309. A project is typically defined in terms of scope, time, cost and which other
parameter?
A. Benefits.
B. Quality.
C. Tolerance.
D. Controls.
Answer:B
311. Which of the following is NOT a project management cause of failed projects?
A. shortcuts taken during the project
B. lack of or imprecise targets
C. inadequate systems analysis and design tools
D. budget overruns
Answer:C
313. The process each manager follows during the life of a project is known as
A. Project Management
B. Manager life cycle
C. Project Management Life Cycle
D. Product management
Answer:C
315. Which of the following is incorrect activity for the configuration management
of a software system?
A. Internship management
318. A _________ is developed using historical cost information that relates some
software metric to the project cost.
A. Algorithmic cost modelling
B. Expert judgement
C. Estimation by analogy
D. Parkinson’s Law
Answer:A
319. Which technique is applicable when other projects in the same analogy
application domain have been completed?
A. Algorithmic cost modelling
B. Expert judgement
C. Estimation by analogy
D. Parkinson’s Law
Answer:C
320. Which of the following states that work expands to fill the time available.
321. Which model is used during early stages of the system design after the
requirements have been established?
A. An application-composition model
B. A post-architecture model
C. A reuse model
D. An early design model
Answer:A
322. The team is responsible for exchange of information and process guidence
either to or from project practitioners.
A. Software engineering process authority.
B. Software engineering environment
C. Project administration
D. Project review
Answer:A
323. _________is the critical factor in understanding how to plan and execute a
software development project.
A. Process flexibility
B. Architecture
C. Risk resolution
D. Domain experience
Answer:D