Professional Documents
Culture Documents
H-6745 00 Gma 00 001 Fe A
H-6745 00 Gma 00 001 Fe A
H-6745 00 Gma 00 001 Fe A
H-674500GMA00001FE /D Page 2 of 12
POWER SYSTEMS
Table of contents
H-674500GMA00001FE /D Page 3 of 12
POWER SYSTEMS
1 PURPOSE OF DOCUMENT
The purpose of this document is to define the following objectives for the Drainage &
dewatering system for HULU TERENGGANU HEP:
• Input parameters for design
• System and operation general description
• Major technical features
• Design and selection criteria.
• Equipment main data & basic arrangement layout
2 REFERENCE DOCUMENTS,
Reference shall be taken from following documents:
H-674500GMA00001FE /D Page 4 of 12
POWER SYSTEMS
3 INPUT PARAMETERS
H-674500GMA00001FE /D Page 5 of 12
POWER SYSTEMS
• Accidental leakages:
1. Exceptional firewater flow from Hydrant system: 114 m3/hr for 2 Hydrants.
The total pumping design capacity of the drainage system shall be considering the calculated seepage
plus normal leakage for two units, turbine floor drainage/leakage and accidental fire water as
D mentioned above during normal operation.
4.1.2 SYSTEM DESCRIPTION
This system consists of:
• Two (2nos.) (1 working + 1 stand-by) submersible bottom suction centrifugal type drainage
pumps, each having 360 m3/hr discharging capacity,
• One (1no.) submersible bottom suction centrifugal type sump pump, having 36 m3/hr & 37mWC
with 20m flexible hose & cable shall be provided at the bottom of drainage pump pit for cleaning
and maintenance of drainage pit equipments,
• A pipe network to discharge drainage water from Powerhouse drainage pit to the tail race surge
chamber above EL.153.50 m through dedicated discharge pipe,
• One set of isolation valve and non-return valve shall be provided in common discharge header to
connect the hose from portable sump pump,
D
Drainage flow of Powerhouse, main access tunnel, shaft seal, Transformer cavern, Transformer cavern
access tunnel, cable ventilation tunnel, Bus duct galleries (IPB), and auxiliary emergency tunnel shall
be collected in the drainage sump through the civil trench. Drainage pump will be used to remove
seepage & drainage water directed by gravity drains around the power house, seepage, normal
drainage & separated water from oil for turbine floor. The water level in oil side of sump reaches up to
the level of weir wall, this level is maintained in such a way that whenever oil leaks from turbine floor,
D being lighter than water; it floats in oil side of sump over the water surface.
Level switches shall be provided in the water side of drainage pit to give signals for automatic pump
start, stop, emergency stop and alarm for maximum water level in the sump. The Powerhouse
drainage sump shall be located at EL 123.30 m.
The seepage from Transformer cavern, cable ventilation tunnel and tunnel between transformer cavern
& service bay shall be directed towards sump (2000 x 2000 x 2300: LxWxH all in mm) provided in
Transformer cavern. Soak pit (11000 x 7500 x 1200: LxWxH all in mm) shall be provided below each
D Unit Transformer. Both soak pits shall be collectively sized to contain single transformer firefighting
water for 40 minutes and volume of oil contained in single Transformer. Common interconnection pipe
between soak pits and seepage collecting sump shall be provided with motorized valve. In event of fire
in transformer, this motorized valve will be closed by Fire alarm panel. A small pit (1000 x 1000 x
2300: LxWxH) shall be provided to access motorized valve.
Transformer oil / water separation system including piping & any other necessary accessories to
discharge accidental water from fire water demand of transformer deluge system from transformer
access tunnel to out side power house are within CW2 scope of supply/ services.
H-674500GMA00001FE /D Page 6 of 12
POWER SYSTEMS
Suitable oil skimmer of 100 LPH capacity and three hour per day duty cycle shall be provided in order
to remove oil from oil side of drainage pit. A separate portable oil handling pump (having capacity of
6m3/hr) shall be provided in the oil side of drainage pit. Grating for portable oil handling pump shall be
provided by CW2.
Each drainage pump shall be provided with isolation valve, non-return valve, and pressure indicator
and pressure switch at the outlet of pump. Air scouring tap shall be provided in common header. Pipe
shall be designed to have maximum water flow velocity between 3m/sec.
D
Note:
Design and construction of all sumps/pits shall be within CW2 scope of supply/ services.
4.1.3 POWER HOUSE DRAINAGE PIT
• Powerhouse drainage pit size shall be approximately 9600 x 2900 x 4000 mm (including slab
thickness).
• In normal leakage case, Pump shall maintain water level below draft tube floor slab EL 127.30m. .
• Minimum pumping water level for drainage submersible pump is about 0.6m from bottom of pit.
• The proposed distance between level switches to start/stop the pumps are indicated in
H-674500GMA00001FB.
Pump cycle time shall be as follow:
Normal Drainage Seepage Rate in Power House pit: 308.90 m3/hr
One drainage pump flow rate: 360 m3/hr
Pit cross-section area (water side): 7.3 x 2.9 = 21.17 m2
Time before start = Time for filling the sump under normal flow rate up to 1st pump starts
= 0.8 x 21.17 x 60 = 3.29 minute
308.90
Time before stop = Time for emptying under normal flow rate
= Volume in Tank (m3) = 0.8 x 21.17 x 60
(Pump flow - Input flow in sump) m3 (360- 308.90)
D
= 19.89 minute
4.2 POWER HOUSE DEWATERING SYSTEM
Three (3nos.: 2W + 1S) dewatering pumps shall be provided for draft tube dewatering & same pumps
(3 nos.: 2W + 1S) shall be used for tailrace dewatering along with two (2nos.) tailrace dewatering
booster pumps provided at EL.162.0m at Construction adit to surge chamber.
4.2.1 PURPOSE OF THE DRAFT TUBE DEWATERING SYSTEM
The purpose of this system is to dewater turbine draft tube and that portion of the power conduit
below tail race water level when turbine is being dewatered for maintenance purpose.
H-674500GMA00001FE /D Page 7 of 12
POWER SYSTEMS
• Three (3nos.:2W + 1S) dewatering pumps shall be used for tailrace dewatering process,
• Two (2nos.) tailrace dewatering booster pumps shall be provided in Construction Adit to surge
chamber at EL.162.00m,
• A dedicated pipe network from dewatering pump pit of surge chamber to outlet of main access
tunnel at EL.195.50m through tailrace dewatering booster pumps,
• A pressure switch at common suction header of tailrace dewatering booster pump shall be provided,
• The expected tailrace dewatering time shall not be more than 120 hour.
Tailrace dewatering is manual process. Isolation valve at the inlet suction header of tailrace dewatering
booster pumps shall be opened manually & isolation valve at common outlet header for Draft tube
dewatering shall be closed manually before starting dewatering pumps.
Total estimated surge chamber volume = 4930 m3
Total estimated tailrace volume = 65118.5 m3
Each dewatering pump shall be provided with isolation valve, non-return valve, and pressure indicator
and pressure switch at the outlet of pump. Air scouring tap shall be provided in common header. Pipe
shall be designed to have maximum water flow velocity between 3 - 4m/sec.
H-674500GMA00001FE /D Page 8 of 12
POWER SYSTEMS
H-674500GMA00001FE /D Page 9 of 12
POWER SYSTEMS
K
DRAINAGE-OIL/WATER SEPARATOR SUMP LEVEL SELECTION
S.No Level definition Elevation in mtr. Remarks / References
Bottom of sump to Emergency
1 123.30 0.6 Minimum water level required for pump
stop level
Emergency stop level to Normal
2 123.90 0.3 Minimum water level required for pump
stop level
Normal stop level to 1st pump Based on above calculation for Pump cycle
3 124.20 0.8
starts level time
1st pump starts level to 2nd Based on above calculation for Pump cycle
4 125.00 0.8
pump starts level time
5 2nd pumps starts level to HLL 125.80 0.5
S.No Source
Quantity units Remarks / References
Draft tube De-watering volume
A
calculation
1 HRT / Penstock 1691.76 m³
H-674500GMA00001FE /D Page 11 of 12
POWER SYSTEMS
S.No Source
Quantity units Remarks / References
1 Depth 1.2 m
2
Length 1.6 m
3
Width 1.2 m
D
4 Area of sump 1.92 m²
H-674500GMA00001FE /D Page 12 of 12