Professional Documents
Culture Documents
LNUU (Unit 471) SD Schedule Final July 22 - For Implementation
LNUU (Unit 471) SD Schedule Final July 22 - For Implementation
LNUU (Unit 471) SD Schedule Final July 22 - For Implementation
11 Purge the reactor loop with nitrogen 19 22-Jul-22 17:00 23-Jul-22 12 :00 9 12, 14, 0
16
12 Blinding of R01 outlet flange 4 23-Jul-22 12:00 23-Jul-22 16 :00 11 13, 15, 0
17, 111,
134, 151,
168, 205,
14 Blinding of R02 outlet flange 4 23-Jul-22 12:00 23-Jul-22 16 :00 11 224,
15 238, 105
16 Blinding of R03 outlet flange 4 23-Jul-22 12:00 23-Jul-22 16 :00 11, 10 17 31
13 Top elbow Blinding of R01 with N2 blanketing 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 24 0
15 Top elbow Blinding of R02 with N2 blanketing 4 23-Jul-22 16:00 23-Jul-22 20 :00 12, 14 51 105
17 Top elbow Blinding of R03 with N2 4 23-Jul-22 16:00 23-Jul-22 20 :00 12, 16 18, 78, 31
blanketing 1486
18 Stripper loop de-pressurizing / purging 30 23-Jul-22 20:00 25-Jul-22 02 :00 17, 5, 523, 555, 31
with Nitrogen 6, 8, 10 563, 571,
579, 639,
667, 688,
Operation/Maintenance/Inspection Jobs 305 23-Jul-22 16:00 05-Aug-22 09:00 710, 731, 111
Mechanical maintenance jobs 305 23-Jul-22 16:00 05-Aug-22 09:00 111
Reactor R01/R02/R03 Catalyst Replacement Jobs (Scope: 301 23-Jul-22 20:00
03 nos) 05-Aug-22 09:00 0
R01 168 23-Jul-22 20:00 30-Jul-22 20 :00 133
R01 Unloading 54 23-Jul-22 20:00 26-Jul-22 02 :00 0
24 Blinding of reactor connected lines 8 23-Jul-22 20:00 24-Jul-22 04 :00 13 25 0
29 Preparation for vessel entry and initial 1 24-Jul-22 13:00 24-Jul-22 14 :00 28 30 0
gas test
30 Unloading of support material and 30 24-Jul-22 14:00 25-Jul-22 20 :00 29 31 0
catalyst by dumping/shovelling
55 Positioning of elbow at ground level and 1 24-Jul-22 12:30 24-Jul-22 13 :00 54 56 105
covering with tarpauline
56 Preparation for vessel entry and initial 1 24-Jul-22 13:00 24-Jul-22 14 :00 55 57 105
gas test
57 Unloading of support material and 30 28-Jul-22 23:00 30-Jul-22 05 :00 56, 42 58, 85 0
catalyst by dumping/shovelling
82 Positioning of elbow at ground level and 1 24-Jul-22 12:30 24-Jul-22 13 :00 81 83 137
covering with tarpauline
83 Preparation for vessel entry and initial 2 24-Jul-22 13:00 24-Jul-22 15 :00 82 84 137
gas test
84 Opening of Top Liquid distribution tray 2 24-Jul-22 15:00 24-Jul-22 17 :00 83 85 137
117 Bundle Pull Out 6 24-Jul-22 18:00 25-Jul-22 00 :00 116 118 162
123 Belzona application on Dome of S01A/B 18 24-Jul-22 18:00 25-Jul-22 12 :00 116 125 191
and Curing
118 Inspection of bundle and shifting to 5 25-Jul-22 00:00 25-Jul-22 05 :00 117 119 162
workshop
119 Hydrojetting 16 25-Jul-22 05:00 25-Jul-22 21 :00 118 120 162
120 Inspection by CES/CTS 4 25-Jul-22 21:00 26-Jul-22 01 :00 119 121 162
Page 5 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
121 Shifting to Site 4 26-Jul-22 01:00 26-Jul-22 05 :00 120 122 162
122 Bundle Insertion 6 26-Jul-22 05:00 26-Jul-22 11 :00 121 124 162
124 Shell side Hydrotest 6 26-Jul-22 11:00 26-Jul-22 17 :00 122 125 162
125 Dome Box Up 6 26-Jul-22 17:00 26-Jul-22 23 :00 124, 123126 162
126 Chemical cleaning 24 26-Jul-22 23:00 27-Jul-22 23 :00 125 127 162
127 Chemical cleaning equipment removal 3 27-Jul-22 23:00 28-Jul-22 02 :00 126 128 162
128 Tube side Hydrotest 6 28-Jul-22 02:00 28-Jul-22 08 :00 127 129 162
129 Belzona application on Tube sheet of 15 28-Jul-22 08:00 28-Jul-22 23 :00 128 130 162
S01A/B and Curing
130 Final Shell side Hydrotest 8 28-Jul-22 23:00 29-Jul-22 07 :00 129 131 162
131 Deblinding and piping box up 8 29-Jul-22 07:00 29-Jul-22 15 :00 130 520 162
ME-RH471-S03A/B (NO. 1 Combined Feed Exchanger) 228 23-Jul-22 16:00 02-Aug-22 04:00 77
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 151
134 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 135 2
135 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 134 136, 186, 185 2
136 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 135 138 151
Maintenance/ Inspection jobs 210 24-Jul-22 10:00 02-Aug-22 04:00 77
138 Piping & Dome removal of S03A/B 6 24-Jul-22 10:00 24-Jul-22 16 :00 136 139 151
139 Bundle puller arrangement & Tube 8 28-Jul-22 04:00 28-Jul-22 12 :00 138, 140, 438 67
bundle pull out 173
140 Tube bundle shifting to HJ bay 4 29-Jul-22 16:00 29-Jul-22 20 :00 139, 173141 77
141 Hydrojetting 30 29-Jul-22 20:00 31-Jul-22 02 :00 140 142 77
142 Inspection by CES/CTS 4 31-Jul-22 02:00 31-Jul-22 06 :00 141 143 77
143 Tube bundle shifting to site 4 31-Jul-22 06:00 31-Jul-22 10 :00 142 144 77
144 Tube bundle insertion 8 31-Jul-22 10:00 31-Jul-22 18 :00 143 145 77
145 Shell side Hydro testing 6 31-Jul-22 18:00 01-Aug-22 00:00 144 146 77
146 Dome Box up S03A/B 8 01-Aug-22 00:00 01-Aug-22 08:00 145 147 77
147 Differential hydrotest @ 30kg/cm2 of 10 01-Aug-22 08:00 01-Aug-22 18:00 146 148 77
S03A/B
148 Deblinding and piping box up 10 01-Aug-22 18:00 02-Aug-22 04:00 147 520 77
ME-RH471-S04A/B (No. 2 Combined Feed Exchanger) 182 23-Jul-22 16:00 31-Jul-22 06 :00 123
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 67
151 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 152 67
152 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 151 153 67
153 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 152 155 67
Maintenance/ Inspection jobs 164 24-Jul-22 10:00 31-Jul-22 06 :00 123
156 Bundle puller arrangement & Tube 8 27-Jul-22 12:00 27-Jul-22 20 :00 155 157, 173, 67
bundle pull out 510
157 Tube bundle shifting to HJ bay 4 27-Jul-22 20:00 28-Jul-22 00 :00 156 158 123
158 Hydrojetting 30 28-Jul-22 00:00 29-Jul-22 06 :00 157 159 123
159 Inspection by CES/CTS 4 29-Jul-22 06:00 29-Jul-22 10 :00 158 160 123
160 Tube bundle shifting to site 4 29-Jul-22 10:00 29-Jul-22 14 :00 159 161 123
161 Tube bundle insertion 8 29-Jul-22 14:00 29-Jul-22 22 :00 160 162 123
162 Shell side Hydro testing 6 29-Jul-22 22:00 30-Jul-22 04 :00 161 163 123
163 Dome Box up S04A/B 8 30-Jul-22 04:00 30-Jul-22 12 :00 162 164 123
164 Differential hydrotest @ 25kg/cm2 of 10 30-Jul-22 12:00 30-Jul-22 22 :00 163 165 123
S04A/B
165 Deblinding and piping box up 8 30-Jul-22 22:00 31-Jul-22 06 :00 164 520 123
ME-RH471-S04C/D (NO. 2 Combined Feed Exchanger) 202 23-Jul-22 16:00 01-Aug-22 02:00 103
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 141
168 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 169 141
169 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 168 170 141
170 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 169 172 141
Maintenance/ Inspection jobs 184 24-Jul-22 10:00 01-Aug-22 02:00 103
172 Piping & Dome removal of S04C/D 8 24-Jul-22 10:00 24-Jul-22 18 :00 170 173 141
173 Bundle puller arrangement & Tube 8 27-Jul-22 20:00 28-Jul-22 04 :00 172, 139, 140, 67
bundle pull out 156 174
174 Tube bundle shifting to HJ bay 4 28-Jul-22 20:00 29-Jul-22 00 :00 173 175 103
175 Hydrojetting 30 29-Jul-22 00:00 30-Jul-22 06 :00 174 176 103
176 Inspection by CES/CTS 4 30-Jul-22 06:00 30-Jul-22 10 :00 175 177 103
177 Tube bundle shifting to site 2 30-Jul-22 10:00 30-Jul-22 12 :00 176 178 103
178 Tube bundle insertion 8 30-Jul-22 12:00 30-Jul-22 20 :00 177 179 103
179 Shell side Hydro testing 6 30-Jul-22 20:00 31-Jul-22 02 :00 178 180 103
180 Dome Box up of S04C/D 6 31-Jul-22 02:00 31-Jul-22 08 :00 179 181 103
181 Differential hydrotest @ 25 kg/cm2 of 10 31-Jul-22 08:00 31-Jul-22 18 :00 180 182 103
S04C/D
182 Deblinding and Piping box up 8 31-Jul-22 18:00 01-Aug-22 02:00 181 520 103
ME-RH471-S05 (NO. 3 COMBINED FEED EXCHANGER) 299 23-Jul-22 20:00 05-Aug-22 07:00 2
Process Handover 14 23-Jul-22 20:00 24-Jul-22 10 :00 2
185 Purging 2 23-Jul-22 20:00 23-Jul-22 22 :00 135 186 2
186 Blinding 8 23-Jul-22 22:00 24-Jul-22 06 :00 135, 185187 2
194 Retubing at CES-W/s (Scope: 1100 227 25-Jul-22 10:00 03-Aug-22 21:00 193 195 2
no's U)
195 Inspection by CES/CTS 2 03-Aug-22 21:00 03-Aug-22 23:00 194 196 2
196 Tube bundle shifting to site 2 03-Aug-22 23:00 04-Aug-22 01:00 195 197 2
197 Tube bundle insertion 4 04-Aug-22 01:00 04-Aug-22 05:00 196 198 2
198 Pneumatic test 4 04-Aug-22 05:00 04-Aug-22 09:00 197 199 2
199 Shell side Hydro test @ 37.5 kg/cm2 6 04-Aug-22 09:00 04-Aug-22 15:00 198 200 2
200 Dome Box up of S05 4 04-Aug-22 15:00 04-Aug-22 19:00 199 201 2
201 Differential hydrotest @ 14.8 kg/cm2 6 04-Aug-22 19:00 05-Aug-22 01:00 200 202 2
of S05
202 Deblinding and Piping box up 6 05-Aug-22 01:00 05-Aug-22 07:00 201 520 2
106 23-Jul-22 16:00
ME-RH471-S06 (NO. 4 COMBINED FEED EXCHANGER) BXU 28-Jul-22 02 :00 199
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 103
205 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 206 103
206 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 205 207 103
207 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 206 209 103
Maintenance/Inspection jobs 88 24-Jul-22 10:00 28-Jul-22 02 :00 199
209 Passivation with Neutralization solution 6 24-Jul-22 10:00 24-Jul-22 16 :00 207 210, 103
1076
210 Dome & Piping bolt detorquing 2 24-Jul-22 16:00 24-Jul-22 18 :00 209 211 199
211 Dome & Piping removal 8 24-Jul-22 18:00 25-Jul-22 02 :00 210 212 199
212 Tube Bundle puller arrangement & 6 25-Jul-22 02:00 25-Jul-22 08 :00 211 213 199
Bundle pullout
213 Tube Bundle shifting to hydrojetting bay 4 25-Jul-22 08:00 25-Jul-22 12 :00 212 214 199
247 Retubing at CES-W/s (Scope: 236 no's 135 26-Jul-22 02:00 31-Jul-22 17 :00 246 248 46
U)
248 Inspection by CES/CTS 2 31-Jul-22 17:00 31-Jul-22 19 :00 247 249 46
249 Tube bundle shifting to site 4 31-Jul-22 19:00 31-Jul-22 23 :00 248 250 46
250 Tube bundle insertion 8 31-Jul-22 23:00 01-Aug-22 07:00 249 251 46
251 Pnuematic test 6 01-Aug-22 07:00 01-Aug-22 13:00 250 252 46
252 Shell side Hydro test (Internal) 12 01-Aug-22 13:00 02-Aug-22 01:00 251 253 46
254 Dome Box up of S08 6 02-Aug-22 13:00 02-Aug-22 19:00 253 255 46
255 Tube side hydrotest 8 02-Aug-22 19:00 03-Aug-22 03:00 254 256 46
256 Deblinding and Piping box up 8 03-Aug-22 03:00 03-Aug-22 11:00 255 520 46
ME-RH471-S09 (MP STEAM SUPERHEATER) 78 23-Jul-22 16:00 26-Jul-22 22 :00 227
Process handover 18 23-Jul-22 16:00 24-Jul-22 10 :00 227
259 Purging 2 23-Jul-22 16:00 23-Jul-22 18 :00 12 260 227
260 Blinding 8 23-Jul-22 18:00 24-Jul-22 02 :00 259 261 227
261 Steaming 8 24-Jul-22 02:00 24-Jul-22 10 :00 260 263 227
Maintenance/Inspection jobs 60 24-Jul-22 10:00 26-Jul-22 22 :00 227
263 Dome & piping bolt detorquing 4 24-Jul-22 10:00 24-Jul-22 14 :00 261 264 227
264 Dome & piping removal 8 24-Jul-22 14:00 24-Jul-22 22 :00 263 265 227
265 Initial Inspection by CES-Inspection 4 24-Jul-22 22:00 25-Jul-22 02 :00 264 266 227
Group
266 In situ HJ 8 25-Jul-22 02:00 25-Jul-22 10 :00 265 267 227
267 Final Inspection 4 25-Jul-22 10:00 25-Jul-22 14 :00 266 268 227
268 Shell side hydrotesting 8 25-Jul-22 14:00 25-Jul-22 22 :00 267 269 227
269 Dome Box up 10 25-Jul-22 22:00 26-Jul-22 08 :00 268 270 227
270 Tube side hydrotesting 6 26-Jul-22 08:00 26-Jul-22 14 :00 269 271 227
271 Deblinding & piping boxup 8 26-Jul-22 14:00 26-Jul-22 22 :00 270 520 227
130 23-Jul-22
ME-RH471-S10A/B (REACTOR NO. 2 FEED - STRIPPER BOTTOMS EX) BEU16:00 29-Jul-22 02 :00 175
Process handover 28 23-Jul-22 16:00 24-Jul-22 20 :00 175
274 Purging 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 275 175
275 Blinding 12 23-Jul-22 20:00 24-Jul-22 08 :00 274 276 175
276 Steaming 12 24-Jul-22 08:00 24-Jul-22 20 :00 275 278 175
Maintenance/Inspection jobs 102 24-Jul-22 20:00 29-Jul-22 02 :00 175
278 Dome & piping bolt detorquing 4 24-Jul-22 20:00 25-Jul-22 00 :00 276 279 175
279 Dome & piping removal 8 25-Jul-22 00:00 25-Jul-22 08 :00 278 280 175
280 Tube bundle puller arrangement & 8 25-Jul-22 08:00 25-Jul-22 16 :00 279 281 175
Bundle pullout
281 Tube bundle shifting to hydrojetting bay 4 25-Jul-22 16:00 25-Jul-22 20 :00 280 282 175
305 Dome box up 10 28-Jul-22 20:00 29-Jul-22 06 :00 304 306 147
306 Tube side hydrotesting at 60 kg/cm2 12 29-Jul-22 06:00 29-Jul-22 18 :00 305 307 147
318 Hydrojetting & inspection of S12A/B 16 27-Jul-22 12:00 28-Jul-22 04 :00 317 319 135
323 Dome box up 10 29-Jul-22 08:00 29-Jul-22 18 :00 322 324 135
324 Tube side hydrotesting at 60 kg/cm2 12 29-Jul-22 18:00 30-Jul-22 06 :00 323 325 135
339 On Tube sheet Belzona-1321/ Stanvac 8 26-Jul-22 18:00 27-Jul-22 02 :00 337 340 155
brushable ceramic coating
340 Dome boxup 8 27-Jul-22 02:00 27-Jul-22 10 :00 338, 339341 155
341 Tube side hydrotest at 37.5 kg/cm2 12 27-Jul-22 10:00 27-Jul-22 22 :00 340 342 155
342 Passivation on tube side 24 27-Jul-22 22:00 28-Jul-22 22 :00 341 343 155
343 Tube side hydrotest at 37.5 kg/cm2 12 28-Jul-22 22:00 29-Jul-22 10 :00 342 344 155
344 Deblinding & piping boxup 12 29-Jul-22 10:00 29-Jul-22 22 :00 343 520 155
74 23-Jul-22 16:00
ME-RH471-S15A (LUBE OIL COOLERS FOR MC-RH471-C01A) 26-Jul-22 18 :00 231
Process handover 10 23-Jul-22 16:00 24-Jul-22 02 :00 231
347 Oil draining 6 23-Jul-22 16:00 23-Jul-22 22 :00 12 348 231
348 Blinding 4 23-Jul-22 22:00 24-Jul-22 02 :00 347 350 231
Maintenance/Inspection jobs 64 24-Jul-22 02:00 26-Jul-22 18 :00 231
350 Channel/Dome removal 6 24-Jul-22 02:00 24-Jul-22 08 :00 348 351, 352 231
353 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 351 354 231
HJ
354 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 352, 353355 231
355 Shell side hydrotest at 15 kg/cm2 with 12 25-Jul-22 06:00 25-Jul-22 18 :00 354 356 231
Oil
356 Channel/Dome box up 10 25-Jul-22 18:00 26-Jul-22 04 :00 355 357 231
357 Tube side hydrotest at 15 kg/cm2 8 26-Jul-22 04:00 26-Jul-22 12 :00 356 358, 520 231
381 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 379 382 231
HJ
395 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 393 396 231
HJ
396 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 394, 395397 231
397 Shell side hydrotest at 15 kg/cm2 with 12 25-Jul-22 06:00 25-Jul-22 18 :00 396 398 231
Oil
398 Channel/Dome box up 10 25-Jul-22 18:00 26-Jul-22 04 :00 397 399 231
399 Tube side hydrotest at 15 kg/cm2 8 26-Jul-22 04:00 26-Jul-22 12 :00 398 400 231
418 S22B: Partition plate replacement at 60 25-Jul-22 02:00 27-Jul-22 14 :00 417 419 179
Workshop
420 Tube bundle puller arrangement & 8 26-Jul-22 16:00 27-Jul-22 00 :00 416 316, 421 133
Bundle pullout
421 Tube bundle shifting to hydrojetting bay 4 27-Jul-22 00:00 27-Jul-22 04 :00 420 422 133
422 Hydrojetting & inspection of S22A/B 36 27-Jul-22 04:00 28-Jul-22 16 :00 421 423 133
419 S22B: Dome shifting back to site 4 27-Jul-22 14:00 27-Jul-22 18 :00 418 427 179
423 Inspection by CES/CTS 4 28-Jul-22 16:00 28-Jul-22 20 :00 422 424 133
424 Tube bundle shifting to site 4 28-Jul-22 20:00 29-Jul-22 00 :00 423 425 133
425 Tube bundle insertion 8 29-Jul-22 00:00 29-Jul-22 08 :00 424 426 133
426 Shell side hydrotest of S22A/B @ 48 8 29-Jul-22 08:00 29-Jul-22 16 :00 425 427 133
kg/cm2 G
427 Dome box up 8 29-Jul-22 16:00 30-Jul-22 00 :00 426, 419428 133
428 Tube side hydrotest of S22A/B @ 62 8 30-Jul-22 00:00 30-Jul-22 08 :00 427 429 133
kg/cm2
429 Deblinding and piping box up 12 30-Jul-22 08:00 30-Jul-22 20 :00 428 520 133
238
ME-RH471-S23A/B (DIOLFIN REACTOR FEED EXCHANGER 23-Jul-22 16:00
NO.1) 02-Aug-22 14:00 67
Process handover 24 23-Jul-22 16:00 24-Jul-22 16 :00 143
432 Purging 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 433 143
433 Blinding 12 23-Jul-22 20:00 24-Jul-22 08 :00 432 434 143
434 Steaming 8 24-Jul-22 08:00 24-Jul-22 16 :00 433 436 143
Maintenance/Inspection jobs 214 24-Jul-22 16:00 02-Aug-22 14:00 67
436 Dome & piping bolt detorquing 4 24-Jul-22 16:00 24-Jul-22 20 :00 434 437 143
437 Dome & piping removal 12 24-Jul-22 20:00 25-Jul-22 08 :00 436 438 143
438 Tube bundle puller arrangement & 8 28-Jul-22 12:00 28-Jul-22 20 :00 437, 439 67
Bundle pullout 139
439 Tube bundle shifting to hydrojetting bay 4 29-Jul-22 20:00 30-Jul-22 00 :00 438 440 67
447 Deblinding & piping boxup 12 02-Aug-22 02:00 02-Aug-22 14:00 446 520 67
140
ME-RH471-S24A/B (DIOLFIN REACTOR FEED EXCHANGER 23-Jul-22 16:00
NO.1) 29-Jul-22 12 :00 165
Process handover 24 23-Jul-22 16:00 24-Jul-22 16 :00 147
450 Purging 4 23-Jul-22 16:00 23-Jul-22 20 :00 12 451 147
451 Blinding 12 23-Jul-22 20:00 24-Jul-22 08 :00 450 452 147
452 Steaming 8 24-Jul-22 08:00 24-Jul-22 16 :00 451 454 147
Maintenance/Inspection jobs 116 24-Jul-22 16:00 29-Jul-22 12 :00 165
454 Dome & piping bolt detorquing 4 24-Jul-22 16:00 24-Jul-22 20 :00 452 455 147
455 Dome & piping removal 12 24-Jul-22 20:00 25-Jul-22 08 :00 454 456 147
456 Tube bundle puller arrangement & 8 25-Jul-22 20:00 26-Jul-22 04 :00 455 298, 457 147
Bundle pullout
457 Tube bundle shifting to hydrojetting bay 4 26-Jul-22 04:00 26-Jul-22 08 :00 456 458 165
458 Hydrojetting & inspection of S24A/B 24 26-Jul-22 08:00 27-Jul-22 08 :00 457 459 165
459 Inspection by CES/CTS 4 27-Jul-22 08:00 27-Jul-22 12 :00 458 460 165
460 Tube bundle shifting to site 4 27-Jul-22 12:00 27-Jul-22 16 :00 459 461 165
461 Tube bundle insertion 8 27-Jul-22 16:00 28-Jul-22 00 :00 460 462 165
462 Shell side hydrotest at 37 kg/cm2 12 28-Jul-22 00:00 28-Jul-22 12 :00 461 463 165
463 Tube side hydrotest at 62.01 kg/cm2 12 28-Jul-22 12:00 29-Jul-22 00 :00 462 464 165
464 Deblinding & piping boxup 12 29-Jul-22 00:00 29-Jul-22 12 :00 463 520 165
ME-RH471-S25A (471-C01C LUBE OIL COOLER) 74 23-Jul-22 16:00 26-Jul-22 18 :00 231
Process handover 10 23-Jul-22 16:00 24-Jul-22 02 :00 231
467 Oil draining 6 23-Jul-22 16:00 23-Jul-22 22 :00 12 468 231
468 Blinding 4 23-Jul-22 22:00 24-Jul-22 02 :00 467 470 231
Maintenance/Inspection jobs 64 24-Jul-22 02:00 26-Jul-22 18 :00 231
470 Channel/Dome removal 6 24-Jul-22 02:00 24-Jul-22 08 :00 468 471, 472 231
471 Inspection of bundle & HJ 12 24-Jul-22 08:00 24-Jul-22 20 :00 470 473 231
472 Belzona application on Channel/Cover 18 24-Jul-22 08:00 25-Jul-22 02 :00 470 474 231
473 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 471 474 231
HJ
474 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 472, 473475 231
487 Belzona application on Tubesheet after 6 24-Jul-22 20:00 25-Jul-22 02 :00 485 488 231
HJ
488 Oil fill up 4 25-Jul-22 02:00 25-Jul-22 06 :00 486, 487489 231
489 Shell side hydrotest at 15 kg/cm2 with 12 25-Jul-22 06:00 25-Jul-22 18 :00 488 490 231
Oil
490 Channel/Dome box up 10 25-Jul-22 18:00 26-Jul-22 04 :00 489 491 231
491 Tube side hydrotest at 15 kg/cm2 8 26-Jul-22 04:00 26-Jul-22 12 :00 490 492 231
517 Tube side hydrotesting at 50.8 kg/cm2 8 29-Jul-22 20:00 30-Jul-22 04 :00 516 518 141
518 Deblinding & piping boxup 8 30-Jul-22 04:00 30-Jul-22 12 :00 517 520 141
Exchanger Jobs Completion 0 05-Aug-22 07:00 05-Aug-22 07:00 2
520 Exchanger Jobs Completion 0 05-Aug-22 07:00 148, 165,1351
182, 202, 221, 235, Exchanger
2 256, 271, 307, 344, 357, 372, 386, 400, 409, 447, Jobs492,
464, 478, Completion
501, 518
Fin Fan Coolers M&I (Scope: 14 nos) 140 25-Jul-22 02:00 30-Jul-22 22 :00 131
42- 01)
ME-RH471-A01-01 (PRODUCTS CONDENSER TUBE BUNDLE 25-Jul-22 02:00 26-Jul-22 20 :00 229
523 Blinding 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 524, 531 131
524 20% plug opening 6 25-Jul-22 08:00 25-Jul-22 14 :00 523 525, 532, 556 159
525 Inspection 2 25-Jul-22 14:00 25-Jul-22 16 :00 524 526, 533 159
526 Hydrojetting 8 25-Jul-22 16:00 26-Jul-22 00 :00 525 527, 534 159
527 Inspection after HJ 2 26-Jul-22 00:00 26-Jul-22 02 :00 526 528 159
528 Hydrotest 10 26-Jul-22 02:00 26-Jul-22 12 :00 527 529, 536 159
529 Deblinding 8 26-Jul-22 12:00 26-Jul-22 20 :00 528 635 229
46- 02)
ME-RH471-A01-02 (PRODUCTS CONDENSER TUBE BUNDLE 25-Jul-22 08:00 27-Jul-22 06 :00 219
531 Blinding 6 25-Jul-22 08:00 25-Jul-22 14 :00 523 532, 539 131
532 20% plug opening 6 25-Jul-22 14:00 25-Jul-22 20 :00 531, 524533, 540 163
533 Inspection 2 25-Jul-22 20:00 25-Jul-22 22 :00 525, 532534, 541 163
534 Hydrojetting 8 26-Jul-22 00:00 26-Jul-22 08 :00 526, 533535, 542 161
535 Inspection after HJ 2 26-Jul-22 08:00 26-Jul-22 10 :00 534 536 161
536 Hydrotest 10 26-Jul-22 12:00 26-Jul-22 22 :00 535, 528537, 544 159
537 Deblinding 8 26-Jul-22 22:00 27-Jul-22 06 :00 536 635 219
50- 03)
ME-RH471-A01-03 (PRODUCTS CONDENSER TUBE BUNDLE 25-Jul-22 14:00 27-Jul-22 16 :00 209
539 Blinding 6 25-Jul-22 14:00 25-Jul-22 20 :00 531 540, 547 131
540 20% plug opening 6 25-Jul-22 20:00 26-Jul-22 02 :00 539, 532541, 548 167
541 Inspection 2 26-Jul-22 02:00 26-Jul-22 04 :00 533, 540542, 549 167
542 Hydrojetting 8 26-Jul-22 08:00 26-Jul-22 16 :00 534, 541543, 550 163
543 Inspection after HJ 2 26-Jul-22 16:00 26-Jul-22 18 :00 542 544 163
Page 18 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
544 Hydrotest 10 26-Jul-22 22:00 27-Jul-22 08 :00 543, 536545, 552 159
545 Deblinding 8 27-Jul-22 08:00 27-Jul-22 16 :00 544 635 209
54- 04)
ME-RH471-A01-04 (PRODUCTS CONDENSER TUBE BUNDLE 25-Jul-22 20:00 28-Jul-22 02 :00 199
547 Blinding 6 25-Jul-22 20:00 26-Jul-22 02 :00 539 548, 555 131
548 20% plug opening 6 26-Jul-22 02:00 26-Jul-22 08 :00 547, 540549 171
549 Inspection 2 26-Jul-22 08:00 26-Jul-22 10 :00 541, 548550, 557 171
550 Hydrojetting 8 26-Jul-22 16:00 27-Jul-22 00 :00 549, 542551, 558 165
551 Inspection after HJ 2 27-Jul-22 00:00 27-Jul-22 02 :00 550 552 165
552 Hydrotest 10 27-Jul-22 08:00 27-Jul-22 18 :00 551, 544553, 560 159
553 Deblinding 8 27-Jul-22 18:00 28-Jul-22 02 :00 552 635 199
58- 05)
ME-RH471-A01-05 (PRODUCTS CONDENSER TUBE BUNDLE 26-Jul-22 02:00 28-Jul-22 12 :00 189
555 Blinding 6 26-Jul-22 02:00 26-Jul-22 08 :00 18, 547 556, 563 131
556 20% plug opening 6 26-Jul-22 08:00 26-Jul-22 14 :00 524, 555557, 564 175
557 Inspection 2 26-Jul-22 14:00 26-Jul-22 16 :00 549, 556558, 565 175
558 Hydrojetting 8 27-Jul-22 00:00 27-Jul-22 08 :00 557, 550559, 566 167
559 Inspection after HJ 2 27-Jul-22 08:00 27-Jul-22 10 :00 558 560 167
560 Hydrotest 10 27-Jul-22 18:00 28-Jul-22 04 :00 559, 552561, 568 159
561 Deblinding 8 28-Jul-22 04:00 28-Jul-22 12 :00 560 635 189
62- 06)
ME-RH471-A01-06 (PRODUCTS CONDENSER TUBE BUNDLE 26-Jul-22 08:00 28-Jul-22 22 :00 179
563 Blinding 6 26-Jul-22 08:00 26-Jul-22 14 :00 18, 555 564, 571 131
564 20% plug opening 6 26-Jul-22 14:00 26-Jul-22 20 :00 563, 556565, 572 179
565 Inspection 2 26-Jul-22 20:00 26-Jul-22 22 :00 557, 564566, 573 179
566 Hydrojetting 8 27-Jul-22 08:00 27-Jul-22 16 :00 565, 558567, 574 169
567 Inspection after HJ 2 27-Jul-22 16:00 27-Jul-22 18 :00 566 568 169
568 Hydrotest 10 28-Jul-22 04:00 28-Jul-22 14 :00 567, 560569, 576 159
569 Deblinding 8 28-Jul-22 14:00 28-Jul-22 22 :00 568 635 179
66- 07)
ME-RH471-A01-07 (PRODUCTS CONDENSER TUBE BUNDLE 26-Jul-22 14:00 29-Jul-22 08 :00 169
571 Blinding 6 26-Jul-22 14:00 26-Jul-22 20 :00 18, 563 572, 579 131
572 20% plug opening 6 26-Jul-22 20:00 27-Jul-22 02 :00 571, 564580 187
573 Inspection 2 26-Jul-22 22:00 27-Jul-22 00 :00 565 574, 581 187
574 Hydrojetting 8 27-Jul-22 16:00 28-Jul-22 00 :00 566, 573575, 582 171
575 Inspection after HJ 2 28-Jul-22 00:00 28-Jul-22 02 :00 574 576 171
576 Hydrotest 10 28-Jul-22 14:00 29-Jul-22 00 :00 575, 568577, 584 159
577 Deblinding 8 29-Jul-22 00:00 29-Jul-22 08 :00 576 635 169
70- 08)
ME-RH471-A01-08 (PRODUCTS CONDENSER TUBE BUNDLE 26-Jul-22 20:00 29-Jul-22 18 :00 159
579 Blinding 6 26-Jul-22 20:00 27-Jul-22 02 :00 18, 571 580, 587 131
580 20% plug opening 6 27-Jul-22 02:00 27-Jul-22 08 :00 579, 572581 187
581 Inspection 2 27-Jul-22 08:00 27-Jul-22 10 :00 573, 580582 187
582 Hydrojetting 8 28-Jul-22 00:00 28-Jul-22 08 :00 574, 581583 173
650 Scaffold erection for buffing/inspection 12 29-Jul-22 10:00 29-Jul-22 22 :00 649 651 65
of weld joints
651 Buffing of top dish end to shell weld joint 8 29-Jul-22 22:00 30-Jul-22 06 :00 650 652, 655 65
656 Scaffold removal for buffing/inspection 8 31-Jul-22 06:00 31-Jul-22 14 :00 652, 657 65
of weld joints 655,
654
657 Tray cleaning before box up 6 31-Jul-22 14:00 31-Jul-22 20 :00 656 658 65
658 CES/CTS final inspection and clearance 4 31-Jul-22 20:00 01-Aug-22 00:00 657 659 65
for tray manway box up
659 Tray manway box up 12 01-Aug-22 00:00 01-Aug-22 12:00 658 660 65
660 Column manway box up (3 nos) 12 01-Aug-22 12:00 02-Aug-22 00:00 659 661 65
661 Column de-blinding 16 02-Aug-22 00:00 02-Aug-22 16:00 660 663 65
Column M&I Completion 0 02-Aug-22 16:00 02-Aug-22 16:00 65
663 Column M&I Completion 0 02-Aug-22 16:00 661 1351 65 Column M&I Completion
Vessel M&I (Scope: 25 nos) 158 25-Jul-22 02:00 31-Jul-22 16 :00 113
MV-RH471-V01 (FEED SURGE DRUM) 114 25-Jul-22 02:00 29-Jul-22 20 :00 157
Process Hand over 54 25-Jul-22 02:00 27-Jul-22 08 :00 157
667 Draining 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 668 157
668 Purging 8 25-Jul-22 08:00 25-Jul-22 16 :00 667 669 157
669 Blinding 8 25-Jul-22 16:00 26-Jul-22 00 :00 668 670 157
670 Steaming 8 26-Jul-22 00:00 26-Jul-22 08 :00 669 671 157
671 Opening of Manholes 4 26-Jul-22 08:00 26-Jul-22 12 :00 670 672 157
672 Establish air circulation 8 26-Jul-22 12:00 26-Jul-22 20 :00 671 673 157
673 Vessel Entry 2 26-Jul-22 20:00 26-Jul-22 22 :00 672 674 157
674 Cleaning of Vessel 10 26-Jul-22 22:00 27-Jul-22 08 :00 673 676 157
Maintenance/Inspection Jobs 60 27-Jul-22 08:00 29-Jul-22 20 :00 157
676 CTS/CES inspection 4 27-Jul-22 08:00 27-Jul-22 12 :00 674 677, 680 157
677 Scaffolding erection 8 27-Jul-22 12:00 27-Jul-22 20 :00 676 678 157
680 Hydro test of LG/LT pipe 12 27-Jul-22 12:00 28-Jul-22 00 :00 676 685 191
678 Buffing of top dish end to shell weld joint 8 27-Jul-22 20:00 28-Jul-22 04 :00 677 679, 681 157
679 WFMPT inspection 4 28-Jul-22 04:00 28-Jul-22 08 :00 678 684 177
681 Thickness survey 12 28-Jul-22 04:00 28-Jul-22 16 :00 678 682 157
682 Scaffolding removal 6 28-Jul-22 16:00 28-Jul-22 22 :00 681 683 157
683 Final Cleaning 6 28-Jul-22 22:00 29-Jul-22 04 :00 682 684 157
684 Manway box up 6 29-Jul-22 04:00 29-Jul-22 10 :00 683, 679685 157
685 De-blinding 10 29-Jul-22 10:00 29-Jul-22 20 :00 684, 6801073 157
MV-RH471-V05 (SEPARATOR) 113 25-Jul-22 02:00 29-Jul-22 19 :00 158
700 WFMPT inspection 4 28-Jul-22 07:00 28-Jul-22 11 :00 699 703 158
703 Scaffolding removal 6 28-Jul-22 11:00 28-Jul-22 17 :00 700 704 158
704 Demister fixing 6 28-Jul-22 17:00 28-Jul-22 23 :00 703, 701,705
702 158
705 Final Cleaning 6 28-Jul-22 23:00 29-Jul-22 05 :00 704 706 158
706 Manway box up 6 29-Jul-22 05:00 29-Jul-22 11 :00 705 707 158
707 De-blinding 8 29-Jul-22 11:00 29-Jul-22 19 :00 706 1073 158
MV-RH471-V06 (COMPRESSOR SUCTION KOD) 106 25-Jul-22 02:00 29-Jul-22 12 :00 165
Process Hand over 56 25-Jul-22 02:00 27-Jul-22 10 :00 165
710 Purging 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 711 165
711 Blinding 8 25-Jul-22 08:00 25-Jul-22 16 :00 710 712 165
712 Steaming 8 25-Jul-22 16:00 26-Jul-22 00 :00 711 713 165
713 Cooling 8 26-Jul-22 00:00 26-Jul-22 08 :00 712 714 165
714 Opening of Manholes 6 26-Jul-22 08:00 26-Jul-22 14 :00 713 715 165
715 Establish air circulation 8 26-Jul-22 14:00 26-Jul-22 22 :00 714 716 165
716 Vessel Entry 2 26-Jul-22 22:00 27-Jul-22 00 :00 715 717 165
717 Cleaning of Vessel 10 27-Jul-22 00:00 27-Jul-22 10 :00 716 719 165
Maintenance/Inspection Jobs 50 27-Jul-22 10:00 29-Jul-22 12 :00 165
719 CTS/CES inspection 4 27-Jul-22 10:00 27-Jul-22 14 :00 717 720, 723 165
720 Scaffolding erection 8 27-Jul-22 14:00 27-Jul-22 22 :00 719 721, 724 165
723 Hydro test of LG/LT pipe 12 27-Jul-22 14:00 28-Jul-22 02 :00 719 726 179
721 Buffing of top dish end to shell weld joint 8 27-Jul-22 22:00 28-Jul-22 06 :00 720 722 165
724 Thickness survey 12 27-Jul-22 22:00 28-Jul-22 10 :00 720 726 171
722 WFMPT inspection 4 28-Jul-22 06:00 28-Jul-22 10 :00 721 725 165
Page 23 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
725 Scaffolding removal 6 28-Jul-22 10:00 28-Jul-22 16 :00 722 726 165
726 Final Cleaning 6 28-Jul-22 16:00 28-Jul-22 22 :00 724, 725,727
723 165
727 Manway box up 6 28-Jul-22 22:00 29-Jul-22 04 :00 726 728 165
728 De-blinding 8 29-Jul-22 04:00 29-Jul-22 12 :00 727 1073 165
MV-RH471-V08 (STRIPPER RECEIVER) 116 25-Jul-22 02:00 29-Jul-22 22 :00 155
Process Hand over 56 25-Jul-22 02:00 27-Jul-22 10 :00 155
731 Purging 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 732 155
732 Blinding 8 25-Jul-22 08:00 25-Jul-22 16 :00 731 733 155
733 Steaming 8 25-Jul-22 16:00 26-Jul-22 00 :00 732 734 155
734 Cooling 8 26-Jul-22 00:00 26-Jul-22 08 :00 733 735 155
735 Opening of Manholes 6 26-Jul-22 08:00 26-Jul-22 14 :00 734 736 155
736 Establish air circulation 8 26-Jul-22 14:00 26-Jul-22 22 :00 735 737 155
737 Vessel Entry 2 26-Jul-22 22:00 27-Jul-22 00 :00 736 738 155
738 Cleaning of Vessel 10 27-Jul-22 00:00 27-Jul-22 10 :00 737 740 155
Maintenance/Inspection Jobs 60 27-Jul-22 10:00 29-Jul-22 22 :00 155
740 CTS/CES inspection 4 27-Jul-22 10:00 27-Jul-22 14 :00 738 741, 744 155
741 Scaffolding erection 8 27-Jul-22 14:00 27-Jul-22 22 :00 740 742, 746 162
744 2 300# Isolation Valve Provision for 24 27-Jul-22 14:00 28-Jul-22 14 :00 740 745 155
Stand Pipe (Scope : 04 nos)
742 Buffing of top dish end to shell weld joint 8 27-Jul-22 22:00 28-Jul-22 06 :00 741 743 162
746 Thickness survey 12 27-Jul-22 22:00 28-Jul-22 10 :00 741 748 171
743 WFMPT inspection 7 28-Jul-22 06:00 28-Jul-22 13 :00 742 747 162
747 Scaffolding removal 6 28-Jul-22 13:00 28-Jul-22 19 :00 743 748 162
745 Hydro test of LG/LT pipe 12 28-Jul-22 14:00 29-Jul-22 02 :00 744 748 155
748 Final Cleaning 6 29-Jul-22 02:00 29-Jul-22 08 :00 745, 746,749
747 155
749 Manway box up 6 29-Jul-22 08:00 29-Jul-22 14 :00 748 750 155
750 De-blinding 8 29-Jul-22 14:00 29-Jul-22 22 :00 749 1073 155
MV-RH471-V09 (FUEL GAS DRUM) 104 25-Jul-22 02:00 29-Jul-22 10 :00 167
Process Hand over 60 25-Jul-22 02:00 27-Jul-22 14 :00 167
753 Purging 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 754 167
754 Blinding 8 25-Jul-22 08:00 25-Jul-22 16 :00 753 755 167
755 Steaming 12 25-Jul-22 16:00 26-Jul-22 04 :00 754 756 167
756 Cooling 8 26-Jul-22 04:00 26-Jul-22 12 :00 755 757 167
757 Opening of Manholes 4 26-Jul-22 12:00 26-Jul-22 16 :00 756 758 167
758 Establish air circulation 8 26-Jul-22 16:00 27-Jul-22 00 :00 757 759 167
759 Vessel Entry 2 27-Jul-22 00:00 27-Jul-22 02 :00 758 760 167
760 Cleaning of Vessel 12 27-Jul-22 02:00 27-Jul-22 14 :00 759 762 167
Maintenance/Inspection Jobs 44 27-Jul-22 14:00 29-Jul-22 10 :00 167
Page 24 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
762 CTS/CES inspection 4 27-Jul-22 14:00 27-Jul-22 18 :00 760 763, 765 167
763 Scaffolding erection 8 27-Jul-22 18:00 28-Jul-22 02 :00 762 764, 766 167
765 Hydro test of LG/LT pipe 12 27-Jul-22 18:00 28-Jul-22 06 :00 762 768 175
764 Demister pad inspection 4 28-Jul-22 02:00 28-Jul-22 06 :00 763 767 169
766 Thickness survey 12 28-Jul-22 02:00 28-Jul-22 14 :00 763 768 167
767 Scaffolding removal 6 28-Jul-22 06:00 28-Jul-22 12 :00 764 768 169
768 Final Cleaning 6 28-Jul-22 14:00 28-Jul-22 20 :00 765, 766,769
767 167
769 Manway box up 6 28-Jul-22 20:00 29-Jul-22 02 :00 768 770 167
770 De-blinding 8 29-Jul-22 02:00 29-Jul-22 10 :00 769 1073 167
MV-RH471-V10 (INTERMITTENT BLOWDOWN DRUM) 106 25-Jul-22 02:00 29-Jul-22 12 :00 165
Process Hand over 56 25-Jul-22 02:00 27-Jul-22 10 :00 165
773 Purging 6 25-Jul-22 02:00 25-Jul-22 08 :00 18 774 165
774 Blinding 8 25-Jul-22 08:00 25-Jul-22 16 :00 773 775 165
775 Steaming 8 25-Jul-22 16:00 26-Jul-22 00 :00 774 776 165
776 Cooling 8 26-Jul-22 00:00 26-Jul-22 08 :00 775 777 165
777 Opening of Manholes 6 26-Jul-22 08:00 26-Jul-22 14 :00 776 778 165
778 Establish air circulation 8 26-Jul-22 14:00 26-Jul-22 22 :00 777 779 165
779 Vessel Entry 2 26-Jul-22 22:00 27-Jul-22 00 :00 778 780 165
780 Cleaning of Vessel 10 27-Jul-22 00:00 27-Jul-22 10 :00 779 782 165
Maintenance/Inspection Jobs 50 27-Jul-22 10:00 29-Jul-22 12 :00 165
782 CTS/CES inspection 4 27-Jul-22 10:00 27-Jul-22 14 :00 780, 882783, 786 165
783 Scaffolding erection 8 27-Jul-22 14:00 27-Jul-22 22 :00 782 784, 787 165
786 Hydro test of LG/LT pipe 12 27-Jul-22 14:00 28-Jul-22 02 :00 782 789 179
784 Buffing of top dish end to shell weld joint 8 27-Jul-22 22:00 28-Jul-22 06 :00 783 785 165
787 Thickness survey 12 27-Jul-22 22:00 28-Jul-22 10 :00 783 789 171
785 WFMPT inspection 4 28-Jul-22 06:00 28-Jul-22 10 :00 784 788 165
788 Scaffolding removal 6 28-Jul-22 10:00 28-Jul-22 16 :00 785 789 165
789 Final Cleaning 6 28-Jul-22 16:00 28-Jul-22 22 :00 786, 787,790
788 165
790 Manway box up 6 28-Jul-22 22:00 29-Jul-22 04 :00 789 791 165
791 De-blinding 8 29-Jul-22 04:00 29-Jul-22 12 :00 790 1073 165
32 25-Jul-22
MV-RH471-V12A (SUCTION DAMPENERS-MC-RH471-C01A(CYL 1)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
794 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 795 239
795 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 794 796 239
796 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 795 797 239
797 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 796 798 239
798 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 797 800 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
802 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 801 803 239
803 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 802 804 239
804 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 803 805 239
805 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 804 1073 239
32 25-Jul-22
MV-RH471-V12B (SUCTION DAMPENERS-MC-RH471-C01B(CYL 1)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
808 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 809 239
809 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 808 810 239
810 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 809 811 239
811 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 810 812 239
812 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 811 814 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
814 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 812 815 239
815 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 814 816 239
816 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 815 817 239
817 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 816 818 239
818 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 817 819 239
819 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 818 1073 239
32 25-Jul-22
MV-RH471-V12C (SUCTION DAMPENERS-MC-RH471-C01C(CYL 1)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
822 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 823 239
823 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 822 824 239
824 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 823 825 239
825 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 824 826 239
826 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 825 828 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
828 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 826 829 239
829 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 828 830 239
830 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 829 831 239
831 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 830 832 239
832 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 831 833 239
833 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 832 1073 239
32
MV-RH471-V13A (DISCH.DAMPENERS-MC-RH471-C01A(CYL 1)) 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
844 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 843 845 239
845 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 844 846 239
846 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 845 847 239
847 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 846 1073 239
32
MV-RH471-V13B (DISCH.DAMPENERS-MC-RH471-C01B(CYL 1)) 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
850 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 851 239
851 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 850 852 239
852 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 851 853 239
853 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 852 854 239
854 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 853 856 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
856 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 854 857 239
857 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 856 858 239
858 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 857 859 239
859 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 858 860 239
860 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 859 861 239
861 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 860 1073 239
32
MV-RH471-V13C (DISCH.DAMPENERS-MC-RH471-C01C(CYL 1)) 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
864 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 865 239
865 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 864 866 239
866 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 865 867 239
867 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 866 868 239
868 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 867 870 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
870 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 868 871 239
871 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 870 872 239
905 WFMPT inspection 4 29-Jul-22 20:00 30-Jul-22 00 :00 904 910 133
907 Thickness survey 12 29-Jul-22 20:00 30-Jul-22 08 :00 904 908 113
908 Scaffolding removal 6 30-Jul-22 08:00 30-Jul-22 14 :00 907 909 113
925 WFMPT inspection 4 28-Jul-22 04:00 28-Jul-22 08 :00 924 930 177
927 Thickness survey 12 28-Jul-22 04:00 28-Jul-22 16 :00 924 928 157
928 Scaffolding removal 6 28-Jul-22 16:00 28-Jul-22 22 :00 927 929 157
929 Final Cleaning 6 28-Jul-22 22:00 29-Jul-22 04 :00 928 930 157
930 Manway box up 8 29-Jul-22 04:00 29-Jul-22 12 :00 925, 929931 157
931 De-blinding 8 29-Jul-22 12:00 29-Jul-22 20 :00 926, 9301073 157
32 25-Jul-22
MV-RH471-V22A (SUCTION DAMPENERS-MC-RH471-C01A (CYL 2)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
934 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 935 239
935 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 934 936 239
936 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 935 937 239
937 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 936 938 239
938 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 937 940 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
940 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 938 941 239
941 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 940 942 239
942 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 941 943 239
943 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 942 944 239
944 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 943 945 239
945 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 944 1073 239
956 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 955 957 239
957 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 956 958 239
958 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 957 959 239
959 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 958 1073 239
32 25-Jul-22
MV-RH471-V22C (SUCTION DAMPENERS-MC-RH471-C01C (CYL 2)) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
962 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 963 239
963 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 962 964 239
964 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 963 965 239
965 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 964 966 239
966 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 965 968 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
968 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 966 969 239
969 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 968 970 239
970 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 969 971 239
971 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 970 972 239
972 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 971 973 239
973 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 972 1073 239
322))25-Jul-22
MV-RH471-V23A (DISCH.DAMPENERS-MC-RH471-C01A (CYL 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
976 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 977 239
977 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 976 978 239
978 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 977 979 239
979 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 978 980 239
980 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 979 982 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
982 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 980 983 239
984 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 983 985 239
985 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 984 986 239
986 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 985 987 239
987 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 986 1073 239
322))25-Jul-22
MV-RH471-V23B (DISCH.DAMPENERS-MC-RH471-C01B (CYL 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
990 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 991 239
991 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 990 992 239
992 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 991 993 239
993 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 992 994 239
994 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 993 996 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
996 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 994 997 239
997 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 996 998 239
998 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 997 999 239
999 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 998 1000 239
1000 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 999 1001 239
1001 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1000 1073 239
322))25-Jul-22
MV-RH471-V23C (DISCH.DAMPENERS-MC-RH471-C01C (CYL 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
1004 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 1005 239
1005 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 1004 1006, 1073 239
1006 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 1005 1007 239
1007 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 1006 1008 239
1008 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 1007 1010 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
1010 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 1008 1011 239
1011 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 1010 1012 239
1012 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1011 1013 239
1013 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 1012 1014 239
1014 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 1013 1015 239
1015 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1014 1073 239
32 TK)
MV-RH471-V24 (CYLINDER CIRCULATING WATER EXPANSION 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
1018 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 1019 239
1026 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1025 1027 239
1027 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 1026 1028 239
1028 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 1027 1029 239
1029 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1028 1073 239
MV-RH471-V25 (PHOSPHATE DAY TANK) 32 25-Jul-22 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
1032 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 1033 239
1033 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 1032 1034 239
1034 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 1033 1035 239
1035 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 1034 1036 239
1036 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 1035 1038 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
1038 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 1036 1039 239
1039 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 1038 1040 239
1040 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1039 1041 239
1041 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 1040 1042 239
1042 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 1041 1043 239
1043 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1042 1073 239
MV-RH471-V26 (471-C01C CYLINDER CIRCULATING WATER32 25-Jul-22
EXPA) 02:00 26-Jul-22 10 :00 239
Process Hand over 10 25-Jul-22 02:00 25-Jul-22 12 :00 239
1046 Isolation 1 25-Jul-22 02:00 25-Jul-22 03 :00 18 1047 239
1047 De-pressurization 1 25-Jul-22 03:00 25-Jul-22 04 :00 1046 1048 239
1048 N2 purging 4 25-Jul-22 04:00 25-Jul-22 08 :00 1047 1049 239
1049 Blinding 2 25-Jul-22 08:00 25-Jul-22 10 :00 1048 1050 239
1050 Opening of Manholes 2 25-Jul-22 10:00 25-Jul-22 12 :00 1049 1052 239
Maintenance/Inspection Jobs 22 25-Jul-22 12:00 26-Jul-22 10 :00 239
1052 Insulation pocket removal 4 25-Jul-22 12:00 25-Jul-22 16 :00 1050 1053 239
1053 CTS/CES inspection (Internal/External) 4 25-Jul-22 16:00 25-Jul-22 20 :00 1052 1054 239
1054 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1053 1055 239
1068 Insulation fixing 4 25-Jul-22 20:00 26-Jul-22 00 :00 1067 1069 239
1069 Manway box up 2 26-Jul-22 00:00 26-Jul-22 02 :00 1068 1070 239
1070 De-blinding 4 26-Jul-22 02:00 26-Jul-22 06 :00 1069 1071 239
1071 Inertization & Leak check 4 26-Jul-22 06:00 26-Jul-22 10 :00 1070 1073 239
Vessel M&I Completion 0 31-Jul-22 16:00 31-Jul-22 16 :00 113
1073 Vessel M&I Completion 0 31-Jul-22 16:00 685, 707,1351
728, 750, 770, 113 Vessel
791, 805, 819, 833, 847, 861, 875, 890, M&I
911, Completion
931, 945, 959, 973, 1005, 1001, 1
MB-RH471-F01 (Charge Heater) Inspection 178 24-Jul-22 16:00 01-Aug-22 02:00 214
Process Hand over 28 24-Jul-22 16:00 25-Jul-22 20 :00 181
1076 Blinding 8 24-Jul-22 16:00 25-Jul-22 00 :00 209 1077, 1095, 1098
103
1077 Mnaway Opening 6 25-Jul-22 00:00 25-Jul-22 06 :00 1076 1078 181
1078 Cooling 12 25-Jul-22 06:00 25-Jul-22 18 :00 1077 1079 181
1079 Vessel Entry Permit 2 25-Jul-22 18:00 25-Jul-22 20 :00 1078 1081, 1082, 1083
181
Maintenance/Inspection Jobs 170 25-Jul-22 00:00 01-Aug-22 02:00 214
1081 All burners dropping, cleaning & re-fixing 72 25-Jul-22 20:00 28-Jul-22 20 :00 1079 1090, 1471 181
1082 Stack damper checking (Mech / Inst) 12 25-Jul-22 20:00 26-Jul-22 08 :00 1079 1090 322
1083 Initial Inspection by CES- Inspection & 4 25-Jul-22 20:00 26-Jul-22 00 :00 1079 1084, 256
Refractory group 1085,
1084 Refractory repair in Access door and 24 26-Jul-22 00:00 27-Jul-22 00 :00 1083 1087
1090 306
Peep doors after inspection (if any-
Outside)
1085 Scaffolding erection 16 26-Jul-22 00:00 26-Jul-22 16 :00 1083 1086 256
1087 Burner block repair (If any) 24 26-Jul-22 00:00 27-Jul-22 00 :00 1083 1088, 1090 306
1088 Tube cleaning job (Outside) 12 26-Jul-22 00:00 26-Jul-22 12 :00 1087 1090 318
1089 Refractory repair in Radiant section, 48 27-Jul-22 02:00 29-Jul-22 02 :00 1086 1090 256
Roof and Convection section including
water curing
1170 Flange Removal (6 Inch-02 Nos) 2 28-Jul-22 17:00 28-Jul-22 19 :00 1169 1171 135
1171 Spool Lifting & Fit Up 2 28-Jul-22 19:00 28-Jul-22 21 :00 1170 1172 135
1172 Coil Fixing for Pre Heating 3 28-Jul-22 21:00 29-Jul-22 00 :00 1171 1173 135
1173 Preheating 4 29-Jul-22 00:00 29-Jul-22 04 :00 1172 1174 135
1174 Root Welding 3 29-Jul-22 04:00 29-Jul-22 07 :00 1173 1175 135
1175 Cooling for Root weld line DP 2 29-Jul-22 07:00 29-Jul-22 09 :00 1174 1176 135
1176 DP testing of Root Line 1 29-Jul-22 09:00 29-Jul-22 10 :00 1175 1177 135
1177 Full Welding 6 29-Jul-22 10:00 29-Jul-22 16 :00 1176 1178 135
1178 Cooling 2 29-Jul-22 16:00 29-Jul-22 18 :00 1177 1179 135
1179 DP Testing of Welding 2 29-Jul-22 18:00 29-Jul-22 20 :00 1178 1180 135
1180 RT 2 29-Jul-22 20:00 29-Jul-22 22 :00 1179 1181 135
1181 PWHT Cycle (Heating upto 750 Deg C) 14 29-Jul-22 22:00 30-Jul-22 12 :00 1180 1182 135
1187 Flange Removal (6 Inch-02 Nos) 2 30-Jul-22 01:00 30-Jul-22 03 :00 1186 1188 103
1188 Spool Lifting & Fit Up 2 30-Jul-22 03:00 30-Jul-22 05 :00 1187 1189 103
1189 Coil Fixing for Pre Heating 3 30-Jul-22 05:00 30-Jul-22 08 :00 1188 1190 103
1190 Preheating 4 30-Jul-22 08:00 30-Jul-22 12 :00 1189 1191 103
1191 Root Welding 3 30-Jul-22 12:00 30-Jul-22 15 :00 1190 1192 103
1192 Cooling for Root weld line DP 2 30-Jul-22 15:00 30-Jul-22 17 :00 1191 1193 103
1193 DP testing of Root Line 1 30-Jul-22 17:00 30-Jul-22 18 :00 1192 1194 103
1194 Full Welding 6 30-Jul-22 18:00 31-Jul-22 00 :00 1193 1195 103
1195 Cooling 2 31-Jul-22 00:00 31-Jul-22 02 :00 1194 1196 103
1196 DP Testing of Welding 2 31-Jul-22 02:00 31-Jul-22 04 :00 1195 1197 103
1197 RT 2 31-Jul-22 04:00 31-Jul-22 06 :00 1196 1198 103
1198 PWHT Cycle (Heating upto 750 Deg C) 14 31-Jul-22 06:00 31-Jul-22 20 :00 1197 1199 103
1204 Flange Removal (6 Inch-02 Nos) 2 28-Jul-22 17:00 28-Jul-22 19 :00 1203 1205 135
1205 Spool Lifting & Fit Up 2 28-Jul-22 19:00 28-Jul-22 21 :00 1204 1206 135
1206 Coil Fixing for Pre Heating 3 28-Jul-22 21:00 29-Jul-22 00 :00 1205 1207 135
1207 Preheating 4 29-Jul-22 00:00 29-Jul-22 04 :00 1206 1208 135
1208 Root Welding 3 29-Jul-22 04:00 29-Jul-22 07 :00 1207 1209 135
1209 Cooling for Root weld line DP 2 29-Jul-22 07:00 29-Jul-22 09 :00 1208 1210 135
1210 DP testing of Root Line 1 29-Jul-22 09:00 29-Jul-22 10 :00 1209 1211 135
1211 Full Welding 6 29-Jul-22 10:00 29-Jul-22 16 :00 1210 1212 135
1212 Cooling 2 29-Jul-22 16:00 29-Jul-22 18 :00 1211 1213 135
1213 DP Testing of Welding 2 29-Jul-22 18:00 29-Jul-22 20 :00 1212 1214 135
1214 RT 2 29-Jul-22 20:00 29-Jul-22 22 :00 1213 1215 135
1215 PWHT Cycle (Heating upto 750 Deg C) 14 29-Jul-22 22:00 30-Jul-22 12 :00 1214 1216 135
1342 PDV 302 HEATER BYPASS STUCK UP 48 25-Jul-22 02:00 27-Jul-22 02 :00 18 1349 223
PROBLEM
1343 COMP. C01 C MAIN MOTOR BACKSIDE 48 25-Jul-22 02:00 27-Jul-22 02 :00 18 1349 223
RAILING HOT WORK TO BE DONE
1344 Steam leak attending as per list 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1345, 1349 139
1336 V-08 BOOT WATER SECOND 96 26-Jul-22 02:00 30-Jul-22 02 :00 18 1349 151
ISOLATION VALVE TO BE REPLACED(
1.5")
1337 V08 boot water sample point (belzona 96 26-Jul-22 02:00 30-Jul-22 02 :00 18 1338, 103
coated ) leaky spool replacement to be 1349
done
1339 FG steam tracing line near XV008 48 26-Jul-22 02:00 28-Jul-22 02 :00 18 1340, 151
(HEATER) steam leak 1349
1347 V005/V008/C007 Provision of Isolation 96 27-Jul-22 02:00 31-Jul-22 02 :00 18 1349 127
valve on U/p of LG/LT
(MOC-JGE1-JHYD-22-009)
1340 Heater Burner no. 2 Air register hand 24 28-Jul-22 02:00 29-Jul-22 02 :00 1339 1341, 151
valve rousing to be done, fixed at 30%. 1349
.Valve Servicing to be done
1338 Heater F01 burner number 1 and 4 not 48 30-Jul-22 02:00 01-Aug-22 02:00 1337 1349 103
firing sufficient. Burner Cleaning
1346 UW VALVE TO BE REPLACED NEAR 12 30-Jul-22 02:00 30-Jul-22 14 :00 1345 1349 139
COL.NO A06 (UTILITY STATION)
1430 INSPECTION OF SPRING 168 25-Jul-22 02:00 01-Aug-22 02:00 18 1432 103
SUPPORT-471 AREA
Misc. MIC Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103
1432 Misc. MIC Completion 0 01-Aug-22 02:00 1429, 1430
1434 103 Misc. MIC Completion
MIC Jobs Completion 0 02-Aug-22 02:00 02-Aug-22 02:00 79
1434 MIC Jobs Completion 0 02-Aug-22 02:00 1366, 1382,
15841387, 1412, 1422,
79 1427, 1432 MIC Jobs Completion
Instrumentation maintenance jobs 270 23-Jul-22 20:00 04-Aug-22 02:00 31
CV/XV Overhaul & Replacement (Scope: 18 nos) 216 25-Jul-22 02:00 03-Aug-22 02:00 55
1437 471HV013 (Meridian Recommendation 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1456 151
no. REC-4 64215)
1438 471HV017 (Meridian Recommendation 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1456 151
no. REC-4 64215)
1439 471FV301 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1456 151
1440 471FV120 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1456 151
1441 471FV020 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1456 127
1442 471FV034 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1456 127
1443 471HV015 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1456 127
1444 471XV021 120 26-Jul-22 02:00 31-Jul-22 02 :00 18 1456 127
1445 471TV046 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1456 103
1446 471XV002 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1456 103
1447 471PV013 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1456 103
1448 471XV022 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1456 103
Page 45 of 52 Prepared by: DTA_TA planning
Actual Work Remaining Work Critical Remaining Work Milestone Actual
11-Jul-22
LNUU (U471) Shutdown Schedule July'22 (SD-3611-3696-014)
Activity ID Activity Name Original Start Finish Predecessors
Successors Total Float
Duration 2022
Jul Aug
1449 471TV060 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1456 79
1450 471HV002 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1456 79
1451 471FV401 120 28-Jul-22 02:00 02-Aug-22 02:00 18 1456 79
1452 471FV402 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1456 55
1453 471XV401 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1456 55
1454 471XV402 120 29-Jul-22 02:00 03-Aug-22 02:00 18 1456 55
CV/XV Overhaul Completion 0 03-Aug-22 02:00 03-Aug-22 02:00 55
1456 CV/XV Overhaul Completion 0 03-Aug-22 02:00 1437, 1438,
15081439, 1440, 1441, CV/XV 1449,
55 1442, 1443, 1444, 1445, 1446, 1447, 1448, Overhaul Completion
1450, 1451, 1452, 14
MOC 168 25-Jul-22 02:00 01-Aug-22 02:00 103
1458 Heater XVs body replacement against 168 25-Jul-22 02:00 01-Aug-22 02:00 18 1462 103
obsolesce plan
-MOC-JGE1-JHYD-18-013 - LNUU
Heater skid XVs (6 Nos) replacement
1459 MOC-JGE1-JHYD-17-020_742_Routing 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1462 151
of DTA Platformer Hydrogen to SEZ
1460 related inst job.
MOC-JGE1-JHYD-20-006 - comp. 144 25-Jul-22 02:00 31-Jul-22 02 :00 1335 1462 127
suction strainer PDT provision.
MOC Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103
1462 MOC Completion 0 01-Aug-22 02:00 1458, 1459,
15081460 103 MOC Completion
Meridium/CES/Reliability recommendations 144 26-Jul-22 02:00 01-Aug-22 02:00 103
1464 REC-716416-JDR-HYD-471-471PSH207-It 48 26-Jul-22 02:00 28-Jul-22 02 :00 18 1465, 103
is observed in certain RIL site that the 1469
Pressure Switch setpoint got changed
1465 due to
REC-740716-JDR-HYD-500-PIB17-JPRH471C02- 48 28-Jul-22 02:00 30-Jul-22 02 :00 1464 1466, 103
To avoid similar failure in other BOSARD 1467,
1466 Heater PLC, it is recommended
REC-799866-RM notification - to revie 48 30-Jul-22 02:00 01-Aug-22 02:00 1465 1469
1469 103
IM2020084087_DTA - Damping for
2oo2/2oo3 ESD transmitters to be
removed considering availab
1467 REC-766644-RM notification - 48 30-Jul-22 02:00 01-Aug-22 02:00 1465 1469 103
IM2020127020_DTA - To set
hardware security switch in Transmitter
to ON for all ESD transm
Recommendations Completion 0 01-Aug-22 02:00 01-Aug-22 02:00 103
1469 Recommendations Completion 0 01-Aug-22 02:00 1464, 1465,
15081466, 1467 103 Recommendations Completion
Miscellaneous Jobs 270 23-Jul-22 20:00 04-Aug-22 02:00 31
1486 471 package PLC systems processor 24 23-Jul-22 20:00 24-Jul-22 20 :00 17 1506 277
changeover (Scope: 02 nos)
1493 TV-46 OF S-09 STUCK ISSUE 96 25-Jul-22 02:00 29-Jul-22 02 :00 18 1494, 1506 55
1473 Displacer LT AND LS to be dropped and 168 27-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
sent to CES FOR O/H (Scope: 18 nos)
1484 Field JB termination tightning and 120 27-Jul-22 02:00 01-Aug-22 02:00 18 1506 103
Earthing Checking (Scope: 45 nos)
1491 COMP C01 A TG-014 DISH TEMP TO 12 27-Jul-22 02:00 27-Jul-22 14 :00 18 1506 211
BE REPLACED
1492 COMP. C01 B CYLINDER 2 SIDE 12 27-Jul-22 02:00 27-Jul-22 14 :00 18 1506 211
COOLING RETURN TG NOT WORKING
1504 C01A/B/C Compressor all instrument 168 27-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
PM to be done (Scope: 96 nos)
1475 Power Supply replacment - C01A/B/C 48 28-Jul-22 02:00 30-Jul-22 02 :00 18 1476, 127
(scope: 06 nos) 1506
1479 R03 Skin temp. element to be check 72 28-Jul-22 02:00 31-Jul-22 02 :00 18 1506 127
(Scope: 15 nos)
1483 ESD all DI Barrier Replacment (Scope: 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1506 103
30 nos)
1485 Compressor and Field ESD SOV 96 28-Jul-22 02:00 01-Aug-22 02:00 18 1506 103
healthyness checking (Scope: 44 nos)
1474 471 All Control Valves /XV Storoke 144 29-Jul-22 02:00 04-Aug-22 02:00 18 1506 31
checking/PM to be done (Scope: 101
nos)
1477 Critical thermowell HT/DPT to be done 144 29-Jul-22 02:00 04-Aug-22 02:00 18 1506 31
at CES (Scope: 10 nos)
1478 R03 Bed temp. ( multiwell HT/DPT 48 29-Jul-22 02:00 31-Jul-22 02 :00 18 1506 127
testing at CES) to be check (Scope: 03
nos)
1482 DCS and ESD panel TB tightning and 72 29-Jul-22 02:00 01-Aug-22 02:00 18 1506 103
Thermography (Scope: 10 nos)
1494 P06B DISH PG TO BE REPLACED 12 29-Jul-22 02:00 29-Jul-22 14 :00 1493 1495, 1506 55
1495 P-11B DISH PG NOT WORKING 12 29-Jul-22 14:00 30-Jul-22 02 :00 1494 1496 55
1480 High H2S and Auto ignition service 36 30-Jul-22 02:00 31-Jul-22 14 :00 18 1506 115
transmitter inst. Tubing Hydrotest to be
done.
1487 Compressor tubing ferrule fitting 96 30-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
,support,clamp cheking (Scope: 100
nos)
1488 Field impulse tubing ferrule fitting 96 30-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
,support,clamp cheking (Scope: 100
nos)
1489 Inst. Air header flushing and AFR 96 30-Jul-22 02:00 03-Aug-22 02:00 18 1506 55
cleaning/draining (Scope: 50 nos)
1490 DP type LT root valve dechocking and 24 30-Jul-22 02:00 31-Jul-22 02 :00 18 1506 127
glyacol filling (Scope: 02 nos)
1496 P-19A/B SEAL ALARM NOT GENERATE 12 30-Jul-22 02:00 30-Jul-22 14 :00 1495 1497 55
IN PENAL (PSL TO BE CHECK OR
REPLACED)
1497 C01A SUCTION BOOT LEVEL ALARM 12 30-Jul-22 14:00 31-Jul-22 02 :00 1496 1498 55
NOT SHOWING IN PENAL (LEVEL
SWITCH TO ATTEND OR REPLACED)
1498 V-08 BOOT WATER LG/LT TO BE 12 31-Jul-22 02:00 31-Jul-22 14 :00 1497 1499 55
ATTEND (LG LEVEL SHOWING FULL
IN FIELD BUT ALARM NOT
GENERATED IN PENAL)
1499 R03 INLET (TT-303) NOT SHOWING VALUE 12 31-Jul-22 14:00 01-Aug-22 02:00 1498 1500 55
1481 IRP panel cleaning and Thermography 12 01-Aug-22 02:00 01-Aug-22 14:00 18 1506 91
(Scope: 02 nos)
1500 V01 LG/LT MISMATCH RELATED 12 01-Aug-22 02:00 01-Aug-22 14:00 1499 1501 55
ISSUE TO BE ATTEND.
1501 MULTIPLE FIN-FAN TO BE ATTEND 12 01-Aug-22 14:00 02-Aug-22 02:00 1500 1502 55
(HIGH VIBRATION ISSUE/ABNORMAL
SOUND)
1503 COMP C01A SUMP LEVEL SWITCH TO 12 02-Aug-22 14:00 03-Aug-22 02:00 1502 1506 55
BE CHECK ALARM GENERATED AT
80% LEVEL ALSO/ OR ELSE CRANK
CASE TO CHECK)
Misc. Jobs Completion 0 04-Aug-22 02:00 04-Aug-22 02:00 31
1506 Misc. Jobs Completion 0 04-Aug-22 02:00 1471, 1472,
15081473, 1474, 1475, Misc.
31 1476, 1477, 1478, 1479, 1480, 1481, 1482, Jobs 1484,
1483, Completion
1485, 1486, 14
Inst. Jobs Completion 0 04-Aug-22 02:00 04-Aug-22 02:00 31
1508 Inst. Jobs Completion 0 04-Aug-22 02:00 1456, 1462,
15841469, 1506 31 Inst. Jobs Completion
Electrical Maintenance Jobs 240 25-Jul-22 02:00 04-Aug-22 02:00 142
1579 MCC Panel Revalidation and VCB,Relay Testing 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1582 151
1580 FIN-FAN A02 (01/0 2) Amp meter to 24 25-Jul-22 02:00 26-Jul-22 02 :00 18 1582 247
be provide
Motor Overhaul - HT (Scope: 03 nos) 240 25-Jul-22 02:00 04-Aug-22 02:00 142
MC-RH471-M01A 216 25-Jul-22 02:00 03-Aug-22 02:00 55
1512 Flywheel removal 24 25-Jul-22 02:00 26-Jul-22 02 :00 18 1513 55
1513 HT motor overhauling 120 26-Jul-22 02:00 31-Jul-22 02 :00 1512 1514, 1516, 156455
1514 Testing & Revalidation of VCB. 24 27-Jul-22 02:00 28-Jul-22 02 :00 1513 1515, 1516 103
1515 Testing of Relay. 24 28-Jul-22 02:00 29-Jul-22 02 :00 1514 1516 103
1516 Flywheel installation 24 31-Jul-22 02:00 01-Aug-22 02:00 1513, 1514,
15171515 55
1517 Alignment 48 01-Aug-22 02:00 03-Aug-22 02:00 1516 1531 55
MC-RH471-M01B 216 26-Jul-22 02:00 04-Aug-22 02:00 31
1519 Flywheel removal 24 26-Jul-22 02:00 27-Jul-22 02 :00 18 1520 31
1520 HT motor overhauling 120 27-Jul-22 02:00 01-Aug-22 02:00 1519 1521, 1523, 156531
1521 Testing & Revalidation of VCB. 24 28-Jul-22 02:00 29-Jul-22 02 :00 1520 1522, 1523 79
1522 Testing of Relay. 24 29-Jul-22 02:00 30-Jul-22 02 :00 1521 1523 79
1523 Flywheel installation 24 01-Aug-22 02:00 02-Aug-22 02:00 1520, 1521,
15241522 31
1524 Alignment 48 02-Aug-22 02:00 04-Aug-22 02:00 1523 1531 31
MP-RH471-M29 144 25-Jul-22 02:00 31-Jul-22 02 :00 238
1526 HT motor overhauling 120 25-Jul-22 02:00 30-Jul-22 02 :00 18 1527, 1529 127
1527 Testing & Revalidation of VCB. 24 26-Jul-22 02:00 27-Jul-22 02 :00 1526 1528 310
1528 Testing of Relay. 24 27-Jul-22 02:00 28-Jul-22 02 :00 1527 310
1529 P.M of Motor + Feeder 24 30-Jul-22 02:00 31-Jul-22 02 :00 1526 1531 127
HT motor overhauling Completion 0 04-Aug-22 02:00 04-Aug-22 02:00 31
1531 HT motor overhauling Completion 0 04-Aug-22 02:00 1529, 1582 31 HT motor overhauling Completion
1517,
Motor Overhaul - LT (Scope: 29 nos) 216 25-Jul-22 02:00 03-Aug-22 02:00 1524 55