TRANSFORMER 150MVA

Sr. No. Stage Tentative Date Of Completion Actual Date Of Completion


1 Shunt fitting 15.01.2024 15.01.2024
2 Cover Hole Matching 17.01.2024 17.01.2024
3 Visual 17.01.2024
4 1st coat of MIO 18.01.2024 17.01.2024
5 2nd coat of MIO 20.01.2024 18.01.2024
6 1st coat of finish paint 21.01.2024 19.01.2024
7 2nd coat of finish paint 23.01.2024 20.01.2024
8 DFT Checking 24.01.2024 20.01.2024
9 Matching Item's 24.01.2024 20.01.2024
10 Dispatch 25.01.2024 20.01.2024

1 BOM 16.01.2024 17.01.2024


Leakage test on
2 17.01.2024 TO 20.01.2024
conservator & Pipe line
3 Shot Blasting 21.01.2024
4 1st coat Primer 21.01.2024
5 Visual 22.01.2024 TO 23.01.2024
6 1st coat of MIO 24.01.2024 TO 25.01.2024
7 2nd coat of MIO 27.01.2024
8 1st coat Finish Paint 28.01.2024
9 2nd Coat Finish Paint 29.01.2024
10 DFT Checking 30.01.2024
11 Matching Item's 30.01.2024
12 Dispatch 31.01.2024
50MVA
Current Status Remarks
Complete
Complete
In-process

KN
TA
Complete

ER
Complete

RM
Complete

FO
In-process plan for today

NS
A
Complete

TR
In-process
Schedule
for today

Complete
In-process plan for today

ES
I
OR
SS
CE
AC