101. Raw material can be classified in which of the below broad categories?
A. Agricultural Products, Mineral Products, Live Stock & Forest Products, Marine Products
B. Agricultural Products, Plastic Products, Industrial Products, Forest and Marine Products
C. Agricultural Products, Mineral Products, Industrial Products, Marine Products
D. Agricultural Products, Mineral Products, Industrial Products, Live Stock and Forest Products
Answer:A
108. While calculating cost of imported machinery, which of the below needs to be
considered?
A. FOB Value
B. Shipping, Freight and Insurance Cost
C. Import Duty
D. All of the Above
Answer:D
116. The prices of material inputs are defined in CIF? What does CIF stand for?
A. Cost, Investment and Fuel
B. Current Investment Flows
C. Cost, Insurance and Freight
D. Cost, Incentive and Freight
Answer:C
121. The analysis of funds can be called an analysis of the working capital.
A. True
B. False
C. none
D. none
Answer:A
126. The liabilities side of the balance sheet shows the sources of finance employed
by the business.
A. True
B. False
C. none
D. none
Answer:A
130. Usually assets which are financed with the Term Loan provide as a prime
security against the Term Loan
131. As a part of Term Loan Procedure the detailed appraisal of project covers
A. Marketing Aspects
B. Technical Aspects
C. Financial Aspects
D. All of the Above
Answer:D
139. Which one of the following was not set up with a motive of industrial finance?
A. SIDBI
B. IDBI
C. IFCI
D. IFFCO
Answer:D
155. When a company has been financed by consortium of banks, who has to
report to BIFR about the sickness?
A. Lead Bank
B. Participating Banks
C. Company
D. None of the Above
Answer:A
156. Managers should manage their firm’s resources with the prime objective of
_______
A. Employee Satisfaction
B. Fulfillment of Tax Obligations
C. Enhancing the firm’s Market Value
D. None of the Above
Answer:C
159. What is the term for organisational development through a formally designed
organisational structure?
A. Organic
B. Mechanistic
160. How can organisational structures that are characterised by democratic and
inclusive styles of management be described?
A. Hierarchical
B. Bureaucratic
C. Flat
D. Functional
Answer:C
162. What is the term for an autonomous business entity within an overall
corporate enterprise which is set apart from other areas of the business?
A. Subsidiary
B. Strategic partnership
C. Strategic alliance
D. Strategic business unit
Answer:D
167. Constructive and destructive conflict are distinguished from each other in
which of the following ways?
A. constructive conflict is We-oriented; destructive conflict is Me-oriented
B. constructive conflict is characterized by de-escalation of the conflict; destructive conflict is
characterized by escalation of the conflict
C. constructive conflict is characterized by cross-complaining; destructive conflict is characterized
by flexibility
D. both a and b
Answer:D
168. Constructive and destructive anger can be distinguished from each other by
the
A. intensity of the anger
B. flexibility of the anger
C. duration of the anger
D. both a and c
171. Conflict is
A. an unavoidable fact of life
B. sometimes constructive
C. a destructive force in relationships if continually avoided
D. all of the above
Answer:D
177. The five stages of the coping cycle are (in order):
A. Denial, defence, discarding, adaptation, internalization
B. Defence, denial, discarding, adaptation, internalization
C. Denial, resistance, discarding, adaptation, internalization
D. Denial, defence, resistance, adaptation, internalization
Answer:A
181. Which of the following are key components of a Total Quality Management
system?
A. Individual responsibility, incremental improvement, use of raw data
B. Collective responsibility, continual improvement, use of raw data
C. Group responsibility, staged improvement, knowledge
D. Involves everyone, continual improvement, use of data and knowledge
Answer:D
182. What is the term for the monitoring of events both internal and external to the
organisation that affects strategy?
A. Operational control
B. Strategic surveillance
C. Strategic control
D. Environmental scanning
Answer:B
184. "How will conflicts over resources/facility usage between this and other
projects be settled?", is critically settled at level
A. Main program
B. Project formation
C. Project Buildup
D. Project Buildup
Answer:B
187. Projects provide an excellent growth environment for future executives and
for developing
A. Sales skills
B. Manufacturing skills
C. Managerial skills
190. What would be the critical path if the duration of activity C increased to 10?
A. ABCF
B. ABCEF
C. ABGHIF
D. ABGHIF & ABDEF
Answer:A
197. Resource requirement in project becomes constant while the project is in its
_____ progress stage.
A. 40 to 55%
B. 55 to 70%
C. 70 to 80%
199. Considers the total cost of ownership, or development plus support costs, for a
project.
A. Learning Curve Theory
B. Life Cycle Costing
C. Parametric Modeling
D. Rate of Performance
Answer:B
200. A time-phased budget that project managers use to measure and monitor cost
performance.
A. Cost Baseline
B. Cost Budgeting
C. Cost Estimating
D. Cost Variance
Answer:A