LNUU (Unit 471) SD Schedule Final July 22 - For Implementation

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 52

11-Jul-22

LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)


Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
LNUU (U471) Shutdown Schedule July'22 456 22-Jul-22 00:00 10-Aug-22 00:00 0

LNUU (Unit-471) SHUTDOWN 456 22-Jul-22 00:00 10-Aug-22 00:00 0

Process Shutdown 74 22-Jul-22 00:00 25-Jul-22 02 :00 75


3 Divert the feed naphtha to RTF/stabilize 0 22-Jul-22 00:00 4, 7, 10 0 Divert the feed naphtha to RTF/stabilize V01
V01
4 Cut off feed to reactor section 2 22-Jul-22 00:00 22-Jul-22 02 :00 3 5, 6, 8 49
7 Cool down up to 60 C & purge the 16 22-Jul-22 00:00 22-Jul-22 16 :00 3 9 0
reactor section continuing gas
10 circulation
Battery limit blinding for positive isolation 20 22-Jul-22 00:00 22-Jul-22 20 :00 3 16, 18 47
5 Draining of V01 upto 20% level 6 22-Jul-22 02:00 22-Jul-22 08 :00 4 18 67
6 Stop recirculation of Naphtha & push 2 22-Jul-22 02:00 22-Jul-22 04 :00 4 18 71
Naphtha to RTF
8 Exchangers bolt easing 24 22-Jul-22 02:00 23-Jul-22 02 :00 4 18 49
9 Depressurize reactor loop gases to 2 Kg 1 22-Jul-22 16:00 22-Jul-22 17 :00 7 11 0

11 Purge the reactor loop with nitrogen 19 22-Jul-22 17:00 23-Jul-22 12 :00 9 12, 14, 0
16
12 Blinding of R01 outlet flange 4 23-Jul-22 12:00 23-Jul-22 16 :00 11 13, 15, 0
17, 111,
134, 151,
168, 205,
14 Blinding of R02 outlet flange 4 23-Jul-22 12:00 23-Jul-22 16 :00 11 224,
15 238, 105
16 Blinding of R03 outlet flange 4 23-Jul-22 12:00 23-Jul-22 16 :00 11, 10 17 31
13 Top elbow Blinding of R01 with N2 blanketing 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 24 0
15 Top elbow Blinding of R02 with N2 blanketing 4 23-Jul-22 16:00 23-Jul-22 20 :00 12, 14 51 105
17 Top elbow Blinding of R03 with N2 4 23-Jul-22 16:00 23-Jul-22 20 :00 12, 16 18, 78, 31
blanketing 1486
18 Stripper loop de-pressurizing / purging 30 23-Jul-22 20:00 25-Jul-22 02 :00 17, 5, 523, 555, 31
with Nitrogen 6, 8, 10 563, 571,
579, 639,
667, 688,
Operation/Maintenance/Inspection Jobs 305 23-Jul-22 16:00 05-Aug-22 09:00 710, 731, 111
Mechanical maintenance jobs 305 23-Jul-22 16:00 05-Aug-22 09:00 111
Reactor R01/R02/R03 Catalyst Replacement Jobs (Scope: 301 23-Jul-22 20:00
03 nos) 05-Aug-22 09:00 0
R01 168 23-Jul-22 20:00 30-Jul-22 20 :00 133
R01 Unloading 54 23-Jul-22 20:00 26-Jul-22 02 :00 0
24 Blinding of reactor connected lines 8 23-Jul-22 20:00 24-Jul-22 04 :00 13 25 0

25 De-torquing of elbow bolts 4 24-Jul-22 04:00 24-Jul-22 08 :00 24 26 0


26 Opening of top elbow 4 24-Jul-22 08:00 24-Jul-22 12 :00 25 27 0
Page 1 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
27 Passivation and lowering of elbow after 1 24-Jul-22 12:00 24-Jul-22 12 :30 26 28 0
passivation from top to bottom reactor

28 Positioning of elbow at ground level and 1 24-Jul-22 12:30 24-Jul-22 13 :00 27 29 0


covering with tarpauline

29 Preparation for vessel entry and initial 1 24-Jul-22 13:00 24-Jul-22 14 :00 28 30 0
gas test
30 Unloading of support material and 30 24-Jul-22 14:00 25-Jul-22 20 :00 29 31 0
catalyst by dumping/shovelling

31 Vacuum cleaning of internals and 6 25-Jul-22 20:00 26-Jul-22 02 :00 30 33 0


inspection
Inspection Activities 52 26-Jul-22 02:00 28-Jul-22 06 :00 0
33 Internal Scaffolding Erection for 8 26-Jul-22 02:00 26-Jul-22 10 :00 31 34 0
Inspection - Confined Space

34 Reactor weld joints (Longitudinal + 24 26-Jul-22 10:00 27-Jul-22 10 :00 33 35 0


circumferential) buffing

35 NDT/UT 12 27-Jul-22 10:00 27-Jul-22 22 :00 34 36 0


36 Internal scaffolding removal - Confined 8 27-Jul-22 22:00 28-Jul-22 06 :00 35 38 0
Space
Loading Preparation 6 28-Jul-22 06:00 28-Jul-22 12 :00 0
38 Preparing for loading of ceramic balls 2 28-Jul-22 06:00 28-Jul-22 08 :00 36 39 0

39 Marking of ceramic balls and catalyst 2 28-Jul-22 08:00 28-Jul-22 10 :00 38 40 0


layers
40 Box up of dump nozzle flange with new 2 28-Jul-22 10:00 28-Jul-22 12 :00 39 42 0
gaskets
R01-Loading 44 28-Jul-22 12:00 30-Jul-22 08 :00 71
42 Loading and leveling of ceramic balls 11 28-Jul-22 12:00 28-Jul-22 23 :00 40 43, 57 0

43 Installation of HDPE Pipes 2 28-Jul-22 23:00 29-Jul-22 01 :00 42 44 71


44 Sock loading of catalyst 31 29-Jul-22 01:00 30-Jul-22 08 :00 43 46, 71 71
Box up activities 12 30-Jul-22 08:00 30-Jul-22 20 :00 133
46 Installation of Top Elbow 4 30-Jul-22 08:00 30-Jul-22 12 :00 44 47 133
47 Torquing of elbow bolts 4 30-Jul-22 12:00 30-Jul-22 16 :00 46 48 133
48 Deblinding of reactor connected lines 4 30-Jul-22 16:00 30-Jul-22 20 :00 47 107 133

Page 2 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
R02 270 23-Jul-22 20:00 04-Aug-22 02:00 31
R02 Unloading 159 23-Jul-22 20:00 30-Jul-22 11 :00 0
51 Blinding of reactor connected lines 8 23-Jul-22 20:00 24-Jul-22 04 :00 15 52 105

52 De-torquing of elbow bolts 4 24-Jul-22 04:00 24-Jul-22 08 :00 51 53 105


53 Opening of top elbow 4 24-Jul-22 08:00 24-Jul-22 12 :00 52 54 105
54 Passivation and lowering of elbow after 1 24-Jul-22 12:00 24-Jul-22 12 :30 53 55 105
passivation from top to bottom reactor

55 Positioning of elbow at ground level and 1 24-Jul-22 12:30 24-Jul-22 13 :00 54 56 105
covering with tarpauline

56 Preparation for vessel entry and initial 1 24-Jul-22 13:00 24-Jul-22 14 :00 55 57 105
gas test
57 Unloading of support material and 30 28-Jul-22 23:00 30-Jul-22 05 :00 56, 42 58, 85 0
catalyst by dumping/shovelling

58 Vacuum cleaning of internals and 6 30-Jul-22 05:00 30-Jul-22 11 :00 57 60 0


inspection
Inspection Activities 52 30-Jul-22 11:00 01-Aug-22 15:00 0
60 Internal Scaffolding Erection for 8 30-Jul-22 11:00 30-Jul-22 19 :00 58 61 0
Inspection - Confined Space

61 Reactor weld joints (Longitudinal + 24 30-Jul-22 19:00 31-Jul-22 19 :00 60 62 0


circumferential) buffing

62 NDT/UT 12 31-Jul-22 19:00 01-Aug-22 07:00 61 63 0


63 Internal scaffolding removal - Confined 8 01-Aug-22 07:00 01-Aug-22 15:00 62 65 0
Space
Loading Preparation 6 01-Aug-22 15:00 01-Aug-22 21:00 0
65 Preparing for loading of ceramic balls 2 01-Aug-22 15:00 01-Aug-22 17:00 63 66 0

66 Marking of ceramic balls and catalyst 2 01-Aug-22 17:00 01-Aug-22 19:00 65 67 0


layers
67 Box up of dump nozzle flange with new 2 01-Aug-22 19:00 01-Aug-22 21:00 66 69 0
gaskets
R02-Loading 41 01-Aug-22 21:00 03-Aug-22 14:00 0
69 Loading and leveling of ceramic balls 8 01-Aug-22 21:00 02-Aug-22 05:00 67 70 0

70 Installation of HDPE Pipes 2 02-Aug-22 05:00 02-Aug-22 07:00 69 71 0


Page 3 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
71 Sock loading of catalyst 31 02-Aug-22 07:00 03-Aug-22 14:00 70, 44 73, 100 0
Box up activities 12 03-Aug-22 14:00 04-Aug-22 02:00 31
73 Installation of Top Elbow 4 03-Aug-22 14:00 03-Aug-22 18:00 71 74 31
74 Torquing of elbow bolts 4 03-Aug-22 18:00 03-Aug-22 22:00 73 75 31
75 Deblinding of reactor connected lines 4 03-Aug-22 22:00 04-Aug-22 02:00 74 107 31

R03 301 23-Jul-22 20:00 05-Aug-22 09:00 0


R03 Unloading 190 23-Jul-22 20:00 31-Jul-22 18 :00 5
78 Blinding of reactor connected lines 8 23-Jul-22 20:00 24-Jul-22 04 :00 17 79 137

79 De-torquing of elbow bolts 4 24-Jul-22 04:00 24-Jul-22 08 :00 78 80 137


80 Opening of top elbow 4 24-Jul-22 08:00 24-Jul-22 12 :00 79 81 137
81 Passivation and lowering of elbow after 1 24-Jul-22 12:00 24-Jul-22 12 :30 80 82 137
passivation from top to bottom reactor

82 Positioning of elbow at ground level and 1 24-Jul-22 12:30 24-Jul-22 13 :00 81 83 137
covering with tarpauline

83 Preparation for vessel entry and initial 2 24-Jul-22 13:00 24-Jul-22 15 :00 82 84 137
gas test
84 Opening of Top Liquid distribution tray 2 24-Jul-22 15:00 24-Jul-22 17 :00 83 85 137

85 Unloading of support material and 30 30-Jul-22 05:00 31-Jul-22 11 :00 84, 57 86 5


catalyst by dumping/shovelling

86 Vacuum cleaning of internals and 7 31-Jul-22 11:00 31-Jul-22 18 :00 85 87 5


inspection
87 R03 reactor thermowell hydro test to 0 31-Jul-22 18:00 86 89 5 R03 reactor thermowell hydro test to be done
be done
Inspection Activities 52 31-Jul-22 18:00 02-Aug-22 22:00 5
89 Internal Scaffolding Erection for 8 31-Jul-22 18:00 01-Aug-22 02:00 87 90 5
Inspection - Confined Space

90 Reactor weld joints (Longitudinal + 24 01-Aug-22 02:00 02-Aug-22 02:00 89 91 5


circumferential) buffing

91 NDT/UT 12 02-Aug-22 02:00 02-Aug-22 14:00 90 92 5


92 Internal scaffolding removal - Confined 8 02-Aug-22 14:00 02-Aug-22 22:00 91 94 5
Space
Loading Preparation 6 02-Aug-22 22:00 03-Aug-22 04:00 5
Page 4 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
94 Preparing for loading of ceramic balls 2 02-Aug-22 22:00 03-Aug-22 00:00 92 95 5

95 Marking of ceramic balls and catalyst 2 03-Aug-22 00:00 03-Aug-22 02:00 94 96 5


layers
96 Box up of dump nozzle flange with new 2 03-Aug-22 02:00 03-Aug-22 04:00 95 98 5
gaskets
R03 Loading 43 03-Aug-22 04:00 04-Aug-22 23:00 0
98 Loading and leveling of ceramic balls 3 03-Aug-22 04:00 03-Aug-22 07:00 96 99 5

99 Installation of HDPE Pipes 2 03-Aug-22 07:00 03-Aug-22 09:00 98 100 5


100 Sock loading of catalyst 31 03-Aug-22 14:00 04-Aug-22 21:00 99, 71 101 0
101 Box up of Top liquid distribution tray 2 04-Aug-22 21:00 04-Aug-22 23:00 100 103 0
manway
Box up activities 10 04-Aug-22 23:00 05-Aug-22 09:00 0
103 Installation of Top Elbow 2 04-Aug-22 23:00 05-Aug-22 01:00 101 104 0
104 Torquing of elbow bolts 4 05-Aug-22 01:00 05-Aug-22 05:00 103 105 0
105 Deblinding of reactor connected lines 4 05-Aug-22 05:00 05-Aug-22 09:00 104 107 0

Reactor R01/R02/R03 Catalyst Replacement Completion 0 05-Aug-22 09:00 05-Aug-22 09:00 0


107 Reactor R01/R02/R03 Catalyst 0 05-Aug-22 09:00 48, 75, 1351 0 Reactor R01/R02/R03 Cataly
Replacement Completion 105

Exchanger Jobs (Scope: 36 nos) 303 23-Jul-22 16:00 05-Aug-22 07:00 2


ME-RH471-S01A/B (Light Naptha Storage Cooler) 143 23-Jul-22 16:00 29-Jul-22 15 :00 162
Process handover 20 23-Jul-22 16:00 24-Jul-22 12 :00 162
111 Draining 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 112 162
112 Purging 2 23-Jul-22 18:00 23-Jul-22 20 :00 111 113 162
113 Blinding 8 23-Jul-22 20:00 24-Jul-22 04 :00 112 114 162
114 Steaming 8 24-Jul-22 04:00 24-Jul-22 12 :00 113 116 162
Maintenance/ Inspection jobs 123 24-Jul-22 12:00 29-Jul-22 15 :00 162
116 Piping & Dome removal of S01A/B 6 24-Jul-22 12:00 24-Jul-22 18 :00 114 117, 123 162

117 Bundle Pull Out 6 24-Jul-22 18:00 25-Jul-22 00 :00 116 118 162
123 Belzona application on Dome of S01A/B 18 24-Jul-22 18:00 25-Jul-22 12 :00 116 125 191
and Curing
118 Inspection of bundle and shifting to 5 25-Jul-22 00:00 25-Jul-22 05 :00 117 119 162
workshop
119 Hydrojetting 16 25-Jul-22 05:00 25-Jul-22 21 :00 118 120 162
120 Inspection by CES/CTS 4 25-Jul-22 21:00 26-Jul-22 01 :00 119 121 162
Page 5 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
121 Shifting to Site 4 26-Jul-22 01:00 26-Jul-22 05 :00 120 122 162
122 Bundle Insertion 6 26-Jul-22 05:00 26-Jul-22 11 :00 121 124 162
124 Shell side Hydrotest 6 26-Jul-22 11:00 26-Jul-22 17 :00 122 125 162
125 Dome Box Up 6 26-Jul-22 17:00 26-Jul-22 23 :00 124, 123126 162
126 Chemical cleaning 24 26-Jul-22 23:00 27-Jul-22 23 :00 125 127 162
127 Chemical cleaning equipment removal 3 27-Jul-22 23:00 28-Jul-22 02 :00 126 128 162

128 Tube side Hydrotest 6 28-Jul-22 02:00 28-Jul-22 08 :00 127 129 162
129 Belzona application on Tube sheet of 15 28-Jul-22 08:00 28-Jul-22 23 :00 128 130 162
S01A/B and Curing
130 Final Shell side Hydrotest 8 28-Jul-22 23:00 29-Jul-22 07 :00 129 131 162
131 Deblinding and piping box up 8 29-Jul-22 07:00 29-Jul-22 15 :00 130 520 162
ME-RH471-S03A/B (NO. 1 Combined Feed Exchanger) 228 23-Jul-22 16:00 02-Aug-22 04:00 77
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 151
134 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 135 2
135 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 134 136, 186, 185 2
136 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 135 138 151
Maintenance/ Inspection jobs 210 24-Jul-22 10:00 02-Aug-22 04:00 77
138 Piping & Dome removal of S03A/B 6 24-Jul-22 10:00 24-Jul-22 16 :00 136 139 151

139 Bundle puller arrangement & Tube 8 28-Jul-22 04:00 28-Jul-22 12 :00 138, 140, 438 67
bundle pull out 173
140 Tube bundle shifting to HJ bay 4 29-Jul-22 16:00 29-Jul-22 20 :00 139, 173141 77
141 Hydrojetting 30 29-Jul-22 20:00 31-Jul-22 02 :00 140 142 77
142 Inspection by CES/CTS 4 31-Jul-22 02:00 31-Jul-22 06 :00 141 143 77
143 Tube bundle shifting to site 4 31-Jul-22 06:00 31-Jul-22 10 :00 142 144 77
144 Tube bundle insertion 8 31-Jul-22 10:00 31-Jul-22 18 :00 143 145 77
145 Shell side Hydro testing 6 31-Jul-22 18:00 01-Aug-22 00:00 144 146 77
146 Dome Box up S03A/B 8 01-Aug-22 00:00 01-Aug-22 08:00 145 147 77
147 Differential hydrotest @ 30kg/cm2 of 10 01-Aug-22 08:00 01-Aug-22 18:00 146 148 77
S03A/B

148 Deblinding and piping box up 10 01-Aug-22 18:00 02-Aug-22 04:00 147 520 77
ME-RH471-S04A/B (No. 2 Combined Feed Exchanger) 182 23-Jul-22 16:00 31-Jul-22 06 :00 123
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 67
151 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 152 67
152 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 151 153 67
153 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 152 155 67
Maintenance/ Inspection jobs 164 24-Jul-22 10:00 31-Jul-22 06 :00 123

Page 6 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
155 Piping & Dome removal of S04A/B 8 24-Jul-22 10:00 24-Jul-22 18 :00 153 156 67

156 Bundle puller arrangement & Tube 8 27-Jul-22 12:00 27-Jul-22 20 :00 155 157, 173, 67
bundle pull out 510
157 Tube bundle shifting to HJ bay 4 27-Jul-22 20:00 28-Jul-22 00 :00 156 158 123
158 Hydrojetting 30 28-Jul-22 00:00 29-Jul-22 06 :00 157 159 123
159 Inspection by CES/CTS 4 29-Jul-22 06:00 29-Jul-22 10 :00 158 160 123
160 Tube bundle shifting to site 4 29-Jul-22 10:00 29-Jul-22 14 :00 159 161 123
161 Tube bundle insertion 8 29-Jul-22 14:00 29-Jul-22 22 :00 160 162 123
162 Shell side Hydro testing 6 29-Jul-22 22:00 30-Jul-22 04 :00 161 163 123
163 Dome Box up S04A/B 8 30-Jul-22 04:00 30-Jul-22 12 :00 162 164 123
164 Differential hydrotest @ 25kg/cm2 of 10 30-Jul-22 12:00 30-Jul-22 22 :00 163 165 123
S04A/B

165 Deblinding and piping box up 8 30-Jul-22 22:00 31-Jul-22 06 :00 164 520 123
ME-RH471-S04C/D (NO. 2 Combined Feed Exchanger) 202 23-Jul-22 16:00 01-Aug-22 02:00 103
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 141
168 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 169 141
169 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 168 170 141
170 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 169 172 141
Maintenance/ Inspection jobs 184 24-Jul-22 10:00 01-Aug-22 02:00 103
172 Piping & Dome removal of S04C/D 8 24-Jul-22 10:00 24-Jul-22 18 :00 170 173 141

173 Bundle puller arrangement & Tube 8 27-Jul-22 20:00 28-Jul-22 04 :00 172, 139, 140, 67
bundle pull out 156 174
174 Tube bundle shifting to HJ bay 4 28-Jul-22 20:00 29-Jul-22 00 :00 173 175 103
175 Hydrojetting 30 29-Jul-22 00:00 30-Jul-22 06 :00 174 176 103
176 Inspection by CES/CTS 4 30-Jul-22 06:00 30-Jul-22 10 :00 175 177 103
177 Tube bundle shifting to site 2 30-Jul-22 10:00 30-Jul-22 12 :00 176 178 103
178 Tube bundle insertion 8 30-Jul-22 12:00 30-Jul-22 20 :00 177 179 103
179 Shell side Hydro testing 6 30-Jul-22 20:00 31-Jul-22 02 :00 178 180 103
180 Dome Box up of S04C/D 6 31-Jul-22 02:00 31-Jul-22 08 :00 179 181 103
181 Differential hydrotest @ 25 kg/cm2 of 10 31-Jul-22 08:00 31-Jul-22 18 :00 180 182 103
S04C/D
182 Deblinding and Piping box up 8 31-Jul-22 18:00 01-Aug-22 02:00 181 520 103
ME-RH471-S05 (NO. 3 COMBINED FEED EXCHANGER) 299 23-Jul-22 20:00 05-Aug-22 07:00 2
Process Handover 14 23-Jul-22 20:00 24-Jul-22 10 :00 2
185 Purging 2 23-Jul-22 20:00 23-Jul-22 22 :00 135 186 2
186 Blinding 8 23-Jul-22 22:00 24-Jul-22 06 :00 135, 185187 2

Page 7 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
187 Steaming 4 24-Jul-22 06:00 24-Jul-22 10 :00 186 189 2
Maintenance / Inspection Jobs 285 24-Jul-22 10:00 05-Aug-22 07:00 2
189 Piping & Dome removal of S05 4 24-Jul-22 10:00 24-Jul-22 14 :00 187 190 2
190 Bundle puller arrangement & Tube 2 24-Jul-22 14:00 24-Jul-22 16 :00 189 191 2
bundle pull out
191 Tube bundle shifting to HJ bay 2 24-Jul-22 16:00 24-Jul-22 18 :00 190 192 2
192 Hydrojetting of S05 14 24-Jul-22 18:00 25-Jul-22 08 :00 191 193 2
193 Shifting to CES-W/s for Retubing 2 25-Jul-22 08:00 25-Jul-22 10 :00 192 194 2

194 Retubing at CES-W/s (Scope: 1100 227 25-Jul-22 10:00 03-Aug-22 21:00 193 195 2
no's U)
195 Inspection by CES/CTS 2 03-Aug-22 21:00 03-Aug-22 23:00 194 196 2
196 Tube bundle shifting to site 2 03-Aug-22 23:00 04-Aug-22 01:00 195 197 2
197 Tube bundle insertion 4 04-Aug-22 01:00 04-Aug-22 05:00 196 198 2
198 Pneumatic test 4 04-Aug-22 05:00 04-Aug-22 09:00 197 199 2
199 Shell side Hydro test @ 37.5 kg/cm2 6 04-Aug-22 09:00 04-Aug-22 15:00 198 200 2

200 Dome Box up of S05 4 04-Aug-22 15:00 04-Aug-22 19:00 199 201 2
201 Differential hydrotest @ 14.8 kg/cm2 6 04-Aug-22 19:00 05-Aug-22 01:00 200 202 2
of S05
202 Deblinding and Piping box up 6 05-Aug-22 01:00 05-Aug-22 07:00 201 520 2
106 23-Jul-22 16:00
ME-RH471-S06 (NO. 4 COMBINED FEED EXCHANGER) BXU 28-Jul-22 02 :00 199
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 103
205 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 206 103
206 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 205 207 103
207 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 206 209 103
Maintenance/Inspection jobs 88 24-Jul-22 10:00 28-Jul-22 02 :00 199
209 Passivation with Neutralization solution 6 24-Jul-22 10:00 24-Jul-22 16 :00 207 210, 103
1076
210 Dome & Piping bolt detorquing 2 24-Jul-22 16:00 24-Jul-22 18 :00 209 211 199
211 Dome & Piping removal 8 24-Jul-22 18:00 25-Jul-22 02 :00 210 212 199
212 Tube Bundle puller arrangement & 6 25-Jul-22 02:00 25-Jul-22 08 :00 211 213 199
Bundle pullout
213 Tube Bundle shifting to hydrojetting bay 4 25-Jul-22 08:00 25-Jul-22 12 :00 212 214 199

214 Hydrojetting 20 25-Jul-22 12:00 26-Jul-22 08 :00 213 215 199


215 Inspection by CES/CTS 4 26-Jul-22 08:00 26-Jul-22 12 :00 214 216 199
216 Tube Bundle shifting to site 4 26-Jul-22 12:00 26-Jul-22 16 :00 215 217 199
217 Tube bundle insertion 4 26-Jul-22 16:00 26-Jul-22 20 :00 216 218 199
218 Shell side hydro testing 6 26-Jul-22 20:00 27-Jul-22 02 :00 217 219 199

Page 8 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
219 Dome boxup of S06 6 27-Jul-22 02:00 27-Jul-22 08 :00 218 220 199
220 Differential hydrotest @17.5 kg/cm2 of 10 27-Jul-22 08:00 27-Jul-22 18 :00 219 221 199
S06
221 Deblinding & piping boxup 8 27-Jul-22 18:00 28-Jul-22 02 :00 220 520 199
ME-RH471-S07 (MP BOILER FEED WATER PREHEATER) 66 23-Jul-22 16:00 26-Jul-22 10 :00 239
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 239
224 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 225 239
225 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 224 226 239
226 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 225 228 239
Maintenance/Inspection jobs 48 24-Jul-22 10:00 26-Jul-22 10 :00 239
228 Dome & piping bolt detorquing 4 24-Jul-22 10:00 24-Jul-22 14 :00 226 229 239
229 Dome & piping removal 8 24-Jul-22 14:00 24-Jul-22 22 :00 228 230 239
230 Initial Inspection by CES-Inspection 4 24-Jul-22 22:00 25-Jul-22 02 :00 229 231 239
Group
231 In situ HJ 8 25-Jul-22 02:00 25-Jul-22 10 :00 230 232 239
232 Final Inspection 4 25-Jul-22 10:00 25-Jul-22 14 :00 231 233 239
233 Shell side hydro testing 6 25-Jul-22 14:00 25-Jul-22 20 :00 232 234 239
234 Tube side hydrotesting 6 25-Jul-22 20:00 26-Jul-22 02 :00 233 235 239
235 Deblinding & piping boxup 8 26-Jul-22 02:00 26-Jul-22 10 :00 234 520 239
ME-RH471-S08 (MP Steam Generator) - IBR Inspection 259 23-Jul-22 16:00 03-Aug-22 11:00 46
Process Handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 46
238 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 239 46
239 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 238 240 46
240 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 239 242 46
Maintenance / Inspection Jobs 241 24-Jul-22 10:00 03-Aug-22 11:00 46
242 Piping & Dome removal of S08 8 24-Jul-22 10:00 24-Jul-22 18 :00 240 243 46
243 Bundle puller arrangement & Tube 8 24-Jul-22 18:00 25-Jul-22 02 :00 242 244 46
bundle pull out
244 Tube bundle shifting to HJ bay 4 25-Jul-22 02:00 25-Jul-22 06 :00 243 245 46
245 Hydrojetting at HJ Bay 16 25-Jul-22 06:00 25-Jul-22 22 :00 244 246 46
246 Shifting to CES-W/s for Retubing 4 25-Jul-22 22:00 26-Jul-22 02 :00 245 247 46

247 Retubing at CES-W/s (Scope: 236 no's 135 26-Jul-22 02:00 31-Jul-22 17 :00 246 248 46
U)
248 Inspection by CES/CTS 2 31-Jul-22 17:00 31-Jul-22 19 :00 247 249 46
249 Tube bundle shifting to site 4 31-Jul-22 19:00 31-Jul-22 23 :00 248 250 46
250 Tube bundle insertion 8 31-Jul-22 23:00 01-Aug-22 07:00 249 251 46
251 Pnuematic test 6 01-Aug-22 07:00 01-Aug-22 13:00 250 252 46
252 Shell side Hydro test (Internal) 12 01-Aug-22 13:00 02-Aug-22 01:00 251 253 46

Page 9 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
253 Shell side Hydro test (IBR - Inspector 12 02-Aug-22 01:00 02-Aug-22 13:00 252 254 46
Presence)

254 Dome Box up of S08 6 02-Aug-22 13:00 02-Aug-22 19:00 253 255 46
255 Tube side hydrotest 8 02-Aug-22 19:00 03-Aug-22 03:00 254 256 46
256 Deblinding and Piping box up 8 03-Aug-22 03:00 03-Aug-22 11:00 255 520 46
ME-RH471-S09 (MP STEAM SUPERHEATER) 78 23-Jul-22 16:00 26-Jul-22 22 :00 227
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 227
259 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 260 227
260 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 259 261 227
261 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 260 263 227
Maintenance/Inspection jobs 60 24-Jul-22 10:00 26-Jul-22 22 :00 227
263 Dome & piping bolt detorquing 4 24-Jul-22 10:00 24-Jul-22 14 :00 261 264 227
264 Dome & piping removal 8 24-Jul-22 14:00 24-Jul-22 22 :00 263 265 227
265 Initial Inspection by CES-Inspection 4 24-Jul-22 22:00 25-Jul-22 02 :00 264 266 227
Group
266 In situ HJ 8 25-Jul-22 02:00 25-Jul-22 10 :00 265 267 227
267 Final Inspection 4 25-Jul-22 10:00 25-Jul-22 14 :00 266 268 227
268 Shell side hydrotesting 8 25-Jul-22 14:00 25-Jul-22 22 :00 267 269 227
269 Dome Box up 10 25-Jul-22 22:00 26-Jul-22 08 :00 268 270 227
270 Tube side hydrotesting 6 26-Jul-22 08:00 26-Jul-22 14 :00 269 271 227
271 Deblinding & piping boxup 8 26-Jul-22 14:00 26-Jul-22 22 :00 270 520 227
130 23-Jul-22
ME-RH471-S10A/B (REACTOR NO. 2 FEED - STRIPPER BOTTOMS EX) BEU16:00 29-Jul-22 02 :00 175
Process handover 28 23-Jul-22 16:00 24-Jul-22 20 :00 175
274 Purging 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 275 175
275 Blinding 12 23-Jul-22 20:00 24-Jul-22 08 :00 274 276 175
276 Steaming 12 24-Jul-22 08:00 24-Jul-22 20 :00 275 278 175
Maintenance/Inspection jobs 102 24-Jul-22 20:00 29-Jul-22 02 :00 175
278 Dome & piping bolt detorquing 4 24-Jul-22 20:00 25-Jul-22 00 :00 276 279 175
279 Dome & piping removal 8 25-Jul-22 00:00 25-Jul-22 08 :00 278 280 175
280 Tube bundle puller arrangement & 8 25-Jul-22 08:00 25-Jul-22 16 :00 279 281 175
Bundle pullout
281 Tube bundle shifting to hydrojetting bay 4 25-Jul-22 16:00 25-Jul-22 20 :00 280 282 175

282 Hydrojetting 16 25-Jul-22 20:00 26-Jul-22 12 :00 281 283 175


283 Inspection by CES/CTS 4 26-Jul-22 12:00 26-Jul-22 16 :00 282 284 175
284 Tube bundle shifting to site 4 26-Jul-22 16:00 26-Jul-22 20 :00 283 285 175
285 Tube bundle insertion 8 26-Jul-22 20:00 27-Jul-22 04 :00 284 286 175
286 Shell side Hydrotesting at 60 kg/cm2 12 27-Jul-22 04:00 27-Jul-22 16 :00 285 287 175

Page 10 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
287 Dome box up 10 27-Jul-22 16:00 28-Jul-22 02 :00 286 288 175
288 Tube side hydrotesting at 60 kg/cm2 12 28-Jul-22 02:00 28-Jul-22 14 :00 287 289 175

289 Deblinding 12 28-Jul-22 14:00 29-Jul-22 02 :00 288 520 175


158 23-Jul-22
ME-RH471-S11A/B (STRIPPER FEED - BOTTOMS EXCHANGER) - BEU 16:00 30-Jul-22 06 :00 147
Process Handover 28 23-Jul-22 16:00 24-Jul-22 20 :00 169
292 Purging 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 293 169
293 Blinding 12 23-Jul-22 20:00 24-Jul-22 08 :00 292 294 169
294 Steaming 12 24-Jul-22 08:00 24-Jul-22 20 :00 293 296 169
Maintenance/Inspection jobs 130 24-Jul-22 20:00 30-Jul-22 06 :00 147
296 Dome & piping bolt detorquing 2 24-Jul-22 20:00 24-Jul-22 22 :00 294 297 169
297 Dome & piping removal 8 24-Jul-22 22:00 25-Jul-22 06 :00 296 298 169
298 Tube bundle puller arrangement & 8 26-Jul-22 04:00 26-Jul-22 12 :00 297, 299 147
Bundle pullout 456
299 Tube bundle shifting to hydrojetting bay 4 26-Jul-22 12:00 26-Jul-22 16 :00 298 300 147

300 Hydrojetting 24 26-Jul-22 16:00 27-Jul-22 16 :00 299 301 147


301 Inspection by CES/CTS 4 27-Jul-22 16:00 27-Jul-22 20 :00 300 302 147
302 Tube bundle shifting to site 4 27-Jul-22 20:00 28-Jul-22 00 :00 301 303 147
303 Tube bundle insertion 8 28-Jul-22 00:00 28-Jul-22 08 :00 302 304 147
304 Shell side Hydrotesting at 60 kg/cm2 12 28-Jul-22 08:00 28-Jul-22 20 :00 303 305 147

305 Dome box up 10 28-Jul-22 20:00 29-Jul-22 06 :00 304 306 147
306 Tube side hydrotesting at 60 kg/cm2 12 29-Jul-22 06:00 29-Jul-22 18 :00 305 307 147

307 Deblinding 12 29-Jul-22 18:00 30-Jul-22 06 :00 306 520 147


170 23-Jul-22
ME-RH471-S12A/B (STRIPPER FEED - REACTOR NO. 2 EFFLUENT 16:00
EXCHANGER) 30-Jul-22 18 :00 135
Process Handover 28 23-Jul-22 16:00 24-Jul-22 20 :00 177
310 Purging 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 311 177
311 Blinding 12 23-Jul-22 20:00 24-Jul-22 08 :00 310 312 177
312 Steaming 12 24-Jul-22 08:00 24-Jul-22 20 :00 311 314 177
Maintenance/Inspection jobs 142 24-Jul-22 20:00 30-Jul-22 18 :00 135
314 Dome & piping bolt detorquing 2 24-Jul-22 20:00 24-Jul-22 22 :00 312 315 177
315 Dome & piping removal 8 24-Jul-22 22:00 25-Jul-22 06 :00 314 316 177
316 Tube bundle puller arrangement & 8 27-Jul-22 00:00 27-Jul-22 08 :00 315, 317 135
Bundle pullout 420
317 Tube bundle shifting to hydrojetting bay 4 27-Jul-22 08:00 27-Jul-22 12 :00 316 318 135

318 Hydrojetting & inspection of S12A/B 16 27-Jul-22 12:00 28-Jul-22 04 :00 317 319 135

Page 11 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
319 Inspection by CES/CTS 4 28-Jul-22 04:00 28-Jul-22 08 :00 318 320 135
320 Tube bundle shifting to site 4 28-Jul-22 08:00 28-Jul-22 12 :00 319 321 135
321 Tube bundle insertion 8 28-Jul-22 12:00 28-Jul-22 20 :00 320 322 135
322 Shell side Hydrotesting at 60 kg/cm2 12 28-Jul-22 20:00 29-Jul-22 08 :00 321 323 135

323 Dome box up 10 29-Jul-22 08:00 29-Jul-22 18 :00 322 324 135
324 Tube side hydrotesting at 60 kg/cm2 12 29-Jul-22 18:00 30-Jul-22 06 :00 323 325 135

325 Deblinding 12 30-Jul-22 06:00 30-Jul-22 18 :00 324 520 135


ME-RH471-S14A/B (STRIPPER BOTTOMS TRIM COOLER)150 23-Jul-22 16:00 29-Jul-22 22 :00 155
Process handover 28 23-Jul-22 16:00 24-Jul-22 20 :00 155
328 Purging 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 329 155
329 Blinding 12 23-Jul-22 20:00 24-Jul-22 08 :00 328 330 155
330 Steaming 12 24-Jul-22 08:00 24-Jul-22 20 :00 329 332 155
Maintenance/Inspection jobs 122 24-Jul-22 20:00 29-Jul-22 22 :00 155
332 Blinding 6 24-Jul-22 20:00 25-Jul-22 02 :00 330 333 155
333 Dome & piping removal 12 25-Jul-22 02:00 25-Jul-22 14 :00 332 334, 338 155
334 Initial Inspection by CES-Inspection 4 25-Jul-22 14:00 25-Jul-22 18 :00 333 335 155
Group
338 Belzona- 5891 on Dome 8 25-Jul-22 14:00 25-Jul-22 22 :00 333 340 183
335 In situ HJ 8 25-Jul-22 18:00 26-Jul-22 02 :00 334 336 155
336 Final Inspection 4 26-Jul-22 02:00 26-Jul-22 06 :00 335 337 155
337 Shell side hydrotest at 37.5 kg/cm2 12 26-Jul-22 06:00 26-Jul-22 18 :00 336 339 155

339 On Tube sheet Belzona-1321/ Stanvac 8 26-Jul-22 18:00 27-Jul-22 02 :00 337 340 155
brushable ceramic coating

340 Dome boxup 8 27-Jul-22 02:00 27-Jul-22 10 :00 338, 339341 155
341 Tube side hydrotest at 37.5 kg/cm2 12 27-Jul-22 10:00 27-Jul-22 22 :00 340 342 155

342 Passivation on tube side 24 27-Jul-22 22:00 28-Jul-22 22 :00 341 343 155
343 Tube side hydrotest at 37.5 kg/cm2 12 28-Jul-22 22:00 29-Jul-22 10 :00 342 344 155

344 Deblinding & piping boxup 12 29-Jul-22 10:00 29-Jul-22 22 :00 343 520 155
74 23-Jul-22 16:00
ME-RH471-S15A (LUBE OIL COOLERS FOR MC-RH471-C01A) 26-Jul-22 18 :00 231
Process handover 10 23-Jul-22 16:00 24-Jul-22 02 :00 231
347 Oil draining 6 23-Jul-22 16:00 23-Jul-22 22 :00 12 348 231
348 Blinding 4 23-Jul-22 22:00 24-Jul-22 02 :00 347 350 231
Maintenance/Inspection jobs 64 24-Jul-22 02:00 26-Jul-22 18 :00 231
350 Channel/Dome removal 6 24-Jul-22 02:00 24-Jul-22 08 :00 348 351, 352 231

Page 12 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
351 Inspection of bundle & HJ 12 24-Jul-22 08:00 24-Jul-22 20 :00 350 353 231
352 Belzona application on Channel/Cover 18 24-Jul-22 08:00 25-Jul-22 02 :00 350 354 231

353 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 351 354 231
HJ
354 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 352, 353355 231
355 Shell side hydrotest at 15 kg/cm2 with 12 25-Jul-22 06:00 25-Jul-22 18 :00 354 356 231
Oil
356 Channel/Dome box up 10 25-Jul-22 18:00 26-Jul-22 04 :00 355 357 231
357 Tube side hydrotest at 15 kg/cm2 8 26-Jul-22 04:00 26-Jul-22 12 :00 356 358, 520 231

358 De-blinding 6 26-Jul-22 12:00 26-Jul-22 18 :00 357 520 231


74 23-Jul-22 16:00
ME-RH471-S15B (LUBE OIL COOLERS FOR MC-RH471-C01A) 26-Jul-22 18 :00 231
Process handover 10 23-Jul-22 16:00 24-Jul-22 02 :00 231
361 Oil draining 6 23-Jul-22 16:00 23-Jul-22 22 :00 12 362 231
362 Blinding 4 23-Jul-22 22:00 24-Jul-22 02 :00 361 364 231
Maintenance/Inspection jobs 64 24-Jul-22 02:00 26-Jul-22 18 :00 231
364 Channel/Dome removal 6 24-Jul-22 02:00 24-Jul-22 08 :00 362 365, 366 231
365 Inspection of bundle & HJ 12 24-Jul-22 08:00 24-Jul-22 20 :00 364 367 231
366 Belzona application on Channel/Cover 18 24-Jul-22 08:00 25-Jul-22 02 :00 364 368 231
367 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 365 368 231
HJ
368 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 366, 367369 231
369 Shell side hydrotest at 15 kg/cm2 with 12 25-Jul-22 06:00 25-Jul-22 18 :00 368 370 231
Oil
370 Channel/Dome box up 10 25-Jul-22 18:00 26-Jul-22 04 :00 369 371 231
371 Tube side hydrotest at 15 kg/cm2 8 26-Jul-22 04:00 26-Jul-22 12 :00 370 372 231

372 De-blinding 6 26-Jul-22 12:00 26-Jul-22 18 :00 371 520 231


74 23-Jul-22 16:00
ME-RH471-S16A (LUBE OIL COOLERS FOR MC-RH471-C01B) 26-Jul-22 18 :00 231
Process handover 10 23-Jul-22 16:00 24-Jul-22 02 :00 231
375 Oil draining 6 23-Jul-22 16:00 23-Jul-22 22 :00 12 376 231
376 Blinding 4 23-Jul-22 22:00 24-Jul-22 02 :00 375 378 231
Maintenance/Inspection jobs 64 24-Jul-22 02:00 26-Jul-22 18 :00 231
378 Channel/Dome removal 6 24-Jul-22 02:00 24-Jul-22 08 :00 376 379, 380 231
379 Inspection of bundle & HJ 12 24-Jul-22 08:00 24-Jul-22 20 :00 378 381 231
380 Belzona application on Channel/Cover 18 24-Jul-22 08:00 25-Jul-22 02 :00 378 382 231

381 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 379 382 231
HJ

Page 13 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
382 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 380, 381383 231
383 Shell side hydrotest at 15 kg/cm2 with 12 25-Jul-22 06:00 25-Jul-22 18 :00 382 384 231
Oil
384 Channel/Dome box up 10 25-Jul-22 18:00 26-Jul-22 04 :00 383 385 231
385 Tube side hydrotest at 15 kg/cm2 8 26-Jul-22 04:00 26-Jul-22 12 :00 384 386 231

386 De-blinding 6 26-Jul-22 12:00 26-Jul-22 18 :00 385 520 231


74 23-Jul-22 16:00
ME-RH471-S16B (LUBE OIL COOLERS FOR MC-RH471-C01B) 26-Jul-22 18 :00 231
Process handover 10 23-Jul-22 16:00 24-Jul-22 02 :00 231
389 Oil draining 6 23-Jul-22 16:00 23-Jul-22 22 :00 12 390 231
390 Blinding 4 23-Jul-22 22:00 24-Jul-22 02 :00 389 392 231
Maintenance/Inspection jobs 64 24-Jul-22 02:00 26-Jul-22 18 :00 231
392 Channel/Dome removal 6 24-Jul-22 02:00 24-Jul-22 08 :00 390 393, 394 231
393 Inspection of bundle & HJ 12 24-Jul-22 08:00 24-Jul-22 20 :00 392 395 231
394 Belzona application on Channel/Cover 18 24-Jul-22 08:00 25-Jul-22 02 :00 392 396 231

395 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 393 396 231
HJ
396 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 394, 395397 231
397 Shell side hydrotest at 15 kg/cm2 with 12 25-Jul-22 06:00 25-Jul-22 18 :00 396 398 231
Oil
398 Channel/Dome box up 10 25-Jul-22 18:00 26-Jul-22 04 :00 397 399 231
399 Tube side hydrotest at 15 kg/cm2 8 26-Jul-22 04:00 26-Jul-22 12 :00 398 400 231

400 De-blinding 6 26-Jul-22 12:00 26-Jul-22 18 :00 399 520 231


28 23-Jul-22 16:00
ME-RH471-S17 (CYL.CIRCUL.WATER COOLER-MC-RH471-C01A/B) 24-Jul-22 20 :00 277
Process handover 8 23-Jul-22 16:00 24-Jul-22 00 :00 277
403 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 404 277
404 Blinding 2 23-Jul-22 18:00 23-Jul-22 20 :00 403 405 277
405 Steaming 4 23-Jul-22 20:00 24-Jul-22 00 :00 404 407 277
Maintenance/Inspection jobs 20 24-Jul-22 00:00 24-Jul-22 20 :00 277
407 External water cleaning 6 24-Jul-22 00:00 24-Jul-22 06 :00 405 408 277
408 Hydrotest at 10 kg/cm2 8 24-Jul-22 06:00 24-Jul-22 14 :00 407 409 277
409 Deblinding 6 24-Jul-22 14:00 24-Jul-22 20 :00 408 520 277
172
ME-RH471-S22A/B (DIOLFIN REACTOR FEED EXCHANGER 23-Jul-22
NO.1) 16:00 30-Jul-22 20 :00 133
Process Handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 133
412 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 413 133
413 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 412 414 133
414 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 413 416 133

Page 14 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
Maintenance / Inspection Jobs 154 24-Jul-22 10:00 30-Jul-22 20 :00 133
416 Piping & Dome removal 12 24-Jul-22 10:00 24-Jul-22 22 :00 414 417, 420 133
417 S22B: Dome shifting to CES-W/s 4 24-Jul-22 22:00 25-Jul-22 02 :00 416 418 179

418 S22B: Partition plate replacement at 60 25-Jul-22 02:00 27-Jul-22 14 :00 417 419 179
Workshop
420 Tube bundle puller arrangement & 8 26-Jul-22 16:00 27-Jul-22 00 :00 416 316, 421 133
Bundle pullout
421 Tube bundle shifting to hydrojetting bay 4 27-Jul-22 00:00 27-Jul-22 04 :00 420 422 133

422 Hydrojetting & inspection of S22A/B 36 27-Jul-22 04:00 28-Jul-22 16 :00 421 423 133

419 S22B: Dome shifting back to site 4 27-Jul-22 14:00 27-Jul-22 18 :00 418 427 179

423 Inspection by CES/CTS 4 28-Jul-22 16:00 28-Jul-22 20 :00 422 424 133
424 Tube bundle shifting to site 4 28-Jul-22 20:00 29-Jul-22 00 :00 423 425 133
425 Tube bundle insertion 8 29-Jul-22 00:00 29-Jul-22 08 :00 424 426 133
426 Shell side hydrotest of S22A/B @ 48 8 29-Jul-22 08:00 29-Jul-22 16 :00 425 427 133
kg/cm2 G

427 Dome box up 8 29-Jul-22 16:00 30-Jul-22 00 :00 426, 419428 133
428 Tube side hydrotest of S22A/B @ 62 8 30-Jul-22 00:00 30-Jul-22 08 :00 427 429 133
kg/cm2

429 Deblinding and piping box up 12 30-Jul-22 08:00 30-Jul-22 20 :00 428 520 133
238
ME-RH471-S23A/B (DIOLFIN REACTOR FEED EXCHANGER 23-Jul-22 16:00
NO.1) 02-Aug-22 14:00 67
Process handover 24 23-Jul-22 16:00 24-Jul-22 16 :00 143
432 Purging 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 433 143
433 Blinding 12 23-Jul-22 20:00 24-Jul-22 08 :00 432 434 143
434 Steaming 8 24-Jul-22 08:00 24-Jul-22 16 :00 433 436 143
Maintenance/Inspection jobs 214 24-Jul-22 16:00 02-Aug-22 14:00 67
436 Dome & piping bolt detorquing 4 24-Jul-22 16:00 24-Jul-22 20 :00 434 437 143
437 Dome & piping removal 12 24-Jul-22 20:00 25-Jul-22 08 :00 436 438 143
438 Tube bundle puller arrangement & 8 28-Jul-22 12:00 28-Jul-22 20 :00 437, 439 67
Bundle pullout 139
439 Tube bundle shifting to hydrojetting bay 4 29-Jul-22 20:00 30-Jul-22 00 :00 438 440 67

440 Hydrojetting 24 30-Jul-22 00:00 31-Jul-22 00 :00 439 441 67


441 Inspection by CES/CTS 4 31-Jul-22 00:00 31-Jul-22 04 :00 440 442 67
442 Tube bundle shifting to site 4 31-Jul-22 04:00 31-Jul-22 08 :00 441 443 67
443 Tube bundle insertion 8 31-Jul-22 08:00 31-Jul-22 16 :00 442 444 67

Page 15 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
444 Shell side hydrotest at 41 kg/cm2 12 31-Jul-22 16:00 01-Aug-22 04:00 443 445 67

445 Dome box up 10 01-Aug-22 04:00 01-Aug-22 14:00 444 446 67


446 Tube side hydrotest at 62.01 kg/cm2 12 01-Aug-22 14:00 02-Aug-22 02:00 445 447 67

447 Deblinding & piping boxup 12 02-Aug-22 02:00 02-Aug-22 14:00 446 520 67
140
ME-RH471-S24A/B (DIOLFIN REACTOR FEED EXCHANGER 23-Jul-22 16:00
NO.1) 29-Jul-22 12 :00 165
Process handover 24 23-Jul-22 16:00 24-Jul-22 16 :00 147
450 Purging 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 451 147
451 Blinding 12 23-Jul-22 20:00 24-Jul-22 08 :00 450 452 147
452 Steaming 8 24-Jul-22 08:00 24-Jul-22 16 :00 451 454 147
Maintenance/Inspection jobs 116 24-Jul-22 16:00 29-Jul-22 12 :00 165
454 Dome & piping bolt detorquing 4 24-Jul-22 16:00 24-Jul-22 20 :00 452 455 147
455 Dome & piping removal 12 24-Jul-22 20:00 25-Jul-22 08 :00 454 456 147
456 Tube bundle puller arrangement & 8 25-Jul-22 20:00 26-Jul-22 04 :00 455 298, 457 147
Bundle pullout
457 Tube bundle shifting to hydrojetting bay 4 26-Jul-22 04:00 26-Jul-22 08 :00 456 458 165

458 Hydrojetting & inspection of S24A/B 24 26-Jul-22 08:00 27-Jul-22 08 :00 457 459 165

459 Inspection by CES/CTS 4 27-Jul-22 08:00 27-Jul-22 12 :00 458 460 165
460 Tube bundle shifting to site 4 27-Jul-22 12:00 27-Jul-22 16 :00 459 461 165
461 Tube bundle insertion 8 27-Jul-22 16:00 28-Jul-22 00 :00 460 462 165
462 Shell side hydrotest at 37 kg/cm2 12 28-Jul-22 00:00 28-Jul-22 12 :00 461 463 165

463 Tube side hydrotest at 62.01 kg/cm2 12 28-Jul-22 12:00 29-Jul-22 00 :00 462 464 165

464 Deblinding & piping boxup 12 29-Jul-22 00:00 29-Jul-22 12 :00 463 520 165
ME-RH471-S25A (471-C01C LUBE OIL COOLER) 74 23-Jul-22 16:00 26-Jul-22 18 :00 231
Process handover 10 23-Jul-22 16:00 24-Jul-22 02 :00 231
467 Oil draining 6 23-Jul-22 16:00 23-Jul-22 22 :00 12 468 231
468 Blinding 4 23-Jul-22 22:00 24-Jul-22 02 :00 467 470 231
Maintenance/Inspection jobs 64 24-Jul-22 02:00 26-Jul-22 18 :00 231
470 Channel/Dome removal 6 24-Jul-22 02:00 24-Jul-22 08 :00 468 471, 472 231
471 Inspection of bundle & HJ 12 24-Jul-22 08:00 24-Jul-22 20 :00 470 473 231
472 Belzona application on Channel/Cover 18 24-Jul-22 08:00 25-Jul-22 02 :00 470 474 231

473 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 471 474 231
HJ
474 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 472, 473475 231

Page 16 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
475 Shell side hydrotest at 15 kg/cm2 with 12 25-Jul-22 06:00 25-Jul-22 18 :00 474 476 231
Oil
476 Channel/Dome box up 10 25-Jul-22 18:00 26-Jul-22 04 :00 475 477 231
477 Tube side hydrotest at 15 kg/cm2 8 26-Jul-22 04:00 26-Jul-22 12 :00 476 478 231

478 De-blinding 6 26-Jul-22 12:00 26-Jul-22 18 :00 477 520 231


ME-RH471-S25B (471-C01C LUBE OIL COOLER) 74 23-Jul-22 16:00 26-Jul-22 18 :00 231
Process handover 10 23-Jul-22 16:00 24-Jul-22 02 :00 231
481 Oil draining 6 23-Jul-22 16:00 23-Jul-22 22 :00 12 482 231
482 Blinding 4 23-Jul-22 22:00 24-Jul-22 02 :00 481 484 231
Maintenance/Inspection jobs 64 24-Jul-22 02:00 26-Jul-22 18 :00 231
484 Channel/Dome removal 6 24-Jul-22 02:00 24-Jul-22 08 :00 482 485, 486 231
485 Inspection of bundle & HJ 12 24-Jul-22 08:00 24-Jul-22 20 :00 484 487 231
486 Belzona application on Channel/Cover 18 24-Jul-22 08:00 25-Jul-22 02 :00 484 488 231

487 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 485 488 231
HJ
488 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 486, 487489 231
489 Shell side hydrotest at 15 kg/cm2 with 12 25-Jul-22 06:00 25-Jul-22 18 :00 488 490 231
Oil
490 Channel/Dome box up 10 25-Jul-22 18:00 26-Jul-22 04 :00 489 491 231
491 Tube side hydrotest at 15 kg/cm2 8 26-Jul-22 04:00 26-Jul-22 12 :00 490 492 231

492 De-blinding 6 26-Jul-22 12:00 26-Jul-22 18 :00 491 520 231


ME-RH471-S26 (571-C01C water cooler) 14 23-Jul-22 16:00 24-Jul-22 06 :00 291
Process handover 8 23-Jul-22 16:00 24-Jul-22 00 :00 291
495 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 496 291
496 Blinding 2 23-Jul-22 18:00 23-Jul-22 20 :00 495 497 291
497 Steaming 4 23-Jul-22 20:00 24-Jul-22 00 :00 496 499 291
Maintenance/Inspection jobs 6 24-Jul-22 00:00 24-Jul-22 06 :00 291
499 External water cleaning 2 24-Jul-22 00:00 24-Jul-22 02 :00 497 500 291
500 Hydrotest at 10 kg/cm2 2 24-Jul-22 02:00 24-Jul-22 04 :00 499 501 291
501 Deblinding 2 24-Jul-22 04:00 24-Jul-22 06 :00 500 520 291
ME-RH471-S33 (STRIPPER REBOILER) 164 23-Jul-22 16:00 30-Jul-22 12 :00 141
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 211
504 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 505 211
505 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 504 506 211
506 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 505 508 211
Maintenance/Inspection jobs 146 24-Jul-22 10:00 30-Jul-22 12 :00 141

Page 17 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
508 Dome & piping bolt detorquing 4 24-Jul-22 10:00 24-Jul-22 14 :00 506 509 211
509 Dome & piping removal 8 24-Jul-22 14:00 24-Jul-22 22 :00 508 510 211
510 Tube bundle puller arrangement & 6 27-Jul-22 20:00 28-Jul-22 02 :00 509, 511 141
Bundle pullout 156
511 Tube bundle shifting to hydrojetting bay 4 28-Jul-22 02:00 28-Jul-22 06 :00 510 512 141

512 Hydrojetting 16 28-Jul-22 06:00 28-Jul-22 22 :00 511 513 141


513 Inspection by CES/CTS 4 28-Jul-22 22:00 29-Jul-22 02 :00 512 514 141
514 Tube bundle shifting to site 4 29-Jul-22 02:00 29-Jul-22 06 :00 513 515 141
515 Tube bundle insertion 6 29-Jul-22 06:00 29-Jul-22 12 :00 514 516 141
516 Shell side hydro testing at 33 kg/cm2 8 29-Jul-22 12:00 29-Jul-22 20 :00 515 517 141

517 Tube side hydrotesting at 50.8 kg/cm2 8 29-Jul-22 20:00 30-Jul-22 04 :00 516 518 141

518 Deblinding & piping boxup 8 30-Jul-22 04:00 30-Jul-22 12 :00 517 520 141
Exchanger Jobs Completion 0 05-Aug-22 07:00 05-Aug-22 07:00 2
520 Exchanger Jobs Completion 0 05-Aug-22 07:00 148, 165,1351
182, 202, 221, 235, Exchanger
2 256, 271, 307, 344, 357, 372, 386, 400, 409, 447, Jobs492,
464, 478, Completion
501, 518
Fin Fan Coolers M&I (Scope: 14 nos) 140 25-Jul-22 02:00 30-Jul-22 22 :00 131
42- 01)
ME-RH471-A01-01 (PRODUCTS CONDENSER TUBE BUNDLE 25-Jul-22 02:00 26-Jul-22 20 :00 229
523 Blinding 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 524, 531 131
524 20% plug opening 6 25-Jul-22 08:00 25-Jul-22 14 :00 523 525, 532, 556 159
525 Inspection 2 25-Jul-22 14:00 25-Jul-22 16 :00 524 526, 533 159
526 Hydrojetting 8 25-Jul-22 16:00 26-Jul-22 00 :00 525 527, 534 159
527 Inspection after HJ 2 26-Jul-22 00:00 26-Jul-22 02 :00 526 528 159
528 Hydrotest 10 26-Jul-22 02:00 26-Jul-22 12 :00 527 529, 536 159
529 Deblinding 8 26-Jul-22 12:00 26-Jul-22 20 :00 528 635 229
46- 02)
ME-RH471-A01-02 (PRODUCTS CONDENSER TUBE BUNDLE 25-Jul-22 08:00 27-Jul-22 06 :00 219
531 Blinding 6 25-Jul-22 08:00 25-Jul-22 14 :00 523 532, 539 131
532 20% plug opening 6 25-Jul-22 14:00 25-Jul-22 20 :00 531, 524533, 540 163
533 Inspection 2 25-Jul-22 20:00 25-Jul-22 22 :00 525, 532534, 541 163
534 Hydrojetting 8 26-Jul-22 00:00 26-Jul-22 08 :00 526, 533535, 542 161
535 Inspection after HJ 2 26-Jul-22 08:00 26-Jul-22 10 :00 534 536 161
536 Hydrotest 10 26-Jul-22 12:00 26-Jul-22 22 :00 535, 528537, 544 159
537 Deblinding 8 26-Jul-22 22:00 27-Jul-22 06 :00 536 635 219
50- 03)
ME-RH471-A01-03 (PRODUCTS CONDENSER TUBE BUNDLE 25-Jul-22 14:00 27-Jul-22 16 :00 209
539 Blinding 6 25-Jul-22 14:00 25-Jul-22 20 :00 531 540, 547 131
540 20% plug opening 6 25-Jul-22 20:00 26-Jul-22 02 :00 539, 532541, 548 167
541 Inspection 2 26-Jul-22 02:00 26-Jul-22 04 :00 533, 540542, 549 167
542 Hydrojetting 8 26-Jul-22 08:00 26-Jul-22 16 :00 534, 541543, 550 163
543 Inspection after HJ 2 26-Jul-22 16:00 26-Jul-22 18 :00 542 544 163
Page 18 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
544 Hydrotest 10 26-Jul-22 22:00 27-Jul-22 08 :00 543, 536545, 552 159
545 Deblinding 8 27-Jul-22 08:00 27-Jul-22 16 :00 544 635 209
54- 04)
ME-RH471-A01-04 (PRODUCTS CONDENSER TUBE BUNDLE 25-Jul-22 20:00 28-Jul-22 02 :00 199
547 Blinding 6 25-Jul-22 20:00 26-Jul-22 02 :00 539 548, 555 131
548 20% plug opening 6 26-Jul-22 02:00 26-Jul-22 08 :00 547, 540549 171
549 Inspection 2 26-Jul-22 08:00 26-Jul-22 10 :00 541, 548550, 557 171
550 Hydrojetting 8 26-Jul-22 16:00 27-Jul-22 00 :00 549, 542551, 558 165
551 Inspection after HJ 2 27-Jul-22 00:00 27-Jul-22 02 :00 550 552 165
552 Hydrotest 10 27-Jul-22 08:00 27-Jul-22 18 :00 551, 544553, 560 159
553 Deblinding 8 27-Jul-22 18:00 28-Jul-22 02 :00 552 635 199
58- 05)
ME-RH471-A01-05 (PRODUCTS CONDENSER TUBE BUNDLE 26-Jul-22 02:00 28-Jul-22 12 :00 189
555 Blinding 6 26-Jul-22 02:00 26-Jul-22 08 :00 18, 547 556, 563 131
556 20% plug opening 6 26-Jul-22 08:00 26-Jul-22 14 :00 524, 555557, 564 175
557 Inspection 2 26-Jul-22 14:00 26-Jul-22 16 :00 549, 556558, 565 175
558 Hydrojetting 8 27-Jul-22 00:00 27-Jul-22 08 :00 557, 550559, 566 167
559 Inspection after HJ 2 27-Jul-22 08:00 27-Jul-22 10 :00 558 560 167
560 Hydrotest 10 27-Jul-22 18:00 28-Jul-22 04 :00 559, 552561, 568 159
561 Deblinding 8 28-Jul-22 04:00 28-Jul-22 12 :00 560 635 189
62- 06)
ME-RH471-A01-06 (PRODUCTS CONDENSER TUBE BUNDLE 26-Jul-22 08:00 28-Jul-22 22 :00 179
563 Blinding 6 26-Jul-22 08:00 26-Jul-22 14 :00 18, 555 564, 571 131
564 20% plug opening 6 26-Jul-22 14:00 26-Jul-22 20 :00 563, 556565, 572 179
565 Inspection 2 26-Jul-22 20:00 26-Jul-22 22 :00 557, 564566, 573 179
566 Hydrojetting 8 27-Jul-22 08:00 27-Jul-22 16 :00 565, 558567, 574 169
567 Inspection after HJ 2 27-Jul-22 16:00 27-Jul-22 18 :00 566 568 169
568 Hydrotest 10 28-Jul-22 04:00 28-Jul-22 14 :00 567, 560569, 576 159
569 Deblinding 8 28-Jul-22 14:00 28-Jul-22 22 :00 568 635 179
66- 07)
ME-RH471-A01-07 (PRODUCTS CONDENSER TUBE BUNDLE 26-Jul-22 14:00 29-Jul-22 08 :00 169
571 Blinding 6 26-Jul-22 14:00 26-Jul-22 20 :00 18, 563 572, 579 131
572 20% plug opening 6 26-Jul-22 20:00 27-Jul-22 02 :00 571, 564580 187
573 Inspection 2 26-Jul-22 22:00 27-Jul-22 00 :00 565 574, 581 187
574 Hydrojetting 8 27-Jul-22 16:00 28-Jul-22 00 :00 566, 573575, 582 171
575 Inspection after HJ 2 28-Jul-22 00:00 28-Jul-22 02 :00 574 576 171
576 Hydrotest 10 28-Jul-22 14:00 29-Jul-22 00 :00 575, 568577, 584 159
577 Deblinding 8 29-Jul-22 00:00 29-Jul-22 08 :00 576 635 169
70- 08)
ME-RH471-A01-08 (PRODUCTS CONDENSER TUBE BUNDLE 26-Jul-22 20:00 29-Jul-22 18 :00 159
579 Blinding 6 26-Jul-22 20:00 27-Jul-22 02 :00 18, 571 580, 587 131
580 20% plug opening 6 27-Jul-22 02:00 27-Jul-22 08 :00 579, 572581 187
581 Inspection 2 27-Jul-22 08:00 27-Jul-22 10 :00 573, 580582 187
582 Hydrojetting 8 28-Jul-22 00:00 28-Jul-22 08 :00 574, 581583 173

Page 19 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
583 Inspection after HJ 2 28-Jul-22 08:00 28-Jul-22 10 :00 582 584 173
584 Hydrotest 10 29-Jul-22 00:00 29-Jul-22 10 :00 583, 576585 159
585 Deblinding 8 29-Jul-22 10:00 29-Jul-22 18 :00 584 635 159
ME-RH471-A02 (STRIPPER CONDENSOR) 42 27-Jul-22 02:00 28-Jul-22 20 :00 181
587 Blinding 6 27-Jul-22 02:00 27-Jul-22 08 :00 579 588, 595 131
588 20% plug opening 6 27-Jul-22 08:00 27-Jul-22 14 :00 587 589, 596 131
589 Inspection 2 27-Jul-22 14:00 27-Jul-22 16 :00 588 590, 597 131
590 Hydrojetting 8 27-Jul-22 16:00 28-Jul-22 00 :00 589 591, 598 131
591 Inspection after HJ 2 28-Jul-22 00:00 28-Jul-22 02 :00 590 592 131
592 Hydrotest 10 28-Jul-22 02:00 28-Jul-22 12 :00 591 593, 600 131
593 Deblinding 8 28-Jul-22 12:00 28-Jul-22 20 :00 592 635 181
ME-RH471-A02-03 (STRIPPER CONDENSER TUBE BUNDLE46
- 02)27-Jul-22 08:00 29-Jul-22 06 :00 171
595 Blinding 6 27-Jul-22 08:00 27-Jul-22 14 :00 587 596, 603 135
596 20% plug opening 6 27-Jul-22 14:00 27-Jul-22 20 :00 595, 588597, 604 135
597 Inspection 2 27-Jul-22 20:00 27-Jul-22 22 :00 589, 596598, 605 135
598 Hydrojetting 8 28-Jul-22 00:00 28-Jul-22 08 :00 597, 590599, 606 133
599 Inspection after HJ 2 28-Jul-22 08:00 28-Jul-22 10 :00 598 600 133
600 Hydrotest 10 28-Jul-22 12:00 28-Jul-22 22 :00 599, 592601, 608 131
601 Deblinding 8 28-Jul-22 22:00 29-Jul-22 06 :00 600 635 171
50 27-Jul-22
ME-RH471-A04-01 (STRIPPER BOTTOMS COOLER TUBE BUNDLE - 01) 14:00 29-Jul-22 16 :00 161
603 Blinding 6 27-Jul-22 14:00 27-Jul-22 20 :00 595 604, 611 139
604 20% plug opening 6 27-Jul-22 20:00 28-Jul-22 02 :00 603, 596605 139
605 Inspection 2 28-Jul-22 02:00 28-Jul-22 04 :00 597, 604606, 613 139
606 Hydrojetting 8 28-Jul-22 08:00 28-Jul-22 16 :00 605, 598607, 614 135
607 Inspection after HJ 2 28-Jul-22 16:00 28-Jul-22 18 :00 606 608 135
608 Hydrotest 10 28-Jul-22 22:00 29-Jul-22 08 :00 607, 600609, 616 131
609 Deblinding 8 29-Jul-22 08:00 29-Jul-22 16 :00 608 635 161
54 27-Jul-22
ME-RH471-A04-02 (STRIPPER BOTTOMS COOLER TUBE BUNDLE - 02) 20:00 30-Jul-22 02 :00 151
611 Blinding 6 27-Jul-22 20:00 28-Jul-22 02 :00 603 612, 619 143
612 20% plug opening 6 28-Jul-22 02:00 28-Jul-22 08 :00 611 613, 620 143
613 Inspection 2 28-Jul-22 08:00 28-Jul-22 10 :00 605, 612614, 621 143
614 Hydrojetting 8 28-Jul-22 16:00 29-Jul-22 00 :00 613, 606615, 622 137
615 Inspection after HJ 2 29-Jul-22 00:00 29-Jul-22 02 :00 614 616 137
616 Hydrotest 10 29-Jul-22 08:00 29-Jul-22 18 :00 608, 615617, 624 131
617 Deblinding 8 29-Jul-22 18:00 30-Jul-22 02 :00 616 635 151
58 28-Jul-22
ME-RH471-A04-03 (STRIPPER BOTTOMS COOLER TUBE BUNDLE - 03) 02:00 30-Jul-22 12 :00 141
619 Blinding 6 28-Jul-22 02:00 28-Jul-22 08 :00 611 620, 627 147
620 20% plug opening 6 28-Jul-22 08:00 28-Jul-22 14 :00 612, 619621, 628 147
621 Inspection 2 28-Jul-22 14:00 28-Jul-22 16 :00 613, 620622, 629 147

Page 20 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
622 Hydrojetting 8 29-Jul-22 00:00 29-Jul-22 08 :00 614, 621623, 630 139
623 Inspection after HJ 2 29-Jul-22 08:00 29-Jul-22 10 :00 622 624 139
624 Hydrotest 10 29-Jul-22 18:00 30-Jul-22 04 :00 623, 616625, 632 131
625 Deblinding 8 30-Jul-22 04:00 30-Jul-22 12 :00 624 635 141
62 28-Jul-22
ME-RH471-A04-04 (STRIPPER BOTTOMS COOLER TUBE BUNDLE - 04) 08:00 30-Jul-22 22 :00 131
627 Blinding 6 28-Jul-22 08:00 28-Jul-22 14 :00 619 628 151
628 20% plug opening 6 28-Jul-22 14:00 28-Jul-22 20 :00 620, 627629 151
629 Inspection 2 28-Jul-22 20:00 28-Jul-22 22 :00 621, 628630 151
630 Hydrojetting 8 29-Jul-22 08:00 29-Jul-22 16 :00 629, 622631 141
631 Inspection after HJ 2 29-Jul-22 16:00 29-Jul-22 18 :00 630 632 141
632 Hydrotest 10 30-Jul-22 04:00 30-Jul-22 14 :00 624, 631633 131
633 Deblinding 8 30-Jul-22 14:00 30-Jul-22 22 :00 632 635 131
Fin Fan Coolers M&I Completion 0 30-Jul-22 22:00 30-Jul-22 22 :00 131
635 Fin Fan Coolers M&I Completion 0 30-Jul-22 22:00 529, 537,1351 569, 577, 585, 593, 601, 625, 633,Fin
545, 553, 561, 131 609,Fan Coolers M&I Completion
617
Column M&I (Scope: 01 no) 206 25-Jul-22 02:00 02-Aug-22 16:00 65
MV-RH471-C07 (STRIPPER) M&I 206 25-Jul-22 02:00 02-Aug-22 16:00 65
Process Hand over 76 25-Jul-22 02:00 28-Jul-22 06 :00 65
639 Purging 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 640 65
640 Blinding 16 25-Jul-22 08:00 26-Jul-22 00 :00 639 641 65
641 Steaming 18 26-Jul-22 00:00 26-Jul-22 18 :00 640 642 65
642 Cooling 6 26-Jul-22 18:00 27-Jul-22 00 :00 641 643 65
643 Open Column Manways (3 nos) 12 27-Jul-22 00:00 27-Jul-22 12 :00 642 644 65
644 Air circulation for Vessel Entry 16 27-Jul-22 12:00 28-Jul-22 04 :00 643 645 65
645 Vessel Entry 2 28-Jul-22 04:00 28-Jul-22 06 :00 644 647 65
Maintenance/Inspection Jobs 130 28-Jul-22 06:00 02-Aug-22 16:00 65
647 Opening of Tray manways 12 28-Jul-22 06:00 28-Jul-22 18 :00 645 648 65
648 Tray cleaning 12 28-Jul-22 18:00 29-Jul-22 06 :00 647 649, 653 65
649 CTS/CES inspection 4 29-Jul-22 06:00 29-Jul-22 10 :00 648 650 65
653 2" 150# Isolation Valve Provision for 24 29-Jul-22 06:00 30-Jul-22 06 :00 648 654 65
Stand Pipe (Scope : 02 nos)

650 Scaffold erection for buffing/inspection 12 29-Jul-22 10:00 29-Jul-22 22 :00 649 651 65
of weld joints

651 Buffing of top dish end to shell weld joint 8 29-Jul-22 22:00 30-Jul-22 06 :00 650 652, 655 65

652 WFDPT inspection 4 30-Jul-22 06:00 30-Jul-22 10 :00 651 656 85


654 Hydro test of LG/LT pipe 24 30-Jul-22 06:00 31-Jul-22 06 :00 653 656 65

Page 21 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
655 Internal Thickness survey for distributer, 24 30-Jul-22 06:00 31-Jul-22 06 :00 651 656 65
pockets, nozzles, shell etc.

656 Scaffold removal for buffing/inspection 8 31-Jul-22 06:00 31-Jul-22 14 :00 652, 657 65
of weld joints 655,
654
657 Tray cleaning before box up 6 31-Jul-22 14:00 31-Jul-22 20 :00 656 658 65
658 CES/CTS final inspection and clearance 4 31-Jul-22 20:00 01-Aug-22 00:00 657 659 65
for tray manway box up

659 Tray manway box up 12 01-Aug-22 00:00 01-Aug-22 12:00 658 660 65
660 Column manway box up (3 nos) 12 01-Aug-22 12:00 02-Aug-22 00:00 659 661 65
661 Column de-blinding 16 02-Aug-22 00:00 02-Aug-22 16:00 660 663 65
Column M&I Completion 0 02-Aug-22 16:00 02-Aug-22 16:00 65
663 Column M&I Completion 0 02-Aug-22 16:00 661 1351 65 Column M&I Completion
Vessel M&I (Scope: 25 nos) 158 25-Jul-22 02:00 31-Jul-22 16 :00 113
MV-RH471-V01 (FEED SURGE DRUM) 114 25-Jul-22 02:00 29-Jul-22 20 :00 157
Process Hand over 54 25-Jul-22 02:00 27-Jul-22 08 :00 157
667 Draining 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 668 157
668 Purging 8 25-Jul-22 08:00 25-Jul-22 16 :00 667 669 157
669 Blinding 8 25-Jul-22 16:00 26-Jul-22 00 :00 668 670 157
670 Steaming 8 26-Jul-22 00:00 26-Jul-22 08 :00 669 671 157
671 Opening of Manholes 4 26-Jul-22 08:00 26-Jul-22 12 :00 670 672 157
672 Establish air circulation 8 26-Jul-22 12:00 26-Jul-22 20 :00 671 673 157
673 Vessel Entry 2 26-Jul-22 20:00 26-Jul-22 22 :00 672 674 157
674 Cleaning of Vessel 10 26-Jul-22 22:00 27-Jul-22 08 :00 673 676 157
Maintenance/Inspection Jobs 60 27-Jul-22 08:00 29-Jul-22 20 :00 157
676 CTS/CES inspection 4 27-Jul-22 08:00 27-Jul-22 12 :00 674 677, 680 157
677 Scaffolding erection 8 27-Jul-22 12:00 27-Jul-22 20 :00 676 678 157
680 Hydro test of LG/LT pipe 12 27-Jul-22 12:00 28-Jul-22 00 :00 676 685 191
678 Buffing of top dish end to shell weld joint 8 27-Jul-22 20:00 28-Jul-22 04 :00 677 679, 681 157

679 WFMPT inspection 4 28-Jul-22 04:00 28-Jul-22 08 :00 678 684 177
681 Thickness survey 12 28-Jul-22 04:00 28-Jul-22 16 :00 678 682 157
682 Scaffolding removal 6 28-Jul-22 16:00 28-Jul-22 22 :00 681 683 157
683 Final Cleaning 6 28-Jul-22 22:00 29-Jul-22 04 :00 682 684 157
684 Manway box up 6 29-Jul-22 04:00 29-Jul-22 10 :00 683, 679685 157
685 De-blinding 10 29-Jul-22 10:00 29-Jul-22 20 :00 684, 6801073 157
MV-RH471-V05 (SEPARATOR) 113 25-Jul-22 02:00 29-Jul-22 19 :00 158

Page 22 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
Process Hand over 51 25-Jul-22 02:00 27-Jul-22 05 :00 158
688 Purging 5 25-Jul-22 02:00 25-Jul-22 07 :00 18 689 158
689 Blinding 8 25-Jul-22 07:00 25-Jul-22 15 :00 688 690 158
690 Steaming/Cooling 16 25-Jul-22 15:00 26-Jul-22 07 :00 689 691 158
691 Opening of Manholes 4 26-Jul-22 07:00 26-Jul-22 11 :00 690 692 158
692 Establish air circulation 8 26-Jul-22 11:00 26-Jul-22 19 :00 691 693 158
693 Vessel Entry 2 26-Jul-22 19:00 26-Jul-22 21 :00 692 694 158
694 Cleaning of Vessel 8 26-Jul-22 21:00 27-Jul-22 05 :00 693 696 158
Maintenance/Inspection Jobs 62 27-Jul-22 05:00 29-Jul-22 19 :00 158
696 CTS/CES inspection 4 27-Jul-22 05:00 27-Jul-22 09 :00 694 697, 701 158
697 Demister removal 6 27-Jul-22 09:00 27-Jul-22 15 :00 696 698, 702 158
701 Hydro test of LG/LT pipe 12 27-Jul-22 09:00 27-Jul-22 21 :00 696 704 178
698 Scaffolding erection 8 27-Jul-22 15:00 27-Jul-22 23 :00 697 699 158
702 Thickness survey 12 27-Jul-22 15:00 28-Jul-22 03 :00 697 704 172
699 Buffing of top dish end to shell weld joint 8 27-Jul-22 23:00 28-Jul-22 07 :00 698 700 158

700 WFMPT inspection 4 28-Jul-22 07:00 28-Jul-22 11 :00 699 703 158
703 Scaffolding removal 6 28-Jul-22 11:00 28-Jul-22 17 :00 700 704 158
704 Demister fixing 6 28-Jul-22 17:00 28-Jul-22 23 :00 703, 701,705
702 158
705 Final Cleaning 6 28-Jul-22 23:00 29-Jul-22 05 :00 704 706 158
706 Manway box up 6 29-Jul-22 05:00 29-Jul-22 11 :00 705 707 158
707 De-blinding 8 29-Jul-22 11:00 29-Jul-22 19 :00 706 1073 158
MV-RH471-V06 (COMPRESSOR SUCTION KOD) 106 25-Jul-22 02:00 29-Jul-22 12 :00 165
Process Hand over 56 25-Jul-22 02:00 27-Jul-22 10 :00 165
710 Purging 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 711 165
711 Blinding 8 25-Jul-22 08:00 25-Jul-22 16 :00 710 712 165
712 Steaming 8 25-Jul-22 16:00 26-Jul-22 00 :00 711 713 165
713 Cooling 8 26-Jul-22 00:00 26-Jul-22 08 :00 712 714 165
714 Opening of Manholes 6 26-Jul-22 08:00 26-Jul-22 14 :00 713 715 165
715 Establish air circulation 8 26-Jul-22 14:00 26-Jul-22 22 :00 714 716 165
716 Vessel Entry 2 26-Jul-22 22:00 27-Jul-22 00 :00 715 717 165
717 Cleaning of Vessel 10 27-Jul-22 00:00 27-Jul-22 10 :00 716 719 165
Maintenance/Inspection Jobs 50 27-Jul-22 10:00 29-Jul-22 12 :00 165
719 CTS/CES inspection 4 27-Jul-22 10:00 27-Jul-22 14 :00 717 720, 723 165
720 Scaffolding erection 8 27-Jul-22 14:00 27-Jul-22 22 :00 719 721, 724 165
723 Hydro test of LG/LT pipe 12 27-Jul-22 14:00 28-Jul-22 02 :00 719 726 179
721 Buffing of top dish end to shell weld joint 8 27-Jul-22 22:00 28-Jul-22 06 :00 720 722 165

724 Thickness survey 12 27-Jul-22 22:00 28-Jul-22 10 :00 720 726 171
722 WFMPT inspection 4 28-Jul-22 06:00 28-Jul-22 10 :00 721 725 165
Page 23 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
725 Scaffolding removal 6 28-Jul-22 10:00 28-Jul-22 16 :00 722 726 165
726 Final Cleaning 6 28-Jul-22 16:00 28-Jul-22 22 :00 724, 725,727
723 165
727 Manway box up 6 28-Jul-22 22:00 29-Jul-22 04 :00 726 728 165
728 De-blinding 8 29-Jul-22 04:00 29-Jul-22 12 :00 727 1073 165
MV-RH471-V08 (STRIPPER RECEIVER) 116 25-Jul-22 02:00 29-Jul-22 22 :00 155
Process Hand over 56 25-Jul-22 02:00 27-Jul-22 10 :00 155
731 Purging 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 732 155
732 Blinding 8 25-Jul-22 08:00 25-Jul-22 16 :00 731 733 155
733 Steaming 8 25-Jul-22 16:00 26-Jul-22 00 :00 732 734 155
734 Cooling 8 26-Jul-22 00:00 26-Jul-22 08 :00 733 735 155
735 Opening of Manholes 6 26-Jul-22 08:00 26-Jul-22 14 :00 734 736 155
736 Establish air circulation 8 26-Jul-22 14:00 26-Jul-22 22 :00 735 737 155
737 Vessel Entry 2 26-Jul-22 22:00 27-Jul-22 00 :00 736 738 155
738 Cleaning of Vessel 10 27-Jul-22 00:00 27-Jul-22 10 :00 737 740 155
Maintenance/Inspection Jobs 60 27-Jul-22 10:00 29-Jul-22 22 :00 155
740 CTS/CES inspection 4 27-Jul-22 10:00 27-Jul-22 14 :00 738 741, 744 155
741 Scaffolding erection 8 27-Jul-22 14:00 27-Jul-22 22 :00 740 742, 746 162
744 2 300# Isolation Valve Provision for 24 27-Jul-22 14:00 28-Jul-22 14 :00 740 745 155
Stand Pipe (Scope : 04 nos)

742 Buffing of top dish end to shell weld joint 8 27-Jul-22 22:00 28-Jul-22 06 :00 741 743 162

746 Thickness survey 12 27-Jul-22 22:00 28-Jul-22 10 :00 741 748 171
743 WFMPT inspection 7 28-Jul-22 06:00 28-Jul-22 13 :00 742 747 162
747 Scaffolding removal 6 28-Jul-22 13:00 28-Jul-22 19 :00 743 748 162
745 Hydro test of LG/LT pipe 12 28-Jul-22 14:00 29-Jul-22 02 :00 744 748 155
748 Final Cleaning 6 29-Jul-22 02:00 29-Jul-22 08 :00 745, 746,749
747 155
749 Manway box up 6 29-Jul-22 08:00 29-Jul-22 14 :00 748 750 155
750 De-blinding 8 29-Jul-22 14:00 29-Jul-22 22 :00 749 1073 155
MV-RH471-V09 (FUEL GAS DRUM) 104 25-Jul-22 02:00 29-Jul-22 10 :00 167
Process Hand over 60 25-Jul-22 02:00 27-Jul-22 14 :00 167
753 Purging 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 754 167
754 Blinding 8 25-Jul-22 08:00 25-Jul-22 16 :00 753 755 167
755 Steaming 12 25-Jul-22 16:00 26-Jul-22 04 :00 754 756 167
756 Cooling 8 26-Jul-22 04:00 26-Jul-22 12 :00 755 757 167
757 Opening of Manholes 4 26-Jul-22 12:00 26-Jul-22 16 :00 756 758 167
758 Establish air circulation 8 26-Jul-22 16:00 27-Jul-22 00 :00 757 759 167
759 Vessel Entry 2 27-Jul-22 00:00 27-Jul-22 02 :00 758 760 167
760 Cleaning of Vessel 12 27-Jul-22 02:00 27-Jul-22 14 :00 759 762 167
Maintenance/Inspection Jobs 44 27-Jul-22 14:00 29-Jul-22 10 :00 167
Page 24 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
762 CTS/CES inspection 4 27-Jul-22 14:00 27-Jul-22 18 :00 760 763, 765 167
763 Scaffolding erection 8 27-Jul-22 18:00 28-Jul-22 02 :00 762 764, 766 167
765 Hydro test of LG/LT pipe 12 27-Jul-22 18:00 28-Jul-22 06 :00 762 768 175
764 Demister pad inspection 4 28-Jul-22 02:00 28-Jul-22 06 :00 763 767 169
766 Thickness survey 12 28-Jul-22 02:00 28-Jul-22 14 :00 763 768 167
767 Scaffolding removal 6 28-Jul-22 06:00 28-Jul-22 12 :00 764 768 169
768 Final Cleaning 6 28-Jul-22 14:00 28-Jul-22 20 :00 765, 766,769
767 167
769 Manway box up 6 28-Jul-22 20:00 29-Jul-22 02 :00 768 770 167
770 De-blinding 8 29-Jul-22 02:00 29-Jul-22 10 :00 769 1073 167
MV-RH471-V10 (INTERMITTENT BLOWDOWN DRUM) 106 25-Jul-22 02:00 29-Jul-22 12 :00 165
Process Hand over 56 25-Jul-22 02:00 27-Jul-22 10 :00 165
773 Purging 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 774 165
774 Blinding 8 25-Jul-22 08:00 25-Jul-22 16 :00 773 775 165
775 Steaming 8 25-Jul-22 16:00 26-Jul-22 00 :00 774 776 165
776 Cooling 8 26-Jul-22 00:00 26-Jul-22 08 :00 775 777 165
777 Opening of Manholes 6 26-Jul-22 08:00 26-Jul-22 14 :00 776 778 165
778 Establish air circulation 8 26-Jul-22 14:00 26-Jul-22 22 :00 777 779 165
779 Vessel Entry 2 26-Jul-22 22:00 27-Jul-22 00 :00 778 780 165
780 Cleaning of Vessel 10 27-Jul-22 00:00 27-Jul-22 10 :00 779 782 165
Maintenance/Inspection Jobs 50 27-Jul-22 10:00 29-Jul-22 12 :00 165
782 CTS/CES inspection 4 27-Jul-22 10:00 27-Jul-22 14 :00 780, 882783, 786 165
783 Scaffolding erection 8 27-Jul-22 14:00 27-Jul-22 22 :00 782 784, 787 165
786 Hydro test of LG/LT pipe 12 27-Jul-22 14:00 28-Jul-22 02 :00 782 789 179
784 Buffing of top dish end to shell weld joint 8 27-Jul-22 22:00 28-Jul-22 06 :00 783 785 165

787 Thickness survey 12 27-Jul-22 22:00 28-Jul-22 10 :00 783 789 171
785 WFMPT inspection 4 28-Jul-22 06:00 28-Jul-22 10 :00 784 788 165
788 Scaffolding removal 6 28-Jul-22 10:00 28-Jul-22 16 :00 785 789 165
789 Final Cleaning 6 28-Jul-22 16:00 28-Jul-22 22 :00 786, 787,790
788 165
790 Manway box up 6 28-Jul-22 22:00 29-Jul-22 04 :00 789 791 165
791 De-blinding 8 29-Jul-22 04:00 29-Jul-22 12 :00 790 1073 165
32 25-Jul-22
MV-RH471-V12A (SUCTION DAMPENERS-MC-RH471-C01A(CYL 1)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
794 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 795 239
795 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 794 796 239
796 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 795 797 239
797 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 796 798 239
798 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 797 800 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239

Page 25 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
800 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 798 801 239
801 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 800 802 239

802 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 801 803 239
803 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 802 804 239
804 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 803 805 239
805 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 804 1073 239
32 25-Jul-22
MV-RH471-V12B (SUCTION DAMPENERS-MC-RH471-C01B(CYL 1)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
808 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 809 239
809 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 808 810 239
810 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 809 811 239
811 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 810 812 239
812 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 811 814 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
814 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 812 815 239
815 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 814 816 239

816 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 815 817 239
817 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 816 818 239
818 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 817 819 239
819 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 818 1073 239
32 25-Jul-22
MV-RH471-V12C (SUCTION DAMPENERS-MC-RH471-C01C(CYL 1)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
822 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 823 239
823 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 822 824 239
824 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 823 825 239
825 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 824 826 239
826 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 825 828 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
828 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 826 829 239
829 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 828 830 239

830 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 829 831 239
831 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 830 832 239
832 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 831 833 239
833 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 832 1073 239
32
MV-RH471-V13A (DISCH.DAMPENERS-MC-RH471-C01A(CYL 1)) 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239

Page 26 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
836 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 837 239
837 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 836 838 239
838 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 837 839 239
839 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 838 840 239
840 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 839 842 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
842 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 840 843 239
843 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 842 844 239

844 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 843 845 239
845 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 844 846 239
846 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 845 847 239
847 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 846 1073 239
32
MV-RH471-V13B (DISCH.DAMPENERS-MC-RH471-C01B(CYL 1)) 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
850 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 851 239
851 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 850 852 239
852 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 851 853 239
853 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 852 854 239
854 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 853 856 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
856 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 854 857 239
857 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 856 858 239

858 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 857 859 239
859 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 858 860 239
860 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 859 861 239
861 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 860 1073 239
32
MV-RH471-V13C (DISCH.DAMPENERS-MC-RH471-C01C(CYL 1)) 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
864 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 865 239
865 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 864 866 239
866 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 865 867 239
867 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 866 868 239
868 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 867 870 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
870 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 868 871 239
871 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 870 872 239

Page 27 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
872 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 871 873 239
873 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 872 874 239
874 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 873 875 239
875 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 874 1073 239
MV-RH471-V15 (CRACKED SLOP DRAIN TANK) 68 25-Jul-22 02:00 27-Jul-22 22 :00 203
Process Hand over 30 25-Jul-22 02:00 26-Jul-22 08 :00 191
878 Blinding 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 879 191
879 Opening of Manholes 4 25-Jul-22 08:00 25-Jul-22 12 :00 878 880 191
880 Establish air circulation 8 25-Jul-22 12:00 25-Jul-22 20 :00 879 881 191
881 Vessel Entry 2 25-Jul-22 20:00 25-Jul-22 22 :00 880 882 191
882 Cleaning of Vessel 10 25-Jul-22 22:00 26-Jul-22 08 :00 881 782, 884 191
Maintenance/Inspection Jobs 38 26-Jul-22 08:00 27-Jul-22 22 :00 203
884 Blinding for Hydro testing (Internal 4 26-Jul-22 08:00 26-Jul-22 12 :00 882 885 203
Steam Coil)
885 Hydrotest 10 26-Jul-22 12:00 26-Jul-22 22 :00 884 886 203
886 CTS/CES inspection 4 26-Jul-22 22:00 27-Jul-22 02 :00 885 887 203
887 De-blinding of Steam Coil 4 27-Jul-22 02:00 27-Jul-22 06 :00 886 888 203
888 Final Cleaning 6 27-Jul-22 06:00 27-Jul-22 12 :00 887 889 203
889 Manway box up 6 27-Jul-22 12:00 27-Jul-22 18 :00 888 890 203
890 De-blinding 4 27-Jul-22 18:00 27-Jul-22 22 :00 889 1073 203
MV-RH471-V16 (HP FLARE KNOCKOUT DRUM) 158 25-Jul-22 02:00 31-Jul-22 16 :00 113
Process Hand over 94 25-Jul-22 02:00 29-Jul-22 00 :00 113
893 Draining 12 25-Jul-22 02:00 25-Jul-22 14 :00 18 894 113
894 Purging 12 25-Jul-22 14:00 26-Jul-22 02 :00 893 895 113
895 Blinding 12 26-Jul-22 02:00 26-Jul-22 14 :00 894 896 113
896 Steaming 24 26-Jul-22 14:00 27-Jul-22 14 :00 895 897 113
897 Opening of Manholes 8 27-Jul-22 14:00 27-Jul-22 22 :00 896 898 113
898 Establish air circulation 16 27-Jul-22 22:00 28-Jul-22 14 :00 897 899 113
899 Vessel Entry 2 28-Jul-22 14:00 28-Jul-22 16 :00 898 900 113
900 Cleaning of Vessel 8 28-Jul-22 16:00 29-Jul-22 00 :00 899 902 113
Maintenance/Inspection Jobs 64 29-Jul-22 00:00 31-Jul-22 16 :00 113
902 CTS/CES inspection 4 29-Jul-22 00:00 29-Jul-22 04 :00 900 903, 906 113
903 Scaffolding erection 8 29-Jul-22 04:00 29-Jul-22 12 :00 902 904 113
906 Hydro test of LG/LT pipe 12 29-Jul-22 04:00 29-Jul-22 16 :00 902 911 149
904 Buffing of top dish end to shell weld joint 8 29-Jul-22 12:00 29-Jul-22 20 :00 903 905, 907 113

905 WFMPT inspection 4 29-Jul-22 20:00 30-Jul-22 00 :00 904 910 133
907 Thickness survey 12 29-Jul-22 20:00 30-Jul-22 08 :00 904 908 113
908 Scaffolding removal 6 30-Jul-22 08:00 30-Jul-22 14 :00 907 909 113

Page 28 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
909 Final Cleaning 6 30-Jul-22 14:00 30-Jul-22 20 :00 908 910 113
910 Manway box up 8 30-Jul-22 20:00 31-Jul-22 04 :00 905, 909911 113
911 De-blinding 12 31-Jul-22 04:00 31-Jul-22 16 :00 906, 9101073 113
MV-RH471-V19 (PILOT FUEL GAS KNOCKOUT DRUM) 114 25-Jul-22 02:00 29-Jul-22 20 :00 157
Process Hand over 54 25-Jul-22 02:00 27-Jul-22 08 :00 157
914 Blinding 8 25-Jul-22 02:00 25-Jul-22 10 :00 18 915 157
915 Steaming 12 25-Jul-22 10:00 25-Jul-22 22 :00 914 916 157
916 Cooling 8 25-Jul-22 22:00 26-Jul-22 06 :00 915 917 157
917 Opening of Manholes 4 26-Jul-22 06:00 26-Jul-22 10 :00 916 918 157
918 Establish air circulation 8 26-Jul-22 10:00 26-Jul-22 18 :00 917 919 157
919 Vessel Entry 2 26-Jul-22 18:00 26-Jul-22 20 :00 918 920 157
920 Cleaning of Vessel 12 26-Jul-22 20:00 27-Jul-22 08 :00 919 922 157
Maintenance/Inspection Jobs 60 27-Jul-22 08:00 29-Jul-22 20 :00 157
922 CTS/CES inspection 4 27-Jul-22 08:00 27-Jul-22 12 :00 920 923, 926 157
923 Scaffolding erection 8 27-Jul-22 12:00 27-Jul-22 20 :00 922 924 157
926 Hydro test of LG/LT pipe 12 27-Jul-22 12:00 28-Jul-22 00 :00 922 931 193
924 Buffing of top dish end to shell weld joint 8 27-Jul-22 20:00 28-Jul-22 04 :00 923 925, 927 157

925 WFMPT inspection 4 28-Jul-22 04:00 28-Jul-22 08 :00 924 930 177
927 Thickness survey 12 28-Jul-22 04:00 28-Jul-22 16 :00 924 928 157
928 Scaffolding removal 6 28-Jul-22 16:00 28-Jul-22 22 :00 927 929 157
929 Final Cleaning 6 28-Jul-22 22:00 29-Jul-22 04 :00 928 930 157
930 Manway box up 8 29-Jul-22 04:00 29-Jul-22 12 :00 925, 929931 157
931 De-blinding 8 29-Jul-22 12:00 29-Jul-22 20 :00 926, 9301073 157
32 25-Jul-22
MV-RH471-V22A (SUCTION DAMPENERS-MC-RH471-C01A (CYL 2)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
934 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 935 239
935 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 934 936 239
936 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 935 937 239
937 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 936 938 239
938 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 937 940 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
940 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 938 941 239
941 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 940 942 239

942 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 941 943 239
943 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 942 944 239
944 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 943 945 239
945 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 944 1073 239

Page 29 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
32 25-Jul-22
MV-RH471-V22B (SUCTION DAMPENERS-MC-RH471-C01B (CYL 2)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
948 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 949 239
949 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 948 950 239
950 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 949 951 239
951 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 950 952 239
952 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 951 954 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
954 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 952 955 239
955 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 954 956 239

956 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 955 957 239
957 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 956 958 239
958 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 957 959 239
959 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 958 1073 239
32 25-Jul-22
MV-RH471-V22C (SUCTION DAMPENERS-MC-RH471-C01C (CYL 2)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
962 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 963 239
963 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 962 964 239
964 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 963 965 239
965 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 964 966 239
966 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 965 968 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
968 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 966 969 239
969 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 968 970 239

970 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 969 971 239
971 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 970 972 239
972 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 971 973 239
973 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 972 1073 239
322))25-Jul-22
MV-RH471-V23A (DISCH.DAMPENERS-MC-RH471-C01A (CYL 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
976 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 977 239
977 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 976 978 239
978 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 977 979 239
979 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 978 980 239
980 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 979 982 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
982 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 980 983 239

Page 30 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
983 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 982 984 239

984 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 983 985 239
985 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 984 986 239
986 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 985 987 239
987 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 986 1073 239
322))25-Jul-22
MV-RH471-V23B (DISCH.DAMPENERS-MC-RH471-C01B (CYL 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
990 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 991 239
991 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 990 992 239
992 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 991 993 239
993 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 992 994 239
994 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 993 996 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
996 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 994 997 239
997 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 996 998 239

998 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 997 999 239
999 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 998 1000 239
1000 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 999 1001 239
1001 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1000 1073 239
322))25-Jul-22
MV-RH471-V23C (DISCH.DAMPENERS-MC-RH471-C01C (CYL 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
1004 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 1005 239
1005 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 1004 1006, 1073 239
1006 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 1005 1007 239
1007 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 1006 1008 239
1008 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 1007 1010 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
1010 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 1008 1011 239
1011 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 1010 1012 239

1012 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1011 1013 239
1013 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 1012 1014 239
1014 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 1013 1015 239
1015 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1014 1073 239
32 TK)
MV-RH471-V24 (CYLINDER CIRCULATING WATER EXPANSION 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
1018 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 1019 239

Page 31 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1019 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 1018 1020 239
1020 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 1019 1021 239
1021 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 1020 1022 239
1022 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 1021 1024 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
1024 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 1022 1025 239
1025 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 1024 1026 239

1026 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1025 1027 239
1027 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 1026 1028 239
1028 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 1027 1029 239
1029 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1028 1073 239
MV-RH471-V25 (PHOSPHATE DAY TANK) 32 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
1032 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 1033 239
1033 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 1032 1034 239
1034 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 1033 1035 239
1035 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 1034 1036 239
1036 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 1035 1038 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
1038 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 1036 1039 239
1039 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 1038 1040 239

1040 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1039 1041 239
1041 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 1040 1042 239
1042 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 1041 1043 239
1043 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1042 1073 239
MV-RH471-V26 (471-C01C CYLINDER CIRCULATING WATER32 25-Jul-22
EXPA) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
1046 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 1047 239
1047 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 1046 1048 239
1048 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 1047 1049 239
1049 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 1048 1050 239
1050 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 1049 1052 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
1052 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 1050 1053 239
1053 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 1052 1054 239

1054 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1053 1055 239

Page 32 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1055 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 1054 1056 239
1056 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 1055 1057 239
1057 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1056 1073 239
MV-RH471-V04 (WATER BREAK TANK) 32 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
1060 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 1061 239
1061 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 1060 1062 239
1062 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 1061 1063 239
1063 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 1062 1064 239
1064 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 1063 1066 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
1066 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 1064 1067 239
1067 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 1066 1068 239

1068 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1067 1069 239
1069 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 1068 1070 239
1070 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 1069 1071 239
1071 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1070 1073 239
Vessel M&I Completion 0 31-Jul-22 16:00 31-Jul-22 16 :00 113
1073 Vessel M&I Completion 0 31-Jul-22 16:00 685, 707,1351
728, 750, 770, 113 Vessel
791, 805, 819, 833, 847, 861, 875, 890, M&I
911, Completion
931, 945, 959, 973, 1005, 1001, 1
MB-RH471-F01 (Charge Heater) Inspection 178 24-Jul-22 16:00 01-Aug-22 02:00 214
Process Hand over 28 24-Jul-22 16:00 25-Jul-22 20 :00 181
1076 Blinding 8 24-Jul-22 16:00 25-Jul-22 00 :00 209 1077, 1095, 1098
103
1077 Mnaway Opening 6 25-Jul-22 00:00 25-Jul-22 06 :00 1076 1078 181
1078 Cooling 12 25-Jul-22 06:00 25-Jul-22 18 :00 1077 1079 181
1079 Vessel Entry Permit 2 25-Jul-22 18:00 25-Jul-22 20 :00 1078 1081, 1082, 1083
181
Maintenance/Inspection Jobs 170 25-Jul-22 00:00 01-Aug-22 02:00 214
1081 All burners dropping, cleaning & re-fixing 72 25-Jul-22 20:00 28-Jul-22 20 :00 1079 1090, 1471 181
1082 Stack damper checking (Mech / Inst) 12 25-Jul-22 20:00 26-Jul-22 08 :00 1079 1090 322

1083 Initial Inspection by CES- Inspection & 4 25-Jul-22 20:00 26-Jul-22 00 :00 1079 1084, 256
Refractory group 1085,
1084 Refractory repair in Access door and 24 26-Jul-22 00:00 27-Jul-22 00 :00 1083 1087
1090 306
Peep doors after inspection (if any-
Outside)

1085 Scaffolding erection 16 26-Jul-22 00:00 26-Jul-22 16 :00 1083 1086 256
1087 Burner block repair (If any) 24 26-Jul-22 00:00 27-Jul-22 00 :00 1083 1088, 1090 306
1088 Tube cleaning job (Outside) 12 26-Jul-22 00:00 26-Jul-22 12 :00 1087 1090 318

Page 33 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1086 Inspection of Refractory lining in Radiant 10 26-Jul-22 16:00 27-Jul-22 02 :00 1085 1089 256
wall,Roof and convection section

1089 Refractory repair in Radiant section, 48 27-Jul-22 02:00 29-Jul-22 02 :00 1086 1090 256
Roof and Convection section including
water curing

1090 Final inspection 4 29-Jul-22 02:00 29-Jul-22 06 :00 1089, 1087,


10911081, 1082, 256
1084, 1088
1091 Scaffolding removal 12 29-Jul-22 06:00 29-Jul-22 18 :00 1090 1092 256
1092 Manway box up 6 29-Jul-22 18:00 30-Jul-22 00 :00 1091 1093 256
1093 De-blinding 8 30-Jul-22 00:00 30-Jul-22 08 :00 1092 256
Coil Hydro testing & Pigging 170 25-Jul-22 00:00 01-Aug-22 02:00 103
1095 N2 Purging for Blinding 6 25-Jul-22 00:00 25-Jul-22 06 :00 1076 1096 103
1098 Insulation removal of Inlet and Outlet 6 25-Jul-22 00:00 25-Jul-22 06 :00 1076 1099 125
spool
1096 Tail Blind provision for passivation ( 6 6 25-Jul-22 06:00 25-Jul-22 12 :00 1095 1097 103
inch-08 Nos)
1097 Passivation of coils 16 25-Jul-22 12:00 26-Jul-22 04 :00 1096 1099 103
1099 Cutting of Inlet line (16 Inch-1 Cut) 6 26-Jul-22 04:00 26-Jul-22 10 :00 1097, 1098
1100, 1101, 1102
103
1100 Bolt Opening of Flanges (6 Inch- 04 6 26-Jul-22 10:00 26-Jul-22 16 :00 1099 1101 117
Flanges)
1102 Cutting of Outlet line-1 (16 Inch-01 6 26-Jul-22 10:00 26-Jul-22 16 :00 1099 1103, 103
Cut) 1104
1101 Inlet Spool Dropping 2 26-Jul-22 16:00 26-Jul-22 18 :00 1100, 1099
1110, 1140, 1155
117
1103 Bolt Opening of Flanges (6 Inch- 02 3 26-Jul-22 16:00 26-Jul-22 19 :00 1102 1104 103
Flanges)
1104 Outlet Spool-1 Dropping 2 26-Jul-22 19:00 26-Jul-22 21 :00 1103, 1102
1105, 1125 103
1105 Cutting of Outlet line-2 (16 Inch-01 6 26-Jul-22 21:00 27-Jul-22 03 :00 1104 1106, 103
Cut) 1107
1106 Bolt Opening of Flanges (6 Inch- 02 3 27-Jul-22 03:00 27-Jul-22 06 :00 1105 1107 103
Flanges)
1107 Outlet Spool-2 Dropping 2 27-Jul-22 06:00 27-Jul-22 08 :00 1106, 1105
1125 103
Coil 1 43 26-Jul-22 18:00 28-Jul-22 13 :00 135
1122 Coil Drying and N2 Purging 4 28-Jul-22 09:00 28-Jul-22 13 :00 1121, 1166
1169 135
Hydrotesting 18 26-Jul-22 18:00 27-Jul-22 12 :00 135
1110Blinding (6 Inch-02 Nos) 3 26-Jul-22 18:00 26-Jul-22 21 :00 1101 1111 135
1111Fixture fittings for Hydro test 2 26-Jul-22 21:00 26-Jul-22 23 :00 1110 1112 135
1112Water Fill up 2 26-Jul-22 23:00 27-Jul-22 01 :00 1111 1113 135
1113Hydro testing 4 27-Jul-22 01:00 27-Jul-22 05 :00 1112 1114 135
1114Inspection 2 27-Jul-22 05:00 27-Jul-22 07 :00 1113 1115 135

Page 34 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1115Fixture Removal 2 27-Jul-22 07:00 27-Jul-22 09 :00 1114 1116 135
1116De-blinding 3 27-Jul-22 09:00 27-Jul-22 12 :00 1115 1118 135
Pigging 21 27-Jul-22 12:00 28-Jul-22 09 :00 135
1118Pig Launcher Fixture set up 6 27-Jul-22 12:00 27-Jul-22 18 :00 1116, 1161
1119 135
1119Pigging 6 27-Jul-22 18:00 28-Jul-22 00 :00 1118 1120 135
1120Pig Launcher Fixture removal 6 28-Jul-22 00:00 28-Jul-22 06 :00 1119 1121 135
1121Blinding of Flange (06 Inch-02 Nos) 3 28-Jul-22 06:00 28-Jul-22 09 :00 1120 1122 135

Coil 2 43 27-Jul-22 08:00 29-Jul-22 03 :00 174


1137 Coil Drying and N2 Purging 4 28-Jul-22 23:00 29-Jul-22 03 :00 1136, 1166
1220 174
Hydrotesting 18 27-Jul-22 08:00 28-Jul-22 02 :00 103
1125Blinding (6 Inch-02 Nos) 3 27-Jul-22 08:00 27-Jul-22 11 :00 1104, 1107
1126 103
1126Fixture fittings for Hydro test 2 27-Jul-22 11:00 27-Jul-22 13 :00 1125 1127 103
1127Water Fill up 2 27-Jul-22 13:00 27-Jul-22 15 :00 1126 1128 103
1128Hydro testing 4 27-Jul-22 15:00 27-Jul-22 19 :00 1127 1129 103
1129Inspection 2 27-Jul-22 19:00 27-Jul-22 21 :00 1128 1130 103
1130Fixture Removal 2 27-Jul-22 21:00 27-Jul-22 23 :00 1129 1131 103
1131De-blinding 3 27-Jul-22 23:00 28-Jul-22 02 :00 1130 1133 103
Pigging 21 28-Jul-22 02:00 28-Jul-22 23 :00 174
1133Pig Launcher Fixture set up 6 28-Jul-22 02:00 28-Jul-22 08 :00 1131, 1161
1134 103
1134Pigging 6 28-Jul-22 08:00 28-Jul-22 14 :00 1133 1135 103
1135Pig Launcher Fixture removal 6 28-Jul-22 14:00 28-Jul-22 20 :00 1134 1136, 1148 103
1136Blinding of Flange (06 Inch-02 Nos) 3 28-Jul-22 20:00 28-Jul-22 23 :00 1135 1137 174

Coil 3 75 26-Jul-22 18:00 29-Jul-22 21 :00 103


1152 Coil Drying and N2 Purging 4 29-Jul-22 17:00 29-Jul-22 21 :00 1151, 1166
1186, 1220 103
Hydrotesting 18 26-Jul-22 18:00 27-Jul-22 12 :00 135
1140Blinding (6 Inch-02 Nos) 3 26-Jul-22 18:00 26-Jul-22 21 :00 1101 1141 135
1141Fixture fittings for Hydro test 2 26-Jul-22 21:00 26-Jul-22 23 :00 1140 1142 135
1142Water Fill up 2 26-Jul-22 23:00 27-Jul-22 01 :00 1141 1143 135
1143Hydro testing 4 27-Jul-22 01:00 27-Jul-22 05 :00 1142 1144 135
1144Inspection 2 27-Jul-22 05:00 27-Jul-22 07 :00 1143 1145 135
1145Fixture Removal 2 27-Jul-22 07:00 27-Jul-22 09 :00 1144 1146 135
1146De-blinding 3 27-Jul-22 09:00 27-Jul-22 12 :00 1145 1148 135
Pigging 21 28-Jul-22 20:00 29-Jul-22 17 :00 103
1148Pig Launcher Fixture set up 6 28-Jul-22 20:00 29-Jul-22 02 :00 1146, 1135
1149 103
1149Pigging 6 29-Jul-22 02:00 29-Jul-22 08 :00 1148 1150 103
1150Pig Launcher Fixture removal 6 29-Jul-22 08:00 29-Jul-22 14 :00 1149 1151 103

Page 35 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1151Blinding of Flange (06 Inch-02 Nos) 3 29-Jul-22 14:00 29-Jul-22 17 :00 1150 1152 103

Coil 4 43 26-Jul-22 18:00 28-Jul-22 13 :00 135


1167 Coil Drying and N2 Purging 4 28-Jul-22 09:00 28-Jul-22 13 :00 1166 1203, 1220 135
Hydrotesting 18 26-Jul-22 18:00 27-Jul-22 12 :00 117
1155Blinding (6 Inch-02 Nos) 3 26-Jul-22 18:00 26-Jul-22 21 :00 1101 1156 117
1156Fixture fittings for Hydro test 2 26-Jul-22 21:00 26-Jul-22 23 :00 1155 1157 117
1157Water Fill up 2 26-Jul-22 23:00 27-Jul-22 01 :00 1156 1158 117
1158Hydro testing 4 27-Jul-22 01:00 27-Jul-22 05 :00 1157 1159 117
1159Inspection 2 27-Jul-22 05:00 27-Jul-22 07 :00 1158 1160 117
1160Fixture Removal 2 27-Jul-22 07:00 27-Jul-22 09 :00 1159 1161 117
1161De-blinding 3 27-Jul-22 09:00 27-Jul-22 12 :00 1160 1118, 1133, 1163
117
Pigging 21 27-Jul-22 12:00 28-Jul-22 09 :00 135
1163Pig Launcher Fixture set up 6 27-Jul-22 12:00 27-Jul-22 18 :00 1161 1164 135
1164Pigging 6 27-Jul-22 18:00 28-Jul-22 00 :00 1163 1165 135
1165Pig Launcher Fixture removal 6 28-Jul-22 00:00 28-Jul-22 06 :00 1164 1166 135
1166Blinding of Flange (06 Inch-02 Nos) 3 28-Jul-22 06:00 28-Jul-22 09 :00 1165 1122, 135
1137,
Outlet Spool Welding-1 (16 Inch) 53 28-Jul-22 13:00 30-Jul-22 18 :00 1152, 135
1169 Weld Edge Preparation for Outlet 4 28-Jul-22 13:00 28-Jul-22 17 :00 1122 1170 135
Spool-1 (16 Inch)

1170 Flange Removal (6 Inch-02 Nos) 2 28-Jul-22 17:00 28-Jul-22 19 :00 1169 1171 135
1171 Spool Lifting & Fit Up 2 28-Jul-22 19:00 28-Jul-22 21 :00 1170 1172 135
1172 Coil Fixing for Pre Heating 3 28-Jul-22 21:00 29-Jul-22 00 :00 1171 1173 135
1173 Preheating 4 29-Jul-22 00:00 29-Jul-22 04 :00 1172 1174 135
1174 Root Welding 3 29-Jul-22 04:00 29-Jul-22 07 :00 1173 1175 135
1175 Cooling for Root weld line DP 2 29-Jul-22 07:00 29-Jul-22 09 :00 1174 1176 135
1176 DP testing of Root Line 1 29-Jul-22 09:00 29-Jul-22 10 :00 1175 1177 135
1177 Full Welding 6 29-Jul-22 10:00 29-Jul-22 16 :00 1176 1178 135
1178 Cooling 2 29-Jul-22 16:00 29-Jul-22 18 :00 1177 1179 135
1179 DP Testing of Welding 2 29-Jul-22 18:00 29-Jul-22 20 :00 1178 1180 135
1180 RT 2 29-Jul-22 20:00 29-Jul-22 22 :00 1179 1181 135
1181 PWHT Cycle (Heating upto 750 Deg C) 14 29-Jul-22 22:00 30-Jul-22 12 :00 1180 1182 135

1182 Cooling 2 30-Jul-22 12:00 30-Jul-22 14 :00 1181 1183 135


1183 RT after PWHT 2 30-Jul-22 14:00 30-Jul-22 16 :00 1182 1184 135
1184 Insulation Fixing 2 30-Jul-22 16:00 30-Jul-22 18 :00 1183 1220 135
Outlet Spool Welding-2 (16 Inch) 53 29-Jul-22 21:00 01-Aug-22 02:00 103

Page 36 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1186 Weld Edge Preparation for Outlet 4 29-Jul-22 21:00 30-Jul-22 01 :00 1152 1187 103
Spool-1 (16 Inch)

1187 Flange Removal (6 Inch-02 Nos) 2 30-Jul-22 01:00 30-Jul-22 03 :00 1186 1188 103
1188 Spool Lifting & Fit Up 2 30-Jul-22 03:00 30-Jul-22 05 :00 1187 1189 103
1189 Coil Fixing for Pre Heating 3 30-Jul-22 05:00 30-Jul-22 08 :00 1188 1190 103
1190 Preheating 4 30-Jul-22 08:00 30-Jul-22 12 :00 1189 1191 103
1191 Root Welding 3 30-Jul-22 12:00 30-Jul-22 15 :00 1190 1192 103
1192 Cooling for Root weld line DP 2 30-Jul-22 15:00 30-Jul-22 17 :00 1191 1193 103
1193 DP testing of Root Line 1 30-Jul-22 17:00 30-Jul-22 18 :00 1192 1194 103
1194 Full Welding 6 30-Jul-22 18:00 31-Jul-22 00 :00 1193 1195 103
1195 Cooling 2 31-Jul-22 00:00 31-Jul-22 02 :00 1194 1196 103
1196 DP Testing of Welding 2 31-Jul-22 02:00 31-Jul-22 04 :00 1195 1197 103
1197 RT 2 31-Jul-22 04:00 31-Jul-22 06 :00 1196 1198 103
1198 PWHT Cycle (Heating upto 750 Deg C) 14 31-Jul-22 06:00 31-Jul-22 20 :00 1197 1199 103

1199 Cooling 2 31-Jul-22 20:00 31-Jul-22 22 :00 1198 1200 103


1200 RT after PWHT 2 31-Jul-22 22:00 01-Aug-22 00:00 1199 1201 103
1201 Insulation Fixing 2 01-Aug-22 00:00 01-Aug-22 02:00 1200 1220 103
Inlet Spool Welding (16 Inch) 53 28-Jul-22 13:00 30-Jul-22 18 :00 135
1203 Weld Edge Preparation for Inlet Spool-1 4 28-Jul-22 13:00 28-Jul-22 17 :00 1167 1204 135
(16 Inch)

1204 Flange Removal (6 Inch-02 Nos) 2 28-Jul-22 17:00 28-Jul-22 19 :00 1203 1205 135
1205 Spool Lifting & Fit Up 2 28-Jul-22 19:00 28-Jul-22 21 :00 1204 1206 135
1206 Coil Fixing for Pre Heating 3 28-Jul-22 21:00 29-Jul-22 00 :00 1205 1207 135
1207 Preheating 4 29-Jul-22 00:00 29-Jul-22 04 :00 1206 1208 135
1208 Root Welding 3 29-Jul-22 04:00 29-Jul-22 07 :00 1207 1209 135
1209 Cooling for Root weld line DP 2 29-Jul-22 07:00 29-Jul-22 09 :00 1208 1210 135
1210 DP testing of Root Line 1 29-Jul-22 09:00 29-Jul-22 10 :00 1209 1211 135
1211 Full Welding 6 29-Jul-22 10:00 29-Jul-22 16 :00 1210 1212 135
1212 Cooling 2 29-Jul-22 16:00 29-Jul-22 18 :00 1211 1213 135
1213 DP Testing of Welding 2 29-Jul-22 18:00 29-Jul-22 20 :00 1212 1214 135
1214 RT 2 29-Jul-22 20:00 29-Jul-22 22 :00 1213 1215 135
1215 PWHT Cycle (Heating upto 750 Deg C) 14 29-Jul-22 22:00 30-Jul-22 12 :00 1214 1216 135

1216 Cooling 2 30-Jul-22 12:00 30-Jul-22 14 :00 1215 1217 135


1217 RT after PWHT 2 30-Jul-22 14:00 30-Jul-22 16 :00 1216 1218 135
1218 Insulation Fixing 2 30-Jul-22 16:00 30-Jul-22 18 :00 1217 1220 135
Heater Inspection Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103
1220 Heater Inspection Completion 0 01-Aug-22 02:00 1218, 1201,
13511184, 1137, 103
1152, 1167 Heater Inspection Completion
Page 37 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
PSV Inspection Jobs (Scope: 43 nos) 216 25-Jul-22 02:00 03-Aug-22 02:00 55
1222 INSP & CAL OF PSV-471-023 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1266 199
1223 INSP & CAL OF PSV-471-024 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1266 199
1224 INSP & CAL OF PSV-471-025A 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1266 199
1225 INSP & CAL OF PSV-471-025B 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1266 199
1226 INSP & CAL OF PSV-471-042A 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1266 199
1227 INSP & CAL OF PSV-471-042B 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1266 199
1228 INSP & CAL OF PSV-471-043 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1266 175
1229 INSP & CAL OF PSV-471-044A 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1266 175
1230 INSP & CAL OF PSV-471-044B 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1266 175
1231 INSP & CAL OF PSV-471-046 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1266 175
1232 INSP & CAL OF PSV-471-047 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1266 175
1233 INSP & CAL OF PSV-471-048A 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1266 175
1234 INSP & CAL OF PSV-471-048B 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1266 151
1235 INSP & CAL OF PSV-471-048C 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1266 151
1236 INSP & CAL OF PSV-471-051A 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1266 151
1237 INSP & CAL OF PSV-471-051B 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1266 151
1238 INSP & CAL OF PSV-471-052A 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1266 151
1239 INSP & CAL OF PSV-471-052B 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1266 151
1240 INSP & CAL OF PSV-471-053A 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1266 127
1241 INSP & CAL OF PSV-471-053B 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1266 127
1242 INSP & CAL OF PSV-471-054A 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1266 127
1243 INSP & CAL OF PSV-471-054B 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1266 127
1244 INSP & CAL OF PSV-471-055A 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1266 127
1245 INSP & CAL OF PSV-471-055B 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1266 127
1246 INSP & CAL OF PSV-471-195A 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1266 103
1247 INSP & CAL OF PSV-471-195B 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1266 103
1248 INSP & CAL OF PSV-471-200 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1266 103
1249 INSP & CAL OF PSV-471-201 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1266 103
1250 INSP & CAL OF PSV-471-202 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1266 103
1251 INSP & CAL OF PSV-471-251A 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1266 103
1252 INSP & CAL OF PSV-471-251B 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1266 79
1253 CALIBRATION OF PSV-471-177 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1266 79
1254 INSP & CAL OF PSV-471-303A 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1266 79
1255 INSP & CAL OF PSV-471-303B 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1266 79
1256 INSPECTION & CALIBRATION OF 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1266 79
PSV-471-309A
1257 INSP & CAL OF PSV-471-309B 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1266 79
1258 INSP & CAL OF PSV-471-310 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1266 55
1259 INSP & CAL OF PSV-471-311 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1266 55
Page 38 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1260 INSP & CAL OF PSV-471-317A 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1266 55
1261 INSP & CAL OF PSV-471-317B 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1266 55
1262 INSP & CAL OF PSV-471-308 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1266 55
1263 INSP & CAL OF PSV-471-048D 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1266 55
1264 INSPECTION OF PSV-471-051C 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1266 55
PSV Inspection Jobs Completion 0 03-Aug-22 02:00 03-Aug-22 02:00 55
1266 PSV Inspection Jobs Completion 0 03-Aug-22 02:00 1222, 1223,
13511224, 1225, 1226, PSV Inspection
55 1227, 1228, 1229, 1230, 1231, 1232, 1233, Jobs Completion
1234, 1235, 1236, 1237, 12
NRV Inspection Jobs (Scope: 54 nos) 216 25-Jul-22 02:00 03-Aug-22 02:00 55
1268 NRV-FLG-471-PA-001-6''-U/S of 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199
FV-005
1269 NRV-FLG-471-PA-007-10''-Hot Nptha 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199
fm Cok

1270 NRV-FLG-471-PA-627-12''-HotNptha 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199


fm ZCok
1271 NRV-FLG-471-NI-001-2''-U/S of 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199
PCV-021
1272 NRV-FLG-471-PA-047-4''-Comp C01A 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199
disch
1273 NRV-FLG-471-PA-048-4''-Comp C01B 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199
disch
1274 NRV-FLG-471-PA-666-4''-Comp C01C 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199
disch
1275 NRV-FLG-471-PA-104-10''-P04A 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199
discharge
1276 NRV-FLG-471-PA-105-10''-P04B 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199
discharge
1277 NRV-FLG-471-PA-018-6''-ChrgePmpComnDisch 72 25-Jul-22 02:00 28-Jul-22 02 :00 18 1323 199

1278 NRV-FLG-471-PA032-6''- FV-007 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1323 175


disch
1279 NRV-FLG-471-PA-0321-6''-RecyleGasToS10AB 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1323 175

1280 NRV-FLG-471-WR-005-2''-WW to 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1323 175


S03A/B OL

1281 NRV-FLG-471-PA-026-2''-WW at 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1323 175


S05A/B O/L

1282 NRV-FLG-471-NI-014-2''-N2 vent 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1323 175


from V04
1283 NRV-FLG-471-WR-007-2''-P05A 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1323 175
discharge

Page 39 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1284 NRV-FLG-471-WR-007-2''-P05B 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1323 175
discharge
1285 NRV-FLG-471-WR-007-2''-P05AB 72 26-Jul-22 02:00 29-Jul-22 02 :00 18 1323 175
disch toA01
1286 NRV-FLG-471-PA-053-10''-P06A 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1323 151
discharge
1287 NRV-FLG-471-PA-105-10''-P06B 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1323 151
discharge

1288 NRV-FLG-471PA-124-6''-P06AB Spill 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1323 151


V05
1289 NRV-FLG-471-PA-085-4''-P07A 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1323 151
discharge
1290 NRV-FLG-471-PA-085-4''-P07B 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1323 151
discharge
1291 NRV-FLG-471-SC-001-4''-P22 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1323 151
discharge
1292 NRV-FLG-471-SC-004-8''-P19A 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1323 151
discharge
1293 NRV-FLG-471-SC-004-8''-P19B 72 27-Jul-22 02:00 30-Jul-22 02 :00 18 1323 151
discharge
1294 NRV-FLG-471-WB-016-3''-BFW to 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1323 127
S07
1295 NRV-WLD-471-CH-016-1''-P24A 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1323 127
discharge
1296 NRV-WLD-471-CH-016-1''-P24B 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1323 127
discharge

1297 NRV-WLD-471-CH-016-1''-P24A/B To 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1323 127


S08
1298 NRV-WLD-471-CH-001-1''-P12AB-P04AB 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1323 127
Suctn
1299 NRV-WLD-471-CH-003-2''-P11AB 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1323 127
Stripr Ovhd
1300 NRV-FLG-471-PE-015-3''-Off gas to 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1323 127
SGCU-2
1301 NRV-FLG-471-PE-017-3''-Off gas to 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1323 127
SGCU-1
1302 NRV-THD-471-WK-002-1.5''-Phlic wtr 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1323 103
fmV01
1303 NRV-FLG-471-PA-092-2''-Unstblzd 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1323 103
Nptha BL

Page 40 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1304 NRV-FLG-471-PA-131-4''-HyttdNthaGsolneBd 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1323 103

1305 NRV-FLG-471-PA-132-8''-HydttdNapNapta 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1323 103


Bd
1306 NRV-FLG-471-PA-237-4''-Hyttd 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1323 103
Nphtha HMU
1307 NRV-FLG-471-PA-236-8''-HyttdNphaAromNtha 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1323 103

1308 NRV-FLG-471-LS-042 -3''-MV-RH471-V16 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1323 103

1309 NRV-FLG-471-LS-003 -4''-MV-RH471-C07 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1323 103

1310 NRV-FLG-471-LS-004 -3''-MV-RH471-V08 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1323 79

1311 NRV-FLG-471-LS-001 -3''-MV-RH471-V01 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1323 79

1312 NRV-FLG-471-NI-004-1''-MC-RH471-C01A 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1323 79

1313 NRV-FLG-471-NI-005-1''-MC-RH471-C01B 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1323 79

1314 NRV-FLG-471-NI-221-2''-MC-RH471-C01C 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1323 79

1315 NRV-FLG-471-NI-202-2''-MC-RH471-C01C 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1323 79

1316 NRV-FLG-471-NI-007-2''-MV-RH471-V04 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1323 79

1317 NRV-FLG-471-NI-222-2''-MV-RH471-R03 72 30-Jul-22 02:00 02-Aug-22 02:00 18 1323 79

1318 NRV-FLG-471-NI-019-2''-MV-RH471-V15 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1323 55

1319 NRV-FLG-471-NI-008-2''-Flare header 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1323 55

1320 NRV-FLG-471-FG-009 -2''-Flre Hder 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1323 55


PCV185
1321 NRV-FLG-471-FG-042 -2''-MV-RH471-V15 72 31-Jul-22 02:00 03-Aug-22 02:00 18 1323 55

NRV Inspection Jobs Completion 0 03-Aug-22 02:00 03-Aug-22 02:00 55


1323 NRV Inspection Jobs Completion 0 03-Aug-22 02:00 1268, 1269,
13511270, 1271, 1272, NRV Inspection
55 1273, 1274, 1275, 1276, 1277, 1278, 1279, Jobs 1282,
1280, 1281, Completion
1283, 12
Sample cooler Inspection/Hydro-test (Scope: 07 nos) 168 25-Jul-22 02:00 01-Aug-22 02:00 103
1325 ME-RH471-Y-PA013 (Fuel gas sample 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1333, 175
cooler) 1414

Page 41 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1326 ME-RH471-Y-PA102 (R02 outlet 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1333, 175
sample coler) 1415
1327 ME-RH471-Y-PA103 (R03 OUTLET 96 27-Jul-22 02:00 31-Jul-22 02 :00 18 1333, 127
SAMPLE COOLER) 1416
1328 ME-RH471-Y-PA101 (R01 OUTLET 96 27-Jul-22 02:00 31-Jul-22 02 :00 18 1333, 127
SAMPLE COOLER) 1417
1329 ME-RH471-Y-PA014 9 BLOWDOWN 96 27-Jul-22 02:00 31-Jul-22 02 :00 18 1333, 127
SAMPLE COOLER) 1418
1330 ME-RH471-Y-PA010 (STRIPPER 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1333, 103
REFLUX SAMPLE COOLER) 1419
1331 ME-RH471-Y-AP002 (FEED SAMPLE 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1333, 103
COOLER) 1420
Sample cooler Inspection/Hydro-test Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103
1333Sample cooler Inspection/Hydro-test 0 01-Aug-22 02:00 1325, 1351 103 Sample cooler Inspection/Hydro-test Comple
Completion 1326,
Miscellaneous Jobs incl. MOC (Scope: 12 nos) 168 25-Jul-22 02:00 01-Aug-22 02:00 1327, 103
1335 471-C01 A/B PDT Provision across 144 25-Jul-22 02:00 31-Jul-22 02 :00 18 1349, 127
suction strainer- Tapping to done - 1460
MOC-JGE1-JHYD-20-006

1342 PDV 302 HEATER BYPASS STUCK UP 48 25-Jul-22 02:00 27-Jul-22 02 :00 18 1349 223
PROBLEM
1343 COMP. C01 C MAIN MOTOR BACKSIDE 48 25-Jul-22 02:00 27-Jul-22 02 :00 18 1349 223
RAILING HOT WORK TO BE DONE

1344 Steam leak attending as per list 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1345, 1349 139
1336 V-08 BOOT WATER SECOND 96 26-Jul-22 02:00 30-Jul-22 02 :00 18 1349 151
ISOLATION VALVE TO BE REPLACED(
1.5")
1337 V08 boot water sample point (belzona 96 26-Jul-22 02:00 30-Jul-22 02 :00 18 1338, 103
coated ) leaky spool replacement to be 1349
done

1339 FG steam tracing line near XV008 48 26-Jul-22 02:00 28-Jul-22 02 :00 18 1340, 151
(HEATER) steam leak 1349
1347 V005/V008/C007 Provision of Isolation 96 27-Jul-22 02:00 31-Jul-22 02 :00 18 1349 127
valve on U/p of LG/LT
(MOC-JGE1-JHYD-22-009)
1340 Heater Burner no. 2 Air register hand 24 28-Jul-22 02:00 29-Jul-22 02 :00 1339 1341, 151
valve rousing to be done, fixed at 30%. 1349
.Valve Servicing to be done

Page 42 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1341 COMP C01A SUCTION BOTTLE 24 29-Jul-22 02:00 30-Jul-22 02 :00 1340 1349 151
ISOLATION VALVE TO BE REPLACED (
1)
1345 V-10 BLOW DRUM DRAIN TO OWS 24 29-Jul-22 02:00 30-Jul-22 02 :00 1344 1346, 139
FUNNEL TO BE DECHOKE 1349

1338 Heater F01 burner number 1 and 4 not 48 30-Jul-22 02:00 01-Aug-22 02:00 1337 1349 103
firing sufficient. Burner Cleaning

1346 UW VALVE TO BE REPLACED NEAR 12 30-Jul-22 02:00 30-Jul-22 14 :00 1345 1349 139
COL.NO A06 (UTILITY STATION)

Misc. Jobs Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103


1349 Misc. Jobs Completion 0 01-Aug-22 02:00 1335, 1336,
13511337, 1338, 103 Misc. Jobs
1339, 1340, 1347, 1341, 1342, 1343, 1344, Completion
1345, 1346
Mechanical Jobs Completion 0 05-Aug-22 09:00 05-Aug-22 09:00 0
1351 Mechanical Jobs Completion 0 05-Aug-22 09:00 107, 520,1584
663, 1073, 1220, 0
1266, 1323, 1333, 1349, 635 Mechanical Jobs Completion
MIC Jobs 192 25-Jul-22 02:00 02-Aug-22 02:00 79
Corrosion Loop (Scope: 11 nos) 114 25-Jul-22 02:00 29-Jul-22 20 :00 157
1354 INSPECTION OF PIPE-471-KCL08 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1366 175
1355 INSPECTION OF PIPE-471-KCL03 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1366 175
1356 INSPECTION OF PIPE-471-CL02 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1366 175
1357 INSPECTION OF PIPE-471-CL02A 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1366 175
1358 INSPECTION OF PIPE-471-CL04 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1366 175
1359 INSPECTION OF PIPE-471-CL05 96 25-Jul-22 20:00 29-Jul-22 20 :00 18 1366 157
1360 INSPECTION OF PIPE-471-CL06 96 25-Jul-22 20:00 29-Jul-22 20 :00 18 1366 157
1361 INSPECTION OF PIPE-471-CL07 96 25-Jul-22 20:00 29-Jul-22 20 :00 18 1366 157
1362 INSPECTION OF PIPE-471-CL09 96 25-Jul-22 20:00 29-Jul-22 20 :00 18 1366 157
1363 INSPECTION OF PIPE-471-CL01 96 25-Jul-22 20:00 29-Jul-22 20 :00 18 1366 157
1364 INSPECTION OF PIPE-471-CL011 96 25-Jul-22 20:00 29-Jul-22 20 :00 18 1366 157
CL Completion 0 29-Jul-22 20:00 29-Jul-22 20 :00 157
1366 CL Completion 0 29-Jul-22 20:00 1354, 1355,
1434 1358, 1359, 1360, 1361, 1362,CL
1356, 1357, 157 Completion
1363, 1364
Injection Points (Scope: 13 nos) 138 25-Jul-22 02:00 30-Jul-22 20 :00 133
1368 INSPECTION OF IP-RH471-001 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1382 175
1369 INSPECTION OF IP-RH471-002 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1382 175
1370 INSPECTION OF IP-RH471-003 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1382 175
1371 INSPECTION OF IP-RH471-004 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1382 175
1372 INSPECTION OF IP-RH471-005 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1382 175
1373 INSPECTION OF IP-RH471-006 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1382 175
1374 INSPECTION OF IP-RH471-007 96 26-Jul-22 20:00 30-Jul-22 20 :00 18 1382 133
1375 INSPECTION OF IP-RH471-008 96 26-Jul-22 20:00 30-Jul-22 20 :00 18 1382 133

Page 43 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1376 INSPECTION OF IP-RH471-009 96 26-Jul-22 20:00 30-Jul-22 20 :00 18 1382 133
1377 INSPECTION OF IP-RH471-010 96 26-Jul-22 20:00 30-Jul-22 20 :00 18 1382 133
1378 INSPECTION OF IP-RH471-011 96 26-Jul-22 20:00 30-Jul-22 20 :00 18 1382 133
1379 INSPECTION OF IP-RH471-012 96 26-Jul-22 20:00 30-Jul-22 20 :00 18 1382 133
1380 INSPECTION OF IP-RH471-013 96 26-Jul-22 20:00 30-Jul-22 20 :00 18 1382 133
IP Completion 0 30-Jul-22 20:00 30-Jul-22 20 :00 133
1382 IP Completion 0 30-Jul-22 20:00 1368, 1369,
14341370, 1371, 133 IP Completion
1372, 1373, 1374, 1375, 1376, 1377, 1378, 1379, 1380
Mixing Points (Scope: 02 nos) 96 27-Jul-22 02:00 31-Jul-22 02 :00 127
1384 INSPECTION OF MXP-RH471-001 96 27-Jul-22 02:00 31-Jul-22 02 :00 18 1387 127
1385 JHYDN4710015 MXP-RH471-002 96 27-Jul-22 02:00 31-Jul-22 02 :00 18 1387 127
MX Completion 0 31-Jul-22 02:00 31-Jul-22 02 :00 127
1387 MX Completion 0 31-Jul-22 02:00 1384, 1385
1434 127 MX Completion
CUI - Equipments (Scope: 22 nos) 168 26-Jul-22 02:00 02-Aug-22 02:00 79
1389 MV-RH471-V23C 96 26-Jul-22 02:00 30-Jul-22 02 :00 18 1412 151
1390 MV-RH471-V23B 96 26-Jul-22 02:00 30-Jul-22 02 :00 18 1412 151
1391 MV-RH471-V23A 96 26-Jul-22 02:00 30-Jul-22 02 :00 18 1412 151
1392 MV-RH471-V22C 96 26-Jul-22 02:00 30-Jul-22 02 :00 18 1412 151
1393 MV-RH471-V22B 96 26-Jul-22 02:00 30-Jul-22 02 :00 18 1412 151
1394 MV-RH471-V22A 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1412 103
1395 MV-RH471-C07 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1412 103
1396 ME-RH471-S23B 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1412 103
1397 ME-RH471-S23A 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1412 103
1398 ME-RH471-S22B 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1412 103
1399 ME-RH471-S22A 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1400 ME-RH471-S12B 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1401 ME-RH471-S12A 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1402 ME-RH471-S11B 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1403 ME-RH471-S11A 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1404 ME-RH471-S10B 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1405 ME-RH471-S10A 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1406 ME-RH471-S07 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1407 ME-RH471-S04D 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1408 ME-RH471-S04B 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1409 ME-RH471-S03B 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
1410 ME-RH471-S03A 96 29-Jul-22 02:00 02-Aug-22 02:00 18 1412 79
CUI-Equipments Completion 0 02-Aug-22 02:00 02-Aug-22 02:00 79
1412 CUI-Equipments Completion 0 02-Aug-22 02:00 1389, 1390,
14341391, 1392, 1393, CUI-Equipments
79 1394, 1395, 1396, 1397, 1398, 1399, 1400, 1401, Completion
1402, 1403, 1404, 14
CUI - Sample Cooler I/L (Scope: 07 nos) 168 25-Jul-22 02:00 01-Aug-22 02:00 103
1414 ME-RH471-Y-PA013 96 25-Jul-22 02:00 29-Jul-22 02 :00 1325 1422 175

Page 44 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1415 ME-RH471-Y-PA102 96 25-Jul-22 02:00 29-Jul-22 02 :00 1326 1422 175
1416 ME-RH471-Y-PA103 96 27-Jul-22 02:00 31-Jul-22 02 :00 1327 1422 127
1417 ME-RH471-Y-PA101 96 27-Jul-22 02:00 31-Jul-22 02 :00 1328 1422 127
1418 ME-RH471-Y-PA014 96 27-Jul-22 02:00 31-Jul-22 02 :00 1329 1422 127
1419 ME-RH471-Y-PA010 96 28-Jul-22 02:00 01-Aug-22 02:00 1330 1422 103
1420 ME-RH471-Y-AP002 96 28-Jul-22 02:00 01-Aug-22 02:00 1331 1422 103
CUI-Sample Cooler I/L Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103
1422 CUI-Sample Cooler I/L Completion 0 01-Aug-22 02:00 1414, 1415,
14341416, 1417, 103
1418, 1419, 1420 CUI-Sample Cooler I/L Completion
Steam Ejector Inspection (Scope: 02 nos) 144 25-Jul-22 02:00 31-Jul-22 02 :00 127
1424 MF-RH471-J01 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1427 175
1425 MF-RH471-Y05 96 27-Jul-22 02:00 31-Jul-22 02 :00 18 1427 127
Steam Ejector Inspection Completion 0 31-Jul-22 02:00 31-Jul-22 02 :00 127
1427 Steam Ejector Inspection Completion 0 31-Jul-22 02:00 1424, 1434 127 Steam Ejector Inspection Completion
1425
Misc. MIC (Scope: 02 nos) 168 25-Jul-22 02:00 01-Aug-22 02:00 103
1429 Thickness survey of piping component 168 25-Jul-22 02:00 01-Aug-22 02:00 18 1432 103
both BFW & condensate circuit

1430 INSPECTION OF SPRING 168 25-Jul-22 02:00 01-Aug-22 02:00 18 1432 103
SUPPORT-471 AREA
Misc. MIC Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103
1432 Misc. MIC Completion 0 01-Aug-22 02:00 1429, 1430
1434 103 Misc. MIC Completion
MIC Jobs Completion 0 02-Aug-22 02:00 02-Aug-22 02:00 79
1434 MIC Jobs Completion 0 02-Aug-22 02:00 1366, 1382,
15841387, 1412, 1422,
79 1427, 1432 MIC Jobs Completion
Instrumentation maintenance jobs 270 23-Jul-22 20:00 04-Aug-22 02:00 31
CV/XV Overhaul & Replacement (Scope: 18 nos) 216 25-Jul-22 02:00 03-Aug-22 02:00 55
1437 471HV013 (Meridian Recommendation 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1456 151
no. REC-4 64215)
1438 471HV017 (Meridian Recommendation 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1456 151
no. REC-4 64215)
1439 471FV301 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1456 151
1440 471FV120 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1456 151
1441 471FV020 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1456 127
1442 471FV034 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1456 127
1443 471HV015 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1456 127
1444 471XV021 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1456 127
1445 471TV046 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1456 103
1446 471XV002 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1456 103
1447 471PV013 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1456 103
1448 471XV022 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1456 103
Page 45 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1449 471TV060 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1456 79
1450 471HV002 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1456 79
1451 471FV401 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1456 79
1452 471FV402 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1456 55
1453 471XV401 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1456 55
1454 471XV402 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1456 55
CV/XV Overhaul Completion 0 03-Aug-22 02:00 03-Aug-22 02:00 55
1456 CV/XV Overhaul Completion 0 03-Aug-22 02:00 1437, 1438,
15081439, 1440, 1441, CV/XV 1449,
55 1442, 1443, 1444, 1445, 1446, 1447, 1448, Overhaul Completion
1450, 1451, 1452, 14
MOC 168 25-Jul-22 02:00 01-Aug-22 02:00 103
1458 Heater XVs body replacement against 168 25-Jul-22 02:00 01-Aug-22 02:00 18 1462 103
obsolesce plan
-MOC-JGE1-JHYD-18-013 - LNUU
Heater skid XVs (6 Nos) replacement
1459 MOC-JGE1-JHYD-17-020_742_Routing 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1462 151
of DTA Platformer Hydrogen to SEZ
1460 related inst job.
MOC-JGE1-JHYD-20-006 - comp. 144 25-Jul-22 02:00 31-Jul-22 02 :00 1335 1462 127
suction strainer PDT provision.
MOC Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103
1462 MOC Completion 0 01-Aug-22 02:00 1458, 1459,
15081460 103 MOC Completion
Meridium/CES/Reliability recommendations 144 26-Jul-22 02:00 01-Aug-22 02:00 103
1464 REC-716416-JDR-HYD-471-471PSH207-It 48 26-Jul-22 02:00 28-Jul-22 02 :00 18 1465, 103
is observed in certain RIL site that the 1469
Pressure Switch setpoint got changed
1465 due to
REC-740716-JDR-HYD-500-PIB17-JPRH471C02- 48 28-Jul-22 02:00 30-Jul-22 02 :00 1464 1466, 103
To avoid similar failure in other BOSARD 1467,
1466 Heater PLC, it is recommended
REC-799866-RM notification - to revie 48 30-Jul-22 02:00 01-Aug-22 02:00 1465 1469
1469 103
IM2020084087_DTA - Damping for
2oo2/2oo3 ESD transmitters to be
removed considering availab
1467 REC-766644-RM notification - 48 30-Jul-22 02:00 01-Aug-22 02:00 1465 1469 103
IM2020127020_DTA - To set
hardware security switch in Transmitter
to ON for all ESD transm
Recommendations Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103
1469 Recommendations Completion 0 01-Aug-22 02:00 1464, 1465,
15081466, 1467 103 Recommendations Completion
Miscellaneous Jobs 270 23-Jul-22 20:00 04-Aug-22 02:00 31
1486 471 package PLC systems processor 24 23-Jul-22 20:00 24-Jul-22 20 :00 17 1506 277
changeover (Scope: 02 nos)

1493 TV-46 OF S-09 STUCK ISSUE 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1494, 1506 55

Page 46 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1471 All Pilot Gun of Heater to be cleaned 72 25-Jul-22 20:00 28-Jul-22 20 :00 1081 1506 181
/PM to be done (Scope: 04 nos)

1472 ESD Transmitters/Switches PM to be 144 27-Jul-22 02:00 02-Aug-22 02:00 18 1506 79


done (Scope: 44 nos)

1473 Displacer LT AND LS to be dropped and 168 27-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
sent to CES FOR O/H (Scope: 18 nos)

1484 Field JB termination tightning and 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1506 103
Earthing Checking (Scope: 45 nos)

1491 COMP C01 A TG-014 DISH TEMP TO 12 27-Jul-22 02:00 27-Jul-22 14 :00 18 1506 211
BE REPLACED
1492 COMP. C01 B CYLINDER 2 SIDE 12 27-Jul-22 02:00 27-Jul-22 14 :00 18 1506 211
COOLING RETURN TG NOT WORKING

1504 C01A/B/C Compressor all instrument 168 27-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
PM to be done (Scope: 96 nos)

1475 Power Supply replacment - C01A/B/C 48 28-Jul-22 02:00 30-Jul-22 02 :00 18 1476, 127
(scope: 06 nos) 1506

1479 R03 Skin temp. element to be check 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1506 127
(Scope: 15 nos)
1483 ESD all DI Barrier Replacment (Scope: 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1506 103
30 nos)
1485 Compressor and Field ESD SOV 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1506 103
healthyness checking (Scope: 44 nos)

1474 471 All Control Valves /XV Storoke 144 29-Jul-22 02:00 04-Aug-22 02:00 18 1506 31
checking/PM to be done (Scope: 101
nos)

1477 Critical thermowell HT/DPT to be done 144 29-Jul-22 02:00 04-Aug-22 02:00 18 1506 31
at CES (Scope: 10 nos)
1478 R03 Bed temp. ( multiwell HT/DPT 48 29-Jul-22 02:00 31-Jul-22 02 :00 18 1506 127
testing at CES) to be check (Scope: 03
nos)
1482 DCS and ESD panel TB tightning and 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1506 103
Thermography (Scope: 10 nos)

1494 P06B DISH PG TO BE REPLACED 12 29-Jul-22 02:00 29-Jul-22 14 :00 1493 1495, 1506 55
1495 P-11B DISH PG NOT WORKING 12 29-Jul-22 14:00 30-Jul-22 02 :00 1494 1496 55

Page 47 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1476 C01A/B/C Compressor DO/DI barrier 24 30-Jul-22 02:00 31-Jul-22 02 :00 1475 1506 127
replacment (Scope: 25 nos)

1480 High H2S and Auto ignition service 36 30-Jul-22 02:00 31-Jul-22 14 :00 18 1506 115
transmitter inst. Tubing Hydrotest to be
done.

1487 Compressor tubing ferrule fitting 96 30-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
,support,clamp cheking (Scope: 100
nos)

1488 Field impulse tubing ferrule fitting 96 30-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
,support,clamp cheking (Scope: 100
nos)

1489 Inst. Air header flushing and AFR 96 30-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
cleaning/draining (Scope: 50 nos)

1490 DP type LT root valve dechocking and 24 30-Jul-22 02:00 31-Jul-22 02 :00 18 1506 127
glyacol filling (Scope: 02 nos)

1496 P-19A/B SEAL ALARM NOT GENERATE 12 30-Jul-22 02:00 30-Jul-22 14 :00 1495 1497 55
IN PENAL (PSL TO BE CHECK OR
REPLACED)

1497 C01A SUCTION BOOT LEVEL ALARM 12 30-Jul-22 14:00 31-Jul-22 02 :00 1496 1498 55
NOT SHOWING IN PENAL (LEVEL
SWITCH TO ATTEND OR REPLACED)

1498 V-08 BOOT WATER LG/LT TO BE 12 31-Jul-22 02:00 31-Jul-22 14 :00 1497 1499 55
ATTEND (LG LEVEL SHOWING FULL
IN FIELD BUT ALARM NOT
GENERATED IN PENAL)
1499 R03 INLET (TT-303) NOT SHOWING VALUE 12 31-Jul-22 14:00 01-Aug-22 02:00 1498 1500 55
1481 IRP panel cleaning and Thermography 12 01-Aug-22 02:00 01-Aug-22 14:00 18 1506 91
(Scope: 02 nos)
1500 V01 LG/LT MISMATCH RELATED 12 01-Aug-22 02:00 01-Aug-22 14:00 1499 1501 55
ISSUE TO BE ATTEND.
1501 MULTIPLE FIN-FAN TO BE ATTEND 12 01-Aug-22 14:00 02-Aug-22 02:00 1500 1502 55
(HIGH VIBRATION ISSUE/ABNORMAL
SOUND)

Page 48 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1502 V05 (BOOT WATER & SOUR GAS 12 02-Aug-22 02:00 02-Aug-22 14:00 1501 1503 55
SAMPLE POINT PG OR NEEDLE TO BE
REPLACED/ HARD TO OPERATE)

1503 COMP C01A SUMP LEVEL SWITCH TO 12 02-Aug-22 14:00 03-Aug-22 02:00 1502 1506 55
BE CHECK ALARM GENERATED AT
80% LEVEL ALSO/ OR ELSE CRANK
CASE TO CHECK)
Misc. Jobs Completion 0 04-Aug-22 02:00 04-Aug-22 02:00 31
1506 Misc. Jobs Completion 0 04-Aug-22 02:00 1471, 1472,
15081473, 1474, 1475, Misc.
31 1476, 1477, 1478, 1479, 1480, 1481, 1482, Jobs 1484,
1483, Completion
1485, 1486, 14
Inst. Jobs Completion 0 04-Aug-22 02:00 04-Aug-22 02:00 31
1508 Inst. Jobs Completion 0 04-Aug-22 02:00 1456, 1462,
15841469, 1506 31 Inst. Jobs Completion
Electrical Maintenance Jobs 240 25-Jul-22 02:00 04-Aug-22 02:00 142
1579 MCC Panel Revalidation and VCB,Relay Testing 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1582 151
1580 FIN-FAN A02 (01/0 2) Amp meter to 24 25-Jul-22 02:00 26-Jul-22 02 :00 18 1582 247
be provide
Motor Overhaul - HT (Scope: 03 nos) 240 25-Jul-22 02:00 04-Aug-22 02:00 142
MC-RH471-M01A 216 25-Jul-22 02:00 03-Aug-22 02:00 55
1512 Flywheel removal 24 25-Jul-22 02:00 26-Jul-22 02 :00 18 1513 55
1513 HT motor overhauling 120 26-Jul-22 02:00 31-Jul-22 02 :00 1512 1514, 1516, 156455
1514 Testing & Revalidation of VCB. 24 27-Jul-22 02:00 28-Jul-22 02 :00 1513 1515, 1516 103
1515 Testing of Relay. 24 28-Jul-22 02:00 29-Jul-22 02 :00 1514 1516 103
1516 Flywheel installation 24 31-Jul-22 02:00 01-Aug-22 02:00 1513, 1514,
15171515 55
1517 Alignment 48 01-Aug-22 02:00 03-Aug-22 02:00 1516 1531 55
MC-RH471-M01B 216 26-Jul-22 02:00 04-Aug-22 02:00 31
1519 Flywheel removal 24 26-Jul-22 02:00 27-Jul-22 02 :00 18 1520 31
1520 HT motor overhauling 120 27-Jul-22 02:00 01-Aug-22 02:00 1519 1521, 1523, 156531
1521 Testing & Revalidation of VCB. 24 28-Jul-22 02:00 29-Jul-22 02 :00 1520 1522, 1523 79
1522 Testing of Relay. 24 29-Jul-22 02:00 30-Jul-22 02 :00 1521 1523 79
1523 Flywheel installation 24 01-Aug-22 02:00 02-Aug-22 02:00 1520, 1521,
15241522 31
1524 Alignment 48 02-Aug-22 02:00 04-Aug-22 02:00 1523 1531 31
MP-RH471-M29 144 25-Jul-22 02:00 31-Jul-22 02 :00 238
1526 HT motor overhauling 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1527, 1529 127
1527 Testing & Revalidation of VCB. 24 26-Jul-22 02:00 27-Jul-22 02 :00 1526 1528 310
1528 Testing of Relay. 24 27-Jul-22 02:00 28-Jul-22 02 :00 1527 310
1529 P.M of Motor + Feeder 24 30-Jul-22 02:00 31-Jul-22 02 :00 1526 1531 127
HT motor overhauling Completion 0 04-Aug-22 02:00 04-Aug-22 02:00 31
1531 HT motor overhauling Completion 0 04-Aug-22 02:00 1529, 1582 31 HT motor overhauling Completion
1517,
Motor Overhaul - LT (Scope: 29 nos) 216 25-Jul-22 02:00 03-Aug-22 02:00 1524 55

Page 49 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1533 MP-RH471-M05A 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1562 151
1534 MP-RH471-M05B 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1562 151
1535 MP-RH471-M11A 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1562 151
1536 MP-RH471-M11B 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1562 151
1537 MP-RH471-M12A 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1562 151
1538 MP-RH471-M12B 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1562 151
1539 MP-RH471-M13B 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1562, 1571 79
1540 MP-RH471-M14B 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1562, 1572 79
1541 MP-RH471-M15A 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1562 127
1542 MP-RH471-M15B 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1562 127
1543 MP-RH471-M22 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1562 127
1544 MP-RH471-M23A 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1562, 1573 79
1545 MP-RH471-M23B 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1562, 1574 55
1546 MP-RH471-M23C 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1562, 1575 55
1547 MP-RH471-M24A 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1562 103
1548 MP-RH471-M24B 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1562 103
1549 MP-RH471-M25B 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1562 103
1550 MP-RH471-M26A 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1562 103
1551 MP-RH471-M26B 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1562 79
1552 ME-RH471-M01-01 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1562 79
1553 ME-RH471-M01-03 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1562 79
1554 ME-RH471-M01-04 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1562 79
1555 ME-RH471-M01-06 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1562 79
1556 ME-RH471-M01-07 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1562 79
1557 ME-RH471-M01-08 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1562 55
1558 ME-RH471-M04-02 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1562 55
1559 ME-RH471-M02-02 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1562 55
1560 ME-RH471-M02-03 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1562 55
Motor Overhaul-LT completion 0 03-Aug-22 02:00 03-Aug-22 02:00 55
1562 Motor Overhaul-LT completion 0 03-Aug-22 02:00 1533, 1534,
15821535, 1536, 1537, Motor Overhaul-LT
55 1538, 1539, 1540, 1541, 1542, 1543, 1544, 1545, 1546,completion
1547, 1548, 15
PM of Motor / Feeder (Scope: 13 nos) 216 25-Jul-22 02:00 03-Aug-22 02:00 55
1566 MC-RH471-M01C 48 25-Jul-22 02:00 27-Jul-22 02 :00 18 1567, 1578 127
1569 MP-RH471-M06A 48 26-Jul-22 02:00 28-Jul-22 02 :00 18 1578 199
1567 MP-RH471-M04A 48 27-Jul-22 02:00 29-Jul-22 02 :00 1566 1568, 1578 127
1570 MP-RH471-M06B 48 27-Jul-22 02:00 29-Jul-22 02 :00 18 1578 175
1576 MP-RH471-M25A 48 28-Jul-22 02:00 30-Jul-22 02 :00 18 1578 151
1568 MP-RH471-M04B 48 29-Jul-22 02:00 31-Jul-22 02 :00 1567 1578 127
1564 MC-RH471-M01A 48 31-Jul-22 02:00 02-Aug-22 02:00 1513 1578 79
1571 MP-RH471-M13B 48 31-Jul-22 02:00 02-Aug-22 02:00 1539 1578 79
1572 MP-RH471-M14B 48 31-Jul-22 02:00 02-Aug-22 02:00 1540 1578 79
Page 50 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1573 MP-RH471-M23A 48 31-Jul-22 02:00 02-Aug-22 02:00 1544 1578 79
1565 MC-RH471-M01B 48 01-Aug-22 02:00 03-Aug-22 02:00 1520 1578 55
1574 MP-RH471-M23B 48 01-Aug-22 02:00 03-Aug-22 02:00 1545 1578 55
1575 MP-RH471-M23C 48 01-Aug-22 02:00 03-Aug-22 02:00 1546 1578 55
PM of Motor/Feeder Completion 0 03-Aug-22 02:00 03-Aug-22 02:00 55
1578 PM of Motor/Feeder Completion 0 03-Aug-22 02:00 1564, 1565,
15821566, 1567, 1568, PM of Motor/Feeder
55 1569, 1570, 1571, 1572, 1573, 1574, 1575, 1576 Completion
Electrical Maintenance Jobs Completion 0 04-Aug-22 02:00 04-Aug-22 02:00 31
1582 Electrical Maintenance Jobs Completion 0 04-Aug-22 02:00 1531, 1562,
15841578, 1579, 1580
31 Electrical Maintenance Jobs Comp
Pre-start up activity 44 05-Aug-22 09:00 07-Aug-22 05:00 0
1584 Reactors inlet/outlet flange Deblinding 8 05-Aug-22 09:00 05-Aug-22 17:00 1434, 1508,
15851582, 1351 0
1585 System line up and inertisation 4 05-Aug-22 17:00 05-Aug-22 21:00 1584 1586 0
1586 Leak check with Nitrogen 6 05-Aug-22 21:00 06-Aug-22 03:00 1585 1587 0
1587 PSSR Level-2 and punch point attending 8 06-Aug-22 03:00 06-Aug-22 11:00 1586 1588, 1589 0
1588 Deblinding at battery limit except H2, 10 06-Aug-22 03:00 06-Aug-22 13:00 1587 1594 16
Fuel gas & Pilot gas Blind
1589 PSSR Level-1 and punch point attending 6 06-Aug-22 11:00 06-Aug-22 17:00 1587 1590, 1591 0
1590 Deblinding at Battery limit H2, Fuel gas 4 06-Aug-22 13:00 06-Aug-22 17:00 1589 1591 0
& Pilot gas Blind
1591 Pressure to 15 Kg/cm2 with Hydrogen 6 06-Aug-22 17:00 06-Aug-22 23:00 1590, 1592 0
& leak check 1589
1592 Pressure to 25 Kg/cm2 with Hydrogen 6 06-Aug-22 23:00 07-Aug-22 05:00 1591 1594 0
& leak check
Start up Activity 67 07-Aug-22 05:00 10-Aug-22 00:00 0
1594 Establish Hydrogen Circulation & burner 2 07-Aug-22 05:00 07-Aug-22 07:00 1592, 1595 0
light up 1588
1595 Heating of Reactor catalyst up to 150 11 07-Aug-22 07:00 07-Aug-22 18:00 1594 1596 0
°C per Hr (Catalyst Drying) @ 20 deg C
per hr
1596 After completion of catalyst drying, 3 07-Aug-22 18:00 07-Aug-22 21:00 1595 1597, 0
Increase Main Reactor (R01 & R02) 1598
inlet temperature to 185 deg C at 20
deg C/h
1597 Introduce HTLN from RTF & naphtha 2 07-Aug-22 21:00* 07-Aug-22 23:00 1596 1598 0
circulation at DIOS R03 outlet
temperature of 165 deg C (above dew
point)
1598 Increase HTLN in R03 from 25 m3/hr 4 07-Aug-22 23:00 08-Aug-22 03:00 1597, 1599 0
to 100 m3/hr and do not operate 1596
recycle pump P06A/B.
1599 Catalyst Prewetting and Draining of 6 08-Aug-22 03:00 08-Aug-22 09:00 1598 1600 0
reactor outlet at V05

Page 51 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1600 Route HTLN to Separator (V05) & 2 08-Aug-22 09:00 08-Aug-22 11:00 1599 1601 0
Stripper (C07) to Slope
1601 Establish HTLN circulation Between 3 08-Aug-22 11:00 08-Aug-22 16:00 1600 1602 0
V01/V05/C07 & back to V01
1602 Start DMDS injection@180deg & 4 08-Aug-22 16:00* 08-Aug-22 20:00 1601 1603 0
increase main reactor I/L temp@25
deg/hr from 180to250deg. to DIOS
R03 O/L temp 180deg
1603 Continue HTLN Circulation & 8 08-Aug-22 20:00 09-Aug-22 02:00 1602 1604 0
stabilization of Unit before LCN
1604 introduction
Introduce LCN feed (50%) along with 20 09-Aug-22 02:00 09-Aug-22 22:00 1603 1605 0
product HTLN (50%) from C07
1605 Line up Product after lab analysis 2 09-Aug-22 22:00 10-Aug-22 00:00 1604 0

Page 52 of 52 Prepared by: DTA_TA planning


Actual Work Remaining Work Critical Remaining Work Milestone Actual