the Maintainer’s Terminal screen. Observe that the EAU/011 Quick BIST tests run to
completion without error.
3.3.12 During the Remainder BIST, press any Observe that the Master Start Up menu is then
Maintainer’s Terminal key. displayed.
3.3.13 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 01<CR> NOTE
(for PME ENET-1) in response to the processor ID
While in Slave Processor Control mode each
prompt.
displayed line is tagged with ‘<01>’ to indicate
Slave PME ENET-1 is being accessed.
3.3.14 From the Slave Start-up menu, select Observe that ‘bist>’ is displayed on the
option 3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
3.3.15 Select and run BIST test 003 (APEX 100 Observe that the selected test is executed, as
Network controller), from the EAU/011 BIST, invoked, through only one iteration in Extended
through five iterations in Extended mode, with mode, and displays an error report for test ‘003’
option to abort test on error. and a status ‘C000001F’, followed by the message:
Type t,3,5,e,a<CR> to invoke test number ‘003’ ‘BIST run aborted due to fatal failure’.
(from the Slave BIST Remainder list).
3.3.16 Select and run BIST test 003 (APEX 100 Observe that the selected test is executed, as
Network Controller), from the EAU/011 BIST, invoked, through five iterations in Extended mode,
through five iterations in Extended mode, with and displays an error report for test ‘003’ and a
option to continue testing on error. status ‘C000001F’, which indicates that the test has
At the ‘bist>’ prompt, type t,3,5,e,c<CR> to continued to run despite the error.
invoke test number ‘003’ (from the Slave BIST
Remainder list).
3.3.17 Exit Operator-Controlled BIST. Observe that the Slave Processor Start Up menu is
Type: e<CR>. displayed on the Maintainer’s Terminal screen.

3.3.18 Exit Slave Processor Control mode: Observe that the Master Processor Start Up menu
Type <Ctrl>e. is displayed on the Maintainer’s Terminal screen.

3.3.19 On the EAU, set the MAINS ON/


ISOLATION switch to ISOLATION. Reconnect
cable D/3J3 at the front of the PME ENET-1 pec
located in slot 3.
3.3.21 On the EAU, set the MAINS ON/ Observe, on the Maintainer’s Terminal, that the
ISOLATION switch to ON. EAU/011 Quick BIST tests run to completion
without error.
3.3.21 During the Remainder BIST, press any
Maintainer’s Terminal key.
View the Maintainer’s Terminal screen. Observe that the Start Up menu is displayed.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 17
TP 3541 UK RESTRICTED

TEST GROUP 4: EAU (EOTS)

Test Group 4 EAU (EOTS)


OBJECTIVE OF TEST
Switch-On and Run-Up Confidence Checks – EAU (013 – EOTS). To demonstrate the Power-ON, run-up
and correct functioning of EAU components. Power-on components included are Power Indicators,
Power-up BIST and BITE indicators for all pec, BIST for all pec in Extended mode.
NOTE
Throughout this test section, the equipments are required to achieve ‘Operational’ state; this requires
a CWCS Console to be powered-up.

Test 4.1 METHOD


Power Indicators and Elapsed Time Meter. Mains supply is connected to the front top panel and the EAU
is switched to ON. Elapsed Time Meter incrementing is checked over at least six minutes. The FAULT
and TEMP indicators are observed.

PROCEDURE EXPECTED RESULTS


4.1.1 Set the MAINS and ACH ISOLATION
switches, located on the top front panel, to
ISOLATION.
4.1.2 Ensure that the 115 V 60 Hz a.c. supplies Observe, at the top front panel, that the MAINS
are available to connectors PLK and PLL on the top AVAIL and ACH AVAIL LEDs are illuminated.
front panel.
4.1.3 Set the ACH ISOLATION switch to ON. Observe, on the top front panel, that the ACH ON
LED illuminates.
4.1.4 Set the MAINS ON/ISOLATION switch to Observe, on the top front panel, that the ACH ON
ON. LED extinguishes and the MAINS ON LED
Note the reading on the Elapsed Time meter. illuminates.
Note also the current time. Observe also that the TEMP LED is illuminated
green and the FAULT LED is illuminated red
NOTE
The FAULT LED is red until all Applications
Software is running when it changes to green.
4.1.5 After at least six minutes from the noted Observe that the time has incremented.
time above, record the reading of the Elapsed Time
Meter.
4.1.6 At the top front panel, set the MAINS ON/ Observe, on the top front panel, that the ACH ON
ISOLATION switch to ISOLATION. LED is illuminated.

HAT(E) Chap 2
Page 18 UK RESTRICTED
UK RESTRICTED TP 3541

Test 4.2 METHOD


All pec pass Power-up BIST and BIST indicators are correct. EAU is switched on, the BIST indications
are observed and the Start Up menu is called. The SMF and Slave Control facilities are selected.

PROCEDURE EXPECTED RESULTS


4.2.1 Ensure that the MAINS ON/ISOLATION
switch is set to ISOLATION.
4.2.2 Connect a Maintainer’s Terminal to the
‘MASTER’ socket on the top front panel and enter
‘Terminal mode’, at the Maintainer’s Terminal, by
selecting the ‘Terminal’ application from the
‘DESKTOP’.
4.2.3 Switch ON the EAU. Observe that the EAU FAULT LED is lit whilst BIST
is running.
Observe that the LEDs: AC FAIL, SYSRESET,
TEMP 1, AIRFLOW and DC LOW 1 on the SIG pec
(Card Carrier slot 7) are extinguished.
NOTE
The SIG SYSFAIL LED remains illuminated until
such time as the Application Software is loaded
and the EAU achieves full operational state.
4.2.4 During the Remainder BIST, press any Observe that the front panel LEDs 0, 1 and 2, on
Maintainer’s Terminal key. the Master SBC pec (Card Carrier slot 1) are
illuminated by counting up in a binary sequence
while the tests are running.
(The colours can be ignored.)
4.2.5 View the Maintainer’s Terminal screen. Observe that ‘PASSED’ is displayed as each test
completes. Observe that no error messages are
displayed.
Observe that ‘System BIST complete’ is displayed
on the Terminal screen and LEDs 0, 1, 2 and 3 on
the Master SBC pec are extinguished. Observe
that the Start Up menu is displayed, thus:
START UP MENU
1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF)
Enter Selection 1–7
4.2.6 Using the scroll bar, on the Maintainer’s Observe that the EAU/013 BIST List is displayed
Terminal, review the displayed EAU/013 BIST list. as defined in Annex F.
4.2.7 Using the scroll bar, on the Maintainer’s Observe that the Start Up menu is displayed.
Terminal, display the Start Up menu.
4.2.8 At the Maintainer’s Terminal, select option Observe that the Restricted System Management
7<CR> from the Start Up Menu. Facilities menu is displayed.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 19
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


4.2.9 From the Restricted SMF menu, select Observe that the operator is prompted for SMF
option U<CR> (Full SMF menu). User name.
4.2.10 Enter the SMF User name: Observe that the operator is prompted for
maintainer1<CR> password.
4.2.11 Enter the Password: Observe that password is accepted and the Full
password<CR> System Management Facilities (SMF) menu is
displayed.
NOTE
Observe that the Copy File (C), Install File (I) and
‘password’ is the default password only and
Install System (Z) options are available.
may be altered at a later date.
4.2.12 At the EAU SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the EAU/
the Maintainer’s Terminal screen. 013 BIST runs to completion without error.
4.2.13 During the Remainder BIST, press any Observe that the Master Processor Start Up menu
Maintainer’s Terminal key. is displayed.
4.2.14 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 01<CR> NOTE
in response to the processor ID prompt.
While in Slave Processor Control mode, each
displayed line is tagged with ‘<01>’ to indicate
that the Slave SBC is being accessed.
4.2.15 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
4.2.16 At the Maintainer’s Terminal, enter l<CR>, Observe that the Slave BIST tests only are listed
(list). on the Maintainer’s Terminal as defined in Annex F.
4.2.17 At the EAU SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the EAU/
the Maintainer’s Terminal screen. 013 BIST runs, rapidly displaying the EAU/013
BIST list.
NOTE
The Slave SBC is no longer being accessed
directly by the Maintainer’s Terminal.
4.2.18 During the Remainder BIST, press any Observe that BIST completes and that the Start Up
Maintainer’s Terminal key. menu is displayed.
4.2.19 At the Maintainer’s Terminal, select option Observe that the operating System and
1<CR> (Run Applications) from the Start Up Menu. Applications Software is loaded in the same
manner as normal start-up.
Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
4.2.20 At the EAU SIG pec, press ‘RESET’. At the Maintainer’s Terminal, observe that the EAU/
013 BIST runs (in Quick mode), rapidly displaying
the EAU/013 BIST list.
On completion of the BIST run, observe that the
Operating System and Applications Software is
loaded.
4.2.21 View the Maintainer’s Terminal screen. Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
(Continued)

HAT(E) Chap 2
Page 20 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test 4.3 METHOD


All pec pass Operator-controlled BIST in Quick and Extended Mode. Operator-controlled BIST is run
from the Start Up menu and Quick and Extended mode is selected.
NOTE
Running Extended BIST proves the Ethernet connection from the unit to the Transceiver and that the
Transceiver is connected to a correctly terminated Highway. Therefore, both Dual Redundant Highway
and Monitor Highway connections are proved.

PROCEDURE EXPECTED RESULTS


4.3.1 At a Maintainer’s Terminal connected to
EAU/013, ensure that the Start Up menu is
displayed on the Terminal screen.
4.3.2 Type 3<CR> to select Operator-Controlled Observe that ‘bist>’ is displayed on the
BIST. Maintainer’s Terminal.
4.3.3 Select all tests (a), one iteration (1), Quick Observe that the EAU/013 Quick BIST tests run,
mode (q), continue on failure (a). displaying the EAU/013 Operator-Controlled Quick
Type: a,1,q,c<CR>. BIST List.

4.3.4 Select all tests (a), through five iterations Observe that the EAU/013 Quick BIST tests run
(5), Quick mode (q), continue on failure (a). through five iterations, displaying the EAU/013
Type: a,5,q,c<CR>. Operator-Controlled Quick BIST List.

4.3.5 Select all tests (a), one iteration (1), Observe that the EAU/013 Extended BIST tests
Extended mode (e), continue on failure (a). run, displaying the EAU/013 Operator-Controlled
Type a,1,e,c<CR>. Extended BIST List.
NOTE
This test takes approximately 40 minutes to
complete.
4.3.6 Extended BIST is completed. Observe that ‘BIST run completed’ is displayed on
the Maintainer’s Terminal screen and the processor
front panel LEDs are all OFF except for PR.
4.3.7 Using the scroll bar on the Maintainer’s Observe that the EAU/013 Operator-Controlled
Terminal, review the displayed EAU/013 BIST list. Extended BIST List, as defined in Annex M, is
displayed.
4.3.8 On the EAU, set the MAINS ON/
ISOLATION switch to ISOLATION.
4.3.9 At the EAU Card Carrier, remove cable D/
3J3 from the front of the PME ENET-1 pec located
in slot 3. (This induces a BIST Slave processor
fatal failure in Extended mode only).
4.3.10 At the EAU, set the MAINS ON/ At the Maintainer’s Terminal, observe that the EAU/
ISOLATION switch to ON. 013 BIST runs, rapidly displaying the EAU/013
BIST list.
4.3.11 View the Maintainer’s Terminal screen. Observe that the EAU/013 Quick BIST tests run to
completion without error.
4.3.12 During the Remainder BIST, press any Observe that the Master Start Up menu is then
Maintainer’s Terminal key. displayed.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 21
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


4.3.13 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 01<CR> NOTE
(for PME ENET-1) in response to the processor ID
While in Slave Processor Control mode, each
prompt. displayed line is tagged with ‘<01>’ to indicate
that the Slave PME ENET-1 is being accessed.
4.3.14 From the Slave Start-up menu, select Observe that ‘bist>’ is displayed on the
option 3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
4.3.15 Select and run BIST test 003 (APEX 100 Observe that the selected test is executed, as
Network controller), from the EAU/013 BIST, invoked, through only one iteration in Extended
through five iterations in Extended mode, with mode, and displays an error report for test ‘003’
option to abort test on error. and a status ‘C000001F’, followed by the message:
Type: t,3,5,e,a<CR> to invoke test number ‘BIST run aborted due to fatal failure’.
‘003’ (from the Slave BIST Remainder list).
4.3.16 Select and run BIST test 003 (APEX 100 Observe that the selected test is executed, as
Network controller), from the EAU/013 BIST, invoked, through five iterations in Extended mode,
through five iterations in Extended mode, with and displays an error report for test ‘003’ and a
option to continue testing on error. status ‘C000001F’, which indicates that the test has
At the ‘bist>’ prompt, type t,3,5,e,c<CR> to continued to run despite the error.
invoke test number ‘003’ (from the Slave BIST
Remainder list).
4.3.17 Exit Operator-Controlled BIST. Observe that the Slave Processor Start Up menu is
Type: e<CR>. displayed on the Maintainer’s Terminal screen.

4.3.18 Exit Slave Processor Control mode. Observe that the Master Processor Start Up menu
Type: <Ctrl>e. is displayed on the Maintainer’s Terminal screen.

4.3.19 On the EAU, set the MAINS ON/


ISOLATION switch to ISOLATION. Reconnect
cable D/3J3 at the front of the PME ENET-1 pec
located in slot 3.
4.3.20 On the EAU, set the MAINS ON/ Observe, on the Maintainer’s Terminal, that the
ISOLATION switch to ON. EAU/013 Quick BIST tests run to completion
During the Remainder BIST, press any Maintainer’s without error.
Terminal key. Observe that the Start Up menu is displayed.
4.3.21 View the Maintainer’s Terminal screen.
(Continued)

HAT(E) Chap 2
Page 22 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

TEST GROUP 5: NRTE

Test Group 5 NRTE


OBJECTIVE OF TEST
Switch-On and Run-Up Confidence Checks – NRTE: To demonstrate the Power-on, Run-up and correct
functioning of NRTE components. Power-on components included are Power Indicators, Power-up BIST
and BITE indicators for all pec, BIST for all pec in Extended mode.
NOTE
Throughout this test section, the equipment is required to achieve ‘Operational’ state; this requires a
CWCS Console to be powered-up.

Test 5.1 METHOD


Power Indicators and Elapsed Time Meter. Mains supply is connected to the Power Input Box and the
NRTE is switched ON. Elapsed Time Meter incrementation is checked over at least six minutes. The
NRTE FAULT and TEMP indicators are observed. The System Monitor connection is observed.

PROCEDURE EXPECTED RESULTS


5.1.1 Set the MAINS and ACH ON/ISOLATION
switches, located on the Power Input Box (PIB), to
ISOLATION.
5.1.2 Connect 115 V 60 Hz a.c. supplies to Observe, at the PIB, that the MAINS AVAIL and
connectors PLK and PLL on the PIB. ACH AVAIL LEDs illuminate.
5.1.3 Set the ACH ON/ISOLATION switch to Observe, on the MPA, that the ACH ON LED
ON. illuminates.
5.1.4 On the PIB, set the MAINS ON/ Observe, on the MPA, that the ACH ON LED
ISOLATION switch to ON. extinguishes and the MAINS ON LED is now
Note the reading on the Elapsed Time meter. illuminated.
Note also the current time. Observe at the PIB, that the TEMP LED is
illuminated green and the FAULT LED is
illuminated red.
NOTE
The FAULT LED is red until all Applications
Software is running when it changes to green.
5.1.5 After at least six minutes from the noted Observe that the time has incremented.
time, above, record the reading of the Elapsed
Time Meter.
5.1.6 At the PIB, set the MAINS ON/ISOLATION Observe, on the MPA, that the ACH ON LED is
switch to ISOLATION. illuminated.

HAT(E) Chap 2
UK RESTRICTED Page 23
TP 3541 UK RESTRICTED

Test 5.2 METHOD


All pec pass Power-up BIST and BIST indicators are correct: NRTE is switched on, the BIST indications
are observed and the Start Up menu is called. The SMF and Slave Control facilities are selected.

PROCEDURE EXPECTED RESULTS


5.2.1 Ensure that the MAINS ON/ISOLATION
switch is set to ISOLATION.
5.2.2 Connect the Maintainer’s Terminal to SKN
on the front of the Power Input Box, and enter
‘Terminal Mode’, at the Maintainer’s Terminal, by
selecting the ‘Terminal’ application from the
‘DESKTOP’
5.2.3 Switch ON the NRTE. Observe that the NRTE FAULT LED is lit while
During the Remainder BIST, press any Maintainer’s BIST is running.
Terminal key. Observe that the LEDs: AC FAIL, SYSRESET,
TEMP 1, AIRFLOW and DC LOW 1 on the SIG pec
(Card Carrier slot 7) are extinguished.
NOTE
The SIG SYSFAIL LED remains illuminated until
such time as the Applications Software is loaded
and the NRTE achieves full operational state.
Observe that the front panel LEDs 0, 1, 2 and 3, on
the Master and Slave SBC pec (Card Carrier slots
1 and 13) illuminate in a binary sequence while the
BIST tests are running.
(The colours can be ignored)
5.2.4 View the Maintainer’s Terminal screen. Observe that the NRTE BIST runs, rapidly
displaying the NRTE BIST list.
5.2.5 View the Maintainer’s Terminal screen. Observe that ‘PASSED’ is displayed as each test
completes. Observe that no error messages are
displayed.
Observe that ‘System BIST complete’ is displayed
on the terminal screen and LEDs 0, 1, 2 and 3 on
the Master SBC pec are extinguished. Observe
that the Start Up menu is displayed, thus:
START UP MENU
1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF)
Enter Selection 1 - 7:
5.2.6 Using the scroll bar on the Maintainer’s Observe that the NRTE BIST List, as defined in
Terminal, review the displayed NRTE BIST list. Annex G, is displayed.
5.2.7 Using the scroll bar on the Maintainer’s Observe that the Start Up menu is displayed.
Terminal, display the Start Up menu.
(Continued)

HAT(E) Chap 2
Page 24 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


5.2.8 At the Maintainer’s Terminal, select option Observe that the Restricted System Management
7<CR> (Run SMF) from the Start Up menu. Facilities menu is displayed.
5.2.9 From the Restricted SMF, menu select Observe that the operator is prompted for SMF
option U<CR> (Full SMF menu). User name.
5.2.10 Enter the SMF User name: Observe that the operator is prompted for
maintainer1<CR>. Password.
5.2.11 Enter the Password: Observe that password is accepted and the Full
password<CR>. System Management Facilities (SMF) menu is
displayed.
NOTE
Observe that the Copy File (C), Install File (I) and
‘password’ is the default password only and
Install System (Z) options are available.
may be altered at a later date.
5.2.12 At the NRTE SIG pec, press RESET At the Maintainer’s Terminal, observe that the
switch. View the Maintainer’s Terminal screen. NRTE BIST runs, rapidly displaying the NRTE
BIST list.
5.2.13 During the Remainder BIST, press any Observe that BIST completes and the Master
Maintainer’s Terminal key. Processor Start Up menu is displayed.
5.2.14 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up menu and enter 02<CR> NOTE
in response to the processor ID prompt.
While in Slave Processor Control mode, each
displayed line is tagged with ‘<02>’ to indicate
that the Slave SBC is being accessed.
5.2.15 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
5.2.16 At the Maintainer’s Terminal, select option Observe that the Slave SBC BIST tests only are
l<CR>, (list). listed on the Maintainer’s Terminal, see Annex G.
5.2.17 At the NRTE SIG pec, press the RESET At the Maintainer’s Terminal, observe that the
switch. View the Maintainer’s Terminal screen. NRTE BIST runs, rapidly displaying the NRTE
BIST list.
5.2.18 During the Remainder BIST, press any Observe that BIST completes and the Master
Maintainer’s Terminal key. Processor Start Up menu is displayed.
5.2.19 At the Maintainer’s Terminal, select option Observe that the operating System and
1<CR> (Run Applications) from the Start Up Menu. Applications Software software is loaded in the
same manner as normal start-up.
Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
5.2.20 At the NRTE SIG pec, press the RESET At the Maintainer’s Terminal, observe that the
switch. NRTE BIST runs in Quick mode, rapidly displaying
the NRTE BIST list.
On completion of the BIST run, observe that the
Operating System and Applications Software is
loaded.
5.2.21 View the Maintainer’s Terminal screen. Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 25
TP 3541 UK RESTRICTED

Test 5.3 METHOD


All pec pass Operator-controlled BIST in Quick and Extended Mode: Operator-controlled BIST is run
from the Start Up menu and Quick and Extended mode are selected.
NOTE
Running Extended BIST proves the Ethernet connection from the unit to the Transceiver and that the
Transceiver is connected to a correctly terminated Highway. Therefore, both Dual Redundant Highway
and Monitor Highway connections are proved.

PROCEDURE EXPECTED RESULTS


5.3.1 At the NRTE SIG pec, press RESET At the Maintainer’s Terminal, observe that the
switch. View the Maintainer’s Terminal screen. NRTE BIST runs, rapidly displaying the NRTE
During the Remainder BIST, press any Maintainer’s BIST list.
Terminal key. Observe that BIST completes and the Master
Processor Start Up menu is displayed.
5.3.2 Type 3<CR> to select Operator-Controlled Observe that ‘bist>’ is displayed on the
BIST. Maintainer’s Terminal.
5.3.3 Select all tests (a), one iteration (1), Quick Observe that the NRTE Quick BIST tests run,
mode (q), continue on failure (c). displaying the NRTE Operator-Controlled Quick
Type: a,1,q,c<CR>. BIST List.

5.3.4 Select all tests (a), through five iterations Observe that the NRTE Quick BIST tests run
(5), Quick mode (q), continue on failure (c). through five iterations, displaying the NRTE
Type: a,5,q,c<CR>. Operator-Controlled Quick BIST List.

5.3.5 Select all tests (a), one iteration (1), Observe that the NRTE Extended BIST tests run,
Extended mode (e), continue on failure (c). displaying the NRTE Operator-Controlled
Type: a,1,e,c<CR>. Extended BIST List.
NOTE
This test takes approximately 50 minutes to
complete.
5.3.6 Wait for Extended BIST tests to complete. Observe that ‘BIST run completed’ is displayed on
the Maintainer’s Terminal screen and the processor
front panel LEDs 0, 1, 2 and 3 on the Master and
Slave SBC pec are all OFF except for PR.
5.3.7 Using the scroll bar on the Maintainer’s Observe that the NRTE Operator-Controlled
Terminal, review the displayed NRTE Extended BIST List, as defined in Annex N, is
Operator-Controlled Extended BIST list. displayed.
5.3.8 On the NRTE set the MAINS ON/
ISOLATION switch to ISOLATION.
5.3.9 At the NRTE Card Carrier, remove cable
D/3J3 from the front of the PME ENET-1 pec
located in slot 3. (This induces a BIST Slave
Processor fatal failure in Extended mode only).
5.3.10 At the NRTE, set the MAINS ON/ At the Maintainer’s Terminal, observe that the
ISOLATION switch to ON. NRTE BIST runs, rapidly displaying the NRTE
BIST list.
(Continued)

HAT(E) Chap 2
Page 26 UK RESTRICTED
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


5.3.11 View the Maintainer’s Terminal screen. Observe, on the Maintainer’s Terminal, that the
NRTE Quick BIST tests run to completion without
error.
5.3.12 During the Remainder BIST, press any Observe that the Master Start Up menu is
Maintainer’s Terminal key. displayed.
5.3.13 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 01<CR> NOTE
(for PME ENET-1) in response to the processor ID
While in Slave Processor Control mode, each
prompt.
displayed line is tagged with ‘<01>’ to indicate
that the Slave PME ENET-1 is being accessed.
5.3.14 From the Slave Start-up menu, select Observe that ‘bist>’ is displayed on the
option 3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
5.3.15 Select and run BIST test 003 (APEX 100 Observe that the selected test is executed, as
Network Controller), from the NRTE BIST, through invoked, through one iteration in Extended mode,
five iterations in Extended mode, with option to and displays an error report for test ‘003’ and a
abort test on error. status ‘C000001F’, followed by the message:
Type: t,3,5,e,a<CR> to invoke test number ‘BIST run aborted due to fatal failure’.
‘003’ (from the Slave BIST Remainder list).
5.3.16 Select and run BIST test 003 (APEX 100 Observe that the selected test is executed, as
Network controller), from the NRTE BIST, through invoked, through five iterations in Extended mode,
five iterations in Extended mode, with option to and displays an error report for test ‘003’; ‘APEX
continue testing on error. 100 external ethernet loop back failure detected’,
At the ‘bist>’ prompt, type t,3,5,e,c<CR> to and a status C000001F, which indicates that the
invoke test number ‘003’ (from the Slave BIST test has continued to run despite the error.
Remainder list).
5.3.17 Exit Operator-Controlled BIST. Observe that the Slave Processor Start Up menu is
Type: e<CR>. displayed on the Maintainer’s Terminal screen.

5.3.18 Exit Slave Processor Control mode. Observe that the Master Processor Start Up menu
Type: <Ctrl>e. is displayed on the Maintainer’s Terminal screen.
5.3.19 At the NRTE, set the MAINS ON/
ISOLATION switch to ISOLATION. Reconnect
cable D/3J3 at the front of the PME ENET-1 pec
located in slot 3.
5.3.20 At the NRTE, set the MAINS ON/ Observe, on the Maintainer’s Terminal, that the
ISOLATION switch to ON. NRTE Quick BIST tests run to completion without
error.
5.3.21 During the Remainder BIST, press any Observe that the Start Up menu is displayed.
Maintainer’s Terminal key.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 27
TP 3541 UK RESTRICTED

TEST GROUP 6: GCP 76mm

Test Group 6 GCP 76mm


OBJECTIVE OF TEST
Switch-On and Run-Up Confidence Checks – GCP 76mm. To demonstrate the Power-ON, run-up and
correct functioning of GCP components. Power-on components demonstrated are Power Indicators,
Power-up BIST and BITE indicators for all pec and BIST for all pec in Extended mode.
NOTE
Throughout this test section, the equipment is required to achieve ‘Operational’ state; this requires a
CWCS Console to be powered-up.

Test 6.1 METHOD


Power Indicators and Elapsed Time Meter. Mains supply is connected to a Power Input Box and the GCP
is switched to ON. Elapsed Time Meter incrementing is checked over at least 6 minutes.

PROCEDURE EXPECTED RESULTS


6.1.1 Set the MAINS, ACH and REF ON/
ISOLATION Switches, located on the Power Input
Box (PIB), to ISOLATION.
6.1.2 Connect 115 V 60 Hz a.c. supplies to Observe, at the PIB, that the MAINS AVAIL, ACH
connectors PLK MAINS and PLL ACH and 115 V AVAIL AND REF AVAIL LEDs illuminate.
400 Hz a.c. supply to connector PLM REF on the
PIB.
6.1.3 Set the ACH ON/ISOLATION switch to Observe, on the MPA, that the ACH ON LED
ON. illuminates.
6.1.4 At the PIB, set the MAINS ON/ISOLATION Observe, on the MPA, that ACH ON LED
switch to ON. extinguishes and the MAINS ON LED is now
Note the reading on the Elapsed Time meter. illuminated.
Note also the current time. Observe, on the PIB, that the TEMP LED is
illuminated green and the FAULT LED is
illuminated red.
NOTE
The FAULT LED is red until all Applications
Software is running when it changes to green.
6.1.5 After at least six minutes from the noted Observe that the time has incremented.
time, above, record the reading of the Elapsed
Time Meter.
6.1.6 At the PIB, set the MAINS ON/ISOLATION Observe, on the MPA, that the ACH ON LED is
switch to ISOLATION. illuminated.

HAT(E) Chap 2
Page 28 UK RESTRICTED
UK RESTRICTED TP 3541

Test 6.2 METHOD


All pec pass Power-Up BIST and BIST indicators are correct. GCP is switched on, the BIST indications
are observed and the Start Up menu is called. The SMF and Slave Control facilities are selected

PROCEDURE EXPECTED RESULTS


6.2.1 Ensure that the MAINS ON/ISOLATION
switch is set to ISOLATION.
6.2.2 Connect the Maintainer’s Terminal to SKN
on the front of the PIB, and enter ‘Terminal Mode’,
at the Maintainer’s Terminal, by selecting the
‘Terminal’ application from the ‘Desktop’.
6.2.3 Set the GCP MAINS and REFERENCE Observe that the GCP FAULT LED is lit while BIST
ON/ISOLATION switches to ON. is running.
Observe that the following LEDs: AC FAIL,
SYSRESET, TEMP 1, AIRFLOW and DC LOW 1
on the SIG pec (Card Carrier slot 15) are
extinguished.
NOTE
The SIG SYSFAIL LED remains illuminated until
such time as the Applications Software is loaded
and the GCP achieves full operational state.
6.2.4 During the Remainder BIST, press any Observe that the front panel LEDs 0, 1, 2 and 3, on
Maintainer’s Terminal key. the Master and Slave SBC pec (Card Carrier slots
1 and 8) are illuminated by counting up in a binary
sequence while the tests are running.
(The colour of the LEDs can be ignored).
6.2.5 View the Maintainer’s Terminal screen. Observe that the GCP (76mm) BIST runs, rapidly
displaying the GCP (76mm) BIST list.
6.2.6 View the Maintainer’s Terminal screen. Observe that ‘PASSED’ is displayed as each test
completes. Observe that no error messages are
displayed.
Observe that LEDs 0, 1, 2 and 3 on the Master and
Slave SBC pecs are extinguished. Observe that the
Start Up menu is displayed, thus:
START UP MENU
1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF)
Enter Selection 1 - 7:
6.2.7 Using the scroll bar on the Maintainer’s Observe that the GCP (76mm) BIST List, as
Terminal, review the displayed GCP (76mm) BIST defined in Annex H, is displayed.
list.
6.2.8 Using the scroll bar on the Maintainer’s
Terminal, display the Start Up menu.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 29
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


6.2.9 At the Maintainer’s Terminal, select option Observe that the Restricted System Management
7<CR> from the Start Up Menu. Facilities menu is displayed.
6.2.10 From the Restricted SMF menu, select Observe that the operator is prompted for SMF
option U<CR> (Full SMF menu). User name.
6.2.11 Enter the SMF User name: Observe that the operator is prompted for
maintainer1<CR>. password.
6.2.12 Enter the Password: Observe that password is accepted and the Full
password<CR>. System Management Facilities (SMF) menu is
displayed.
NOTE
Observe that the Copy File (C), Install File (I) and
‘password’ is the default password only and Install System (Z) options are available.
may be altered at a later date.
6.2.13 At the GCP SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the GCP
the Maintainer’s Terminal screen. BIST runs to completion without error.
During the Remainder BIST, press any Maintainer’s Observe that the Start Up menu is displayed.
Terminal key.
6.2.14 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 02<CR> NOTE
in response to the processor ID prompt.
While in Slave Processor Control mode, each
displayed line is tagged with ‘<02>’ to indicate
that the Slave SBC is being accessed.
6.2.15 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
6.2.16 At the Maintainer’s Terminal, enter l<CR>, Observe that the Slave SBC BIST tests only are
(list). listed on the Maintainer’s Terminal, see Annex H.
6.2.17 At the GCP SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the GCP
the Maintainer’s Terminal screen. BIST runs, rapidly displaying the GCP BIST list.
NOTE
The Slave SBC is no longer being accessed
directly by the Maintainer’s Terminal.
6.2.18 During the Remainder BIST, press any Observe that BIST completes and that the Start Up
Maintainer’s Terminal key. menu is displayed.
6.2.19 At the Maintainer’s Terminal, select option Observe that the operating System and
1<CR> (Run Applications) from the Start Up Menu. Applications Software software is loaded in the
same manner as normal start-up.
Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
6.2.20 At the GCP SIG pec, press ‘RESET’. At the Maintainer’s Terminal, observe that the GCP
BIST runs (in Quick mode), rapidly displaying the
GCP BIST list.
On completion of the BIST run, observe that the
Operating System and Applications Software is
loaded.
6.2.21 View the Maintainer’s Terminal screen. Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
(Continued)

HAT(E) Chap 2
Page 30 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test 6.3 METHOD


All pec pass Operator-controlled BIST in Quick and Extended Mode. Operator-controlled BIST is run
from the Start Up menu and Quick and Extended mode is selected.
NOTE
Running Extended BIST proves the Ethernet connection from the unit to the Transceiver and that the
Transceiver is connected to a correctly terminated Highway. Therefore, both Dual Redundant Highway
and Monitor Highway connections are proved.

PROCEDURE EXPECTED RESULTS


6.3.1 At the GCP SIG pec press ‘RESET’. View Observe that BIST completes and that the Start Up
the Maintainer’s Terminal screen. menu is displayed.
During the Remainder BIST, press any Maintainer’s
Terminal key.
6.3.2 Type 3<CR> to select Operator-Controlled Observe that ‘bist>’ is displayed on the terminal.
BIST.
6.3.3 Select all tests (a), one iteration (1), Quick Observe that the GCP Quick BIST tests run,
mode (q), continue on failure (c). displaying the GCP Operator-Controlled Quick
Type: a,1,q,c<CR>. BIST List.

6.3.4 Select all tests (a), through five iterations Observe that the GCP Quick BIST tests run
(5), Quick mode (q), continue on failure (c). through five iterations, displaying the GCP
Type: a,5,q,c<CR>. Operator-Controlled Quick BIST List.

6.3.5 Select all tests (a), one iteration (1), Observe that the GCP 76mm Extended BIST tests
Extended mode (e), continue on failure (c). run, displaying the GCP 76mm Operator-Controlled
Type: a,1,e,c<CR>. Extended BIST List.
NOTE
This test takes approximately 50 minutes to
complete.
6.3.6 Extended BIST is completed. Observe that ‘BIST run completed’ is displayed on
the terminal screen and the processor front panel
LEDs are all OFF except for PR.
6.3.7 Using the scroll bar on the Maintainer’s Observe that the GCP 76mm Operator-Controlled
Terminal, review the displayed GCP Extended BIST list, as defined in Annex O, is
Operator-Controlled Extended BIST list. displayed.
6.3.8 Set the GCP MAINS ON/ISOLATION
switch to ISOLATION.
Also, ensure that the Reference voltage connector
(PLM) is disconnected.
6.3.9 At the GCP Card Carrier, Slot 12, remove
MPV997A-21 (RTD 1) and remove link A11.
Replace the RTD 1.
(This induces a BIST non-fatal failure).
6.3.10 Re-connect the Reference voltage At the Maintainer’s Terminal, observe that the GCP
connector (PLM). BIST runs, rapidly displaying the GCP BIST list.
Set the GCP MAINS ON/ISOLATION switch to ON.
6.3.11 View the Maintainer’s Terminal screen. Observe that BIST test 009 (MPV997A-21 RTD 1)
reports a non-fatal failure (due to the missing link).
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 31
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


6.3.12 During the Remainder BIST, press any Observe that the Start Up menu is displayed.
Maintainer’s Terminal key.
6.3.13 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 01<CR> NOTE
(for PME ENET-1) in response to the processor ID
While in Slave Processor Control mode, each
prompt.
displayed line is tagged with ‘<01>’ to indicate
that the Slave PME ENET-1 is being accessed.
6.3.14 Enter <Ctrl>e to exit from Slave Processor Observe that the Master Start Up menu is
control. displayed.
6.3.15 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
6.3.16 Select and run BIST test 009 Observe that the selected test is executed, as
(MPV997A-21 RTD 1), from the GCP BIST, through invoked, through only one iteration in Extended
five iterations in Extended mode, with option to mode, and displays an error report for test ‘009’
abort test on error. with a status ‘40000000’, and followed by the
Type t,9,5,e,a<CR> to invoke test number ‘009’ message:
(from the BIST Remainder list). ‘BIST run aborted due to fatal failure.
6.3.17 Select and run BIST test 009 Observe that the selected test is executed, as
(MPV997A-21 (RTD 1)), from the GCP BIST, invoked, through five iterations in Extended mode,
through five iterations in Extended mode, with and at each iteration displays an error report for
option to continue testing on error. test ‘009’ and a status ‘40000000’, which indicates
At the ‘bist>’ prompt, type t,9,5e,c<CR> to that the test has continued to run despite the error.
invoke test number ‘009’ (from the BIST
Remainder list).
6.3.18 Type e<CR> to exit from Observe that the Start Up menu is displayed on the
Operator-Controlled BIST. terminal screen.
6.3.19 Set the GCP MAINS ON/ISOLATION
switch to ISOLATION.
Ensure also that the Reference voltage connector
(PLM) is disconnected.
6.3.20 At the GCP Card Carrier, Slot 12, remove
MPV997A-21 (RTD 1) and restore link A11.
Replace the RTD 1.
6.3.21 Ensure that the Reference voltage Observe, on the Maintainer’s Terminal, that the
connector (PLM) is reconnected. Set the GCP GCP (76mm) Quick BIST tests run to completion
MAINS ON/ISOLATION switch to ON. without error.
View the Maintainer’s Terminal screen.
(Continued)

HAT(E) Chap 2
Page 32 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

TEST GROUP 7: GCP 30MM

Test Group 7 GCP 30mm


OBJECTIVE OF TEST
Switch-On and Run-Up Confidence Checks – GCP 30 mm. To demonstrate the Power-on, run-up and
correct functioning of GCP components. Power-on components demonstrated are Power Indicators,
Power-up BIST and BITE indicators for all pec and BIST for all pec in Extended mode.
NOTES
(1) Throughout this test section, the equipment is required to achieve ‘Operational’ state; this
requires a CWCS Console to be powered-up.
(2) These procedures are also to be repeated for the second 30mm GCP.

Test 7.1 METHOD


Power Indicators and Elapse Time Meter. Mains supply is connected to the Power Input Box (PIB) and
the GCP is switched to ON. Elapsed Time Meter incrementing is checked over at least six minutes.

PROCEDURE EXPECTED RESULTS


7.1.1 Set the MAINS, ACH and REF
ISOLATION switches located on the PIB to
ISOLATION.
7.1.2 Connect 115 V 60 Hz a.c. supplies to Observe, at the PIB, that the MAINS AVAIL, ACH
connectors PLK MAINS and PLL ACH and the AVAIL and REF AVAIL LEDs illuminate.
115 V 400 Hz a.c. supply to connector PLM REF on
the PIB.
7.1.3 Set the ACH ON/ISOLATION switch to Observe, on the MPA, that the ACH ON LED
ON. illuminates.
7.1.4 On the PIB set the MAINS ON/ISOLATION Observe, on the MPA, that the ACH ON LED
switch to ON. extinguishes and the MAINS ON LED illuminates.
Note the reading on the Elapsed Time meter. Observe, on the PIB, that the TEMP LED is
Note also the current time. illuminated green and the FAULT LED is
illuminated red.
NOTE
The FAULT LED is red until all Applications
Software is running when it changes to green.
7.1.5 After at least six minutes from the noted Observe that the time has incremented.
time, above, record the reading of the Elapsed
Time Meter.
7.1.6 At the PIB set the MAINS ON/ISOLATION Observe, on the MPA, that the ACH ON LED is
switch to ISOLATION. illuminated.

HAT(E) Chap 2
UK RESTRICTED Page 33
TP 3541 UK RESTRICTED

Test 7.2 METHOD


All pec pass Power-up BIST and BIST indicators are correct. GCP is switched on, the BIST indications
are observed and the Start Up menu is called. The SMF and Slave Control facilities are selected

PROCEDURE EXPECTED RESULTS


7.2.1 Ensure that the MAINS ON/ISOLATION
switch is set to ISOLATION.
7.2.2 Connect the Maintainer’s Terminal to SKN
on the front of the Power Input Box, and enter
‘Terminal Mode’, at the Maintainer’s Terminal, by
selecting the ‘Terminal’ application from the
‘DESKTOP’.
7.2.3 Set the GCP MAINS and REFERENCE Observe that the GCP FAULT LED is illuminated.
ON/ISOLATION switches to ON. Observe that the LEDs: AC FAIL, SYSRESET,
TEMP 1, AIRFLOW and DC LOW 1 on the SIG pec
(Card Carrier slot 7) are extinguished.
NOTE
The SIG SYSFAIL LED remains illuminated until
such time as the Applications Software is loaded
and the GCP achieves full operational state.
7.2.4 During the Remainder BIST, press any Observe that the front panel LEDs 0, 1, 2 and 3, on
Maintainer’s Terminal key. the Master and Slave SBC pec (Card Carrier slots
1 and 8) illuminate in a binary sequence while the
BIST tests are running.
(The colour of the LEDs can be ignored).
7.2.5 View the Maintainer’s Terminal screen. Observe that the GCP (30mm) BIST runs, rapidly
displaying the GCP (30mm) BIST list.
7.2.6 View the Maintainer’s Terminal screen. Observe that ‘PASSED’ is displayed as each test
completes. Observe that no error messages are
displayed.
Observe that LEDs 0, 1, 2 and 3 on the Master and
Slave SBC pec are extinguished. Observe that the
Start Up menu is displayed, thus:
START UP MENU
1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF)
Enter Selection 1 - 7:
7.2.7 Using the scroll bar on the Maintainer’s Observe that the GCP (30mm) BIST List, as
Terminal, review the displayed GCP (30mm) BIST defined in Annex I, is displayed.
list.
7.2.8 Using the scroll bar on the Maintainer’s Observe that the Start Up menu is displayed.
Terminal, display the Start Up menu.
(Continued)

HAT(E) Chap 2
Page 34 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


7.2.9 At the Maintainer’s Terminal, select option Observe that the Restricted System Management
7<CR> from the Start Up Menu. Facilities menu is displayed.
7.2.10 From the Restricted SMF menu, select Observe that the operator is prompted for SMF
option U<CR> (Full SMF menu). User name.
7.2.11 Enter SMF User name: Observe that the operator is prompted for
maintainer1<CR> password.
7.2.12 Enter Password: Observe that the password is accepted and the Full
password<CR> System Management Facilities (SMF) menu is
displayed.
NOTE
Observe that the Copy File (C), Install File (I) and
‘password’ is the default password only and
Install System (Z) options are available.
may be altered at a later date.
7.2.13 At the GCP SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the GCP
the Maintainer’s Terminal screen. BIST runs to completion without error.
During the Remainder BIST, press any Maintainer’s Observe that the Start Up menu is displayed.
Terminal key.
7.2.14 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 02<CR> NOTE
in response to the processor ID prompt.
While in Slave Processor Control mode each
displayed line is tagged with ‘<02>’ to indicate
that the Slave SBC is being accessed.
7.2.15 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
7.2.16 At the Maintainer’s Terminal, enter l<CR>, Observe that the Slave SBC BIST tests only are
(list). listed on the Maintainer’s Terminal, see Annex I.
7.2.17 At the GCP SIG pec, press ‘RESET’. View At the Maintainer’s Terminal, observe that the GCP
the Maintainer’s Terminal screen BIST runs, rapidly displaying the GCP BIST list.
NOTE
The Slave SBC is no longer being accessed
directly by the Maintainer’s Terminal.
7.2.18 During the Remainder BIST, press any Observe that BIST completes and that the Start Up
Maintainer’s Terminal key. menu is displayed.
7.2.19 At the Maintainer’s Terminal, select option Observe that the operating System and
1<CR> (Run Applications) from the Start Up Menu. Applications Software software are loaded in the
same manner as normal start-up.
Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
7.2.20 At the GCP SIG pec, press ‘RESET’ At the Maintainer’s Terminal, observe that the GCP
BIST runs (in Quick mode), rapidly displaying the
GCP BIST list.
On completion of the BIST run, observe that the
Operating System and Applications Software is
loaded.
7.2.21 View the Maintainer’s Terminal screen. Observe, at the Maintainer’s Terminal, that the
Restricted SMF menu is displayed.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 35
TP 3541 UK RESTRICTED

Test 7.3 METHOD


All pec pass Operator-controlled BIST in Quick and Extended Mode. Operator-controlled BIST is run
from the Start Up menu and Quick and Extended mode is selected.
NOTE
Running Extended BIST proves the Ethernet connection from the unit to the Transceiver and that the
Transceiver is connected to a correctly terminated Highway. Therefore, both Dual Redundant Highway
and Monitor Highway connections are proved.

PROCEDURE EXPECTED RESULTS


7.3.1 At the GCP SIG pec, press ‘RESET’. View Observe that BIST completes and that the Start Up
the Maintainer’s Terminal screen. menu is displayed.
During the Remainder BIST, press any Maintainer’s
Terminal key.
7.3.2 Type 3<CR> to select Operator-Controlled Observe that ‘bist>’ is displayed on the Terminal.
BIST.
7.3.3 Select all tests (a), one iteration (1), Quick Observe that the GCP Quick BIST tests run,
mode (q), continue on failure (c). displaying the GCP Operator-Controlled Quick
Type: a,1,q,c<CR>. BIST List.

7.3.4 Select all tests (a), through five iterations Observe that the GCP Quick BIST tests run
(5), Quick mode (q), continue on failure (c). through five iterations, displaying the GCP
Type: a,5,q,c<CR>. Operator-Controlled Quick BIST List.

7.3.5 Select all tests (a), one iteration (1), Observe that the GCP 30mm Extended BIST tests
Extended mode (e), continue on failure (c). run, displaying the GCP 30mm Operator-Controlled
Type: a,1,e,c<CR>. Extended BIST List.
NOTE
This test takes approximately 50 minutes to
complete.
7.3.6 Extended BIST is completed. Observe that ‘BIST run completed’ is displayed on
the terminal screen and the processor front panel
LEDs are all OFF except for PR.
7.3.7 Using the scroll bar on the Maintainer’s Observe that the GCP 30mm Operator-Controlled
Terminal, review the displayed GCP Extended BIST list, as defined in Annex P, is
Operator-Controlled Extended BIST list. displayed.
7.3.8 Set the GCP MAINS ON/ISOLATION
switch to ISOLATION.
Ensure also that the Reference voltage connector
(PLM) is disconnected.
7.3.9 At the GCP card carrier Slot 12, remove
MPV997A-21 (RTD 1) and remove link A11.
Replace the RTD 1.
(This induces a BIST non-fatal failure).
(Continued)

HAT(E) Chap 2
Page 36 UK RESTRICTED
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


7.3.10 Re-connect the Reference voltage
connector (PLM).
Set the GCP MAINS ON/ISOLATION switch to ON.
7.3.11 View the Maintainer’s Terminal screen. At the Maintainer’s Terminal, observe that the GCP
BIST runs, rapidly displaying the GCP BIST list.
Observe that BIST test 009 (MPV997A-21 (RTD 1))
reports a non-fatal failure due to the missing link.
7.3.12 During the Remainder BIST, press any Observe that the Master Start Up menu is then
Maintainer’s Terminal key. displayed.
7.3.13 At the Maintainer’s Terminal, select option Observe that the Slave Start Up menu is displayed.
5<CR> from the Start Up Menu and enter 01<CR> NOTE
(for PME ENET-1) in response to the processor ID
While in Slave Processor Control mode, each
prompt.
displayed line is tagged with ‘<01>’ to indicate
that the Slave PME ENET-1 is being accessed.
7.3.14 Enter <Ctrl>e to exit from Slave Processor Observe that the Master Start Up menu is then
control. displayed.
7.3.15 From the Start-up menu, select option Observe that ‘bist>’ is displayed on the
3<CR> (Operator-Controlled BIST). Maintainer’s Terminal.
7.3.16 Select and run BIST test 009 (MPV997A- Observe that the selected test is executed, as
21 (RTD 1)), from the GCP BIST, through five invoked, through only one iteration in Extended
iterations in Extended mode, with option to abort mode, and displays an error report for test ‘009’
test on error. and a status ‘40000000’, and followed by the
Type t,9,5,e,a<CR> to invoke test number ‘009’ message:
(from the BIST Remainder list). ‘BIST run aborted due to fatal failure’.
7.3.17 Select and run BIST test 009 (MPV997A- Observe that the selected test is executed, as
21 (RTD 1)), from the GCP BIST, through five invoked, through five iterations in Extended mode,
iterations in Extended mode, with option to and displays an error report for test ‘009’ and a
continue testing on error. status ‘40000000’, which indicates that the test has
At the ‘bist>’ prompt, type t,9,5,e,c<CR> to continued to run despite the error.
invoke test number ‘009’ (from the BIST
Remainder list).
7.3.18 Exit Operator-Controlled BIST. Observe that the Start Up menu is displayed on the
Type e<CR>. terminal screen.

7.3.18 Set the GCP MAINS ON/ISOLATION


switch to ISOLATION.
Ensure also that the Reference voltage connector
(PLM) is disconnected.
7.3.19 At the GCP card carrier slot 12, remove
MPV997A-21 (RTD 1) and restore link A11.
Replace the RTD 1.
7.3.20 Ensure that the Reference voltage
connector (PLM) is reconnected. Set the GCP
MAINS ON/ISOLATION switch to ON.
7.3.21 View the Maintainer’s Terminal screen. Observe, on the Maintainer’s Terminal, that the
GCP (30mm) Quick BIST tests run to completion
without error.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 37
TP 3541 UK RESTRICTED

TEST GROUP 8: WASP

Test Group 8 WASP


OBJECTIVE OF TEST
Check all WASP Switch Lamps illuminate. Check all Gun and Laser Enable Keys are unique.

Test 8.1 METHOD


Using the ‘Lamp Test’ facility, check all Switches illuminate. Check all Gun and Laser Enable Keys are
unique.

PROCEDURE EXPECTED RESULTS


8.1.1 Ensure that the VCS WASP
illumination supply is available.
8.1.2 Power up the 76mm GCP Check at the WASP: All 76mm Switch lamps illuminate.
8.1.23 Power up the 30mm Port GCP Check at the WASP: All 30mm Port Switch lamps
illuminate.
8.1.4 Power up the 30mm Starboard GCP Check at the WASP: All 30mm Starboard Switch lamps
illuminate.
8.1.5 Power up the EOTS EAU Check at the WASP: All EOTS Switch lamps illuminate.
8.1.6 At the WASP front panel: Press the Check at the WASP: All Switch lamps illuminate except
‘Test Lamps’ button. TEST LAMPS.
8.1.7 Insert all Gun and Laser Enable keys Prove that all keys are unique and cannot select any
in the correct key switch. other Enable switch.

HAT(E) Chap 2
Page 38 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

TEST GROUP 9: DATALINK Y

Test Group 9 DATALINK Y


OBJECTIVE OF TEST
Switch-On and Run-up confidence checks.
To demonstrate the Power On indicators and that all DATALINK Y System pec function correctly.
Power-up BIT runs from power-up and in REMOTE mode.
Operator initiated Short Loop Test is run.
Communications between Link Y EAU and Link Y Processor are confirmed.

Test 9.1 METHOD


Power Supply Inspection Checks.
Power, ACH and Switch-On confidence and BITE checks.
Power supplies are connected and the unit is powered up.
Power indicators, Power-up (Remote mode) and BIT tests.
Operator initiated Short Loop Test is run.
NOTE
Prior to commencing these tests, one console and the Link Y EAU have been STW and are to be
powered on in Operational mode (default configuration).

PROCEDURE EXPECTED RESULTS


9.1.1 Ensure the Mains and ACH power
distribution for the LINK Y is available.
Ensure the Remote Control Panel (RCP) power
distribution is available.
9.1.2 Ensure, at the Link Y Terminal, that the Observe on the LINK Y Terminal:
MAINS circuit breaker VL1 is set to MAINS (up), LED Mains AVAIL is illuminated.
the REMOTE/LOCAL switch on the BTS panel is in LED AC ON is illuminated.
the ‘Remote’ position, and select the ‘POWER ON’ (AC ON is Anti-Condensation Heaters ON)
switch to up. LED POWER ON is OFF.
The POWER ON LED is illuminated.
9.1.3 At the Link Y Switch Box, set the ON/OFF Observe on the LINK Y Terminal:
switch to ON. LED MAINS AVAIL is illuminated.
LED AC ON is extinguished.
LED POWER ON is illuminated.
Software starts loading (i.e., pec LEDs flash).
LED ‘FAIL’ is illuminated.
Observe on the RCP:
The POWER LED is illuminated.
9.1.4 When the software loading is completed, Observe on the LINK Y Terminal:
(approximately three minutes). LED FAIL is extinguished.
Observe on the RCP:
The Software Version menu is displayed on the
RCP display.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 39
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


9.1.5 On the RCP, press the ‘EXEC’ button and Observe that a ‘+’ is displayed in front of the
check that the Link Mode is in ‘STANDBY’. selected test.
On the Main menu, using the cursor buttons, select Observe, at the console CWCS Node Status tote:
‘LOOP TEST’. Link Y is ‘AB’ and ‘Nor’ in green with an
Press the ‘EXEC’ button. interface status of ‘O’ in green.
Observe, at the console Link Y Status tote:
Mode field is ‘Loop test’ in yellow.
9.1.6 Ensure that the cursor is positioned on the At the RCP: Observe that the ‘RESULT: BUSY’
‘START TEST’ test and press the ‘EXEC’ button changes to ‘RESULT: OK’ when the test has
twice to start the Loop Test. successfully completed.
The cursor is then positioned on ‘EXIT’. Whilst the test is running, observe, at the Console
CWCS Node Status tote:
Link Y is ‘AB’ and ‘Nor’ in green with an
interface status of ‘N’ in red.
Observe, in the Link Y Mk2 Status tote:
Mode field is ‘Loop test’ in yellow.
9.1.7 At the Link Y Switch Box, set the ON/OFF Observe on the LINK Y Terminal:
switch to OFF'. LED Mains AVAIL is illuminated.
LED AC ON is illuminated.
LED POWER ON is extinguished.
Observe on the RCP:
The POWER LED is extinguished.
(Continued)

HAT(E) Chap 2
Page 40 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

TEST GROUP 10: RTVDU

Test Group 10 RTVDU


OBJECTIVE OF TEST
Switch-On and Run-Up Confidence Checks – RTVDU.

Test 10.1 – RDDU 1 and 2 METHOD


Power Supply Inspection Checks.
Power, ACH and Switch-On confidence and BITE checks.
Power supplies are connected and the unit is powered up.
CWCS radar connections are inspected.
THESE TESTS ARE TO BE REPEATED FOR RDDU 2.

PROCEDURE EXPECTED RESULTS


10.1.1 Observe that the RDDU connectors PLW At the RDDU monitor panel, the ACH AVAIL LED
and SKAS are connected to the 115 V 60 Hz ACH illuminates green.
supply to the unit.
10.1.2 Observe that the RDDU connectors PLV At the RDDU monitor panel, the MAINS AVAIL LED
and SKAR are connected to the 115 V 60 Hz illuminates green.
MAINS supply to the unit.
10.1.3 Observe that the RDDU connector PLX is At the RDDU monitor panel, the REF AVAIL LED
connected to the 115 V 400 Hz REFERENCE illuminates green.
supply to the unit.
10.1.4 Connect the RTVDU serial monitor cable
to the Maintainer’s Terminal and the RDDU output
selector Test Port
10.1.5 At the Monitor Panel, switch the RDDU Observe, at the monitor panel, that the –12 V,
MAINS to ON. +12 V and +5 V LEDs are illuminated.
At the Maintainer’s Terminal, observe the following:
START UP BIT
FLASH ROM PASS
QUART PASS
RUNNING FULL BIT TEST
FLASH ROM PASS
SRAM PASS
REGS PASS
RTVDU OUTPUT SELECTOR n.n.n
(where n.n.n is the version number)
BOARD is RDDUn
(where n is 1 or 2 for the RDDU-under-test)
NOTE
This is followed by a report of default pattern.
10.1.6 Check the correct operation of the fan unit. Observe that, at the fan unit, the fans are
functioning correctly and that air is being drawn in
at the base of the unit and expelled at the top of the
unit.
10.1.7 View the CWCS radar connections at the Observe that there are connections between each
rear Termination Panel. Console and the RDDU(s), for radar and the RVG.

HAT(E) Chap 2
UK RESTRICTED Page 41
TP 3541 UK RESTRICTED

Test 10.2 TVDU1 and TVDU2 METHOD


Power Supply Inspection Checks.
Power, ACH and Switch-On confidence and BITE checks.
Power supplies are connected and the unit is powered up.
CWCS TV connections are inspected.
THESE TESTS ARE TO BE REPEATED FOR TVDU 2.

PROCEDURE EXPECTED RESULTS


10.2.1 Observe that the cable between RDDU At the TVDU monitor panel, the ACH AVAIL LED
connector SKAS and TVDU PLBS is connected, illuminates green.
connecting the 115 V 60 Hz ACH supply to the unit.
10.2.2 Observe that the cable between the RDDU At the TVDU monitor panel, the MAINS AVAIL LED
connector SKAR and TVDU PLBR is connected, illuminates green.
connecting the 115 V 60 Hz MAINS supply to the
unit.
10.2.3 Connect the RTVDU serial monitor cable
to the Maintainer’s Terminal and the TVDU output
selector Test Port
10.2.4 At the monitor panel, switch the TVDU Observe, at the Monitor Panel, that the –12 V,
MAINS to ON. +12 V and +5 V LEDs are illuminated.
At the Maintainer’s Terminal, observe the following:
START UP BIT
FLASH ROM PASS
QUART PASS
RUNNING FULL BIT TEST
FLASH ROM PASS
SRAM PASS
REGS PASS
RTVDU OUTPUT SELECTOR n.n.n
(where n.n.n is the version number)
BOARD is TVDUn
(where n is 1 or 2 for the TVDU-under-test)
NOTE
This is followed by a report of default pattern.
10.2.5 Check the correct operation of the fan unit. Observe that at the fan unit the fans are functioning
correctly and that air is being drawn in at the base
of the unit and expelled at the top of the unit.
10.2.6 View the TV connections at the rear Observe that there are connections between each
Termination Panel. Console and the TVDU(s), for the TV source.

HAT(E) Chap 2
Page 42 UK RESTRICTED
UK RESTRICTED TP 3541

TEST GROUP 11: RADAR VIDEO GENERATOR

Test Group 11 RVG


OBJECTIVE OF TEST
Switch-On and Run-Up Confidence Checks – RVG. To demonstrate the Power-on, run-up and correct
functioning of RVG components. Power-on components demonstrated are Power Indicators, Power-up
BIT and Operator initiated BIT.

Test 11.1 METHOD


Power Indicators and Miniature Circuit Breakers (MCB) tests.
Inspection of the RVG is carried out.

PROCEDURE EXPECTED RESULTS


11.1.1 Ensure that the ON/OFF switch of the
RVG is set to OFF.
11.1.2 Connect 115 V 60 Hz a.c. supplies to Observe that the Green RVG lamp is OFF.
connectors PL1 and PL2 Observe that the Green HEATER lamp is ON.
Observe that the Red POWER FAULT lamp is
OFF.
11.1.3 Set the ON/OFF switch of the RVG to ON. Observe that the Green RVG lamp is ON.
Observe that the Green HEATER lamp is OFF.
Observe that the Red POWER FAULT lamp is
OFF.
11.1.4 Open RVG door and press MCB2 down. Observe that MCB1 trips.
Observe that the Green RVG lamp is OFF.
Observe that the Green HEATER lamp is ON,
Observe that the Red POWER FAULT lamp is ON.
11.1.5 Reset MCB2, then MCB1 Observe that the Green RVG lamp is ON
Observe that the Green HEATER lamp is OFF,
Observe that the Red POWER FAULT lamp is
OFF.
11.1.6 Press MCB3 down. Observe that MCB1 trips.
Observe that the Green RVG lamp is OFF.
Observe that the Green HEATER lamp is ON.
Observe that the Red POWER FAULT lamp is ON.
11.1.7 Set the ON/OFF switch of the RVG to OFF Observe that the Green RVG lamp is OFF.
Observe that the Green HEATER lamp is ON.
Observe that the Red POWER FAULT lamp is
OFF.
11.1.8 Press MCB4 down. Observe that the Green RVG lamp is OFF.
Observe that the Green HEATER lamp is OFF,
Observe that the Red POWER FAULT lamp is ON.
(Continued)

HAT(E) Chap 2
UK RESTRICTED Page 43
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


11.1.9 Reset all MCBs, with MCB1 last. Observe that the Green RVG lamp is OFF.
Observe that the Green HEATER lamp is ON.
Observe that the Red POWER FAULT lamp is
OFF.
(Continued)

HAT(E) Chap 2
Page 44 UK RESTRICTED
UK RESTRICTED TP 3541

Test 11.2 METHOD


RVG Power-Up BIT and Operator Initiated Extended BIT

PROCEDURE EXPECTED RESULTS


11.2.1 Connect the Control Unit to the RVG at
SKT2.
11.2.2 Connect Control Unit to the 240 V 60 Hz
mains supply using the a.c. power lead and switch
to AC at rear of unit.
11.2.3 Set the ON/OFF switch of the RVG to ON. Observe that the Green RVG lamp is ON. Observe
that the Green heater lamp is OFF. Observe that
the Red Power Fault lamp is OFF.
11.2.4 Switch on the Control Unit. When the Observe, on the Control Unit, that the software is
BOPVRVG window is displayed on the Control loaded, and that the Power-Up BIT runs with a
Unit, press ALT and F and select ‘Boot RSS’ PASS displayed after each test.
(Radar Simulator Sub-system) from the menu. RSS Internal Memory/Configuration Test
Select ‘Ok’ on the Power-Up BIT selection page. RSS External Memory Test
STGB Status Register Test
STGB Interface Register Test
VIB BITE Register Test
RVG Board Interface Register Test
RVG Board VRAM Test
RVG Video Spoke Generation Test
11.2.5 Press ALT and A Confirm the BOPVRVG Issue and date.
Select Ok on completion.
11.2.6 Press ALT and F and select ‘Run BIT’ from Observe the Extended BIT runs and a PASS is
the menu. Select ‘Ok’ on the Operator Initiated displayed after each test.
Extended BIT Selection page. RSS Internal Memory/Configuration Test
RSS External Memory Test
STGB Status Register Test
STGB Interface Register Test
VIB BITE Register Test
RVG Board Interface Register Test
RVG Board VRAM Test
RVG Video Spoke Generation Test

HAT(E) Chap 2
UK RESTRICTED Page 45
TP 3541 UK RESTRICTED

TEST GROUP 12: GUN FOOTPUSH

Test Group 12 Gun Footpush


OBJECTIVE OF TEST
This test checks the correct operation of the Gun Footpush at Consoles WCC1, WCC2 and WCC3, for
the 76mm, 30mm Port and the 30mm Starboard GCPs.

Test 12.1 – 76mm Gun METHOD


The Gun Footpush(s) are observed to be fitted.
This test checks the correct operation of the Gun Footpush at Consoles WCC1, WCC2 and WCC3 and
MGD(B) for the 76mm gun.

PROCEDURE EXPECTED RESULTS


12.1.1 Check that a firing Footpush is located Observe that a firing Footpush is located next to
with each Weapon Control Console and the each Weapon Control Console and MGD(B)
MGD(B) Console. Console.
12.1.2 On the WASP panel, set the 76mm Gun to
WCC1. Ensure the Gun enable is set to ON.
12.1.3 Connect the Maintainer’s Terminal to SKN Observe that the GCP (76mm) BIST List, as
on the front of the Power Input Box of the 76mm defined in Annex H, is displayed.
GCP. Apply power to or reset the 76mm GCP.
12.1.4 Press the WCC1 Footpush, and keep it Observe that the BIST test 007 (Safety Function
pressed down, whilst resetting the 76mm GCP and (Set 1)) reported a fatal failure with a status
during the running of the BIST. ‘C0000001’ and the following error message:
‘Safety Function foot switch active detected’.
12.1.5 Release the WCC1 Footpush. Observe that the GCP (76mm) BIST List, as
On the WASP panel, set the 76mm Gun to WCC2. defined in Annex H, is displayed.
Ensure the Gun enable is set to ON and reset the
76mm GCP.
12.1.6 Press the WCC2 Footpush, and keep it Observe that the BIST test 007 (Safety Function
pressed down, whilst resetting the 76mm GCP and (Set 1)) reported a fatal failure with a status
during the running of the BIST. ‘C0000001’ and the following error message:
‘Safety Function foot switch active detected’.
12.1.7 Release the WCC2 Footpush. Observe that the GCP (76mm) BIST List, as
On the WASP panel, set the 76mm Gun to WCC3. defined in Annex H, is displayed.
Ensure the Gun enable is set to ON and reset the
76mm GCP.
12.1.8 Press WCC3 Footpush, and keep it pressed Observe that the BIST test 007 (Safety Function
down, whilst resetting the 76mm GCP and during (Set 1)) reported a fatal failure with a status
the running of the BIST. ‘C0000001’ and the following error message:
‘Safety Function foot switch active detected’.
12.1.9 Release the WCC3 Footpush. Observe that the GCP (76mm) BIST List, as
On the WASP panel, set the 76mm Gun to defined in Annex H, is displayed.
MGD(B). Ensure the Gun enable is set to ON and
reset the 76mm GCP.
(Continued)

HAT(E) Chap 2
Page 46 UK RESTRICTED
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


12.1.10 Press the MGD(B) Footpush, and keep it Observe that the BIST test 007 (Safety Function)
pressed down, whilst resetting the 76mm GCP and reported a fatal failure with a status ‘C0000001’ and
during the running of the BIST. the following error message:
‘Safety Function foot switch active detected’.
12.1.11 Release the MGD(B) Footpush.
(Continued)

HAT(E) Chap 2
UK RESTRICTED Page 47
TP 3541 UK RESTRICTED

Test 12.2 – 30mm Stbd Gun METHOD


This test checks the correct operation of the Gun Footpush at Consoles WCC1, WCC2 and WCC3 and
MGD(B) for the 30mm Stbd gun.

PROCEDURE EXPECTED RESULTS


12.2.1 On the WASP panel, set the 30mm Gun
Stbd to WCC1. Ensure the Gun enable is set to
ON.
12.2.2 Connect the Maintainer’s Terminal to SKN Observe that the GCP (30mm) BIST List, as
on the front of the Power Input Box of the 30mm defined in Annex I, is displayed.
Gun Stbd GCP. Apply power to or reset the 30mm
Gun Stbd GCP.
12.2.3 Press the WCC1 Footpush, and keep it Observe that the BIST test 007 (Safety Function)
pressed down, whilst resetting the 30mm Gun Stbd reported a fatal failure with a status ‘C0000001’ and
GCP and during the running of the BIST. the following error message:
‘Safety Function foot switch active detected’.
12.2.4 Release the WCC1 Footpush. Observe that the GCP (30mm) BIST List, as
On the WASP panel, set the 30mm Gun Stbd to defined in Annex I, is displayed.
WCC2. Ensure the Gun enable is set to ON and
reset the 30mm Gun Stbd GCP.
12.2.5 Press the WCC2 Footpush, and keep it Observe that the BIST test 007 (Safety Function)
pressed down, whilst resetting the 30mm Gun Stbd reported a fatal failure with a status ‘C0000001’ and
GCP and during the running of the BIST. the following error message:
‘Safety Function foot switch active detected’.
12.2.6 Release the WCC2 Footpush. Observe that the GCP (30mm) BIST List, as
On the WASP panel set the 30mm Gun Stbd to defined in Annex I, is displayed.
WCC3. Ensure the Gun enable is set to ON and
reset the 30mm Gun Stbd GCP.
12.2.7 Press the WCC3 Footpush, and keep it Observe that the BIST test 007 (Safety Function)
pressed down, whilst resetting the 30mm Gun Stbd reported a fatal failure with a status ‘C0000001’ and
GCP and during the running of the BIST. the following error message:
‘Safety Function foot switch active detected’.
12.2.8 Release the WCC3 Footpush. Observe that the GCP (30mm) BIST List, as
On the WASP panel set the 30mm Gun Stbd to defined in Annex I, is displayed.
MGD(B). Ensure the Gun enable is set to ON and
reset the 30mm Gun Stbd GCP.
12.2.9 Press the MGD(B) Footpush, and keep it Observe that the BIST test 007 (Safety Function)
pressed down, whilst resetting the 30mm Gun Stbd reported a fatal failure with a status ‘C0000001’ and
GCP and during the running of the BIST. the following error message:
‘Safety Function foot switch active detected’.
12.2.10 Release the MGD(B) Footpush.

HAT(E) Chap 2
Page 48 UK RESTRICTED
UK RESTRICTED TP 3541

Test 12.3 – 30mm GUN Port METHOD


This test checks the correct operation of the Gun Footpush at consoles WCC1, WCC2, WCC3 and
MGD(B) for the 30mm Port gun.

PROCEDURE EXPECTED RESULTS


12.3.1 On the WASP panel, set the 30mm Gun
Port to WCC1. Ensure the Gun enable is set to ON.
12.3.2 Connect the Maintainer’s Terminal to SKN Observe that the GCP (30mm) BIST List, as
on the front of the Power Input Box of the 30mm defined in Annex I, is displayed.
Gun Port GCP. Apply power to or reset the 30mm
Gun Port GCP.
12.3.3 Press the WCC1 Footpush, and keep it Observe that the BIST test 007 (Safety Function)
pressed down, whilst resetting the 30mm Gun Port reported a fatal failure with a status ‘C0000001’ and
GCP and during the running of the BIST. the following error message:
‘Safety Function foot switch active detected’.
12.3.4 Release the WCC1 Footpush. Observe that the GCP (30mm) BIST List, as
On the WASP panel, set the 30mm Gun Port to defined in Annex I, is displayed.
WCC2. Ensure the Gun Enable is set to ON and
reset the 30mm Gun Port GCP.
12.3.5 Press the WCC2 Footpush, and keep it Observe that the BIST test 007 (Safety Function)
pressed down, whilst resetting the 30mm Gun Port reported a fatal failure with a status ‘C0000001’ and
GCP and during the running of the BIST. the following error message:
‘Safety Function foot switch active detected’.
12.3.6 Release the WCC2 footpush. Observe that the GCP (30mm) BIST List, as
On the WASP panel, set the 30mm Gun Port to defined in Annex I, is displayed.
WCC3. Ensure the Gun enable is set to ON and
reset the 30mm Gun Port GCP.
12.3.7 Press the WCC3 Footpush, and keep it Observe that the BIST test 007 (Safety Function)
pressed down, whilst resetting the 30mm Gun Port reported a fatal failure with a status ‘C0000001’ and
GCP and during the running of the BIST. the following error message:
‘Safety Function foot switch active detected’.
12.3.8 Release the WCC3 Footpush. Observe that the GCP (30mm) BIST List, as
On the WASP panel, set the 30mm Gun Port to defined in Annex I, is displayed.
MGD(B). Ensure the Gun Enable is set to ON and
reset the 30mm Gun Port GCP.
12.3.9 Press the MGD(B) Footpush, and keep it Observe that the BIST test 007 (Safety Function)
pressed down, whilst resetting the 30mm Gun Port reported a fatal failure with a status ‘C0000001’ and
GCP and during the running of the BIST. the following error message:
‘Safety Function foot switch active detected’.
12.3.10 Release the MGD(B) Footpush.

HAT(E) Chap 2
UK RESTRICTED Page 49
TP 3541 UK RESTRICTED

TEST GROUP 13: SYSTEM

Test Group 13 SYSTEM


OBJECTIVE OF TEST
This group contains the demonstration of ‘general’ requirements not covered in any other test group. It
also contains a description of the tests used to demonstrate that the individual elements of the CWCS
hardware are functioning correctly when installed onboard ship and interconnected via ships cabling.

13.0 PREREQUISITES METHOD


These tests confirm that all CWCS ‘internal’ interconnections are in place prior to commencing the
System Tests.

PROCEDURE EXPECTED RESULTS


13.0.1 At the rear of each Console, view the Confirm, at each Console, that all cables are
Termination Panel. connected with the exception of the following:
SKT (1802 Fwd Joystick Control)
SKU (1802 Aft Joystick Control)
SKG (EOTS Joystick Control)
PLM (EOTS ‘SYNC)
NOTES
(1) In addition to the above cables, the
following is only connected to PWO and TPS:
SKK, SKN, SKP, SKQ and SKR.
(Bridge Display Connections)
(2) In addition to the above cables, no cable is
connected to PLE of the following consoles:
PWO, TPS/TDL, APC and SPC as these
have no Laser Fire capability.
13.0.2 At the top of each SAP EAU, view the Confirm, at each SAP EAU, that all cables are
Termination Panel. connected with the exception of the following:
PLG (SAP/1802 RS422 Control interface)
13.0.3 At the top of the EOTS EAU, view the Confirm, at the EOTS EAU, that all cables are
Termination Panel. connected with the exception of the following:
PLH (Checkfire)
PLG (EOTS RS-422/Discrete Control interface)
13.0.4 At the top of the 76mm GCP, view the Confirm, at the 76mm GCP, that all cables are
Termination Panel. connected with the exception of the following:
SKH (SDDS Synchro Data)
SKP (SDDS ‘Validity’ signals)
PLR (EOTS Tracking Data)
PLT (1802 Fwd Tracking Data)
PLU (1802 Aft Tracking Data)
PLV (Checkfire)
Cable 1105 (GLL) TPB1/2/3/4/5 (Gun Synchro
Demands/Tellbacks)
Cable 1106 (GLC) TPB1/2/3/4/5 (Gun Control
Demands and Tellbacks)
(Continued)

HAT(E) Chap 2
Page 50 UK RESTRICTED
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


13.0.5 At the top of both 30mm GCPs, view the Confirm, at both 30mm GCPs, that all cables are
Termination Panel. connected with the exception of the following:
SKH (SDDS Synchro Data)
SKP (SDDS ‘Validity’ signals)
PLR (EOTS Tracking Data)
PLT (1802 Fwd Tracking Data)
PLU (1802 Aft Tracking Data)
PLV (Checkfire)
Cable 1095 (GLC) TPB1/2/3/4/5
(Gun Synchro Demands/Tellbacks)
Cable 1098 (GLJ) TPB1/2/3/4/5
(GCP Discrete O/P Controls)
Cable 1097 (GLK) TPB1/2/3/4/5
(Gun Discrete Tellbacks)
Cable 1096 (GLL) TPB1/2/3/4/5 (Fire
Demands)
13.0.6 At the rear of RTVDU1, view the Confirm, at RTVDU1, that all cables are connected
Termination Panel. with the exception of the following:
PLC (Nav Radar Data)
SKA (Nav Radar Video)
SKB (Nav Radar Sync.)
SKD (Nav Radar Mode)
SKE (1802 Fwd Turning Data)
SKF (1802 Fwd Video)
SKG (1802 Fwd Sync.)
SKAT (Output to RVR – Nav Radar Video)
SKAU (Output to RVR – Nav Radar Sync.)
PLAV (Output to RVR – Nav Radar Data)
SKAX (Unused Output)
13.0.7 At the rear of RTVDU2, view the Confirm, at RTVDU2, that all cables are connected
Termination Panel. with the exception of the following:
SKE (1802 Aft Turning Data)
SKF (1802 Aft Video)
SKG (1802 Aft Sync.)
PLH (AWS-9 Composite Video)
SKAT (Unused Output)
SKAU (Unused Output)
PLAV (Unused Output)
SKAX (Output to RVR – AWS-9 Composite
Video)
13.0.8 View the RVG and RVG Junction Box: Confirm, at RVG and RVG Junction Box, that all
All connections are to be made to the RVG and cables are connected.
RVG Junction Box.
13.0.9 View the WASP and Footpushes. Confirm, at WASP and Footpushes, that all cables
are connected.
(Continued)

HAT(E) Chap 2
UK RESTRICTED Page 51
TP 3541 UK RESTRICTED

Test 13.1 METHOD


RTVDU TV Test Picture generation and distribution. This test section demonstrates that the RTVDU
internally generated test picture can be displayed at each Console for both TVDU1 and TVDU2. It also
uses these test pictures to demonstrate that the two inputs to the Bridge Display are correct.
NOTE
Prior to commencing this test section, Test Groups 1 (Console) and 10 (RTVDU) are to have
been conducted.

PROCEDURE EXPECTED RESULTS


13.1.1 At each CWCS Console except TPS, Observe, at each Console except TPS, that the
ensure that SES test 22, ‘External TV input’ test is External TV Test picture is displayed as described
selected using Annex B. in Annex Q
13.1.2 At RTVDU1, ensure that the TVDU is Observe that the MAINS AVAILABLE LED is
powered OFF. illuminated.
NOTE
For the purpose of this test, the RDDU status is
irrelevant.
13.1.3 At RTVDU1 power-up the TVDU. Observe, at each Console (except TPS) in the TV1
NOTE test window, that the TVDU test picture is correctly
displayed.
On Power-Up the TVDU automatically selects
channel 7, the test picture. Observe, on the Bridge Display (INP 1) in the TV1
Ensure that INP 1 is selected at the Bridge test window that the TVDU test picture is correctly
Display. displayed.

13.1.4 Select INP 2 at the Bridge Display Observe, on the Bridge Display that the Display is
blank.
13.1.5 At TPS Console, ensure that SES test 22, Observe, at TPS Console in the TV1 test window,
‘External TV input’ test is selected using Annex B. that the TVDU test picture is correctly displayed.
Observe, on the Bridge Display (INP 2) in the TV1
test window that the TVDU test picture is correctly
displayed.
13.1.6 At RTVDU2, ensure that the TVDU is Observe that the MAINS AVAILABLE LED is
powered OFF. illuminated.
13.1.7 At RTVDU2, power-up the TVDU. Observe, at all Consoles, in the TV2 test window
NOTE that the TVDU test picture is correctly displayed.
On Power-Up the TVDU automatically selects Observe, on the Bridge Display (INP 2), in the TV2
channel 7, the test picture. test window that the TVDU test picture is correctly
displayed.
13.1.8 At RTVDU1 and RTVDU2, power OFF the
TVDUs.

HAT(E) Chap 2
Page 52 UK RESTRICTED
UK RESTRICTED TP 3541

Test 13.2 METHOD


Simulated video control and distribution. This test section uses CWCS Application software, running in
CTT mode of operation, to verify the hardware connectivity between the RVG, RTVDUs, Consoles and
NRTE associated with the distribution of simulated Radar video. The test initially verifies that Console
1 (PWO), when configured as ‘Game Controller’, is capable of controlling the RVG video simulation.
Distribution to, and selection of, this video, to Consoles 2 to 8, via the RTVDU system is also demon-
strated.
Subsequently Consoles 2 to 8 are configured as ‘Game Controller’ to demonstrate their ability to
control the RVG and Console 1 is used to verify that its video inputs and selection lines are correct.
NOTE
Prior to commencing this test section, Test Groups 1 (Console), 3 (Sync EAU), 5 (NRTE),
10 (RTVDU) and 11 (RVG) must have been conducted.

PROCEDURE EXPECTED RESULTS


13.2.1 At the RVG, ensure that the Control Unit/ Ensure that the RVG runs up and that it indicates
Expansion Chassis is connected to the RVG ‘Available’ at the Control Unit.
cabinet and power-up the Chassis/Control Unit and
the RVG cabinet.
At the RVG Cabinet, ensure that Console 1 is
selected.
13.2.2 At RTVDU1 and RTVDU2, ensure that the
RDDUs and TVDUs are powered down
13.2.3 At all consoles, using Annex B ensure that Observe that the status response is received from
the console is powered up with SES test 38, each of the RTVDUs, RDDUs and TVDUs
‘RTVDU Status and Video Selection Test’ selected. indicating a ‘PASS’.
Press <CR> for the remaining prompts.
13.2.4 Power down all consoles.
13.2.5 At Console 1 (PWO), power up the Observe that the console powers up to the
console and ensure that, when it powers up, ‘Scen Scenario Execution mode.
Exec’ state is selected at the ELP. At the Access
Privilege Level menu, select ‘Game Contrl’ and
enter the password
13.2.6 Using the display Layout menu, select Observe, at the PWO Console CWCS Node Status
display layout of ‘GAME CTRL’. tote:
Power up the consoles 2 to 8, the NRTE and the PWO Console Operational state is ‘Exc’ (in
AWS-9 EAU and ensure that they power up into the amber).
CTT mode of operation. Consoles 2 to 8, Operational state is ‘Trn’ (in
amber).
NRTE and AWS-9 EAU, Operational state is
‘Sim’ in amber.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 53
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


13.2.7 At the Console DAT Drive, insert the Observe that the tape loads and that, in the MTU
Scenario test tape, part No: ‘380/FU/35075/000’ Status tote, the file ‘FATGSIM’ is indicated.
At the ELP, select the Scenario Execution menu, Observe that, when started, the scenario vehicles
select the ‘Load’ button and enter the filename are displayed on the LPD.
“FATGSIM” followed by ‘Start’.
NOTES
(1) The file FATGSIM contains vehicles for
both AWS-9 and Nav Radar.
(2) Dependant upon the time taken to
complete the remainder of this test section, it
may be necessary to re-start the scenario.
13.2.8 At the Console 1 (PWO), using the Sim
AWS-9 menu, select ‘AWS-9 on’.
At the IFF Inhibit Sector Control menu, select
‘Silnce off’.
At the IFF Scan Set 1 menu, select ’Primry Mode
1’, Second None’, ‘Tertry None’.
At the IFF Scan Set 2 menu, select ‘Primry None’,
Second None’ ‘Tertry None’.
Using the Super Mode menu, select ‘Set 1 SM Off’
and ‘Confrm’.
13.2.9 At all consoles, press the ‘RAD VID’ SFK Observe, at each console, that simulated AWS-9
once. Processed Log video returns and Ship’ Head
At each console, using the Radar Source menu, Marker video are displayed:
select ‘Surv’. Ensure that ‘Norm’ and ‘SHM are Two video returns at approx.270 ° 100 nm
selected for display. 315 ° 86 nm

13.2.10 At each console, using the Radar Source Observe, at each console, that simulated AWS-9
menu, select ‘MTI’. MTI video returns are displayed:
One video return at approx. 130 ° 7 nm visible
for 30 s between 130–160 s and 180–205 s.
13.2.11 At each console, using the Radar Source Observe, at each console, that simulated AWS-9
menu, select ‘Norm’ and ‘IFF’ Processed Log video returns and associated IFF
returns are displayed. (Eyebrow 270 ° 100 nm).
13.2.12 At each console, using the Radar Source Observe at each console, simulated Navigation
menu, select ‘Nav’ and ‘SHM’. Log video returns and Ship’s Head Marker video
are displayed.
13.2.13 At any console, ensure that a Point Track Observe in the console Point Track Sitrep tote:
Sitrep tote is displayed then, place the RBM over Source field is ‘Nav’.
any displayed Navigation radar video track and
Two video returns at 186 ° 9 nm and
press the ‘AUTO SURF’ SFK once. 255 ° 7.5 nm
Place the RBM over the track and select it using then another at 136 ° 14 nm
the Hook button. then another at 102 ° 7.8 nm (120 s)
13.2.14 At the Console 1 (PWO), at the Scenario
menu, select ‘Stop’.
Eject the DAT tape from the drive and power down
the PWO console and all other consoles
(Continued)

HAT(E) Chap 2
Page 54 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


13.2.15 At the RVG cabinet, ensure that console 2 At the RVG Control Unit Control menu, ensure that
is selected. the RVG indicates ‘Playing’.
At Console 2 (TPS), power up the console. When it
powers up, select ‘Scen Exec’ state at the ELP.
At the console DAT Drive, insert the Scenario Test
tape part No. 380/FU/35075/000.
At the ELP, select the Scenario Execution menu,
select the ‘Load’ button and enter the filename
“FATGSIMS” followed by ‘Start’.
13.2.16 At the Console 2 (TPS), at the Scenario
Execution, menu, select ‘Stop’.
Eject the DAT tape from the drive and power down
the console.
13.2.17 Repeat the above two test steps for
Consoles 3 to 8.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 55
TP 3541 UK RESTRICTED

Test 13.3 METHOD


WASP Switching and Selection. The purpose of this test section is to confirm, using the GCP and EOTS
EAU SES tests that the control signals from the WASP are correct. The routing of the Footpush pressed
signals to the various GCPs, via the WASP, is also confirmed. The routing of the EOTS Laser fire signal
from Consoles, via the WASP, is also confirmed.
NOTE
Prior to commencing this test section , Test Groups 1 (Console), 4 (EOTS EAU), 6 (76mm GCP),
7 (30mm GCP), 8 (WASP) and 12 (Footpush) must have been conducted.

PROCEDURE EXPECTED RESULTS


13.3.1 Connect the Maintainer’s Terminal to the Observe that the Start Up menu is displayed, thus:
‘SKN’ connection on the 76mm GCP PIB. Power
START UP MENU
up the GCP. 1 ...........Run Applications
During Remainder BIST, select <CR> and, from the 2 ...........Run System Exerciser Software (SES)
ensuing Start Up menu, select Option 6<CR> 3 ...........Operator Controlled Built In Self Test (BIST)
(Configuration). 4 ...........Run Debug Monitor
5 ...........Slave Processor Control
At the prompt ‘Is manual configuration required? [Y
6 ...........Configuration
or N]’, enter y<CR> for the Manual Configuration 7 ...........Run System Management Facilities (SMF)
menu to be displayed.
Enter Selection 1 - 7:
Select option p<CR> (SES filename) and enter
/fmd0/tdq.scr<CR>.
Select x<CR> to exit the Configuration menu.
NOTE
Enter n<CR> when prompted to stop the Real
Time Clock.
13.3.2 From the Start Up menu, select option Observe that the Maintainer’s Terminal screen
2<CR> (Run SES) displays the start of the SES tests.
13.3.3 Using Annex B, enter 1<CR> when Observe that the following test is selected and run:
prompted for test numbers ‘001 WASP Interconnect Test’
13.3.4 When the test is completed, view the Observe that the following table is displayed:
Terminal screen.
SES end of pass time date
Pass number....................... 1
Passes required.................. 1
Iterations required............... 1
Errors this pass ................... 0 * (1)
Total Error count ................. 0 * (1)
**As Checkfire is not connected, an error appears.
(Continued)

HAT(E) Chap 2
Page 56 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


13.3.5 Reset the 76mm GCP.
During Remainder BIST, select <CR> and, from the
ensuing Start Up menu, select Option 6<CR>
(Configuration).
At the prompt ‘Is manual configuration required? [Y
or N]’, enter y<CR> for the Manual Configuration
menu to be displayed.
Select option p<CR> (SES filename) and enter
/fmd0/tdl.scr<CR>.
Select x<CR> to exit the Configuration menu.
NOTE
Enter n<CR> when prompted to stop the Real
Time Clock.
13.3.6 Power down the 76mm GCP.
13.3.7 Connect the Maintainer’s Terminal to the Observe that the Start Up menu is displayed, thus:
‘SKN’ connection on the 30mm Stbd GCP PIB.
START UP MENU
Power up the 30mm Stbd GCP 1 ...........Run Applications
During Remainder BIST, select <CR> and, from the 2 ...........Run System Exerciser Software (SES)
ensuing Start Up menu, select Option 6<CR> 3 ...........Operator Controlled Built In Self Test (BIST)
(Configuration). 4 ...........Run Debug Monitor
5 ...........Slave Processor Control
At the prompt ‘Is manual configuration required? [Y
6 ...........Configuration
or N]’, enter y<CR> for the Manual Configuration 7 ...........Run System Management Facilities (SMF)
menu to be displayed.
Enter Selection 1 - 7:
Select option p<CR> (SES filename) and enter
/fmd0/tdq.scr<CR>. Select x<CR> to exit the
configuration menu.
NOTE
Enter n<CR> when prompted to stop the Real
Time Clock.
13.3.8 From the Start Up menu, select option Observe that the Maintainer’s Terminal screen
2<CR> (Run SES) displays the start of the SES tests.
13.3.9 Using Annex B, enter 1<CR> when Observe that the following test is selected and run:
prompted for the test number. ‘001 WASP Interconnect Test’
13.3.10 When the test is completed, view the Observe that the following table is displayed:
terminal screen.
SES end of pass time date
Pass number....................... 1
Passes required.................. 1
Iterations required............... 1
Errors this pass ................... 0 * (1)
Total Error count ................. 0 * (1)
*As Checkfire is not connected, an error appears.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 57
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


13.3.11 Reset the 30mm Stbd GCP.
During Remainder BIST, select <CR> and, from the
ensuing Start Up men, select Option 6<CR>
(Configuration).
At the prompt ‘Is manual configuration required? [Y
or N]’, enter y<CR> for the Manual Configuration
menu to be displayed.
Select option p<CR> (SES filename) and enter
/fmd0/tdl.scr<CR>.
Select x<CR> to exit the Configuration menu.
NOTE
Enter n<CR> when prompted to stop the Real
Time Clock.
13.3.12 Power down the 30mm Stbd GCP.
13.3.13 Connect the Maintainer’s Terminal to the Observe that the Start Up menu is displayed, thus:
‘SKN’ connection on the 30mm Port GCP PIB. START UP MENU
Power up the 30mm Port GCP. 1 ...........Run Applications
During Remainder BIST, select <CR> and, from the 2 ...........Run System Exerciser Software (SES)
ensuing Start Up menu, select Option 6<CR> 3 ...........Operator Controlled Built In Self Test (BIST)
(Configuration). 4 ...........Run Debug Monitor
5 ...........Slave Processor Control
At the prompt ‘Is manual configuration required? [Y 6 ...........Configuration
or N]’, enter y<CR> for the Manual Configuration 7 ...........Run System Management Facilities (SMF)
menu to be displayed.
Enter Selection 1 - 7:
Select option p<CR> (SES filename) and enter
/fmd0/tdq.scr<CR>.
Select x<CR> to exit the Configuration menu.
NOTE
Enter n<CR> when prompted to stop the Real
Time Clock.
13.3.14 From the Start Up menu, select option Observe that the Maintainer’s Terminal screen
2<CR> (Run SES) displays the start of the SES tests.
13.3.15 Using Annex B, enter 1<CR> when Observe that the following test is selected and run:
prompted for test numbers ‘001 WASP Interconnect Test’
13.3.16 When the test is completed, view the Observe that the following table is displayed:
Terminal screen.
SES end of pass time date
Pass number....................... 1
Passes required.................. 1
Iterations required............... 1
Errors this pass ................... 0 * (1)
Total Error count ................. 0 * (1)
*As Checkfire is not connected, an error appears.
(Continued)

HAT(E) Chap 2
Page 58 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PROCEDURE EXPECTED RESULTS


13.3.17 Reset the 30mm Port GCP.
During Remainder BIST, select <CR> and, from the
ensuing Start Up menu, select option 6<CR>
(Configuration).
At the prompt ‘Is manual configuration required? [Y
or N]’, enter y<CR> for the Manual Configuration
menu to be displayed.
Select option p<CR> (SES filename) and enter
/fmd0/tdl.scr<CR>.
Select x<CR> to exit the Configuration menu.
NOTE
Enter n<CR> when prompted to stop the Real
Time Clock.
13.3.18 Power down the 30mm Port GCP.
13.3.19 Using Annex B at the MGD(B), WCC1,
WCC2 and WCC3 Consoles, ensure that the
Consoles are powered-up with SES test 35, ‘Laser
Fire enable test’ selected.
13.3.20 At the EOTS EAU, connect a Maintainer’s Observe that the Start Up menu is displayed, thus:
Terminal to the ‘MASTER’ socket on the top front
START UP MENU
panel of the EOTS EAU and power up the EAU. 1 ...........Run Applications
During Remainder BIST, select <CR> and, from the 2 ...........Run System Exerciser Software (SES)
ensuing Start Up menu, select Option 6<CR> 3 ...........Operator Controlled Built In Self Test (BIST)
(Configuration). 4 ...........Run Debug Monitor
5 ...........Slave Processor Control
At the prompt ‘Is manual configuration required? [Y
6 ...........Configuration
or N]’, enter y<CR> for the Manual Configuration 7 ...........Run System Management Facilities (SMF)
menu to be displayed.
Enter Selection 1 - 7:
Select option p<CR> (SES filename) and enter
/fmd0/tdq.scr<CR>.
Select x<CR> to exit the Configuration menu.
NOTE
Enter n<CR> when prompted to stop the Real
Time Clock.
13.3.21 From the Start Up menu, select option Observe that the Maintainer’s Terminal screen
2<CR> (Run SES) displays the start of the SES tests.
13.3.22 Using Annex B, enter 1<CR> when Observe that the following test is selected and run:
prompted for the test number. ‘001 WASP Interconnect Test’
13.3.23 When the test is completed, view the Observe that the following table is displayed:
Terminal screen.
SES end of pass time date
Pass number....................... 1
Passes required.................. 1
Iterations required............... 1
Errors this pass ................... 0 * (1)
Total Error count ................. 0 * (1)
*As Checkfire is not connected, an error appears.
(Continued)

HAT(E) Chap 2
Oct 03 (Amdt 1) UK RESTRICTED Page 59
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


13.3.24 At the MGD(B), WCC1, WCC2 and WCC3
Consoles, complete test 35.
NOTE
The responses can be ignored in this instance.
13.3.25 Reset the EOTS EAU.
During Remainder BIST, select <CR> and, from the
ensuing Start Up menu, select Option 6<CR>
(Configuration).
At the prompt ‘Is manual configuration required? [Y
or N]’, enter y<CR> for the Manual Configuration
menu to be displayed.
Select option p<CR> (SES filename) and enter
/fmd0/tar3.scr<CR>.
Select x<CR> to exit the Configuration menu.
NOTE
Enter n<CR> when prompted to stop the Real
Time Clock.
13.3.26 Power down the EOTS EAU.
(Continued)

HAT(E) Chap 2
Page 60 UK RESTRICTED
UK RESTRICTED TP 3541

Test 13.4 METHOD


WASP SAP Node Active Selection switch.

PROCEDURE EXPECTED RESULTS


13.4.1 At the WASP, ensure that SAP ‘A’ is
selected. Connect the Maintainer’s Terminal to the
‘MASTER’ connection on the SAP ‘A’ EAU.
13.4.2 Switch on the SAP ‘A’ EAU. Observe that the LEDs: AC FAIL, SYSRESET,
TEMP 1, AIRFLOW and DC LOW 1 on the SIG pec
(Card Carrier slot 7) are extinguished.
NOTE
The SIG SYSFAIL LED remains illuminated until
such time as the Applications Software is loaded
and the EAU achieves full operational state).
13.4.3 During the Remainder BIST, press any Observe that the front panel LEDs 0, 1 and 2, on
Maintainer’s Terminal key. the Master SBC pec (Card Carrier slot 1) illuminate
in a binary sequence while the BIST tests are
running.
(The colours can be ignored)
13.4.4 View the Maintainer’s Terminal screen. Observe that the SAP ‘A’ EAU/011 BIST runs,
rapidly displaying the SAP ‘A’ EAU/011 BIST list
Observe that BIST completes.
Observe that LEDs 0, 1, 2 and 3 on the Master
SBC pec are extinguished.
Observe that the Start Up menu is displayed, thus:
START UP MENU
1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF)
Enter Selection 1 - 7:
13.4.5 From the Start Up menu, select option Observe that the Maintainer’s Terminal screen
2<CR> (Run SES) displays the start of the SES tests.
13.4.6 Using Annex B, enter 6<CR> when Observe that the test:
prompted for test numbers. ‘006 SIG Node Active Sensor Test’ runs and
passes with no error messages.
13.4.7 When test is completed, view the terminal Observe that the following table is displayed:
screen.
SES end of pass time date
Pass number....................... 1
Passes required.................. 1
Iterations required............... 1
Errors this pass ................... 0
Total Error count ................. 0
(Continued)

HAT(E) Chap 2
UK RESTRICTED Page 61
TP 3541 UK RESTRICTED

PROCEDURE EXPECTED RESULTS


13.4.8 Type: <Ctrl>C. Observe, on the terminal screen, that the system
returns to the start of the SES tests.
13.4.9 Switch OFF SAP ‘A’ EAU.
At the WASP, ensure that SAP ‘F’ is selected.
Connect the Maintainer’s Terminal to the
‘MASTER’ connection on the SAP ‘F’ EAU.
13.4.10 Switch on the SAP ‘F’ EAU. Observe that the LEDs: AC FAIL, SYSRESET,
TEMP 1, AIRFLOW and DC LOW 1 on the SIG pec
(Card Carrier slot 7) are extinguished.
NOTE
The SYSFAIL LED remains illuminated until
such time as the Applications Software is loaded
and the EAU achieves full operational state).
13.4.11 During the Remainder BIST, press any Observe that the front panel LEDs 0, 1 and 2, on
Maintainer’s Terminal key. the Master SBC pec (Card Carrier slot 1) illuminate
in a binary sequence while the BIST tests are
running.
(The colours can be ignored)
13.4.12 View the Maintainer’s Terminal screen. Observe that the SAP ‘F’ EAU/011 BIST runs,
rapidly displaying the SAP ‘F’ EAU/011 BIST list.
Observe that BIST completes.
Observe that LEDs 0, 1, 2 and 3 on the Master
SBC pec are extinguished.
Observe that the Start Up menu is displayed, thus:
START UP MENU
1 ...........Run Applications
2 ...........Run System Exerciser Software (SES)
3 ...........Operator Controlled Built In Self Test (BIST)
4 ...........Run Debug Monitor
5 ...........Slave Processor Control
6 ...........Configuration
7 ...........Run System Management Facilities (SMF)
Enter Selection 1 - 7:
13.4.13 From the Start Up menu, select option Observe that the Maintainer’s Terminal screen
2<CR> (Run SES) displays the start of the SES tests.
13.4.14 Using Annex B, enter 6<CR> when Observe that the tests:
prompted for test numbers. ‘006 SIG Node Active Sensor Test’ runs and
passes with no error messages.
13.4.15 When test is completed, view the Terminal Observe that the following table is displayed:
screen.
SES end of pass time date
Pass number....................... 1
Passes required.................. 1
Iterations required............... 1
Errors this pass ................... 0
Total Error count ................. 0
13.4.16 Type: <Ctrl>C. Observe, on the terminal screen, that the system
Switch OFF SAP ‘F’. returns to the start of the SES tests.
(Continued)

HAT(E) Chap 2
Page 62 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

HAT(E) ANNEX A

TEST RECORDS

CONTENTS

Para

1 Introduction

Record Page

1 HAT(E) results record for the Brunei OPV CWCS – Console . . . . . . . . . . . . . . . . . . 2


2 HAT(E) results record for the Brunei OPV CWCS – EAU (Async 010). . . . . . . . . . . 4
3 HAT(E) results record for the Brunei OPV CWCS – EAU (Sync 011). . . . . . . . . . . . 6
4 HAT(E) results record for the Brunei OPV CWCS – EAU (EOTS 013). . . . . . . . . . . 8
5 HAT(E) results record for the Brunei OPV CWCS – NRTE. . . . . . . . . . . . . . . . . . . . 10
6 HAT(E) results record for the Brunei OPV CWCS – GCP 76mm . . . . . . . . . . . . . . . 12
7 HAT(E) results record for the Brunei OPV CWCS – GCP 30mm . . . . . . . . . . . . . . . 14
8 HAT(E) results record for the Brunei OPV CWCS – WASP . . . . . . . . . . . . . . . . . . . 16
9 HAT(E) results record for the Brunei OPV CWCS – Datalink Y . . . . . . . . . . . . . . . . 17
10 HAT(E) results record for the Brunei OPV CWCS – RTVDU . . . . . . . . . . . . . . . . . . 18
11 HAT(E) results record for the Brunei OPV CWCS – RVG. . . . . . . . . . . . . . . . . . . . . 19
12 HAT(E) results record for the Brunei OPV CWCS – Footpush 76mm GCP . . . . . . . 20
13 HAT(E) results record for the Brunei OPV CWCS – Footpush 30mm Stbd GCP . . . 21
14 HAT(E) results record for the Brunei OPV CWCS – Footpush 30mm Port GCP . . . 22
15 HAT(E) results record for the Brunei OPV CWCS – General . . . . . . . . . . . . . . . . . . 23
16 HAT(E) results record for the Brunei OPV CWCS – General . . . . . . . . . . . . . . . . . . 24
17 HAT(E) results record for the Brunei OPV CWCS – General . . . . . . . . . . . . . . . . . . 25/26

INTRODUCTION

1 The forms in this Annex are for local reproduction when required. Sufficient quantity should
be reproduced to record the results for all Consoles and equipment fitted.

2 Completed forms should be presented to Trials Authority conducting the HAT(S) for onward
transmission to Ship’s Staff and their embodiment in ship’s equipment records.

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 1
TP 3541 UK RESTRICTED

1 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – CONSOLE

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... . Issue ...................................................................

Test No. Test Description Result


1.1 Console MAINS and ACH Availability ~~~~~~~
1.1.1 ICP MAINS AVAILABLE and ACH ON LED extinguished.
1.1.2 Console to ON, ICP ACH ON LED extinguished, MAINS ON LED lit.
1.1.3 ICP FAULT lit red until Applications Software loaded then green and
OVERHEAT LED lit green.
1.1.4 ICP LEDs BRIGHT and DIM in response to the BRIGHT/DIM switch.
1.1.5 Elapsed Time Meter incremented.
1.1.6 Console to OFF, ICP ACH ON and MAINS AVAILABLE LEDs lit,
MAINS ON LED extinguished.
1.1.7 Maintainer’s Terminal Serial Port connected and ‘Terminal Mode’
entered.
1.1.8 Console BIST runs in Quick Mode, Console BIST list displayed,
Operating System and Applications Software loaded.
1.2 Console Power-up BIST Tests ~~~~~~~
1.2.4 SIG front panel LEDs extinguished, Console FAULT LED lit red,
Master and Slave SBC front panel LEDs lit in binary count. (SYSFAIL
LED lit until Applications Software loaded.)
1.2.5 Console BIST runs. BIST complete within approx. 30 minutes.
1.2.6 Master/Slave SBC LEDs OFF.
1.2.7-8 Start Up menu displayed and Console BIST List checked (Annex C).
1.2.9-10 Start Up menu then Restricted SMF menu displayed.
1.2.11-13 Full SMF menu displayed, C, I and Z options available.
1.2.14 Console BIST run.
1.2.15-16 Start Up menu displayed then Slave Processor Control accessed,
Slave Start Up menu displayed.
1.2.17 Slave Operator-Controlled BIST selected.
1.2.18 Slave Operator-Controlled BIST List checked (Annex C).
1.2.19-20 Console BIST run, BIST completed, Start Up menu displayed.
1.2.21 Manual Load – Operating System and Applications Software loaded.
(Continued)

HAT(E) Annex A
Page 2 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test No. Test Description Result


1.3 Console Quick and Extended Mode BIST Tests ~~~~~~~
1.3.4 Operator-Controlled BIST selected, ‘bist>’ prompt displayed.
1.3.5 Console Quick BIST all tests run one iteration, continue on failure,
Console Operator-Controlled Quick BIST list displayed.
1.3.6 Console Quick BIST all tests run five iterations, continue on failure,
Console Operator-Controlled Quick BIST list displayed.
1.3.7 Console Quick BIST nine tests for Master PME68-42 with two
iterations, continue on failure . Displayed correct status (Annex C)
without errors.
1.3.8 As above for Slave PME68-42.
1.3.9 As above for PME ENET-1.
1.3.10 Operator-Controlled BIST selected, ‘bist>’ prompt displayed.
1.3.11-12 All tests at Master Processor run, Console Operator-Controlled
Extended BIST List completed. Master and Slave Processor LEDs
OFF except PR.
1.3.13 Console Extended BIST list displayed (Annex J).
1.3.14 Console Extended BIST nine tests for Master PME68-42 with two
iterations, continue on failure . Displayed correct status (Annex J)
without errors.
1.3.15 Console Extended BIST seven tests for Slave PME68-42 with two
iterations, continue on failure . Displayed correct status (Annex J)
without errors.
1.3.16 Console Extended BIST seven tests for PME ENET-1 with two
iterations, continue on failure . Displayed correct status (Annex J)
without errors.
1.3.17-18 Non-fatal failure simulated by hardware disconnection.
1.3.19 Console Quick BIST run, BIST non-fatal failure (test 008 (Slave Test
Control) reported remaining tests complete.
1.3.20-21 Operator-Controlled BIST access to Slave Processor Control
selected.
1.3.23 Operator-Controlled BIST abort on error check (error report for test
007 with status ‘C00000FF’, test run aborted).
1.3.24 Operator-Controlled BIST continue on error check (error report for
test 007 with status ‘C00000FF’, test run completes).
1.3.25 Exit Operator-Controlled BIST – Slave Start Up menu displayed.
1.3.26 Exit Slave Processor Control mode – Master Start Up menu
displayed.
1.3.28 Console BIST runs, BIST completes Start Up menu displayed.
(Continued)

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 3
TP 3541 UK RESTRICTED

2 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – EAU (ASYNC 010)

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


2.1 EAU – ASYNC (010) MAINS and ACH Availability ~~~~~~~
2.1.2 MAINS Available and ACH Available check.
2.1.3 ACH ISOLATOR On – ACH LED On check.
2.1.4 MAINS ISOLATOR ON – ACH LED Off / MAINS Available On check.
2.1.5 MAINS On / Elapsed Time Meter check.
2.1.5 Elapsed Time Meter incremented.
2.1.6 MAINS ISOLATION and ACH On check.
2.2 EAU – ASYNC (/010) Power-up BIST Test ~~~~~~~
2.2.2 Maintainer’s Terminal in ‘Terminal Mode’.
2.2.3 EAU /010 BIST run. EAU FAULT red until Applications Software
loaded then green, SIG pec LEDs (except SYSFAIL) extinguished.
2.2.4 BIST runs. Master SBC LEDs lit in binary sequence while BIST runs.
No error messages.
2.2.5 BIST completes with ’PASSED’ displayed as each completes without
error messages, Master SBC LEDs off, Start Up menu displayed.
2.2.6 EAU /010 BIST List check (Annex D).
2.2.7-8 Start Up menu displayed, SMF Restricted access selected.
2.2.9-12 SMF Full access menu displayed, C, I and Z options available.
2.2.13-14 Slave Control access selected. Operator-Controlled BIST selected,
‘bist>’ prompt displayed.
2.2.15 Slave BIST tests only listed (Annex D).
2.2.16 Slave Operator-Controlled BIST List check (Annex D).
2.2.17-18 Slave Operator-Controlled BIST run to completion, Start Up menu
displayed. (Master SBC access via Maintainer’s Terminal.)
2.2.19 Manual Load Operating System and Applications Software (not COT
EAU).
2.2.20-21 Auto Quick BIST run / Auto Load – Operating System and
Applications (except COT EAU) Software.
(Continued)

HAT(E) Annex A
Page 4 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test No. Test Description Result


2.3 EAU – ASYNC (010) Quick and Extended Mode BIST Test ~~~~~
2.3.1 Monitor Highway connections check. Start Up menu displayed
2.3.2 Operator-Controlled BIST selected. ‘bist>’ prompt displayed.
2.3.3 EAU/010 Quick BIST run, all tests one iteration, continue on failure.
Operator-Controlled Quick BIST list displayed.
2.3.4 EAU/010 Quick BIST continuous run. all tests five iterations, continue
on failure. Operator-Controlled Quick BIST list displayed.
2.3.5 EAU/010 Extended BIST run. all tests one iteration, continue on
failure. Operator-Controlled Extended BIST list displayed.
2.3.6 Extended BIST completed in approx. 40 minutes with ‘ BIST run
completed’, Processor LEDs OFF (except PR LED).
2.3.7 EAU/010 Operator Extended BIST List check (Annex K).
2.3.8-9 Operator Slave (ENET-1) Processor Control Access (with Slave
Processor fatal failure in Extended mode simulated).
2.3.10-12 Operator-Controlled BIST Access (Slave PME ENET-1). EAU/010
Quick BIST completed without error.
2.3.13-14 Slave Slave Processor Control mode accessed, Operator-controlled
BIST selected.
2.3.15 Operator-Controlled BIST test ‘003’ (APEX 100 Network Controller),
aborted on error. Error and status ‘C00001F’ report. Error message:
‘BIST run aborted due to fatal failure’.
2.3.16 Operator-Controlled BIST test ‘003’, continued on error. Error and
status ‘C00001F’ report.
2.3.17 Exited Operator-Controlled BIST, Slave Single Board Computer
(SBC) Start Up menu displayed.
2.3.18 Exited Slave Processor Control mode, Master SBC Start Up menu
displayed.
2.3.19-21 Simulated fault removed. EAU /010 Quick BIST runs, completed
without error, and Start Up menu displayed.
(Continued)

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 5
TP 3541 UK RESTRICTED

3 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – EAU (SYNC 011)

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


3.1 EAU – SYNC (/011) MAINS and ACH Availability ~~~~~~~
3.1.2 MAINS Available and ACH Available check.
3.1.3 ACH ISOLATOR ON / ACH ON LED check.
3.1.4 MAINS ISOLATOR ON / MAINS Available check.
3.1.4 MAINS ON / LED(s) and Elapsed Time Meter check.
3.1.5 Elapsed Time Meter incremented.
3.1.6 MAINS ISOLATION and ACH ON check.
3.2 EAU – SYNC (/011) Power-up BIST Test ~~~~~~~
3.2.2 Maintainer’s Terminal in ‘Terminal Mode’.
3.2.3 EAU /011 BIST run. EAU FAULT red until Applications Software
loaded then green, SIG pec LEDs (except SYSFAIL) extinguished.
3.2.4 BIST runs. Master SBC LEDs lit in binary sequence while BIST runs.
No error messages.
3.2.5 BIST completes with ’PASSED’ displayed as each completes without
error messages, Master SBC LEDs off, Start Up menu displayed.
3.2.6 EAU /011 BIST List check (Annex E).
3.2.7-8 Start Up menu displayed, SMF Restricted access selected.
3.2.9-12 SMF Full access menu displayed, C, I and Z options available.
3.2.13-14 Slave Control access selected. Operator-Controlled BIST selected,
‘bist>’ prompt displayed.
3.2.15 Slave BIST tests only listed (Annex D).
3.2.16 Slave Operator-Controlled BIST List check (Annex D).
3.2.17-18 Slave Operator-Controlled BIST run to completion, Start Up menu
displayed. (Master SBC access via Maintainer’s Terminal.)
3.2.19 Manual Load Operating System and Applications Software (not COT
EAU).
3.2.20-21 Auto Quick BIST run / Auto Load – Operating System and
Applications Software.
(Continued)

HAT(E) Annex A
Page 6 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test No. Test Description Result


3.3 EAU – SYNC (011) Quick and Extended Mode BIST Test ~~~~~~~
3.3.1 Monitor Highway connections check. Start Up menu displayed
3.3.2 Operator-Controlled BIST selected. ‘bist>’ prompt displayed.
3.3.3 EAU/011 Quick BIST run, all tests one iteration, continue on failure.
Operator-Controlled Quick BIST list displayed.
3.3.4 EAU/011 Quick BIST continuous run. all tests five iterations, continue
on failure. Operator-Controlled Quick BIST list displayed.
3.3.5 EAU/011 Extended BIST run. all tests one iteration, continue on
failure. Operator-Controlled Extended BIST list displayed.
3.3.6 Extended BIST completed in approx. 40 minutes with ‘ BIST run
completed’, Processor LEDs OFF (except PR LED).
3.3.7 EAU/011 Operator Extended BIST List check (Annex L).
3.3.8-9 Operator Slave (PME ENET-1) Processor Control Access (with BIST
Slave Processor fatal failure in Extended mode simulated).
3.3.10-12 Operator-Controlled BIST Access (Slave PME ENET-1). EAU/011
Quick BIST completed without error.
3.3.13-14 Slave Slave Processor Control mode accessed, Operator-controlled
BIST selected.
3.3.15 Operator-Controlled BIST test ‘003’, (APEX 100 Network Controller)
aborted on error. Error and status ‘C00001F’ report. Error message:
‘BIST run aborted due to fatal failure’.
3.3.16 Operator-Controlled BIST test ‘003’, continued on error. Error and
status ‘C00001F’ report.
3.3.17 Exited Operator-Controlled BIST, Slave Single Board Computer
(SBC) Start Up menu displayed.
3.3.18 Exited Slave Processor Control mode, Master SBC Start Up menu
displayed.
3.3.19-21 Simulated fault removed.EAU /011 Quick BIST runs, completed
without error, and Start Up menu displayed.
(Continued)

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 7
TP 3541 UK RESTRICTED

4 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – EAU (EOTS 013)

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


4.1 EAU – EOTS (/013) MAINS and ACH Availability ~~~~~~~
4.1.2 MAINS Available and ACH Available check.
4.1.3 ACH ISOLATOR / ACH ON LED check.
4.1.4 MAINS ISOLATOR ON / ACH LED Off and MAINS AVAILABLE LED
check.
4.1.4 MAINS ON / Elapsed Time Meter check.
4.1.5 Elapsed Time Meter incremented.
4.1.6 MAINS ISOLATION and ACH ON LED check.
4.2 EAU – EOTS (/013) Power-up BIST Test ~~~~~~~
4.2.2 Maintainer’s Terminal in ‘Terminal Mode’.
4.2.3 EAU /013 BIST run. EAU FAULT red until Applications Software
loaded then green, SIG pec LEDs (except SYSFAIL) extinguished.
4.2.4 BIST runs. Master SBC LEDs lit in binary sequence while BIST runs.
No error messages.
4.2.5 BIST completes with ’PASSED’ displayed as each completes without
error messages, Master SBC LEDs off, Start Up menu displayed.
4.2.6 EAU /013 BIST List check (Annex F).
4.2.7-8 Start Up menu displayed, SMF Restricted access selected.
4.2.9-12 SMF Full access menu displayed, C, I and Z options available.
4.2.13-14 Slave Control access selected. Operator-Controlled BIST selected,
‘bist>’ prompt displayed.
4.2.15 Slave BIST tests only listed (Annex D).
4.2.16 Slave Operator-Controlled BIST List check (Annex D).
4.2.17-18 Slave Operator-Controlled BIST run to completion, Start Up menu
displayed. (Master SBC access via Maintainer’s Terminal.)
4.2.19 Manual Load Operating System and Applications Software (not COT
EAU).
4.2.20-21 Auto Quick BIST run / Auto Load – Operating System and
Applications Software.
(Continued)

HAT(E) Annex A
Page 8 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test No. Test Description Result


4.3 EAU – EOTS (013) Quick and Extended Mode BIST Test ~~~~~
4.3.1 Monitor Highway connections check. Start Up menu displayed
4.3.2 Operator-Controlled BIST selected. ‘bist>’ prompt displayed.
4.3.3 EAU/013 Quick BIST run, all tests one iteration, continue on failure.
Operator-Controlled Quick BIST list displayed.
4.3.4 EAU/013 Quick BIST continuous run. all tests five iterations, continue
on failure. Operator-Controlled Quick BIST list displayed.
4.3.5 EAU/013 Extended BIST run. all tests one iteration, continue on
failure. Operator-Controlled Extended BIST list displayed.
4.3.6 Extended BIST completed in approx. 40 minutes with ‘ BIST run
completed’, Processor LEDs OFF (except PR LED).
4.3.7 EAU/013 Operator Extended BIST List check (Annex L).
4.3.8-9 Operator Slave (PME ENET-1) Processor Control Access (with BIST
Slave Processor fatal failure in Extended mode simulated).
4.3.10-12 Operator-Controlled BIST Access (Slave PME ENET-1). EAU/013
Quick BIST completed without error.
4.3.13-14 Slave Slave Processor Control mode accessed, Operator-controlled
BIST selected.
4.3.15 Operator-Controlled BIST test ‘003’ (APEX 100 Network Controller),
aborted on error. Error and status ‘C00001F’ report. Error message:
‘BIST run aborted due to fatal failure’.
4.3.16 Operator-Controlled BIST test ‘003’, continued on error. Error and
status ‘C00001F’ report.
4.3.17 Exited Operator-Controlled BIST, Slave Single Board Computer
(SBC) Start Up menu displayed.
4.3.18 Exited Slave Processor Control mode, Master SBC Start Up menu
displayed.
4.3.19-21 Simulated fault removed.EAU /013 Quick BIST runs, completed
without error, and Start Up menu displayed.
(Continued)

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 9
TP 3541 UK RESTRICTED

5 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – (NRTE)

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


5.1 NRTE MAINS and ACH availability ~~~~~~~
5.1.2 MAINS AVAIL and ACH AVAIL LEDs check.
5.1.3 ACH ISOLATION ON LED check.
5.1.4 MAINS ISOLATION ON LED check.
5.1.4 MPA MAINS ON LED, and PIB OVERTEMP and FAULT LEDs ON.
5.1.5 Elapsed Time Meter incrementation.
5.1.6 PIB MAINS to ISOLATION / ACH LED ON check.
5.2 NRTE Power-up BIST Test ~~~~~~~
5.2.21 Maintainer’s Terminal in ‘Terminal Mode’.
5.2.3 NRTE BIST run. NRTE FAULT red until Applications Software loaded
then green, SIG pec LEDs (except SYSFAIL) extinguished.
5.2.4 BIST runs. Master SBC LEDs lit in binary sequence while BIST runs.
No error messages.
5.2.5 BIST completes with ’PASSED’ displayed as each completes without
error messages, Master SBC LEDs off, Start Up menu displayed.
5.2.6 NRTE BIST List check (Annex G).
5.2.7-8 Start Up menu displayed, SMF Restricted access selected.
5.2.9-11 SMF Full access menu displayed, C, I and Z options available.
5.2.12 NRTE BIST run, displayed NRTE BIST list.
5.2.13 BIST runs to completion, Master Processor Start Up menu displayed.
5.2.14 Slave Start Up menu displayed.
5.2.15 Operator-Controlled BIST selected, ‘bist>’ prompt displayed.
5.2.16 Slave BIST tests only listed (Annex G).
5.2.17-18 Slave Operator-Controlled BIST run to completion, Master Processor
Start Up menu displayed.
5.2.19 Manual Load – Operating System and Applications Software.
Restricted SMF menu displayed.
5.2.20-21 Auto Quick BIST run/auto Load – Operating System and Applications
Software. Restricted SMF menu displayed.
(Continued)

HAT(E) Annex A
Page 10 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test No. Test Description Result


5.3 NRTE Quick and Extended Mode BIST Test ~~~~~
5.3.1 BIST ran, displayed the NRTE BIST list and completed Master
Processor Start Up menu displayed.
5.3.2 Operator-Controlled BIST selected. ‘bist>’ prompt displayed.
5.3.3 NRTE Quick BIST run, all tests one iteration, continue on failure.
Operator-Controlled Quick BIST list displayed.
5.3.4 NRTE Quick BIST continuous run. all tests five iterations, continue on
failure. Operator-Controlled Quick BIST list displayed.
5.3.5 NRTE Extended BIST run. all tests one iteration, continue on failure.
Operator-Controlled Extended BIST list displayed.
5.3.6 Extended BIST completed in approx. 50 minutes with ‘ BIST run
completed’, Processor LEDs OFF (except PR).
5.3.7 NRTE Operator Extended BIST List check (Annex N).
5.3.8-9 Operator Slave (PME ENET-1) Processor Control Access (with BIST
Slave Processor fatal failure in Extended mode simulated).
5.3.10-12 Operator-Controlled BIST Access (Slave PME ENET-1). NRTE Quick
BIST completed without error.
5.3.13-14 Slave Slave Processor Control mode accessed, Operator-controlled
BIST selected.
5.3.15 Operator-Controlled BIST test ‘003’ (APEX 100 Network Controller),
aborted on error. Error and status ‘C00001F’ report. Error message:
‘APEX 100 external ethernet loop back failure detected’.
5.3.16 Operator-Controlled BIST test ‘003’, continued on error. Error and
status ‘C00001F’ report.
5.3.17 Exited Operator-Controlled BIST, Slave Single Board Computer
(SBC) Start Up menu displayed.
5.3.18 Exited Slave Processor Control mode, Master SBC Start Up menu
displayed.
5.3.19-21 Simulated fault removed. NRTE Quick BIST runs, completed without
error, and Start Up menu displayed.
(Continued)

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 11
TP 3541 UK RESTRICTED

6 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – GCP 76mm

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


6.1 GCP 76mm MAINS and ACH availability ~~~~~~~
6.1.2 MAINS, ACH and REFERENCE AVAILABLE LEDs check.
6.1.3 ACH ISOLATOR On check.
6.1.4 MAINS ISOLATOR On check.
6.1.4 MPA ON/OFF switch On check.
6.1.5 Elapse Time Meter incremented.
6.1.6 PIB MAINS to ISOLATION.
6.2 GCP 76mm Power-up BIST Test ~~~~~~~
6.2.2 Maintainer’s Terminal in ‘Terminal Mode’.
6.2.3 GCP 76mm BIST run. GCP FAULT red until Applications Software
loaded then green, SIG pec LEDs (except SYSFAIL) extinguished.
6.2.4 GCP 76mm BIST run. Master SBC LEDs lit in binary sequence while
BIST runs. No error messages.
6.2.5 GCP BIST List check (Annex H).
6.2.6 BIST completes with ’PASSED’ displayed as each completes without
error messages, Master SBC LEDs off, Start Up menu displayed.
6.2.7-8 Start Up menu displayed, SMF Restricted access selected.
6.2.9-11 SMF Full access menu displayed, C, I and Z options available.
6.2.12 GCP 76mm BIST run, displayed GCP BIST list (Annex H).
6.2.13 BIST run to completion, Master Processor Start Up menu displayed.
6.2.14 Slave Start Up menu displayed.
6.2.15 Operator-Controlled BIST selected, ‘bist>’ prompt displayed.
6.2.16 Slave BIST tests only listed (Annex H).
6.2.17-18 Slave Operator-Controlled BIST run to completion, Master Processor
Start Up menu displayed.
6.2.19 Manual Load – Operating System and Applications Software.
Restricted SMF menu displayed.
6.2.20-21 Auto Quick BIST run/auto Load – Operating System and Applications
Software. Restricted SMF menu displayed.
(Continued)

HAT(E) Annex A
Page 12 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test No. Test Description Result


6.3 GCP 76mm Quick and Extended Mode BIST ~~~~~~~
6.3.1 BIST ran and completed. Start Up menu displayed.
6.3.2 Operator-Controlled BIST selected. ‘bist>’ prompt displayed.
6.3.3 GCP Quick BIST run, all tests one iteration, continue on failure.
Operator-Controlled Quick BIST list displayed.
6.3.4 GCP Quick BIST continuous run. all tests five iterations, continue on
failure. Operator-Controlled Quick BIST list displayed.
6.3.5 GCP 76 mm Extended BIST run. all tests one iteration, continue on
failure. Operator-Controlled Extended BIST list displayed.
6.3.6 Extended BIST completed in approx. 50 minutes with ‘ BIST run
completed’, Processor LEDs OFF (except PR).
6.3.7 GCP Operator Extended BIST List check (Annex O).
6.3.8-10 BIST non-fatal failure simulated, GCP BIST list redisplayed.
6.3.11 BIST test ‘009’ (MPV997A-21 RTD 1) reported non-fatal failure (due
to missing link).
6.3.12-13 Slave Slave Processor Control mode (PME ENET-1) accessed,
Operator-controlled BIST selected.
6.3.14 Exited from Slave Processor Control mode. Master Start Up menu
displayed.
6.3.15 Entered Operator-Controlled BIST. ‘bist>’ prompt displayed.
6.3.16 Operator-Controlled BIST test ‘009’ (MPV997A-21 RTD 1), aborted
on error. Error report for test ‘009’ and a status of ‘40000000’. Error
Message: ‘ BIST run aborted due to fatal failure’
6.3.17 Operator-Controlled BIST test ‘009’ (MPV997A-21 RTD 1), continued
on error. Error report for test ‘009’ and a status of ‘40000000’.
6.3.18 Exited Slave Processor Control mode, Start Up menu displayed.
6.3.19-21 Simulated fault removed. GCP 76mm Quick BIST runs, completed
without error.
(Continued)

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 13
TP 3541 UK RESTRICTED

7 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – GCP 30mm

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


7.1 GCP 30mm MAINS and ACH availability ~~~~~~~
7.1.2 MAINS, ACH and REFERENCE AVAILABLE LEDs check.
7.1.3 ACH ISOLATOR On check.
7.1.4 MAINS ISOLATOR On check.
7.1.4 MPA ON/OFF switch On check.
7.1.5 Elapse Time Meter incremented.
7.1.6 PIB MAINS to ISOLATION checks.
7.2 GCP 30mm Power-up BIST Test ~~~~~~~
7.2.2 Maintainer’s Terminal in ‘Terminal Mode’.
7.2.3 GCP 30mm BIST run. GCP FAULT red until Applications Software
loaded then green, SIG pec LEDs (except SYSFAIL) extinguished.
7.2.4 GCP 30mm BIST run. Master SBC LEDs lit in binary sequence while
BIST runs. No error messages.
7.2.5 GCP 30mm BIST List check (Annex I).
7.2.6 GCP 30mm BIST completes with ’PASSED’ displayed as each
completes without error messages, Master SBC LEDs off, Start Up
menu displayed.
7.2.7-8 Start Up menu displayed, SMF Restricted access selected.
7.2.9-11 SMF Full access menu displayed, C, I and Z options available.
7.2.12 GCP 30mm BIST run, displayed GCP 30mm BIST list.
7.2.13 GCP 30mm BIST runs to completion, Master Processor Start Up
menu displayed.
7.2.14 Slave Start Up menu displayed.
7.2.15 Operator-Controlled BIST selected, ‘bist>’ prompt displayed.
7.2.16 Slave BIST tests only listed (Annex I).
7.2.17-19 Slave Operator-Controlled BIST run to completion, Master Processor
Start Up menu displayed.
7.2.20-21 Manual Load – Operating System and Applications Software.
Restricted SMF menu displayed.
(Continued)

HAT(E) Annex A
Page 14 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

Test No. Test Description Result


7.3 GCP 30mm Quick and Extended Mode BIST Test ~~~~~~~
7.3.1 BIST ran and completed. Start Up menu displayed.
7.3.2 Operator-Controlled BIST selected. ‘bist>’ prompt displayed.
7.3.3 GCP Quick BIST run, all tests one iteration, continue on failure.
Operator-Controlled Quick BIST list displayed.
7.3.4 GCP Quick BIST continuous run. all tests five iterations, continue on
failure. Operator-Controlled Quick BIST list displayed.
7.3.5 GCP 30 mm Extended BIST run. all tests one iteration, continue on
failure. Operator-Controlled Extended BIST list displayed.
7.3.6 Extended BIST completed in approx. 50 minutes with ‘ BIST run
completed’, Processor LEDs OFF (except PR).
7.3.7 GCP Operator Extended BIST List check (Annex P).
7.3.8-10 BIST non-fatal failure simulated, GCP BIST list redisplayed.
7.3.11 BIST test ‘009’ (MPV997A-21 RTD 1) reported non-fatal failure (due
to missing link).
7.3.12 Slave Slave Processor Control mode (PME ENET-1) accessed,
Operator-controlled BIST selected.
7.3.13 Exited from Slave Processor Control mode. Master Start Up menu
displayed.
7.3.14 Entered Operator-Controlled BIST. ‘bist>’ prompt displayed.
7.3.17 Operator-Controlled BIST test ‘009’ (MPV997A-21 RTD 1), aborted
on error. Error report for test ‘009’ and a status of ‘40000000’. Error
Message: ‘ BIST run aborted due to fatal failure’
7.3.18 Operator-Controlled BIST test ‘009’ (MPV997A-21 RTD 1), continued
on error. Error report for test ‘009’ and a status of ‘40000000’.
7.3.17 Exited Slave Processor Control mode, Start Up menu displayed.
7.3.19-21 Simulated fault removed. GCP 30mm Quick BIST runs, completed
without error.
(Continued)

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 15
TP 3541 UK RESTRICTED

8 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – WASP

Part No .......................................................... Date ....................................................................

Serial No........................................................ ............................................................ Tested by

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


8.1 WASP Switch Lamp Check ~~~~~~~
8.1.1 VCS WASP illumination supply available.
8.1.2 Power up 76mm GCP – all WASP 76mm lamps check.
8.1.3 Power up 30mm Port GCP – all WASP 30mm Port lamp check.
8.1.4 Power up 30mm Starboard GCP – all WASP 30mm Starboard lamp
check.
8.1.5 Power up EOTS EAU – all WASP EOTS lamps check.
8.1.6 Lamp Test check – all switch lamps lit (except LAMP TEST).
8.1.7 Gun and Laser Enable Keys – Unique check – unable to select any
other Enable switch.

HAT(E) Annex A
Page 16 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

9 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – DATALINK Y

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


9.1 Power Indicators, Power-Up (Remote mode), BIT, Short Loop ~~~~~~~
Tests
9.1.1 Link Y comprises Link Y Processor and Remote Control Panel (RCP).
Ships MAINS and AC power ON, Link Y and RCP LED check
9.1.2 REMOTE/LOCAL switch to Remote, LINK and RCP LED check.
9.1.3 LINK Y Terminal: Mains AVAIL lit, AC ON OFF, POWER ON lit.
Software start loading (pec LEDs flash), FAIL lit. RCP: POWER lit.
9.1.4 Software loaded and BIT passed. FAIL extinguished on Link Y
Terminal, Software Version menu displayed on RCP display.
9.1.5 RCP in STANDBY and ’LOOP TEST’ and EXEC selected.
Test Menu Displayed with a ‘+’ in front of the selected test.
Console CWCS Node Status tote:
Link Y is ‘AB’ and ‘Nor’ in green with an interface status of ‘O’ in
green.
Console Link Y Status tote:
Mode field is ‘Loop test’ in yellow.
9.1.6 ‘SHORT LOOP’ Test executed. At the RCP: ‘RESULT: BUSY’
changed to ‘RESULT: OK’ on successful completion.
Console CWCS Node Status tote:
Link Y is ‘AB’ and ‘Nor’ in green with an interface status of ‘N’ in
red whilst the test ran.
Console Link Y Mk2 Status tote:
Mode field is ‘Loop test’ in yellow.
9.1.7 Link Y and RCP POWER OFF, Link Y and RCP LED check.
LINK Y Terminal: Mains AVAIL lit.
AC ON lit.
POWER ON OFF.
RCP: POWER LED OFF.

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 17
TP 3541 UK RESTRICTED

10 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – RTVDU

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by.............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result

10.1 RDDU Power Indicator Test ~~~~~~~


10.1.1 RDDU ACH AVAIL LED lit green.
10.1.2 RDDU MAINS AVAIL LED lit green.
10.1.3 RDDU REF AVAIL LED lit green.
10.1.5 RDDU Power Up BITE check
10.1.5 RDDU MAINS, –12 V, +12 V and +5 V LED check.
10.1.6 RDDU Fan check.
10.1.7 RDDU / CWCS Console / Radar / RVG Interconnections .
10.2 TVDU Power Indicator Test ~~~~~~~
10.2.1 TVDU ACH AVAIL LED lit green.
10.2.2 TVDU MAINS AVAIL LED lit green.
10.2.4 TVDU MAINS, –12 V, +12 V and +5 V LED check.
10.2.4 TVDU Power Up BITE check.
10.2.5 TVDU Fan check.
10.2.6 TV Interconnections between TVDUs and CWCS Consoles check.

HAT(E) Annex A
Page 18 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

11 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – RVG

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result

11.1 Power Indicators and MCB tests ~~~~~~~


11.1.2 115 V 60 Hz AC supply OFF – lamp checks.
11.1.3 115 V 60 Hz AC supply ON – lamp checks.
11.1.4 MCB2 ON – MCB1 trips, lamp checks.
11.1.5 Reset MCB2, MCB1 – Green RVG lamp check.
11.1.6 MCB3 ON – MCB1 trips.
11.1.7 115 V 60 Hz a.c. supply OFF – lamp checks.
11.1.8 MCB4 ON – lamp checks.
11.1.9 Reset all MCBs – RED fault lamp is OFF.
11.2 Power-Up BIT and Operator Initiated Extended BIT ~~~~~~~
11.2.2 RVG Control Unit MAINS supply via a.c. adaptor.
11.2.3 RVG ON – lamp checks.
11.2.4 RVG System Boots. Power-Up BIT tests OK.
11.2.5 RVG BOPVRVG Issue and Date check.
11.2.6 RVG Operator Initiated Extended BIT tests OK.

HAT(E) Annex A
UK RESTRICTED Page 19
TP 3541 UK RESTRICTED

12 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – FOOTPUSH 76mm GCP

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


12.1 Gun Footpush for WCC1, WCC2, WCC3 and MGD(B) for the ~~~~~~~
76mm GCP
12.1.1 Gun Footpush fitted at WCC1,WCC2, WCC3 and MGD(B).
12.1.2 GCP (76mm) to WCC1 – Gun Enable set to ON at WASP.
12.1.3 GCP (76mm) to WCC1 – GCP (76mm) BIST List displayed
(Annex H).
12.1.4 GCP (76mm) to WCC1 – BIST footpush fatal failure.
12.1.5 GCP (76mm) to WCC2 – GCP (76mm) BIST List displayed
(Annex H).
12.1.6 GCP (76mm) to WCC2 – BIST footpush fatal failure.
12.1.7 GCP (76mm) to WCC3 – GCP (76mm) BIST List displayed
(Annex H).
12.1.8 GCP (76mm) to WCC3 – BIST footpush fatal failure.
12.1.9 GCP (76mm) to MGD(B) – GCP (76mm) BIST List displayed
(Annex H).
12.1.10 GCP (76mm) to MGD(B) – BIST footpush fatal failure.

HAT(E) Annex A
Page 20 UK RESTRICTED Oct 03 (Amdt 1)
TP 3541 UK RESTRICTED

13 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – FOOTPUSH 30mm Stbd GCP

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


12.2 Gun Footpush for WCC1, WCC2, WCC3 and MGD(B) for the ~~~~~~~~
30mm Stbd GCP
12.2.1 GCP (30mm Stbd) to WCC1 – Gun Enable set to ON at WASP.
12.2.2 GCP (30mm Stbd) to WCC1 – GCP (30mm) BIST List displayed
(Annex I).
12.2.3 GCP (30mm Stbd) to WCC1 – BIST footpush fatal failure.
12.2.4 GCP (30mm Stbd) to WCC2 – GCP (30mm) BIST List displayed
(Annex I).
12.2.5 GCP (30mm Stbd) to WCC2 – BIST footpush fatal failure.
12.2.6 GCP (30mm Stbd) to WCC3 – GCP (30mm) BIST List displayed
(Annex I).
12.2.7 GCP (30mm Stbd) to WCC3 – BIST footpush fatal failure
12.2.8 GCP (30mm Stbd) to MGD(B) – GCP (30mm) BIST List displayed
(Annex I).
12.2.9 GCP (30mm Stbd) to MGD(B) – BIST footpush fatal failure.

HAT(E) Annex A
Page 21 UK RESTRICTED Oct 03 (Amdt 1)
TP 3541 UK RESTRICTED

14 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – FOOTPUSH 30mm Port GCP

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result

12.3 Gun Footpush for WCC1, WCC2, WCC3 and MGD(B) for the ~~~~~~~
30mm Port GCP
12.3.1 GCP (30mm Port) to WCC1 – Gun Enable set to ON at WASP.
12.3.2 GCP (30mm Port) to WCC1 – GCP (30mm) BIST List displayed
(Annex I).
12.3.3 GCP (30mm Port) to WCC1 – BIST footpush fatal failure.
12.3.4 GCP (30mm Port) to WCC2 – GCP (30mm) BIST List displayed
(Annex I).
12.3.5 GCP (30mm Port) to WCC2 – BIST footpush fatal failure.
12.3.6 GCP (30mm Port) to WCC3 – GCP (30mm) BIST List displayed
(Annex I).
12.3.7 GCP (30mm Port) to WCC3 – BIST footpush fatal failure.
12.3.8 GCP (30mm Port) to MGD(B) – GCP (30mm) BIST List displayed
(Annex I).
12.3.9 GCP (30mm Port) to MGD(B) – BIST footpush fatal failure.

HAT(E) Annex A
Page 22 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

15 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – GENERAL

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


13.1 RTVDU Test Picture and Distribution ~~~~~
13.1.1 External Test Picture is displayed on all consoles except TPS as per
Annex Q.
13.1.2 Mains Available LED is lit.
13.1.3 TV1 Test Picture is correctly displayed on all consoles and Bridge
Display (INP 1) except TPS.
13.1.4 Select INP 2 Bridge Display blank.
13.1.5 TV1 Test Picture displayed on TPS Console and Bridge Display.
13.1.6 Mains Available LED is illuminated.
13.1.7 TV2 Test Picture is correctly displayed on all consoles and Bridge
Display (INP 2).

HAT(E) Annex A
UK RESTRICTED Page 23
TP 3541 UK RESTRICTED

16 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – GENERAL

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


13.2 RVG Simulated Video Control and Distribution ~~~~~~~
13.2.1 RVG indicates ‘Available’ at the Control Unit. Console 1 selected.
13.2.3 Observe, using SES Test 38, the RDDU and TVDU of each RTVDU
indicates a Pass.
13.2.5 Console 1 (PWO) powered up into the Scenario execution mode.
13.2.6 Observe, in the PWO Console Node Status tote: PWO Console
Operational state ‘Exc’ in amber, Consoles 2 to 8 are ‘Trn’ in amber,
NRTE and AWS-9 EAU is ‘Sim’ in amber. Consoles 2 to 8 powered up
into the CTT mode.
13.2.7 Scenarion Test Tape loaded, MTU Status tote displays ‘FATSIM’.
Scenario vehicles displayed on the LPD. Each Console displays
simulated AWS-9 MTI video and Ship’s Head Marker video.
13.2.8 Sim AWS-9 menu used to select simulated AWS-9 radar.
13.2.9 Each Console display simulated AWS-9 Processed Log video and
Ship’s Head Marker video.
13.2.10 Each Console displays simulated AWS-9 MTI video.
13.2.11 Each Console displays simulated AWS-9 Processed Log video and
associated IFF video.
13.2.12 Each Console displays simulated Navigation Log video and Ship’s
Head Marker video.
13.2.13 Ensure Console 2 (TPS) is selected. Load DAT Tape and Start
scenario.
13.2.14 Scenario stopped and Tape ejected.
13.2.15 Console 2 (TPS) selected at RVG. Scenarion Test Tape loaded and
Scenario started. VG indicates ‘Playing’ on RVG Control Unit menu.
13.2.16 Scenario stopped.Tape ejected and Console 2 powered down.
13.2.17 Steps 13.2.14 and 13.2.15 for Console 3 repeated.
13.2.17 Steps 13.2.14 and 13.2.15 for Console 4 repeated.
13.2.17 Steps 13.2.14 and 13.2.15 for Console 5 repeated.
13.2.17 Steps 13.2.14 and 13.2.15 for Console 6 repeated.
13.2.17 Steps 13.2.14 and 13.2.15 for Console 7 repeated.
13.2.17 Steps 13.2.14 and 13.2.15 for Console 8 repeated.

HAT(E) Annex A
Page 24 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

17 HAT(E) RESULTS RECORD FOR THE BRUNEI OPV CWCS – GENERAL

Part No. ......................................................... Date ....................................................................

Serial No........................................................ Tested by ............................................................

Identity........................................................... Checked by.........................................................

System Software No...................................... Issue ...................................................................

Test No. Test Description Result


13.3 WASP Switching and Selection ~~~~~~~
13.3.1 At the 76mm GCP, SES package ‘/fmd0/tdq.scr’ test loaded.
13.3.2 SES selected.
13.3.3 ‘001 WASP Interconnect test’ run, no errors.
13.3.4 SES result table displayed, no errors (apart from Checkfire error).
13.3.5 At the 76mm GCP, SES package ‘tdl.scr’ loaded.
13.3.7 At the 30mm Stbd GCP, SES package ‘/fmd0/tdq.scr’ loaded.
13.3.8 SES selected.
13.3.9 ‘001 WASP Interconnect test run’, no errors.
13.3.10 SES result table displayed, no errors (apart from Checkfire error).
13.3.11 At the 30mm Stbd GCP, SES package ‘/fmd0/tdl.scr’ loaded.
13.3.13 At the 30mm Port GCP, SES package ‘/fmd0/tdq.scr’ test loaded.
13.3.14 SES Selected.
13.3.15 ‘001 WASP Interconnect test’ run, no errors.
13.3.16 SES result table displayed, no errors (apart from Checkfire error).
13.3.17 At the 30mm Port GCP, SES package ‘/fmd0/tdl.scr’ loaded.
13.3.19 SES test 35 in WCC1, WCC2, WCC3 and MGD(B) loaded.
13.3.20 At the EOTS EAU, SES package ‘/fmd0/tdq.scr’ test loaded.
13.3.21 SES selected.
13.3.22 ‘001 WASP Interconnect test’ run, no errors
13.3.23 SES result table displayed, no errors (apart from Checkfire error).
13.3.24 SES test 35 in WCC1, WCC2, WCC3 and MGD(B) completed.
(Responses irrelevant.)
13.3.22 EOTS EAU reset, manually configured with SES package ‘/fmd0/
tar3.scr’ loaded.

HAT(E) Annex A
Oct 03 (Amdt 1) UK RESTRICTED Page 25/26
UK RESTRICTED TP 3541

HAT(E) ANNEX B

SES RUNNING INSTRUCTIONS

1 Respond to the following:

Do you wish to change configuration data [Y or N]?: <CR>

Do you want to set up a test list [Y or N]?: y<CR>

Do you wish to remove tests from the test list [Y or N]?: <CR>

Please enter test number to be selected: *<CR>

Please enter the number of passes required: <CR>

Please enter the number of iterations required: <CR>

Option register value = 040 Enter new value = <CR>

NOTES

(1) All operator responses are in bold, screen text is in Courier font.

(2) * Indicates to enter the test number required. Repeat this step until all required test
numbers have been entered then proceed to the next step.

(3) Where only <CR> is the operator response to a question, the test program defaults to
an answer set up on a previous test run or its default answer. The default answers to all Y or
N questions above are N and the default numbers for both passes and iterations is 1.

HAT(E) Annex B
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX C

CONSOLE BIST LIST

Resident SBC BIST 310/FL/04551/000 Iss *


Copyright Alenia Marconi Systems Ltd yyyy

001 SBC MPE Status Report Iss * (Q) C0000007 PASSED


002 SBC BIST Iss * (Q) xxC01F7FEB PASSED

Resident BIST complete, loading remaining system BIST


hit any key to enter menu on completion of BIST testing (see Note (2))

003 System BIST 310/FU/04614/000 Iss * (Q) 00000001 PASSED


004 Control Grip Iss * (Q) C000007F PASSED
005 CRR-2 FLASH Iss * (Q) C0000081 PASSED
006 Slave Test Control (ENET-1) Iss * (Q)
<01>
<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *
<01> Copyright GEC-Marconi Ltd yyyy
<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
Slave processor overall status is .... (Q) C000001F PASSED
007 CRR-2 SRAM Iss * (Q) C0000009 PASSED
008 Slave Test Control (PME68-42) Iss * (Q)
<02>
<02> Resident SBC BIST 310/FL/04551/000 Iss *
<02> Copyright Alenia Marconi Systems Ltd yyyy
<02> 001 SBC MPE Status report Iss * (Q) C0000007 PASSED
<02> 002 SBC BIST Iss * (Q) C01F7FEB PASSED
<02> 003 Sub-system BIST 310/FU/04614/000 Iss * (Q) 00000001 PASSED
<02> 004 Keyboard and Rolling Ball Iss * (Q) C000007F PASSED
<02> 005 C.A.T. card BIST Iss * (Q) C00000FF PASSED
<02> 006 Vantage II card BIST Iss * (Q) C1FCED9F PASSED
<02> 007 Virgo ++ card BIST Iss * (Q) C000036F PASSED
Slave processor overall status is ..... (Q) C000007F PASSED
009 System Interrupt Generator Iss * (Q) FFFFFFFF PASSED

System BIST complete, hit any key for menu

NOTES

(1) Where:
* = current issue status applicable to the relevant BIST package.
xx = undefined characters.
yyyy = copyright year value, e.g. 1994.
(2) This paragraph is not seen when run in ‘Operator Controlled Bist’.

HAT(E) Annex C
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX D

EAU/010 (ASYNC) BIST LIST

Resident SBC BIST 310/FL/04551/000 Iss *


Copyright Alenia Marconi Systems Ltd yyyy

001 SBC MPE Status Report Iss * (Q) C0000007 $


002 SBC BIST Iss * (Q) xC01F7FEB $

Resident BIST complete, loading remaining system BIST


Hit any key to enter menu on completion of BIST testing (see Note (2))

003 System BIST 310/FU/04575/000 Iss * (Q) 00000001 $


004 CRR-2 FLASH Iss * (Q) C0000081 $
005 Slave Test Control ( ENET-1) Iss * (Q)
<01>
<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *
<01> Copyright GEC-Marconi Ltd yyyy
<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 $
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB $
<01> 003 APEX 100 Network controller Iss * (Q) C000001F $
Slave processor overall status is (Q) C000001F $
006 System Interrupt Generator Iss * (Q) FFFFFFFF $

NOTES

(1) Where:
* = current issue status applicable to the relevant BIST package.
x = undefined character.
$ = PASSED if test has passed and FAILED if test has failed).
yyyy = copyright year value, e.g., 1999.
(2) This paragraph is not seen when run in 'Operator Controlled Bist'.

HAT(E) Annex D
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX E

EAU/011 (SYNC) BIST LIST

Resident SBC BIST 310/FL/04551/000 Iss *


Copyright Alenia Marconi Systems Ltd yyyy

001 SBC MPE Status Report Iss * (Q) C0000007 $


002 SBC BIST Iss * (Q) xxC01F7FEB $

Resident BIST complete, loading remaining system BIST


Hit any key to enter menu on completion of BIST testing (See Note (2))

003 System BIST 310/FU/04576/000 Iss * (Q) 00000001 $


004 CRR-2 FLASH Iss * (Q) C0000081 $
005 Slave Test Control (ENET-1) Iss * (Q)
<01>
<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *
<01> Copyright GEC-Marconi Ltd yyyy
<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 $
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB $
<01> 003 APEX 100 Network controller Iss * (Q) C000001F $
Slave processor overall status is (Q) C000001F $
006 System Interrupt Generator Iss * (Q) FFFFFFFF $
007 MPCC-1 Serial Comms Controller Iss * (Q) C0007FFF $

NOTES

(1) Where:
* = current issue status applicable to the relevant BIST package.
xx = undefined character and $ = PASSED if test has passed and
FAILED if test has failed.
yyyy = copyright year value, e.g. 1999.
(2) This paragraph is not seen when run in 'Operator Controlled Bist'.

HAT(E) Annex E
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX F

EAU/013 (EOTS) BIST LIST

Resident SBC BIST 310/FL/04551/000 Iss *


Copyright Alenia Marconi Systems Ltd yyyy

001 SBC MPE Status Report Iss * (Q) C0000007 $


002 SBC BIST Iss * (Q) xxC01F7FEB $

Resident BIST complete, loading remaining system BIST


Hit any key to enter menu on completion of BIST testing (See Note (2))

003 System BIST 310/FU/04578/000 Iss * (Q) 00000001 $


004 CRR-2 FLASH Iss * (Q) C0000081 $
005 Slave Test Control (ENET-1) Iss * (Q) $
<01>
<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *
<01> Copyright GEC-Marconi Ltd yyyy
<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 $
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB $
<01> 003 APEX 100 Network controller Iss * (Q) C000001F $
<01>
Slave processor overall status is (Q) C000001F $
006 System Interrupt Generator Iss * (Q) FFFFFFFF $
007 Safety Function Iss * (Q) C00001FF $

NOTES

(1) Where:
* = current issue status applicable to the relevant BIST package.
xx = undefined character and $ = PASSED if test has passed and
FAILED if test has failed.
yyyy = copyright year value, e.g., 1999.
(2) This paragraph is not seen when run in 'Operator Controlled Bist'.

HAT(E) Annex F
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX G

NRTE BIST LIST

Resident SBC BIST 310/FL/04551/000 Iss *


Copyright Alenia Marconi Systems Ltd yyyy

001 SBC MPE Status Report Iss * (Q) C0000007 PASSED


002 SBC BIST Iss * (Q) xxC01F7FEB PASSED

Resident BIST complete, loading remaining system BIST


Hit any key to enter menu on completion of BIST testing (see Note (2))

003 System BIST 310/FL/04532/000 Iss * (Q) 00000001 PASSED


004 CRR-2 FLASH Iss * (Q) C0000081 PASSED
005 Slave Test Control (ENET-1) Iss * (Q)
<01>
<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *
<01> Copyright GEC-Marconi Ltd yyyy
<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
Slave processor overall status is ..... (Q) C000001F PASSED
006 System Interrupt Generator Iss * (Q) FFFFFFFF PASSED
007 Slave Test Control (PME68-41) Iss * (Q)
<02>
<02> Resident SBC BIST 310/FL/04551/000 Iss *
<02> Copyright GEC-Marconi Ltd yyyy
<02> 001 SBC MPE Status Report Iss * (Q) C0000007 PASSED
<02> 002 SBC BIST Iss * (Q) C01F7FEB PASSED
<02> 003 Sub-system BIST 310/FU/04532/000 Iss * (Q) 00000001 PASSED
<02> 005 Radar Front End Iss * (Q) C000000F PASSED
<02> 004 Plot Extractor Iss * (Q) C0000FFF PASSED
Slave processor overall status is ..... (Q) C000007F PASSED

System BIST complete, hit any key for menu

NOTES

(1) Where:
* = current issue status applicable to the relevant BIST package.
xx = undefined characters.
yyyy = copyright year value, e.g., 1994.
(2) This paragraph is not seen when run in ‘Operator Controlled Bist’.

HAT(E) Annex G
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX H

GCP (76MM) BIST LIST

Resident SBC BIST 310/FL/04551/000 Iss *


Copyright Alenia Marconi Systems Ltd yyyy

001 SBC MPE Status Report Iss * (Q) C0000007 PASSED


002 SBC BIST Iss * (Q) xxC01F7FEB PASSED

Resident BIST complete, loading remaining system BIST


Hit any key to enter menu on completion of BIST testing (See Note (2))

003 System BIST 310/FU/04614/000 Iss *(Q) 00000001 PASSED


004 CRR-2 FLASH Iss *(Q) C0000081 PASSED
005 Slave Test Control (ENET-1) Iss *(Q)
<01>
<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *
<01> Copyright GEC-Marconi Ltd yyyy
<01> 001 ENET-1 MPE Status Report Iss *(Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss *(Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss *(Q) C000001F PASSED
<01>
Slave processor overall status is .... (Q) C000001F PASSED
006 Slave Test Control (PME68-42) Iss *(Q)
<02>
<02> Resident SBC BIST 310/FL/04551/000 Iss *
<02> Copyright Alenia Marconi Systems Ltd yyyy
<02> 001 SBC MPE Status Report Iss *(Q) C0000007 PASSED
<02> 002 SBC BIST Iss *(Q) C01F7FEB PASSED
<02>
Slave processor overall status is ..... (Q) C000001F PASSED
007 Safety Function Iss *(Q) C00001FF PASSED
008 MPV996A-21 (DTS) Iss *(Q) C0000BBF PASSED
009 MPV997A-21 (RTD 1) Iss *(Q) C000003F PASSED
010 MPV997A-21 (RTD 2) Iss *(Q) C000003F PASSED
011 MPV997A-21 (RTD 3) Iss *(Q) C000003F PASSED
012 System Interrupt Generator Iss *(Q) FFFFFFFF PASSED

System BIST complete, hit any key for menu

NOTES

(1) Where:
* = current issue status applicable to the relevant BIST package.
xx = undefined characters.
yyyy = copyright year value, e.g., 1994.
(2) This paragraph is not seen when run in ‘Operator Controlled Bist’.

HAT(E) Annex H
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX I

GCP (30MM) BIST LIST

Resident SBC BIST 310/FL/04551/000 Iss *


Copyright Alenia Marconi Systems Ltd yyyy

001 SBC MPE Status Report Iss * (Q) C0000007 PASSED


002 SBC BIST Iss * (Q) xxC01F7FEB PASSED

Resident BIST complete, loading remaining system BIST


Hit any key to enter menu on completion of BIST testing (See Note (2))

003 System BIST 310/FU/04614/000 Iss * (Q) 00000001 PASSED


004 CRR-2 FLASH Iss * (Q) C0000081 PASSED
005 Slave Test Control (ENET-1) Iss * (Q)
<01>
<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *
<01> Copyright GEC-Marconi Ltd yyyy
<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
<01>
Slave processor overall status is ..... (Q) C000001F PASSED
006 Slave Test Control (PME68-42) Iss * (Q)
<02>
<02> Resident SBC BIST 310/FL/04551/000 Iss *
<02> Copyright Alenia Marconi Systems Ltd yyyy
<02> 001 SBC MPE Status report Iss * (Q) C0000007 PASSED
<02> 002 SBC BIST Iss * (Q) C01F7FEB PASSED
<02>
Slave processor overall status is ..... (Q) C000001F PASSED
007 Safety Function Iss * (Q) C00001FF PASSED
008 MPV996A-21 (DTS) Iss * (Q) C0000BBF PASSED
009 MPV997A-21 (RTD 1) Iss * (Q) C000003F PASSED
010 MPV997A-21 (RTD 2) Iss * (Q) C000003F PASSED
011 MPV997A-21 (RTD 3) Iss * (Q) C000003F PASSED
012 System Interrupt Generator Iss * (Q) FFFFFFFF PASSED

System BIST complete, hit any key for menu

NOTES

(1) Where:
* = current issue status applicable to the relevant BIST package.
xx = undefined characters.
yyyy = copyright year value, e.g., 1994.
(2) This paragraph is not seen when run in ‘Operator Controlled Bist’.

HAT(E) Annex I
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX J

CONSOLE OPERATOR-CONTROLLED EXTENDED BIST LIST

Test iteration 1 of 1
001 SBC MPE Status Report Iss * (E) C0000007 PASSED
002 SBC BIST Iss * (E) xxC03FFFFF PASSED
003 System BIST 310/FU/04614/000 Iss * (E) 00000001 PASSED
004 Control Grip Iss * (E) C000007F PASSED
005 CRR-2 FLASH Iss * (E) C0000081 PASSED
006 Slave Test Control (ENET-1) Iss * (E)
<01>
<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *
<01> Copyright GEC-Marconi Ltd yyyy
<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
Extended auto run invoked
<01> 001 ENET-1 MPE Status Report Iss * (E) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (E) C00001FF PASSED
<01> 003 APEX 100 Network controller Iss * (E) C000003F PASSED
Slave processor overall status is ..... (E) C000019F PASSED
007 CRR-2 SRAM Iss * (E) C0000019 PASSED
008 Slave Test Control (PME68-42) Iss * (E)
<02>
<02> Resident SBC BIST 310/FL/04551/000 Iss *
<02> Copyright Alenia Marconi Systems Ltd yyyy
<02> 001 SBC MPE Status report Iss * (Q) C0000007 PASSED
<02> 002 SBC BIST Iss * (Q) C01F7FEB PASSED
<02> 003 Sub-system BIST 310/FU/04614/000 Iss * (Q) 00000001 PASSED
<02> 004 Keyboard and Rolling Ball Iss * (Q) C000007F PASSED
<02> 005 C.A.T. card BIST Iss * (Q) C00000FF PASSED
<02> 006 Vantage II card BIST Iss * (Q) C1FCED9F PASSED
<02> 007 Virgo ++ card BIST Iss * (Q) C000036F PASSED
Extended auto run invoked
<02> 001 SBC MPE Status report Iss * (E) C0000007 PASSED
<02> 002 SBC BIST Iss * (E) C03FFFFF PASSED
<02> 003 Sub-system BIST 310/FU/04614/000 Iss * (E) 00000001 PASSED
<02> 004 Keyboard and Rolling Ball Iss * (E) C000007F PASSED
<02> 005 C.A.T. card BIST Iss * (E) C00000FF PASSED
<02> 006 Vantage II card BIST Iss * (E) C1FEFFFF PASSED
<02> 007 Virgo ++ card BIST Iss * (E) C00003FF PASSED
Slave processor overall status is ..... (E) C00001FF PASSED
009 System Interrupt Generator Iss * (E) FFFFFFFF PASSED
BIST run completed
bist>
NOTE
* = current issue status applicable to the relevant BIST package.
xx = undefined characters.
yyyy = copyright year value, e.g., 1994.

HAT(E) Annex J
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX K

EAU/010 (ASYNC) OPERATOR-CONTROLLED EXTENDED BIST LIST

Test iteration 1 of 1
001 SBC MPE Status Report Iss * (E) C0000007 PASSED
002 SBC BIST Iss * (E) xxC03FFFFF PASSED
003 System BIST 310/FU/04575/000 Iss * (E) 00000001 PASSED
004 CRR-2 FLASH Iss * (E) C0000081 PASSED
005 Slave Test Control (ENET-1) Iss * (E)
<01>

<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *


<01> Copyright GEC-Marconi Ltd yyyy

<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
Extended auto run invoked
<01> 001 ENET-1 MPE Status Report Iss * (E) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (E) C00001FF PASSED
<01> 003 APEX 100 Network controller Iss * (E) C000003F PASSED
Slave processor overall status is ..... (E) C000019F PASSED
006 System Interrupt Generator Iss * (E) FFFFFFFF PASSED

BIST run completed

bist>

NOTE

* = current issue status applicable to the relevant BIST package.


xx = undefined characters.
yyyy = copyright year value, e.g., 1994.

HAT(E) Annex K
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX L

EAU/011 (SYNC) OPERATOR-CONTROLLED EXTENDED BIST LIST

Test iteration 1 of 1
001 SBC MPE Status Report Iss * (E) C0000007 PASSED
002 SBC BIST Iss * (E) xxC03FFFFF PASSED
003 System BIST 310/FU/04576/000 Iss * (E) 00000001 PASSED
004 CRR-2 FLASH Iss * (E) C0000081 PASSED
005 Slave Test Control (ENET-1) Iss * (E)
<01>

<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *


<01> Copyright GEC-Marconi Ltd yyyy

<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
Extended auto run invoked
<01> 001 ENET-1 MPE Status Report Iss * (E) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (E) C00001FF PASSED
<01> 003 APEX 100 Network controller Iss * (E) C000003F PASSED
Slave processor overall status is ..... (E) C000019F PASSED
006 System Interrupt Generator Iss * (E) FFFFFFFF PASSED
007 MPCC-1 serial Comms Controller Iss * (E) C0007FFF PASSED

BIST run completed

bist>

NOTE

* = current issue status applicable to the relevant BIST package.


xx = undefined characters.
yyyy = copyright year value, e.g., 1994.

HAT(E) Annex L
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX M

EAU/013 (EOTS) OPERATOR-CONTROLLED EXTENDED BIST LIST

Test iteration 1 of 1
001 SBC MPE Status Report Iss * (E) C0000007 PASSED
002 SBC BIST Iss * (E) xxC03FFFFF PASSED
003 System BIST 310/FU/04578/000 Iss * (E) 00000001 PASSED
004 CRR-2 FLASH Iss * (E) C0000081 PASSED
005 Slave Test Control (ENET-1) Iss * (E)
<01>

<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *


<01> Copyright GEC-Marconi Ltd yyyy

<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
Extended auto run invoked
<01> 001 ENET-1 MPE Status Report Iss * (E) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (E) C00001FF PASSED
<01> 003 APEX 100 Network controller Iss * E) C000003F PASSED
Slave processor overall status is .... (E) C000019F PASSED
006 System Interrupt Generator Iss * (E) FFFFFFFF PASSED
007 Safety Function Iss * (E) C00001FF PASSED

BIST run completed

bist>

NOTE

* = current issue status applicable to the relevant BIST package.


xx = undefined characters.
yyyy = copyright year value, e.g., 1994.

HAT(E) Annex M
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX N

NRTE OPERATOR-CONTROLLED EXTENDED BIST LIST

Test iteration 1 of 1
001 SBC MPE Status Report Iss * (E) C0000007 PASSED
002 SBC BIST Iss * (E) xxC03FFFFF PASSED
003 System BIST 310/FL/04532/000 Iss * (E) 00000001 PASSED
004 CRR-2 FLASH Iss * (E) C0000081 PASSED
005 Slave Test Control (ENET-1) Iss * (E)
<01>

<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *


<01> Copyright GEC-Marconi Ltd yyyy

<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
Extended auto run invoked
<01> 001 ENET-1 MPE Status Report Iss * (E) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (E) C00001FF PASSED
<01> 003 APEX 100 Network controller Iss * (E) C000003F PASSED
Slave processor overall status is ..... (E) C000019F PASSED
006 System Interrupt Generator Iss * (E) FFFFFFFF PASSED
007 Slave Test Control (PME68-41) Iss * (E)
<02>
<02> Resident SBC BIST 310/FL/04551/000 Iss *
<02> Copyright GEC-Marconi Ltd yyyy
<02> 001 SBC MPE Status Report Iss * (Q) C0000007 PASSED
<02> 002 SBC BIST Iss * (Q) C01F7FEB PASSED
<02> 003 Sub-system BIST 310/FU/04532/000 Iss * (Q) 00000001 PASSED
<02> 004 Radar Front End Iss * (Q) C000000F PASSED
<02> 005 Plot Extractor Iss * (Q) C0000FFF PASSED
Extended auto run invoked
<02> 001 SBC MPE Status Report Iss * (E) C0000007 PASSED
<02> 002 SBC BIST Iss * (E) C03FFFFF PASSED
<02> 003 Sub-system BIST 310/FU/04532/000 Iss * (E) 00000001 PASSED
<02> 004 Radar Front End Iss * (E) C000000F PASSED
<02> 005 Plot Extractor Iss * (E) C0000FFF PASSED
Slave processor overall status is ..... (E) C00001FF PASSED

BIST run completed

bist>

NOTE

* = current issue status applicable to the relevant BIST package.


xx = undefined characters.
yyyy = copyright year value, e.g., 1994.

HAT(E) Annex N
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX O

GCP 76MM OPERATOR-CONTROLLED EXTENDED BIST LIST

Test iteration 1 of 1
001 SBC MPE Status Report Iss * (E) C0000007 PASSED
002 SBC BIST Iss * (E) xxC03FFFFF PASSED
003 System BIST 310/FU/04616/000 Iss * (E) 00000001 PASSED
004 CRR-2 FLASH Iss * (E) C0000081 PASSED
005 Slave Test Control (ENET-1) Iss * (E)
<01>

<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *


<01> Copyright GEC-Marconi Ltd yyyy

<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
Extended auto run invoked
<01> 001 ENET-1 MPE Status Report Iss * (E) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss *(E) C00001FF PASSED
<01> 003 APEX 100 Network controller Iss * (E) C000003F PASSED
Slave processor overall status is ..... (E) C000019F PASSED
006 Slave Test Control (PME68-42) Iss * (E)
<02> Resident SBC BIST 310/FL/04551/000 Iss *
<02> Copyright Alenia Marconi Systems Ltd yyyy
<02> 001 SBC MPE Status report Iss * (Q) C0000007 PASSED
<02> 002 SBC BIST Iss * (Q) C01F7FEB PASSED
Extended auto run invoked
<02> 001 SBC MPE Status report Iss * (E) C0000007 PASSED
<02> 002 SBC BIST Iss * (E) C03FFFFF PASSED
Slave processor overall status is ..... (E) C000019F PASSED
007 Safety Function (Set 1) Iss * (E) C00001FF PASSED
008 MPV996A-21 (DTS) Iss * (E) C0000FFF PASSED
009 MPV997A-21 (RTD 1) Iss * (E) C000003F PASSED
010 MPV997A-21 (RTD 2) Iss * (E) C000003F PASSED
011 MPV997A-21 (RTD 3) Iss * (E) C000003F PASSED
012 System Interrupt Generator Iss * (E) FFFFFFFF PASSED

BIST run completed

bist>

NOTE

* = current issue status applicable to the relevant BIST package.


xx = undefined characters.
yyyy = copyright year value, e.g., 1994.

HAT(E) Annex O
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX P

GCP 30MM OPERATOR-CONTROLLED EXTENDED BIST LIST

Test iteration 1 of 1
001 SBC MPE Status Report Iss * (E) C0000007 PASSED
002 SBC BIST Iss * (E) xxC03FFFFF PASSED
003 System BIST 310/FU/04616/000 Iss * (E) 00000001 PASSED
004 CRR-2 FLASH Iss * (E) C0000081 PASSED
005 Slave Test Control (ENET-1) Iss * (E)
<01>

<01> Resident ENET-1 BIST 310/FL/04553/000 Iss *


<01> Copyright GEC-Marconi Ltd yyyy

<01> 001 ENET-1 MPE Status Report Iss * (Q) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (Q) C00000FB PASSED
<01> 003 APEX 100 Network controller Iss * (Q) C000001F PASSED
Extended auto run invoked
<01> 001 ENET-1 MPE Status Report Iss * (E) C0000007 PASSED
<01> 002 ENET-1 Network controller Iss * (E) C00001FF PASSED
<01> 003 APEX 100 Network controller Iss * (E) C000003F PASSED
Slave processor overall status is ..... (E) C000019F PASSED
006 Slave Test Control (PME68-42) Iss * E)
<02>
<02> Resident SBC BIST 310/FL/04551/000 Iss *
<02> Copyright Alenia Marconi Systems Ltd yyyy
<02> 001 SBC MPE Status report Iss * (Q) C0000007 PASSED
<02> 002 SBC BIST Iss * (Q) C01F7FEB PASSED
Extended auto run invoked
<02> 001 SBC MPE Status report Iss * (E) C0000007 PASSED
<02> 002 SBC BIST Iss * (E) C03FFFFF PASSED
Slave processor overall status is ..... (E) C000019F PASSED
007 Safety Function Iss * (E) C00001FF PASSED
008 MPV996A-21 (DTS) Iss * (E) C0000FFF PASSED
009 MPV997A-21 (RTD 1) Iss * (E) C000003F PASSED
010 MPV997A-21 (RTD 2) Iss * (E) C000003F PASSED
011 MPV997A-21 (RTD 3) Iss * (E) C000003F PASSED
012 System Interrupt Generator Iss * (E) FFFFFF1FF PASSED

BIST run completed

bist>

NOTE

* = current issue status applicable to the relevant BIST package.


xx = undefined characters.
yyyy = copyright year value, e.g. 1994.

HAT(E) Annex P
UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX Q

SES TEST 022 TV EXTERNAL TEST PICTURE DESCRIPTION

CONTENTS

Para

1 Description

Fig Page

1 SES Test 022 TV external test picture. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

DESCRIPTION

1 A static test picture is displayed at the start of the test which comprises an unfilled, white
rectangle drawn on a 74% blue background (G = R = 0). This rectangle describes the extent of the
addressable portion of the display.

NOTE
THIS PICTURE IS NOT
TO SCALE.

Fig 1 SES Test 022 TV external test picture

2 Two live TV windows are displayed, window A in the top left of the screen and window B in
the bottom right. Each window is bordered by a white rectangle to show the extent of the TV
window. Each TV window has a resolution of 768 x 575 pixels.

3 The test pattern, selected from either TVDU1 or TVDU2, is displayed in one of the two
windows.

4 A text string is displayed above the centre line which identifies the test picture:
SES TV Input Test
Copyright Alenia-Marconi Systems Ltd

5 Text strings are also displayed below window A and above window B.

HAT(E) Annex Q
UK RESTRICTED Page 1
TP 3541 UK RESTRICTED

6 On pressing <CR>, scaling is applied to both pictures. Both channels can still display a TV
picture, but the pictures are one quarter of their size.

NOTE

It is necessary to move the cable between SKJ and SKH to display both pictures.

HAT(E) Annex Q
Page 2 UK RESTRICTED
UK RESTRICTED TP 3541

HAT(E) ANNEX R

EQUIPMENT DESIGNATIONS WITHIN CWCS

1 The CWCS equipment each have a specific, individual, ‘Node ID’ which is used to select them
for communication over the Ethernet Highway. Table 1 gives the ‘Node ID’ for each piece of CWCS
equipment. This ID is required to be selected/set during STW.

TABLE 1 CWCS EQUIPMENT NODE IDENTITIES (ID)

NODE ID EQUIPMENT
EQUIPMENT DESCRIPTION
Decimal Hex LOCATION

1 01 NAUTIC II CONSOLE OPERATIONS ROOM – PWO


2 02 NAUTIC II CONSOLE OPERATIONS ROOM – TPS
3 03 NAUTIC II CONSOLE OPERATIONS ROOM – APC
4 04 NAUTIC II CONSOLE OPERATIONS ROOM – SPC
5 05 NAUTIC II CONSOLE OPERATIONS ROOM – MGD(B)
6 06 NAUTIC II CONSOLE OPERATIONS ROOM – WCC1
7 07 NAUTIC II CONSOLE OPERATIONS ROOM – WCC2
8 08 NAUTIC II CONSOLE OPERATIONS ROOM – WCC3
9 09 SDDS EAU (TYPE 010) GYRO ROOM
11 0B AWS-9/IFF EAU (TYPE 011) RADAR ROOM
14 0E NRTE OPERATIONS ROOM
16 10 ESM EAU (TYPE 010) OPERATIONS ROOM
17 11 SONAR EAU (TYPE 011) SONAR INSTRUMENT SPACE
18 12 LINK Y EAU (TYPE 010) OPERATIONS ROOM
20 14 GOP EAU (TYPE 010) OPERATIONS ROOM
21 15 TDS-PORT EAU (TYPE 010) ENCLOSED BRIDGE
22 16 TDS-STBD EAU (TYPE 010) CHART ROOM
23 17 EOTS EAU (TYPE 013) FWD TRACKER ROOM
25 19 SAP F EAU-Fwd (TYPE 011) FWD TRACKER ROOM
26 1A SAP A EAU-Aft (TYPE 011) AFT TRACKER ROOM
27 1B DECOY EAU (TYPE 010) ENCLOSED BRIDGE
28 1C 76mm GCP GUN CONTROL ROOM
29 1D 30mm PORT GCP SSGW POWER ROOM
30 1E 30mm STBD GCP SSGW POWER ROOM
32 20 ITL70A EAU (TYPE 011) SSGW POWER ROOM
34 22 COT (ASYNC) (TYPE 010) SSGW POWER ROOM

HAT(E) Annex R
Oct 03 (Amdt 1) UK RESTRICTED Page 1/2
UK RESTRICTED TP 3541

HAT(E) ANNEX S

LIST OF ABBREVIATIONS

A Amp(ere)
AAW Anti Air Warfare
a.c. Alternating Current
ACH Anti-Condensation Heater
ACOS Automatic Change Over Switch
ACP Azimuth Change Pulse
AEW Airborne Early Warning
AGI Auxiliary Gatherer of Intelligence
AMD Advanced Micro Devices
AMS Alenia Marconi Systems
ANSI American National Standards Institution
AOS Angle Of Sight
APC Air Picture Compiler
APEX Advanced Processor Extension bus
ARCU 1802 Autonomous Radar Control Unit
ARP Azimuth Reset Pulse
ASCII American Standard Code for Information Interchange
ASM Anti Ship Missile
ASVW Anti Surface Vessel Warfare
ASW Anti Submarine Warfare
AWS-9 Surveillance Radar
AT Autotrack
AUI Attachment Unit Interface
AVR Analogue Video Receiver
AWG American Wire Gauge

BADL British Aerospace Dynamics Ltd. (a division of British Aerospace Defence Ltd.)
BALMET Ballistic Meteorological (data)
BDA Bridge Display Unit
BIST Built In Self Test
BIT Built In Test
BITE Built In Test Equipment
BP Blind Pilotage
BPO Blind Pilotage Officer
BSM BAE Systems Marine Ltd.

CA Collision Avoidance
CACP Corrected Azimuth Change Pulse
CARP Corrected Azimuth Reference Pulse
CATE Computer Assisted Threat Evaluation
CCG Cartesian Co-ordinate Grid
CCIR Comite Consultatif International Radiophonique
CCITT Comite Consultatif International Telephonique et Telegraphique
CIOS Common Input Output Software
Co & Sp Course and Speed
C of G Centre of Gravity
COG Course Over Ground
COT Combined Operator Trainer
COZ Cross Over Zone
CP Configuration Package (a Software Component of SES)
CPA Closest Point of Approach
CPU Central Processing Unit

HAT(E) Annex S
Oct 03 (Amdt 1) UK RESTRICTED Page 1
TP 3541 UK RESTRICTED

CRT Cathode Ray Tube


CS Command System
CSMA/CD Carrier Sense Multiple Access with Collision Detection
CSMG Course and Speed Made Good
CTT Command Team Training
CWCS Command and Weapon Control System

DAT Digital Audio Tape (magnetic tape cartridge format)


d.c. Direct Current
DLCG Digital Landmass/Coastline Generator (part of RVG)
DLRP Data Link Reference Point
DLYS Data Link Y Subsystem
DMA Direct Memory Access
DOS Disk Operating System
DR Dead Reckoning
DRAM Dynamic Random Access Memory
DRH Dual Redundant Highway
DRMS Distance Root Mean Square
DRP Dual Redundant Protocol

EAU Ethernet Adaptor Unit


ECM Electronic Counter Measures
ECL Emitter Coupled Logic
ECS External Communication System (for Data Link)
EDBM Equipment Datum Bench Mark
EEPROM Electrically Erasable Programmable Read Only Memory
EERAM Electrically Erasable Random Access Memory
EEZ Exclusive Economic Zone
EIA Electronic Industries Associates
ELP Electro Luminescent Panel
EMC Electro Magnetic Compatibility
EMP Electro Magnetic Pulse
EOB End of Buffer
EOL End of Line
EOTS Electro Optical Tracking System
EP Estimated Position
EPROM Electrically Programmable Read Only Memory
ESD Electrostatic Sensitive Device
ESM Electronic Surveillance Measures
ETM Eleapsed Time Meter
EW Electronic Warfare
EWD Electronic Warfare Director

FAT(E) Factory Acceptance Trial (Equipment)


FAT(S) Factory Acceptance Trial (System)
FCA Functional Configuration Audit
FCS Fire Control System
FE Functional Evaluation
FEZ Fighter Engagement Zone
FOC Furthest On Circle
FSI Foundation Services Interface
FWD Forward

GC Game Controller
GFC Gunfire Control
GCP Gunfire Control Predictor
GIU Gun Interface Unit

HAT(E) Annex S
Page 2 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

GMT Greenwich Mean Time (Z or Zulu)


GOP General Operations Plot
GPS Global Positioning System
GRU Grid Reference Unit
GTR General Technical Requirement
GUI Graphics User Interface

HAT(E) Harbour Acceptance Trial (Equipment)


HAT(S) Harbour Acceptance Trial (System)
HAU Heading and Attitude Unit
HCER High Capacity Extended Range
HCI Human Computer Interface
HDLC High-level Data Link Control (protocol)
HE High Explosive
HEI High Explosive – Incendiary
HHCU Hand Held Control Unit (for RVG Control or Maintainer’s Terminal)
HPU Highway Processing Unit
Hz Hertz (cycles per second)

ICAO International Civil Aviation Organisation


ID Identity
IEEE Institute of Electrical and Electronic Engineers
IFF Identification Friend or Foe
II Installation Inspection
IP Internal Protocol
IR Infra Red
ISC Initial Search Course
ISD Initial Search Depth
ISO International Standards Organisation
ISR Initial Straight Run

kg kilogram
kVA kilo Volt Amp
kW kilo Watt

LAN Local Area Network


LANCE Local Area Network Controller for Ethernet
LED Light Emitting Diode
LFH Low Fire Hazard (cable)
LPD Labelled Plan Display
LLA Limiting Lines of (submerged) Approach
LOS Line Of Sight
LRU Line Replaceable Unit

mA milli Amp
MAC Media Access Control (Ethernet)
MART Mean Active Repair Time
MBO Major Bought Out (Sub-contract)
MCMV Mine Counter Measures Vessel
MDSL Marconi Defence Systems Ltd. (now BAE SYSTEMS Defence Systems Ltd.)
ME(F)R Maximum Effective (Firing) Range
MER Maximum Effective Range
MEZ Missile Engagement Zone
MFU Missile Firing Unit
MGD(B) Missile Gun Director (Blind)
MHz mega Hertz
MID Manual Input Device

HAT(E) Annex S
Oct 03 (Amdt 1) UK RESTRICTED Page 3
TP 3541 UK RESTRICTED

MIP Manually Injected Point


MLA Mean Line of Advance
MLD Master Level Datum
mm millimetre
MMI Man Machine Interface
MPE Minimum Processing Environment
m/s millisecond
MSP Master Synchronisation Pulse
MTBF Mean Time Between Failures
MTD Master Training Datum
MTI Moving Target Indication
MTTR Mean Time To Repair
MTU Magnetic Tape Unit
MV Muzzle Velocity

n/a not applicable


NAV Next Average Video
NATO North Atlantic Treaty Organisation
NAUTIS Naval AUTonomous Information System
NAV Navigation
NCS Net Control Station
NES Naval Engineering Standard
NFS Network Filing System
NGS Naval Gunfire Support
Nm Newton metre
nm nautical mile
NRTE Navigation Radar Track Extractor
ns nanosecond
NSP Node Specific Processor

OA Operational Analysis
OCP Operator’s Control Panel (for Data Link Y Subsystem), or
Operational Control Package (a Software Component of SES)
OCU Operator Control Unit for DLYS
OEM Original Equipment Manufacturer
OES Original Equipment Supplier
OMG Ownship Master Grid
OPV Offshore Patrol Vessel
OR Operations (Ops) Room
ORS Ops Room Supervisor
OSG Ownship System Grid
OTC Officer in Tactical Command

PAC Pre-Action Calibration


PATEC Plot and Track Extractor (AWS-9)
PC Personal Computer
PCA Physical Configuration Audit
PEC Panel, Electronic Circuit
PEX Plot Extractor
PF Power Factor
PFHE Pre-Fragmented High Explosive
PGS Prima Graphics Sub-system
PI Pulse Interval
PIB Power Input Box
PIM Position and Intended Movement
PIOD Periperal Input Output Device
PL Plug

HAT(E) Annex S
Page 4 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

PMA Processor Module Assembly


PPI Plan Position Indicator
PRF Pulse Repetition Frequency
PRI Pulse Repetition Interval
PROM Programmable Read Only Memory
PSU Power Supply Unit
PU Participating Unit
PW Pulse Width
PWO Principal Warfare Officer

QAFK Quick Action Function Key


Qty Quantity

RAM Random Access Memory


RBAF Royal Brunei Armed Forces
RBM Rolling Ball Marker
RC Receiver Control
RCAD Radar Control and Distribution Unit
RCP Remote Control Panel
RDDU Radar Data Distribution Unit
RDR Recording for Display Replay
rev/min revolutions per minute
RF Radio Frequency
RFE Radar Front End
RFEI Radar Front End Interface
RFI Radio Frequency Interference
RGB Red Green Blue (separate primary colour video signals)
RH Relative Humidity
RISC Reduced Instruction Set Computer
RN Royal Navy
ROA Recording for Operational Analysis
ROM Read Only Memory
RPM Rounds Per Minute
RR Radar Receiver
RTE Real Time Executive
RTOS Real Time Operating System
RTVDU Radar TV Video Distribution Unit
RU Relay Unit
RV Relative Velocity
RVG Radar Video Generator
RVI Relative Velocity Intercept
RVRS Radar Video Recording System

SAP Seawolf Allocation Processor


SAT Sea Acceptance Trial
SBAR Super Barricade
SBC Single Board Computer
SBU Serial Buffer Unit
SCC System Control Computer for RVG
SCSI Small Computer Systems Interface
SDDS Ship’s Data Distribution System
SDL Sonar Datum Line
SDS System Design Specification
SEC Servo Electronics Cubicle
SEP System Exerciser Package(s) (a Software Component of SES)
SES System Exerciser Software
SFK Special Function Key on Nautis console keyboard

HAT(E) Annex S
Oct 03 (Amdt 1) UK RESTRICTED Page 5
TP 3541 UK RESTRICTED

SGRC Signal Generator Receiver Cabinet (ASW-9)


SHM Ship’s Head Marker
SIG System Interrupt Generator
SIU Safety Inhibit Unit
SITREP Situation Report
SK Socket
SLC Submarine Limiting Course
SLUTT Ship Launched Underwater Transponder Target
SMF System Management Funtions/Facilities
SMH System Monitoring Highway
SPARC Scalable Processor Architecture
SOG Speed Over Ground
SOB Start of Buffer
SOL Start of Line
SPC Surface Picture Compiler, or
Signal Processing Cabinet (AWS-9)
SPI Special Position Indicator (IFF)
SRAM Static Random Access Memory
SRTE Standard Range Test Equipment
SS System Specification
SSGW Surface to Surface Guided Weapon
SSM Surface to Surface Missile
Stdb Starboard
STD Secondary Training Datum
STTE Special-to-Type Test Equipment
STTTE Special-to-Type Trials Test Equipment
STW Setting-To-Work
SVT Signal/Voice Track

TB Terminal Block
TBA To Be Advised
TBD To Be Defined
TCFS Thermofit Cable Feedthrough System
TCP Transmission Control Protocol
TDA Torpedo Danger Area
TDL Tactical Data Link
TDS Target Designation Sight
TDZ Torpedo Danger Zone
TE Threat Evaluation
TED Target editor
TEWA Threat Evaluation and Weapon Assignment
TI Target Indication
TMGU Tracker Missile Guidance Unit
TOV Time Of Validity
TPS Tactical Picture Supervisor
TRR Test Readiness Review
TSA Torpedo Seduction Area
TSI Track Status Indicator
TTG Time To Go
TTI Time To Impact/Interception
TTL Transistor/Transistor Logic
TV Television
TVDU TV Video Distribution Unit
TVRS TV Recording System
TWS Track While Scan

HAT(E) Annex S
Page 6 UK RESTRICTED Oct 03 (Amdt 1)
UK RESTRICTED TP 3541

UPSE Uninterruptable Power Supply Equipment


UTC Universal Time Constant
UTM Universal Transverse Mercator
UTMG Universal Transverse Mercator Grid

V Volt
VA Volt Amp
VCS Versatile Console System
VDU Visual Display Unit
VECTAC Vectored Attack (by Torpedo-carrying helicopter)
VLCC Very Large Crude Carrier, i.e., supertanker
VME Versa Module European
VSB VME Subsystem Bus

W Watt
WA Weapon Assignment
WASP Weapon Auxiliary Switching Panel
WC Weapon Controller
WCC Weapon Control Console
WGS84 World Geodetic System 1984

µs microsecond

HAT(E) Annex S
Oct 03 (Amdt 1) UK RESTRICTED Page 7/8