SOFEA

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID WBS Task Task Name Duration Start Finish Predecessors

Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024


Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 1 Construction of New 30.2 wks? Thu 1/6/23 Sat 30/12/23
Bukit Katil Link Road
2 1.1 Project Start 1 day Thu 1/6/23 Thu 1/6/23
3 1.2 Preliminaries 10 wks Fri 2/6/23 Fri 11/8/23
4 1.2.1 Establish and 3.4 wks Fri 2/6/23 Sat 24/6/23
removal of site
office (initial on
completion)
5 1.2.2 stockpile of 3.4 wks Mon 26/6/23 Wed 19/7/23
gravel
6 1.2.3 Progress Report 3.4 wks Thu 20/7/23 Fri 11/8/23

7 1.3 Site Clearing 1.8 wks Sat 12/8/23 Wed 23/8/23


8 1.4 Road Works 15 wks Thu 24/8/23 Thu 7/12/23
9 1.4.1 Subgrade 3.4 wks Thu 24/8/23 Mon 18/9/23
10 1.4.2 Base course 1.8 wks Tue 19/9/23 Fri 29/9/23
11 1.4.3 Premix work 3.4 wks Sat 30/9/23 Mon 23/10/23
12 1.4.4 Line marking 3.2 wks Tue 24/10/23 Tue 14/11/23
works
13 1.4.5 Road 3.4 wks Wed 15/11/23 Thu 7/12/23
accessories
14 1.5 Testing and 1.6 wks Fri 8/12/23 Tue 19/12/23
commisioning
15 1.6 Project Finish 1.8 wks Wed 20/12/23 Sat 30/12/23

Task Project Summary Manual Task Start-only Deadline

Project: SOFEA Split Inactive Task Duration-only Finish-only Progress


Date: Tue 23/5/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1