Daily Report 21-Mar-2024

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

PROJET : UCB MUNGO BREWERY

PHASE 1 : GENERAL EARTHWORKS

__________________________________________________________________________________

Daily site report

CONTRACTOR: CAMBUILD SARL BTP


Date : 21/03/2024 Site : KSA MUNGO Sheet N° : 49
Beginning hour : End time : Duration Comments

8 :30 a.m. 2 :00 p.m. 5hr30 1 hr break from 1 :00 p.m to 2 : 00 p.m

Atmospheric weather rain wind


1
conditions Good (cloudy)
People who Names : Hour
visited the site
2

Stoppage of Period: Cause :


3
construction
Equipment Number Condition Equipment Number Condition
Excavator 03 01 off Grader 02 01 off
Bulldozer 02 01 off Compactor 02 off
Construction site
4 Backhoe 01 broken Water tank 00 demobilized
equipment
loader down
Truck 04 Good H. Hammer / /
Autre : Total station and levels for topographic survey
Type Number Type Number
Work supervisor 01 meter 01
Head site 01 Pointer 01
QHSE officer 01 Machine operator 08
5 Human means
Head topography 01 Truck driver 03
Topographer 03 Laboratory team 01
Topographer help 03 storekeeper 01
Earthwork manager 01 Labourer 05
Work completed U Qty Position Team
Continued backfilling PF1 earthwork
Continued cut and fill PF4 earthwork
Adjustment of the Axis 1 car park: from PF2 earthwork
KP 0+320 to KP 0+384.31 (end)
6 Daily activities
Layout for adjustment of the Axis 1 PF2 Topo
from KP 0+260 to KP 0+300 and KP
0+330 to KP 0+440.
Layout of earthworks in the mangrove PF2 Topo
Spoil deposited for mangrove fill PF2 earthwork
Progress of work
and comments
7 /
from the
contractor
8 External control

___________________________________________________________________________
Daily report of 21/03/2024
1
PROJET : UCB MUNGO BREWERY
PHASE 1 : GENERAL EARTHWORKS

__________________________________________________________________________________

Topographic Checking the layout for adjustment of the Axis 1 from KP 0+260 to KP 0+300 and KP 0+330
control to KP 0+440.

External control
Geotechnical
9
control
Nothing to report.

11 Incident or others

1-start of work at 08:30 with an excavator and a Monitoring Engineer


tipper truck;
2- Work stopped without justification from 14:00 to
Observations of 17:30.
10
Engineering 3- repeated delays in carburation (starting at NDINDJOCK Jacques M.
08:30)
4-mobilising the tanker truck for spraying the
backfill layers.

Representative of contractor Representative of Engineering Representative of Project Owner


GODWILL KASE, work supervisor NDINDJOCK Jacques Martial,
Monotoring Engineer.

STATE OF THE DAY'S CONSTRUCTION SITE IN PICTURES

Layout of earthworks in the mangrove at the PF2. Layout for adjustment of the Axis 1 from KP 0+260 to KP
0+300 and KP 0+330 to KP 0+440 at the PF2.

Layout for adjustment of the Axis 1 from KP 0+260 to KP Spoil deposited for mangrove fill at the PF2.
0+300 and KP 0+330 to KP 0+440 at the PF2.

___________________________________________________________________________
Daily report of 21/03/2024
2
PROJET : UCB MUNGO BREWERY
PHASE 1 : GENERAL EARTHWORKS

__________________________________________________________________________________

STATE OF THE DAY'S CONSTRUCTION SITE IN PICTURES

Continuation of the backfill at PF1.

___________________________________________________________________________
Daily report of 21/03/2024
3