Professional Documents
Culture Documents
Performance - Manual - Exc - B - Series (1) (1) RENDIMIENTO VOLVO
Performance - Manual - Exc - B - Series (1) (1) RENDIMIENTO VOLVO
Performance - Manual - Exc - B - Series (1) (1) RENDIMIENTO VOLVO
PERFORMANCE MANUAL
Contents
Introduction 4
Production estimation 8
Cost calculation 10
Appendix-Material property 13
3
Introduction
Preface
This manual is intended as an aid for planners, Since working conditions vary so widely between
estimators and machine owners in forecasting the different operating sites, it has not been possible to
cycle time, production and cost for performing bulk take into account all the factors affecting performance
movement of materials with Volvo excavators. and cost; therefore, we cannot accept responsibility for
any differences that may arise between calculations
The results gained by using the manual can be and actual results.
regarded as fully reliable, provided that the nature of
the ground and other factors are correctly evaluated To make proper use of this manual, a certain
and that the operator is of normal competence. amount of experience in the planning of bulk movement
of materials, time studies and technical terms occurring
in the business are necessary.
4
Cycle time estimation
Excavation Classes
Clearly, the performance of an excavator will filling the bucket. Excavation classes are therefore
depend on the kinds of material to be excavated. a way of categorizing ground conditions (see table
The harder or tougher the material, the longer it below). Problems such as underground services,
takes to fill the bucket and the longer it takes to trench support systems and men working close to
perform the cycle. Categorizing different ground the bucket can slow the bucket filling operation
conditions is not easy, and everyone will have their regardless of the nature of the excavated material,
own opinions on the matter. Nevertheless, it is and therefore affect cycle times. The following table
useful to communicate the degree of difficulty in may be used as a guide.
Loading position
Can be represented by 4 positions.
- Hauler is below the excavator and swings 45° to load hauler
- Hauler is below the excavator and swings 90° to load hauler
- Hauler and excavator are on the same level and swing 90° to load hauler
- Hauler and excavator are on the same level and swing 180° to load hauler
5
Cycle time estimation
Assumptions
- The power mode set: G mode ~ H mode
- Digging depth or the bench height: 40% ~ 70% of max. digging depth
- A competent operator
- No obstacles interfering with loading of the hauler
Cycle time with hauler below the excavator and swing angle at 45 degrees unit: sec
Excavation material class
Model
1 2 3 4
EC140B 6.9 ~ 9.4 7.9 ~ 10.4 9.4 ~ 11.9 10.4 ~ 13.3
EC160B 7.7 ~ 10.2 8.7 ~ 11.2 10.2 ~ 13.0 11.4 ~ 14.7
EC180B 7.7 ~ 10.2 8.7 ~ 11.2 10.2 ~ 13.0 11.4 ~ 14.7
EC210B 9.5 ~ 12.0 10.5 ~ 13.0 12.0 ~ 15.5 13.5 ~ 17.5
EC240B 9.5 ~ 12.5 11.0 ~ 13.5 12.5 ~ 16.0 14.0 ~ 18.0
EC290B 9.5 ~ 12.5 11.0 ~ 14.0 12.5 ~ 16.0 14.0 ~ 18.0
EC330B 9.7 ~ 12.6 11.2 ~ 14.6 12.6 ~ 16.0 14.1 ~ 18.0
EC360B 9.7 ~ 12.6 11.2 ~ 14.6 12.6 ~ 16.0 14.1 ~ 18.0
EC460B 10.2 ~ 13.5 11.6 ~ 14.9 13.0 ~ 17.2 14.9 ~ 19.6
Cycle time with hauler below the excavator and swing angle at 90 degrees unit: sec
Excavation material class
Model
1 2 3 4
EC140B 7.9 ~ 10.4 8.9 ~ 11.4 9.9 ~ 12.9 11.4 ~ 14.3
EC160B 8.6 ~ 11.4 9.7 ~ 12.5 10.7 ~ 14.0 12.4 ~ 15.8
EC180B 8.6 ~ 11.4 9.7 ~ 12.5 10.7 ~ 14.0 12.4 ~ 15.8
EC210B 10.0 ~ 13.5 11.5 ~ 15.0 12.5 ~ 16.5 14.5 ~ 19.0
EC240B 11.5 ~ 14.5 13.0 ~ 16.0 14.0 ~ 18.0 16.0 ~ 20.0
EC290B 12.0 ~ 15.0 13.5 ~ 16.5 14.0 ~ 18.0 16.0 ~ 20.5
EC330B 12.1 ~ 15.5 13.6 ~ 17.5 15.1 ~ 18.9 17.0 ~ 21.9
EC360B 12.1 ~ 15.5 13.6 ~ 17.5 15.1 ~ 18.9 17.0 ~ 21.9
EC460B 13.0 ~ 16.8 14.9 ~ 18.6 16.3 ~ 20.5 18.6 ~ 23.3
6
Cycle time estimation
Cycle time with hauler and excavator on same level and swing angle at 90 degrees unit: sec
Excavation material class
Model
1 2 3 4
EC140B 8.9 ~ 12.4 9.4 ~ 13.3 9.9 ~ 13.8 11.4 ~ 15.8
EC160B 9.7 ~ 13.4 10.2 ~ 14.4 10.9 ~ 14.9 12.4 ~ 17.0
EC180B 9.7 ~ 13.4 10.2 ~ 14.4 10.9 ~ 14.9 12.4 ~ 17.0
EC210B 11.5 ~ 15.5 12.0 ~ 16.5 13.0 ~ 17.0 14.5 ~ 19.5
EC240B 12.0 ~ 15.5 12.5 ~ 16.5 13.5 ~ 17.0 15.5 ~ 19.5
EC290B 12.5 ~ 16.0 13.0 ~ 17.0 14.0 ~ 17.5 16.0 ~ 20.0
EC330B 13.1 ~ 17.5 14.1 ~ 18.5 14.6 ~ 18.9 17.0 ~ 21.9
EC360B 13.1 ~ 17.5 14.1 ~ 18.5 14.6 ~ 18.9 17.0 ~ 21.9
EC460B 14.4 ~ 17.7 14.9 ~ 18.6 15.8 ~ 19.6 18.2 ~ 22.3
Cycle time with hauler and excavator on same level and swing angle at 180 degrees unit: sec
Excavation material class
Model
1 2 3 4
EC140B 10.9 ~ 14.3 11.4 ~ 15.3 12.4 ~ 15.8 13.3 ~ 17.3
EC160B 11.9 ~ 15.7 12.4 ~ 16.7 13.4 ~ 17.3 14.5 ~ 19.0
EC180B 11.9 ~ 15.7 12.4 ~ 16.7 13.4 ~ 17.3 14.5 ~ 19.0
EC210B 14.0 ~ 18.5 14.5 ~ 19.5 15.5 ~ 20.5 17.0 ~ 22.5
EC240B 15.0 ~ 19.0 15.5 ~ 20.0 16.5 ~ 21.5 18.0 ~ 23.5
EC290B 15.5 ~ 19.5 16.0 ~ 20.5 17.0 ~ 22.0 18.5 ~ 24.0
EC330B 16.0 ~ 20.4 17.0 ~ 21.4 18.0 ~ 22.3 19.4 ~ 24.8
EC360B 16.0 ~ 20.4 17.0 ~ 21.4 18.0 ~ 22.3 19.4 ~ 24.8
EC460B 15.8 ~ 20.9 16.8 ~ 21.9 17.7 ~ 23.3 19.6 ~ 25.1
7
Production estimation
Production estimation
The producted volume per hour can be detemined by the following formula.
Hourly production (m3/h) =3.6 x Bucket volume (l) x Bucket fill factor x Job efficiency / Cycle time (sec)
(yd3 /h) =3,600 x Bucket volume (yd3 ) x Bucket fill factor x Job efficiency / Cycle time (sec)
Job efficiency
is the actual working time rate per 1 hour.
Example
How much is the production per hour for EC210B with 920 l, 1.20 yd3 K-Bucket?
Excavation class is 2 and the loading position is above the hauler and 90° swing.
Get the average cycle time from the table: 13.3 sec
Bucket fill factor is 1.0 and assume the actual working time as 50 min. per hour.
The production per hour will be 3.6 x 920 x 1.0 x 0.83 / 13.3 = 207 m3/h
3,600 x 1.20 x 1.0 x 0.83 / 13.3 = 270 yd3 /h
8
Production estimation
9
Cost calculation
Cost input
Input valves for hourly cost estimation Formula
e. Interest rate %
10
Cost calculation
Cost calculation
Machine
A. Owning cost per hour Formula
Depreciation d
__
o
Interest f
__
o
g
__
Machine tax o
Insurance h
__
o
Fuel ixj
Oil kxl
11
Cost calculation
Fuel consumption
The power mode set: G mode ~ H mode
The hourly fuel consumption is estimated in the
table below using three different working conditions.
Working conditions:
- Light work: Easy digging conditions with 40% digging of the daily working hour.
- Medium work: Medium digging conditions with 60% digging of the daily working hour.
- Heavy work: Hard digging conditions with 90% digging of the daily working hour.
12
Appendix-Material property
Compacted volume
Fig. 1
Bank volume (Bm3, Byd3 ) is the undisturbed Compacted volume (Cm3, Cyd3 ) is the
material in the ground, before excavation. Note that volume of the materials after leveling and compaction
the volume that is actually excavated often is some- on the site. This volume is smaller than the loose,
what larger than the one calculated from drawings. and can be either larger or smaller than the bank
volume depending on the material properties. As for
Loose volume (Lm3, Lyd3 ) is the volume of the bank volumes, it is important to note that the actual
material when it is loaded on the transport machine. filled volume often is larger than the volume calcu-
The loose volume is larger than the bank volume lated from drawings.
since the material expands when excavated, this
difference is called swell. The graph below shows an example of how the
volume of material can vary during excavation and
transport (Fig. 2).
Volume Transport
Swell Compacted
Bank Loading
Blasting
13
Appendix-Material property
Density
The relationship of the weight of a material to its Density and swell of a material vary with grain size
volume is called density. and moisture content. To make an accurate
determination of density and swell, measurements
WEIGHT have to be made on the site, but rough estimates
DENSITY = __________
VOLUME can be made from table 1-4.
Density is expressed in kg/m3, lb/yd3 . The graph below shows an example of how the
Density of the same material may be different density of a material can vary during excavation and
depending on whether it is in the bank, loose or transport (Fig. 3.)
compacted form. The difference is noted by using
the same abbreviations as for volumes, e.g. 1,700
kg/L3, lb/Lyd3 means that one loose cubic yard
(meter) of the material weight 1,700 kg, 2,870 lb.
Density
Blasting
Bank Loading
Compacted
Loose
14
Appendix-Material property
Swell
When soil and rock materials are loaded into a Volume changes:
dumper, the volume increases due to expansion of LOOSE VOLUME = BANK VOLUME x SWELL
the material. This increase is called swell. This is
usually expressed as a swell-factor which is the LOOSE VOLUME
loose volume divided by the bank volume, see BANK VOLUME = _________________
SWELL
below, but it can also be expressed as a percent-
age. For conversions between bank and loose Density changes:
BANK DENSITY
forms, the following formulas are used. LOOSE DENSITY = _________________
SWELL
LOOSE VOLUME BANK DENSITY = LOOSE DENSITY x SWELL
SWELL = _________________
BANK VOLUME
Example:
Dry clay has a bank density of 1,700 kg/Bm3, 2,870 lb/Byd3 and the swell-factor 1.3
(it swells 30%)
1,700
LOOSE DENSITY = ________ = 1,308 kg/Lm3, 2,208 lb/Lyd3
1.3
What is the weight of a full load in a 16.5 m3, 21.6 yd3 dumper-body:
If 75,000 Bm3, 98,100 Byd3 are to be excavated, how many Lm3, Lyd3 are to be transported?
LOOSE VOLUME = 75,000 Bm3 x 1.3 = 97,500 Lm3, 98,100 Byd3 x 1.3 = 127,530 Lyd3
15
Appendix-Material property
Material density
Bank volume Loose volume Swell-
Material kg/m3 lb/yd3 kg/m3 lb/yd3 factor
Clay
dry 1,640 2,750 1,170 1,950 1.4
moist 2,100 3,550 1,500 2,550 1.4
dry with gravel 1,660 2,800 1,424 2,400 1.2
wet with gravel 1,840 3,100 1,660 2,750 1.2
compact 2,017 3,400 1,660 2,750 1.2
Soil
dry 1,100 1,850 960 1,600 1.2
moist 2,100 3,550 1,680 2,850 1.3
mixed with sand/gravel 1,660 2,800 1,420 2,400 1.2
stony (25% stones) 1,960 3,300 1,570 2,650 1.3
Sand
dry 1,600 2,700 1,420 2,400 1.1
moist 2,070 3,500 1,840 3,100 1.1
dry with gravel 1,930 3,250 1,720 2,900 1.1
wet with gravel 2,230 3,750 2,020 3,400 1.1
Gravel
dry 1,470 2,500 1,330 2,250 1.1
wet 2,340 3,950 2,130 3,600 1.1
Rocks and minerals
granite 2,970 5,000 1,980 3,350 1.5
limestone 2,640 4,450 1,590 2,700 1.7
sandstone 2,400 4,050 1,440 2,450 1.7
crushed stone 2,670 4,500 1,620 2,750 1.7
gypsum 2,580 4,350 1,980 _ 1.3
Ores
iron ore 2,760 4,650 2,340 3,950 1.2
copper ore 2,600 4,400 2,200 3,700 1.2
zinc ore 3,000 5,050 2,500 4,200 1.2
Other material
slag 1,700 2,850 1,020 1,700 1.7
cement 1,540 2,600 1,400 2,350 1.1
These weights are only approximate, the densities vary with moisture content, grain size, etc.
Test must be carried out to detemine exact material characteristics.
16
Appendix-Bucket capacity rating
Struck capacity
Volume actually enclosed inside the outline of the
sideplates and rear and front bucket enclosures
without any consideration for any material supported
or carried by the spillplate or bucket teeth.
1 1
1 1
1 1
1 1
Strike
Heaped off
plane Struck
capacity
capacity
Heaped capacity
Volume in the bucket under the strike off plane plus
the volume of the heaped material above the strike
off plane, having an angle of repose of 1:1 without
any consideration for any material supported or
carried by the spillplate or bucket teeth.
The Committee on European Construction
Equipment (CECE) rates heaped bucket pay loads
on a 2:1 angle of repose for material above the
strike off plane.
17
Appendix-Digging force calculation
18
Note
19
All products are not available in all markets. Under our policy of continuous improvement, we reserve the right to change specifications
and designs without prior notice. The illustrations do not necessarily show the standard version of the machine.