Professional Documents
Culture Documents
General Specification - Complete
General Specification - Complete
SECTION 1 - GENERAL
1
SECTION 1 – GENERAL 综述
PRELIMINARY 1001.
The conditions of contract and the drawings shall be read in conjunction with this
specification and matters referred to, shown or described in any one of them are not
necessarily repeated in the other two.
DEFINITIONS 1002.
The terms "Approved", "Directed" and "Required" shall mean to the approval,
direction or requirement of the Engineer or, his duly authorized representative.
The letters B.S. refer to the latest British Standards published by the British
Standards Institution. The British Standards mentioned in the specification are
particularly described in Schedule VII of Volume III of these Specifications bound
together with the Bill of Quantities. Where no particular direction is given, the letters
B.S. refer to the latest British Standards including any amendments in force at the time
of the tendering. Materials specified to be in accordance with the British Standards are
to be branded or a certificate provided where and as described in the particular
Standard.
2
Association of State Highway & Transportation Officials, current edition.
"C.P." or "B.S.C.P." refer to the latest (unless otherwise stated) British Standard
Code of Practice, including any amendments.
The works comprised in this Contract are described in Schedule V of Volume III
of these specifications bound together with the Bills of Quantities.
The drawings showing the dimensions and layouts of the works are listed in
Schedule IV appended to Volume III of these specifications bound together with the Bills
of Quantities.
The scope of the contract covers the supply of materials, plant, equipment,
labour and supervision necessary for the complete works all as specified together with
all temporary works and traffic diversions required during the construction of the works.
Where called for, the contract also includes the maintenance of a diversion for
traffic during construction, and the maintenance of the works in terms of Clause 49 of
the conditions of contract for a period after completion as stated in the appendix to
Tender.
In the event of other works being in progress concurrently with and adjacent to
the works specified in this contract, liaison shall be maintained with such other works to
ensure that the several works being undertaken shall not cause any mutual interference
with progress and shall culminate in the integrated improvement as a whole. If so
required by the Engineer, the Contractor shall vary his programme of work in
accordance with Clauses 14 and 90 of the Conditions of Contract, to coordinate the
works with any other works on or adjacent to the site of the works, whether being
carried out by contract or by direct labour of the Ministry.
3
The Contractor shall arrange his programme of works and control of traffic in
such a way as to avoid damage to the works at any stage of their construction.
DATUM 1006.
The datum to which the various levels have been reduced for the purposes of
the contract are as stated on the respective drawings. Where these datums are likely to
be covered by the new works, the Contractor shall transfer the levels to such fixed
points or beacons, to be provided by the Contractor at his own cost, as shall be required
and specified by the Engineer's Representative. The positions of such transferred
datums shall be accurately surveyed and shown on the working and as made drawings.
Before the works or any part thereof are begun the Contractor and the
Engineer's Representative shall together survey and take levels of the site of the works
and agree all particulars on which measurements of works are to be based. Such
surveys shall be recorded and signed as agreed by the Engineer's Representative and
the Contractor and shall form basis of the measurements for the Engineer's Certificates.
Failing such surveys and agreements being signed by the Contractor the surveys of the
Engineer's Representative shall be final and binding on the Contractor.
The dimensions and levels shown on the drawings are believed to be correct but
the Contractor must verify the same on the ground, as well as all other particular of the
contract and he will be held responsible for the consequences of any error contained
therein or omission therefrom. Levels on existing roads will depend upon the amount of
wear and maintenance which has taken place between the time of survey and the time
of construction and similarly the levels of river beds and banks will be affected by the
amount of erosion and repair which has taken place in the same interval. Should any
discrepancy be discovered between the levels shown on the drawings and those found
on the site, which may affect the levels and dimensions of any part of the works, the
Contractor shall notify the Engineer's Representative in sufficient time to enable the
Engineer to prepare drawings showing the amended levels and dimensions. The
attention of the Contractor in this respect is particularly directed to the extent of wing
walls (also see Clause 1010).
4
modified, it will be the responsibility of the Contractor to satisfy himself absolutely in all
respects in all matters pertaining to the carrying out and completion of the works and
the rates given in the priced Bill of Quantities for the carrying out and completion of the
work shall be deemed to be fully inclusive and no extras will be allowed to the
Contractor on the said rates.
Before any part of the works is put in hand the Contractor must prepare and
submit for the approval of the Engineer's Representative copies in duplicate (in the first
instance) of any further detailed working drawings which may be required for that part
of the work and at the same time call the attention of the Engineer's Representative to
any differences between these and the contract drawings. The Engineer's
Representative will, after the Contractor has made any alterations which he may require,
record on the copies, as amended, his approval and will return one copy to the
Contractor who shall carry out the work in accordance there-with. The Contractor shall
forward to the Engineer's Representative four additional copies of the working drawings
as approved. In addition, working drawings are also to be submitted (the same
procedure being followed as above described) in respect of any work proposed to be
executed by Sub-Contractors, the distribution of drawings being as directed by the
Engineer's Representative. The approval by the Engineer's Representative of all or any
of the drawings shall not relieve the Contractor of his responsibility.
The Contractor shall submit to the Engineers Representative for his approval,
complete drawings of all temporary works, stagings, required for carrying out the
work, together with the calculations relating to their strength and anticipated
deflections. The drawings shall show the method proposed for the erection of the
various parts of the temporary works and their application to the carrying out of the
permanent works. All temporary works shall be properly designed and substantially
constructed to carry the loads to which they will be subjected and all drawings and
calculations pertaining thereto shall be forwarded to the Engineer's Representative
sufficiently in advance of the intention to proceed as will allow for their proper study and
the incorporation of any modification which the Engineer's Representative may require
notwithstanding the approval or modification by the Engineer's Representative of any
submitted design for any of the temporary works, stagings, etc., the Contractor shall
remain wholly and entirely responsible until the removal of such works for their
efficiency security and maintenance and for all obligations and risks in regard to such
works specified or implied in the contract and he shall reinstate the same at his own
entire cost should any mishap or accident occur causing damage or injury thereto
subject however to such provisions of the conditions of contract as may be applicable in
5
the case of such damage or injury.
The cost of complying with all the requirements of this clause shall be borne by
the Contractor.
SETTING-OUT 1013.
The Contractor shall satisfy himself entirely as to the location of all existing
drains, pipes, cables and similar services whether above or below ground level. Drains,
pipes, cables and similar services encountered in the course of the works shall be
guarded from injury by the Contractor at his own cost so that they may continue in full
and uninterrupted use to the satisfaction of the owners thereof and the Contractor shall
not store materials or otherwise occupy any part of the site in a manner likely to hinder
the operations of such owners. If the interests of the work shall in the opinion of the
Engineer so require, the Contractor shall on his direction arrange for the construction by
the respective departments, bodies, corporations or authorities of permanent protective
works or permanent or temporary diversions of the said drains etc., (afterwards
reinstating if temporary) and the cost of such works or diversions including
6
reinstatement shall be charged against the appropriate provisional sum provided in the
Bill of Quantities. The Contractor shall be at liberty subject to the approval of the owners
and the requirements of Clause 90 of the Conditions of Contract to make any further
diversions he may consider necessary. The cost of these additional diversions including
the cost of reinstatement shall be borne by the Contractor. No services may be
tampered with by the Contractor and all works in connection with any services shall be
carried out by their respective owners.
The Contractor shall be held liable for damage and interference to mains and
pipes, to electric cables or services of any kind either above or below ground caused by
him or his Sub-Contractors in the execution of the works. Should any damage be done
to mains, pipes, wires, telecommunications or electrical apparatus or any other service,
whether shown on the drawings or not, the Contractor must make good the same
without delay and do any further work considered necessary by the Engineer or the
owners all at his own cost or pay the costs to the owner in so doing. The Contractor will
be deemed to have provided for these contingencies in fixing the rates, etc., inserted in
the Bill of Quantities.
The Contractor shall take all precautions and provide any temporary fences
necessary to protect the public from accidents which may be caused by the presence
of any excavations, mounds, heaps or earth or any other materials or stores connected
with the works. The Contractor shall, at his own expense, and immediately upon
completion of any part of the work, fill up all holes and trenches and level all mounds
and heaps of earth which have been excavated or made in connection with the works.
The Contractor shall bear and pay all costs, charges, damages and expenses incurred or
sustained on account of or in consequence of any accident which may happen by reason
of holes and trenches being dug and left unprotected, or materials being left or placed
in unprotected or improper situations.
In the event of the Contractor having to execute any work or provide any
material in regard to which he may propose to claim extras, he shall first obtain a
written order from the Engineer's Representative and shall at once make arrangements
to take the measurements of the said work or materials with the Engineer's
Representative. If these measurements are not taken jointly and booked and agreed at
the time the work is being executed the Contractor's measurements will not afterwards
be recognized by the Engineer. The fact of such joint measurements having being made
will in no way commit the Engineer to a recognition of the claim if he considers such a
claim without foundation. The Engineer's Representative shall at all times have full
access to the Contractor's time book and may daily check the time of any extra works
with the Contractor's time keeper or otherwise, but the fact of his agreeing upon any
time shall in no way bind the Engineer to value the work other than by measurement if
he thinks fit so to do.
7
PROTECTION FROM WEATHER 1019.
All materials shall be stored on the site in a manner approved by the Engineer
and the Contractor shall carefully protect from weather all work and materials which
may be affected thereby.
All those parts of the works required to be carried out in the dry, whether
within any part specified to be enclosed or not, shall be kept free at all times from
water from whatever source it may come to the satisfaction of the Engineer's
Representative. The costs of complying with the provisions of this clause shall be borne
by the Contractor.
The Contractor shall at his own expense provide for himself suitable offices and
housing for his staff and labour. If required by the Engineer, the Contractor shall
supply, erect and maintain suitable furnished offices and Residential quarters for the
Engineer's Representative and his assistants, inspectors and staff on a site or sites to be
selected, together with all proper lighting, heating, water, sanitary arrangements and
attendance.
The Contractor shall make his own arrangements for the provision of water and
electricity, whether for use in the execution and construction of permanent works or
otherwise. In the event of the source of water being from any existing piped supply, the
Contractor shall comply with any regulation laid down by the water authority and shall
pay for such supply, standpipes, connections, meter rent and all other charges as
required all at his own expense. The same conditions apply for the temporary supply of
electrical power.
Every working day, the Contractor shall supply the Engineers Representative
with a return of the men employed the previous day and of the work on which they
were engaged, specifying also the number employed in each trade. He shall also supply
any other returns, which may be required from time to time, as to the number of men
and plant employed and the nature, quality and quantity of the work done.
PHOTOGRAPHS 1024.
8
be charged against the appropriate provisional sum.
The copyright of the photographs shall be held by the Employers. The Contractor
shall provide the Engineer's Representative (within 5 days of the photographs having
been taken) with the negative and three prints of each photograph which shall be I.O. ,
standard size A4 or a minimum of 200mm x 300mm. On the reverse side of each
print the following information shall be shown:
(2) A brief description of the location illustrated or the name of the structure.
The prints of each approved photograph shall be signed and dated by the
Contractor and the Engineer's Representative.
(B) The Contractor will be responsible for the maintenance other than grass
cutting, of all verges, margins and side
slopes, including stone pitching, for the period of maintenance and shall make good all
erosions during such period whether attributable to defects in workmanship or not.
9
On completion of the works, the Contractor shall prepare as made drawings
giving complete details of the entire works as constructed, including all work carried out
by Sub Contractors. The as made drawings shall be prepared in accordance with the
requirements of the respective clauses in the specifications and all costs arising out of
their preparation, supply and distribution etc., shall be deemed to be included in the
tendered rates for the work to which they refer.
The Contractor shall, at his own expense, and during the period of this Contract,
maintain in a safe condition and adequately protect any work executed by him which is
exposed to traffic. The Contractor shall supply adequate advance warning signs of
reflecting type with letters not less than 150mm high and such warning signs shall be
placed in positions approved by the Engineer and shall be left in such positions as long
as traffic is still utilizing any such temporary running surface.
The Contractor shall make arrangements and cooperate with all other
contractors working in the area for directing, routing, marshalling, controlling and
circulating the traffic connected with the works under this contract in accordance with
the Engineer's Requirements, in order that the flow of all traffic may be facilitated, that
all obstruction, inconvenience and delay may be minimized, and that the interests of all
concerned, including the general public, may be protected.
The Contractor shall allow in his tender for complying with the requirements of
10
this clause and for any directions in connection therewith which the Engineer may issue
from time to time. The Contractor will be deemed to have allowed for additional
expense he may incur on account of extra running or kilometre covered by his vehicle or
labour or material involved in compliance with these requirements.
The Contractor shall be responsible for ensuring that the highways in the vicinity
of the works are kept clean of mud and other debris falling from vehicles connected with
the works or spreading on to the highways as a result of the works in any way.
The Contractor will at all times during the contract, provide, erect and maintain
such barricades, warning lights, dangers signals, reflectors, signs and watchmen as may
be necessary to the satisfaction of the Engineer's Representative. Any such warning
signs etc., shall be left in position as long as traffic is utilizing any temporary running
surface and/or until such time as their removal is sanctioned by the Engineer's
Representative.
Barricades and signs shall be constructed and used in accordance with the
requirements of the Engineer's Representative. All barricades, obstructions and such
other conveniences as are necessary to protect the travelling public, or as required by
the Engineer's Representative shall be illuminated at night by reflectors or red lanterns.
The cost of barricades, danger, warning and deviation signs and providing
watchmen, shall be deemed to be included in the tendered rates and prices.
The Contractors shall be deemed to have taken all possible weather conditions
into account when preparing their tender and they shall not be entitled to extra payment
by reason of the occurrence or effect of high winds, tornadoes, excessive rainfall,
temperature or humidity or any other meteorological phenomena.
During the continuance of the contract the employer may cause other works
such as the installation of services to be carried out on, through or adjacent to the site.
The Contractor shall at all times comply with the requirements of the general
conditions of contract in respect of these and any other works not included in the
Contract and shall allow reasonable access as approved by the Engineer on and through
the site of the works to any other Contractors or workmen who may be working on or
near the site.
11
The Contractor shall make his own arrangements for and shall provide any
service (including telephone and radio communications) which he may require in
addition to the foregoing.
(i) provide details of the sequence he proposes for carrying out the works,
(ii) state and allow a reasonable margin of time for contingencies and
He shall furnish an explanation of any deviation from the programme and shall
state proposals for improving progress should this be lacking in any respect.
The Contractor shall provide, maintain and staff laboratories at his own expense
throughout the Contract. The said laboratories shall be in a waterproof building or
rooms designated and used exclusively for the purpose and shall be maintained in a
clean and tidy fashion to the satisfaction of the Engineer's Representative. The
laboratories shall have an adequate water and electricity supply. The laboratories shall
be staffed with Engineers well experienced in materials testing and approved by the
Engineer. The laboratories shall be located within 50 Km. of all works in the field
requiring sampling and testing. Work will not be permitted to begin until laboratories
and staff have been provided within this distance.
The Contractor shall provide all the testing equipment, tools, etc., and shall carry
out tests on materials as directed and shall supply the Engineer's Representative with
two copies of the results of each test on approved printed forms. A third copy of the
results shall be retained in the laboratories.
12
Without limiting the Contractor's responsibility as stipulated above, the facilities
of the laboratories shall be available for the use of the Engineer's Representative and his
assistants to perform control tests on workmanship and materials as provided for in the
Specification.
Note: Where construction is carried out in arid region where moisture of finished fill,
subbase base or stone base can dry out from the surface rapidly, the time of notification
may be reduced at the request of the Contractor making representation to the
Engineer's Representative on same.
Unless otherwise specified, the cost of carrying out all tests shall be deemed to
be included in the tendered rates and prices and the Contractor shall be deemed to have
allowed for the costs of providing all facilities necessary. No claim for delay of any kind
shall be entertained by the Engineer in this respect if the stipulations of the foregoing
have not been observed.
The laboratory building shall be in accordance with the standards specified for
the office of the Engineer's Representative. Concrete floors shall be provided
throughout. The Contractor also shall provide air conditioning throughout the laboratory
and shall service, clean and light the building to the standards specified for the Office of
the Engineer's Representative.
Where directed by the Engineer the Contractor shall remove and dispose of the
13
building and unserviceable vehicles make good any damage to the site and leave it clean
and neat.
The facilities of the testing laboratory shall be made available for use by the
Engineer's Representative at all times for the purpose of the works.
The Contractor shall arrange for the testing of all materials used throughout the
contract, to ensure that they are up to the standards specified.
The Contractor shall carry out such laboratory and field tests (including tests to
check the accuracy of testing equipment and methods but excluding tests specified to
be carried out in an independent testing laboratory) as specified and as may be
necessary to ensure and satisfy the Engineer that the requirements of the Specifications
are met. The type and frequency of testing shall be in accordance with the relevant
Nigerian Industrial Standards or British Standards except as otherwise specified herein
or directed by the Engineer.
When any material or article is required to comply with a British Standard or any
other Standard specified herein such material or article or its container shall bear the
stamp of the registered certificate trade mark of the British Standards Institution or the
certification of the applicable standard. Alternatively, the Contractor shall submit to the
Engineer certified test certificates furnished by the supplier or manufacturer of the
14
material or article indicating compliance with the relevant British Standards or a copy of
the manufacturer's or supplier's test certificate showing that the material has been
tested and found to comply in all respects with the relevant standard. Notwithstanding
the above, the Engineer's Representative may require additional tests to be carried out
by an approved local testing establishment and the material shall be supplied by the
Contractor. In such cases a copy of the test result shall be submitted to the Engineer's
Representative in lieu of the Manufacturer's/Supplier's certificate. All testing carried out
by the Contractor shall be undertaken by approved qualified staff who shall be
nominated by the Contractor and sufficient notice of the intention to carry out such tests
shall be given to the Engineer's Representative to enable him to be present during the
tests should he so desire.
The Contractor shall arrange and the Engineer shall have power to send
inspectors to the premises of the manufacturers and suppliers to inspect the
manufacture and testing of the materials intended for use in the works. Materials tested
before leaving the manufacturer's or supplier's premises may be tested again after
delivery at the site, at the discretion of the Engineer's Representative.
The Contractor shall be deemed to have included in his tendered rates and prices
all costs arising out of compliance with the requirements of this clause.
Notwithstanding successful t test results being submitted for any material, and in
addition to the tests required under other clauses of this specification, the Engineer may
order further tests of any material to be carried out by his own central laboratory or by
an independent tester at such places as he may determine. The Contractor shall
provide the samples for such tests free of charge, but payment for the tests shall be the
employer's responsibility and charged against the appropriate provisional sum except as
detailed in Clause 36 (4) of the Conditions of Contract.
For the purposes of this contract and in accordance with Clause 36 of the
Conditions of Contract, the Engineer may appoint one or more Inspection Engineers for
all imported materials to be used in connection with the contract.
For all materials of Nigerian origin the Inspection Engineer shall be the
15
Engineer's duly Authorized Representative in Nigeria.
Where an Inspection Engineer has been appointed for imported materials the
Contractor shall before he enters into any arrangement for the supply or manufacture of
materials, submit for the approval of the Inspection Engineer, the names of the
manufacturers or merchants he proposes to employ. Should the Inspection Engineer at
any time be dissatisfied with any of the methods or operations carried out at the
manufacturer's works or place of business, he shall be empowered to cancel his previous
consent for materials to be obtained from such manufacturer or merchant. Should the
Contractor fail to submit for the approval of the Inspection Engineer samples of material
of satisfactory quality or workmanship, the Inspection Engineer shall have the power to
specify any particular manufacturer or merchant for the supply of the materials and the
Contractor shall obtain such materials from the said manufacturers or merchants without
additional charge.
The Inspection Engineer shall examine and test and if necessary analyze all
materials and test the fabrication of any structures or structural components to be used
in the permanent works. The Inspection Engineer and his Representatives shall have
free access at all reasonable times to the manufacturer's or merchant's premises and
shall be afforded every facility for making inspections and for taking of samples for
testing and analyses.
All materials to be provided by the Contractor shall be submitted for the approval
of the Inspection Engineer before removal from the place of manufacture and under no
circumstances shall materials be shipped without the approval certificate issued by the
Inspection Engineer. The Contractor shall give twenty one days' notice in writing to the
Inspection Engineer of his intention to remove materials from the place of manufacture
or fabrication.
Invoices or shipping lists in triplicate showing in detail the net weights and
quantities of all materials for the permanent work despatched to the site shall be
forwarded to the Inspection Engineer directly when the materials are despatched. In
the case of steel and iron work such invoices or shipping lists shall show separately the
net weight of articles under each item in the schedule of prices included in the invoice or
shipping lists.
All materials and any iron or steel articles supplied by the Contractor for use in
16
the permanent works or any materials for fabricating permanent steel or iron structures
and other articles shall be subjected from time to time before the issue of the approval
certificate to such tests and inspections as may be required or directed by the
Inspection Engineer.
All the tests shall be carried out in the presence of the Inspection Engineer or his
Representative and shall be performed in such a manner and by such processes at such
premises and at such times as he may consider desirable.
Notwithstanding any examination or tests that the Inspection Engineer may wish
to be carried out on any perishable materials prior to their despatch to the site, the
Engineer shall be at liberty to carry out any further tests that he may consider desirable
after delivery of such perishable materials at the site and to reject such materials which
fail to comply with the required quality or conditions, notwithstanding any provisional
approval before despatch to the site. The Engineer shall arrange for the inspection on
site of all materials and fabricated components to ascertain whether these materials and
fabricated components have in any way become damaged in transit to site.
The Engineer and the Inspection Engineer shall be kept properly informed as to
the progress of any work in hand or materials being prepared and supplied by the
Contractor in order that they shall be able to make such arrangements for examination,
testing and analysis as they may desire.
The Contractor shall weigh without any extra charge any materials, articles or
things supplied for the execution of the permanent work that the Engineer or the
Inspection Engineer may require and such weighing shall be carried out in their
presence or in the presence of their representatives.
When the Inspection Engineer is satisfied in all respects with the inspection,
regarding samples and test results of materials and fabrication of structures, he shall
issue to the Contractor an approval certificate thereof.
Where the Contractor/Manufacturer could not agree with the inspection Engineer
the Contractor may request with the permission of the Engineer that such materials be
tested by an independent testing body as may be agreed by both parties in dispute,
and cost of such test shall be borne by the Contractor.
The Contractor shall arrange for the testing of all materials used throughout the
17
contract to ensure that they are up to the standard specified, i.e., aggregates, sand,
cement, water, reinforcement, concrete, blinding materials as specified or decided by
the Engineer.
The tests to be carried out on any material except as detailed hereafter, shall be
those specified, implied or intended in the appropriate N.I.S or B.S.
The Engineer shall be the final arbitrator on which tests are necessary for the
proper execution of the works.
Where the Contractor is responsible for the carrying out of any control test, he
shall first give notice of his intention to carry out such a test to the Engineer's
Representative to enable him to be present during the test. Where the Engineer or his
Representative conducts any control test, he shall give the Contractor sufficient notice to
enable him, should he so wish, to be present during the test. Should the Contractor not
wish to witness any control tests conducted by the Engineer or his Representative, the
Contractor shall be deemed to accept the validity of the results of such tests.
SAMPLING 1047.
Trial pits in proposed borrow pit areas shall be dug from original ground level.
Trial pits shall be at least one metre by one metre in size, dug to such a depth that
the full extent of the material intended for incorporation in the works is exposed.
Materials for testing shall not be taken from the spoil of the trial pit but shall be
18
made up of increments taken from each face of the pit, each increment to be a
representative sample of the entire depth of a horizon. The four increments shall be
mixed three times and quartered or riffled down to the size required for testing. Visual
examination will be made to ensure that sampling more than one horizon in any sample
is avoided.
The surface material of a stock pile shall be removed before sampling. At least
twelve samples shall be taken from different parts of the stockpile, avoiding
segregated material, and thoroughly mixed by hand before quartering down to required
size.
(1) Materials for testing shall be moisturized, mixed for 15 minutes and
sealed in an approved air tight container for a minimum period of 24
hours before testing.
(2) After the above period of curing, the material shall be removed from the
container and remixed with 10mm spatula for an exact period of fifteen
minutes.
(3) For the method of determining the liquid limit as laid down in B.S. 1377
19
at least five points in the range 10-60 blows, evenly distributed when
plotted on a logarithm scale, shall be made. Consecutive tests with
respect to moisture content shall form a wetting and not a drying curve.
(4) Alternatively the one point method of determining the liquid limit may be
used.
(5) The plastic limit of material shall be taken as the mean of at least three
tests.
20
(A) All material passing the 5mm sieve shall be sampled for moisture content,
weighed, wet sieved through the No. 75m sieve oven dried, and sieved
through the full nest of sieves. The portion retained on each sieve shall
be weighed. The weight of the original sample shall be adjusted for
moisture content.
(B) Material retained on the 5mm sieve if it is porous or tends to retain fine
particles on the surface shall be wet sieved as described in the paragraph
above full allowance being made for the air dry moisture content.
(C) If the material retained on the 5mm sieve is clean of clay and contains no
pores or adhesions, the coarse fraction may be dry sieved.
(D) Pre-treatment and the analysis of the fraction passing 75(m sieve may be
omitted.
(I) The size of the mould shall be, 150mm internal diameter, and 125mm
internal effective height and a volume of 2210cm3.
(II) The weight of the metal rammer shall be 4.5kg instead of 2.5kg (the
diameter of bottom face remaining at 50mm
(IV) The moist soil shall be compacted in the mould in five equal layers each
layer being given twenty five blows.
(VI) Separate materials shall be used for each compaction point, i.e. materials
only air dried previously and not oven dried, mixed with water and
21
allowed to moisturize for 12 hours before compaction.
(I) The size of the mould shall be 150mm internal diameter, and 125mm
internal effective height and a volume of 2210 cm².
(II) The weight of the metal rammer shall be 4.5kg instead of 2.5kg (the
diameter of bottom face remaining at 50mm
(IV) The moist soil shall be compacted in the mould in 5 equal layers, each
layer being given 61 blows from the rammer dropped from a height of
450mm above the soil.
(VI) Separate materials shall be used for each compaction point, i.e. materials
only air dried previously and not oven dried, mixed with water and
allowed to moisturize for 12 hours before compaction.
(I) Different samples of materials shall be used for each point in the
compaction for C.B.R. Test.
(II) The materials for testing shall be moisturized and sealed in an airtight
container for a minimum period of 12 hours before testing.
(III) The Standard Compaction used for C.B.R. Tests shall be as follows:
22
A.A.S.H.O. Standard as directed by the Engineer may be used for
laterite, stone or Mechanically Stabilized Base Course and the B.S.
Compaction for Cement Stabilized Base Course. For other type of
Base Course Compaction shall be decided by the Engineer.
Should in the opinion of the Engineer's Representative any of the results of the
specified tests on materials be unsatisfactory, the Engineer's Representative may order
the work to be stopped pending his further instruction. Executed work for which test
results are unsatisfactory shall be liable to be rejected, and, if so directed by the
Engineer, the work represented by the tests shall be cut out and re
executed at Contractor's Expense.
The cost of all such cutting, preparation of specimens, testing, and of making
good the portions of the works affected shall be borne by the Contractor.
23
TRIAL SECTIONS OF ROAD 1052.
It is likely that these stretches will be incorporated in the works. Should one or
all of these stretches or a part thereof be rejected the Contractor will be reimbursed for
the rejected work in accordance with the rates at which the relevant items have been
priced in the Bill of Quantities.
ROLLING TEST
1052A. DEFINITION
Rolling Test shall be used to establish the optimum moisture and maximum dry
density of the proposed plant for a particular type of soil material. In addition it shall be
used to determine the economic number of passes of the plant that may be required to
achieve the maximum dry density at a known moisture. This test is a corollary to
laboratory tests already carried out using CBR mould and specified compactive effort.
(b) Spread the loose material on the prepared platform to a desired loose
depth. (Between 200mm to 300mm for laterite)
(c) Divide the test section into at least five bays (each bay not less than 8m)
and leaving a gap of two metres between bays to avoid intermixing of
materials from adjacent bays. Determine the moisture of the material in
each bay. This may be done by using the speedy method and sampling in
various points, taking the mean result of four as the moisture content.
(d) Adjust the moisture content in each bay with a view to straddling the
optimum moisture content. This could be achieved by progressively
increasing the passes of the water tank in different bays as shown in the
Table 1.2
24
4 6 8 10 12
Passes Passes Passes Passes Passes
(e) Mix the loose soil and water to ensure thorough moisturization using
either hand, pulvimixer or rotovator. (To ensure uniform moisturization
the watered material could be left over night before mixing).
(f) Compact to refusal the loose material whose OMC and MDD is required
with the available plant. For practical purposes fifteen to twenty passes of
10 to 15 tonnes of a three wheel roller or ten or fifteen passes of a
vibrating roller will be adequate for a lateritic material. For the three
wheel roller the rear wheel is the compacting wheel while the front is the
compacting wheel for he vibrating roller.
(g) Determine the insitu dry density and moisture content of each bay based
on the mean of four tests. Concentrating the measurement on the wheel
path of the rear or front wheel as the case may be.
(h) Plot results of the dry density and moisture content and determine the
optimum moisture content and dry density appropriate to the plant.
(a) Prepare another test section as in clause 1052B and bring the moisture
content to the optimum moisture content earlier determined.
(b) Divide the section into bays and vary the number of passes of the roller
on each bay as shown in Table 1.3
4 6 8 10 12
Passes Passes Passes Passes Passes
(c) After rolling determine the dry density of each bay (based on mean of
four tests)
25
(Four) Plot the dry density and number of passes relationship to determine the
minimum number of passes that will achieve the maximum density.
SOIL TYPE
GRAVELLY
HEAVY SILTY SNADY
SAND SANDY
COMPACTION CLAY CLAY CLAY
CLAY
MD OM MD OM MD OM MD OM MD OMC
D C D C D C D C D
B.S. 155 166 184 193 206
26 21 14 11 9
2.5Kg. 4 6 2 8 7
B.S.
181 192 205 208 221
(Heavy) 17 14 11 9 7
0 2 1 3 1
4.5 Kg.
2800Kg.
152 176 182 203 214
S.W. 21 17 16 10 8
2 2 6 4 7
Roller
8000 Kg.
166 177 185 211 221
S.W. 20 16 14 8 7
6 8 8 5 1
Roller
Pneumatic
157 166 173 203 201
Tyred 25 20 19 11 7
0 6 0 4 8
Roller
Sheepsfoot
(Tapper-Foot) 1714 15 1842 14 1927 12 2051 5
Roller
All materials to be used in the works shall be handled with due care and
whenever not in immediate use shall be adequately stored and protected having
particular regard in all cases and throughout to the nature of the material and its
susceptibility to damage, breakage, deterioration, attack by weather or any act of
abuse.
The Contractor shall provide at all times during the continuance of the contract
26
all equipment and instruments for the exclusive use of the Engineer's Representative
on the scale as set out in detail in Schedule No. VI. The Contractor shall be solely
responsible for all such instruments and shall ensure that they are at all times in good
repair and adjustment.
The Contractor also shall supply such workmen as may be deemed necessary by
the Engineer's Representative, from time to time during the continuance of the contract,
to assist the Engineer's Representative in carrying out his duties. These workmen shall
be selected for their intelligence and knowledge of the English language, and where
possible the same men shall be provided throughout the period of the Contract.
Payment for furnishing workmen and instruments, etc. to assist the Engineer's
Representative shall be charged against provisional sum item "Payment of Wages to
Engineer's Daily Paid Staff". All instruments and equipment so furnished become the
property of the Federal Ministry of Works on the completion of the Works.
The offices shall be 28.95 metres long by 5.55 metres wide with 2.45 metres
headroom all measured internally complete with ceiling and smooth concrete or wooden
floor, and a 2.02 metres wide covered veranda on all sides. The office shall be divided
into three rooms each 3.6 metres long. The rooms shall be adequately ventilated and
lighted and through ventilation shall be provided in the roof space. The walls must be
constructed of either prefabricated timber sections or sand cement blocks. All doors and
windows shall be arranged so that they can be securely fastened on the inside. All
doors shall be provided with cylinder locks with two keys.
27
2 Stainless Steel straight edges 1 metre long
1 Refrigerator
1 Conference Table with 8 chairs
4 Small Tables with chairs
1 Set of Applicable British Standards, Current Edition
1 Copy of AASHTO Standard Specifications for Highway Materials and Method of
Sampling and Testing Volumes 1 & II, Current Edition.
1 Civil Engineer's Radius Guide
1 Set of transparent plastic railroad curves
1 Electronic calculator
1 Electric adding machine
1 Electric erasing machine
1 Photocopy machine with accessories and supplies.
Adjacent to the two ends of the building the Contractor shall erect a board
750mm x 600mm bearing the following inscriptions.
(Project Designation)
In addition each door of the building shall be lettered in accordance with the
instructions of the Engineer's Representative.
The Contractor shall provide two water closets and two wash hand basins with
mirrors in rooms attached to the use of the Engineer's Representative. The Contractor
shall keep clean and maintain this lavatory accommodation. He shall also provide soap,
towels and all necessary fittings and cleaning materials.
The Contractor shall arrange for the offices to be connected to a water and
electricity supply.
The Contractor shall provide a roofed shelter for six cars which shall be built
adjoining the offices.
The cost of providing the offices, water, electricity supply and maintenance
during the whole period of the contract shall be deemed to be included in the price
inserted under the appropriate item in the Bill of Quantities. The buildings and
equipment shall be for the sole use of the Engineer's Representative during the period of
the Contract and shall remain the property of the Employer after the completion of the
28
Contract.
FENCING 1062.
The Contractor shall provide and erect fencing or walls complete with access
gates along the land acquisition boundaries during the period of construction as and
where directed by the Engineer's Representative.
Payment for fencing and walling will be made from the appropriate item in the
Bill of Quantities.
No payment will be made for fencing or walls erected by the Contractor for the
purpose of making secure his own working areas, yards, stores, as this will be deemed
included in this pricing.
Where the works abut, enter into or pass over property or properties belonging
to the Nigerian Railway Corporation, the Contractor shall comply with all the
regulations laid down and give all notices required by the Nigerian Railways Corporation
and the Government Inspector of Railways.
Where the works are sited in, or operations connected with the works in any way
whatsoever pass through, waters controlled by the Nigerian Ports Authority the
Contractor shall abide by all the regulations laid down, and give all notices required, by
the Nigerian Ports Authority.
The site shall be handed over to the Contractor in minimum lengths of sixteen
kilometres. The date on which each portion is taken over shall be recorded and certified
in writing by both the Engineer's Representative and the Contractor's Agent and from
the date on which each portion is taken over the Contractor shall be responsible for
maintaining that portion of road in good condition and for repairing damage of any kind
to the road culverts or bridges arising from whatever cause save and except the
excepted risks as defined in Clause 20 of the "General Conditions".
29
SPECIFICATION
30
SECTION II MASS AND REINFORCED CONCRETE 大体积钢筋混凝土
GENERAL 2000.
In addition to any other relevant clause of this specification, the following shall
be deemed to apply in particular to mass and reinforced concrete work, and shall be
read in conjunction with all other relevant clauses of the conditions of Contract and this
Specification.
PART A - MATERIALS
2001.
(1) GENERAL
The Cement shall be ordinary or rapid hardening portland cement and shall
conform to the requirements of NIS 11 or B.S. No. 12 portland cement (ordinary and
rapid hardening) and B.S.C.P.114 and shall be supplied by manufacturers of good repute
to be approved by the Engineer.
(4) BLENDING
There shall be no blending or mixing of cements, and the use of any air-
entraining, wetting agents, or accelerators such as calcium chloride will only be
permitted if called for by the Engineer.
31
(5) EXTRA PAYMENT
The Contractors shall not receive extra payment for using rapid hardening
portland cement unless they do so under the specific instructions of the Engineer.
Each consignment of cement intended for use in the works shall be accompanied
by a manufacturer's test certificate showing that the cement offered has been tested
and analysed, the date and results of such tests and analyses, and that the cement
conforms in all respects with NlS 11 or B.S.12.
After each consignment of cement has been tested and approved as complying
with B.S. No. 12 and unless approval is given by the Engineer's Representative for the
handling of cement in bulk, all cement shall be packed into bags of an approved type.
The bags of each consignment shall be given a distinctive mark, to be agreed between
the Contractor and the Engineer's Representative, also a consignment number, so that
each consignment can be easily identified on being delivered to the site and when being
used subsequently in the works.
When each consignment is delivered to the site, the Contractor shall issue to the
32
Engineer's Representative a written statement showing the number of the consignment,
the name of the manufacturer, the number of tonnes in the consignment, the number of
bags and enclosing the respective test certificates. The statement shall also show where
the consignment is stored. Cement may be shipped in bulk or in 50 Kg bags subject to
approval of the Engineer and subject to such requirements as he may deem necessary.
Railroad cars or trucks in which cement is shipped shall be loaded under the supervision
of and sealed by the Engineer. Cars or trucks with broken seals may be unloaded, but
the cement shall not be used until retested and approved.
On delivery at the site, the cement shall be stored in suitable, thoroughly dry and
well ventilated lock up sheds to be erected by the Contractor and approved by the
Engineer's Representative. Great care must be taken to provide a perfectly dry floor of
timber or concrete for each shed so as to prevent damp rising to the cement. Small
quantities left at the site shall be stored on suitable platforms and protected with
waterproof covering to the satisfaction of the Engineer.
Each consignment, brand and type of cement shall be kept separate in the sheds
and suitable labels are to be provided for each consignment, brand and type, on which
shall be entered the consignment number, date of despatch, date of delivery at the site,
the number of bags, the date when using commenced and the date when using finished.
All these labels shall be handed to the Engineer's Representative when the cement has
been used and will be retained by him.
The Contractor shall at all times maintain at the site such a stock of cement as
will ensure due and proper progress of the works.
Each month, on the date corresponding to the interim certificate date, the
Contractor shall forward to the Engineer's Representative, a return of the various
consignments in store, giving the total tonnage at site, the quantity received during the
month, from whom it was obtained and in what sheds it has been deposited.
Also the quantity issued during the month, from what consignment and sheds it
was issued and in what portions of the works it was used.
After delivery on the site the Engineer's Representative may require each
consignment of cement to be subjected to any or all of the tests and analyses required
by B.S.12
33
Payment for these tests shall be the Contractor's responsibility and deemed to be
included in the tendered rates and prices.
The Contractor shall remove all rejected cement from the site without delay and
at his own expense.
(14) ADMIXTURES
Admixtures for accelerating or retarding the setting of the cement, etc., shall not
be used in any circumstances except with the written permission of the Engineer. When
such permission is sought, the Contractor must supply full details of the admixture he
wishes to use.
WATER 2002.
Water used for mixing and curing concrete shall be clean, fresh water from an
approved source and it shall be free from injurious oils, chemicals, vegetable matter,
organic and other impurities and shall comply with the requirements of B.S.3148
The Contractor shall ensure that all pipes, tanks and other receptacles for the
storage of water intended for use in the makings of concrete are kept in a clean
condition.
2003.
(1) GENERAL
The aggregates (fine, coarse and all in) for all grades of concrete and mortar
shall comply in all respects with B.S.882 (1973) and the Contractor shall test all samples
as described therein and in B.S.812 (1967) as often as the Engineer's Representative
may require,to ensure that they are continuously up to these standards. All aggregates
shall be hard, strong, durable, perfectly clean and free from organic matter and
deleterious coatings such as clay. They shall contain no harmful material in such
quantities as to affect adversely the strength or durability of the concrete, or attack the
reinforcement as ascertained by tests on concrete cubes as described hereafter and by
tests as described in B.S.882 (1973).
34
All aggregates whether fine or coarse if considered unsuitable by the Engineer's
Representative shall be removed from the site by the Contractor at his own expense.
(3) TESTING
The minimum frequency of testing at each concrete mixing plant shall not be less
than the following:
35
(iv) Moisture content Immediately prior to
commencement of mixing
concrete for each cast thereafter
every half hour during which
concrete is being mixed.
(4) WASHING
Washing of aggregate may only be carried out using clean fresh water obtained
from an approved source. The Contractor is to provide adequate storage facilities and
arrange to obtain this water at times chosen so as to cause the minimum of
inconvenience to other consumers.
The Contractor shall provide proper means of storing the aggregates at each
point where concrete is made and in such a manner that there is no possibility of the
various aggregates mixing one with the other. Effective precautions shall be taken to
prevent the aggregates segregating in the storage heaps and from being contaminated
by the ground and other foreign matter.
Storage heaps shall be capable of draining freely. Wet aggregates shall not be
used until, in the Engineer's Representative's opinion, they have completely drained.
Where aggregates are damp, the Contractor must measure the moisture contents of the
aggregates continuously and adjust the amounts of aggregates and added water in each
batch of concrete mixed to allow for the water contained in the aggregates. If
necessary, to meet the requirements of this Clause, the Contractor shall protect the
heaps of aggregates from inclement weather.
(a) Procedure
Sufficient fine aggregate passing sieve 1.25mm and retained on pan shall be
prepared and dried to constant weight. Weigh 3 kg to make 20 separate number of
specimen.
(b) Air-tight moisture content tins shall be weighed empty and to each shall
be placed 200 g of the dried soil and weighed again.
36
(c) Varying quantity of water as indicated in the table below shall be added
to each pair of container and allowed self moisturization for 24 hours and
weighed thereafter before placing in the oven or for speedy tester
method.
TABLE II-1 OVEN METHOD
Tin Number A b c d E
No. of
2 2 2 2 2
Specimen
Weight of dry
200 200 200 200 200
soil, g
Volume of
20 24 28 32 40
water cc
Tin Number A b C d E
No. of
2 2 2 2 2
Specimen
Weight of dry
200 200 200 200 200
soil, g
Volume of
20 24 28 32 40
water cc
(d) Calibration
37
(1) GENERAL
The total quantity of fine dust passing through a 75 µm mesh sieve in fine
aggregate derived by crushing rock shall be determined by the method described in
B.S.812. and shall not exceed 8% by weight.
The total quantity of clay and silt in natural sand shall not exceed 4% by weight
when determined by the field settling test decantation method described in B.S.812.
The quantity of organic impurities present in natural sand shall not be such as to
produce a reaction as dark as the standard solution when the organic impurities are
determined by the method described in B.S.812 (1975).
TABLE II - 2
* For crushed stone sands, the permissible limit is increased to 20% because of its
non clay nature of the fine materials. The 5% tolerance permitted may be applied to
the percentages. In the last three sets of sieves, it can be applied as follows: 1% on
the first of the three sieves and 2% on the others or 4% on one sieve and 1% on
others. The application of tolerance will depend upon the shape of the grading graph.
38
crushing sound hard granite taken from a source approved by the Engineer's
Representative and shall contain no harmful material in sufficient quantity to adversely
affect the strength or durability of the concrete or in the case of reinforced concrete to
attack the reinforcement. All coarse aggregate shall be washed after crushing if
necessary to comply with the specification. The flakiness index when determined by the
method described in B.S.812 (1975) shall not exceed 30 per cent. The individual pieces
shall be roughly cubical or spherical in shape and have neither glassy nor powdery
surfaces.
The aggregate crushing value of coarse aggregate shall not exceed 45 per cent
when determined by the method described in B.S.812.
(I) Rolled steel bars or hard drawn steel wire complying with the
requirements of B.S.785 "Rolled steel bars and hard drawn steel wire for
concrete reinforcement" and B.S.4449 (1969) Hot rolled steel bars for the
reinforcement of Concrete.
(II) Cold twisted steel bars complying with the requirement of B.S.114 "Cold
twisted steel bars for concrete reinforcement and B.S. 4461 (1969) Cold
works steel bars for the reinforcement of concrete.
(III) Such other reinforcement as may be suitable having regard to the yield
stress, ductility tensile strength and other essential properties.
The Diameter of any Bar for the purposes of this code should be taken as
that of a circle having an area equal to the cross sectional area of the
bar.
At the option of the Contractor, the reinforcing bars can be purchased from the
manufacturer using metric units provided that the area of required steel will not be
rounded downwards.
39
When the diameters of the reinforcing bars are given in one system on the
contract drawings, and they do not have exact equivalent of the bar in another system,
the basic dimension must be converted to the nearest higher cross section area. The
cost arising from additional weight of the reinforcing steel shall be borne by the
Contractor.
For each consignment of steel reinforcement used in the works, the Contractor
shall supply a certificate giving the ultimate strength, yield stress, elongation and result
of the cold bend test described in B.S.4449 and B.S. 4461. The Engineer's
Representative shall have power to select pieces of steel for testing if no test data are
supplied by the Contractor and the costs arising out of such tests shall be borne by the
Contractor.
(4) DELIVERY
When each consignment is delivered to the site, the Contractor shall issue to the
Engineer's Representative a written statement showing the number of the consignment,
the name of the manufacturer, the number of tonnes in the consignment.
(5) STORAGE
Reinforcement shall be stored on site in racks off the ground and shall be
protected from rusting, damage, oil or other deleterious matter and shall be clean and
free from all such matter before concrete is placed.
The prices inserted in the Bill of Quantities for steel reinforcement shall include
for supplying, handling, bending, wiring, placing, cutting, cleaning, supporting and every
other expenses necessary to complete the works as shown on the drawings or as may
be directed by the Engineer. The Contractor shall be paid for the net calculated weight
of reinforcement, excluding binding wire used in the work, in accordance with the
drawings, or as may be directed by the Engineer's Representative and no allowance will
be made for margins or otherwise.
40
encountered in Nigeria.
The joint sealing compound shall be hot poured material approved by the
Engineer. The material shall adhere readily to the concrete and to the primer. It shall
be ductile, not excessively soft or tacky at a temperature of 820C nor brittle at a
temperature of 20C.
A priming paint suitable for the joint sealing compound used, shall be applied to
the concrete surfaces prior to the pouring of the sealing compound with the object of
improving the adhesion.
PART B - WORKMANSHIP
At the commencement of the works, the Contractor shall indicate the type of
compaction which he intends to use in the various parts of the works and obtain the
approval of the Engineer's Representative thereto. The Contractor shall then design
mixes for concretes of grade as required, each design fulfilling the following
requirements:
(A) The cement, the aggregates and the water shall all comply with the appropriate
clauses of this specification.
(B) The cement shall not be less than that shown in Table II-3 of this specification.
The water content for each mix shall be in accordance with Clause 2013 (2) of
this specification and shall be such as to give the required compacting factor
and/or slump: where different methods of compaction are to be employed for
the same grade of concrete, involving different compacting factors and/or slump,
then a separate design mix shall be prepared for each case, to satisfy the
requirements of the appropriate clause of this specification.
41
Following the Engineer's Representative's approval of the mix designs, the
Contractor shall prepare, in the presence of the Engineer's Representative, a trial mix of
each design grade of concrete. The mixes shall be prepared as follows:
Before mixing, a sieve analysis of the aggregate shall be made by the method
described in B.S.812 (1975) and the weight and volume of the cement, fine aggregate,
coarse aggregate and water comprising the mix carefully determined. Each trial mix
shall be not less than half a cubic meter in bulk before mixing and shall be mixed as
specified in Clause 2012 of this specification in a mechanical mixer of the type approved
for use in the works.
The compacting factor and slump of each trial mix shall be determined
immediately after mixing as directed in NIS 12 B.S.1881 (1970)and shall not exceed the
maximum value obtained in the mix design.
Each trial mix shall be handled and compacted by the methods which the Contractor
proposes to use for that mix in the works, and the mixes shall show no tendency of
inadequate compaction by the methods proposed.
Six cubes of 150mm compression test cubes shall be made from each trial mix. The
cubes shall be made, cured, stored and tested in accordance with the requirements of
B.S.1881 (1971).
42
-do- 35 20 400 0.45 – 25 35
0.55
REINFORCED 0.45 –
30 20 350 20 30
CONCRETE 0.55
-do- 25 20 295 0.45 – 15 25
0.55
-do- 20 20 235 0.45 – 12 20
Or
0.55
Po
-do- 15 20 205 0.55 – 10 15
Ce
0.65
MASS 12 40 175 0.55 – 7 10
CONCRETE 0.65
BLINDING 0.65 –
10 40 150 7 10
CONCRETE 0.75
Three cubes shall be tested 7 days after manufacture and three 28 days after
manufacture. The strength requirements of the cubes at each age shall be considered
to be satisfied if none of the strengths of the three cubes tested at each age falls below
the appropriate design strength or if the average strength of the three cubes is not less
than the strength and the difference between the greatest and least strengths is not
more than 20 per cent of that average.
Failing this, the Contractor shall re-design the mix and make such further trial
mixes and test such further cubes as the Engineer's Representative may direct until the
requirements of this specification are satisfied.
The design mixes which fulfill the requirements of this specification for a
particular grade of concrete shall be called the approved mixes for that grade of
concrete and the Contractor shall only use the approved mixes where that grade of
concrete is specified, and shall not depart therefrom without the written permission of
the Engineer's Representative. The Engineer's Representative may require further trial
mixes and further cube tests to be made before such permission is given.
The Contractor shall allow ample time in his programme for designing and
making trial mixes and for the preparation and testing of compression test cubes
obtained therefrom. Should any design mix fail to satisfy the requirements of this
specification and should the Engineer consider that it is essential to commence the
production of that grade of concrete before the results of the cube tests of a further
design mix are available, he will consult with the Contractor and decide on an interim
mix for use until such time as the results of the cube tests have become known, any
extra cost involved being borne by the Contractor.
The Contractor shall be deemed to have satisfied himself that the materials on
which he has quoted will produce a concrete which, with the specified nominal
proportions and subsequent adjustments as indicated by trial mixes, will develop the
43
cube strengths specified and at same time have the desired workability in the work
itself.
The cost of all trial mixes, test cubes and their testing shall be deemed to be
included in the tendered rates for concrete.
(1) GENERAL
Concrete shall be mixed in mechanical mixers of the weigh batch type as stated
in the Contractor's mix design proposal, complying with the requirements of B.S. 1305
(1967) and fitted with an approved weight measuring device. No hand mixing will be
permitted. Mixing shall continue until there is a thorough distribution of the materials,
and the mass is of uniform colour and consistency. The period of mixing, judged from
the time that all materials including the water are in mixer, shall be not less than that
or should not be more than 2 minutes per m3 or as recommended by the
manufacturer. The concrete mixer shall revolve at the speed recommended by the
manufacturer, or as ordered by the Engineer's Representative. The entire contents of
the drum shall be discharged before materials for the next batch are fed in. Should
there, for any reason, be a stoppage of greater than 30 minutes duration, the drum of
the mixer shall be thoroughly washed out with clean fresh water before mixing is
resumed. Stationary mixers shall be equipped with an acceptable timing device that will
not permit the batch to be discharged until the specified mixing time has elapsed.
No partly set concrete shall be placed in the works. Concrete which has
commenced to set shall not be re-mixed either with or without additional water and in
no case shall such concrete be used in the works.
Before their use in the works, the Contractor shall show, to the satisfaction of
the Engineer's Representative that all materials and methods of storage and mixing to
be employed in the production of concrete, conform in every way with the requirements
of this specification.
Such deliveries of materials to the site as the Engineer's Representative may
designate shall be tested and analyzed to ensure that they do so comply and the tests
shall be carried out sufficiently in advance of their intended use in the works to allow the
results to be studied and the materials approved, modified or rejected by the Engineer's
Representative as the case may be. The Contractor shall remove all rejected materials
from the site without delay and at his own cost. Permission to use any material shall not
be construed as an approval of its source, nor any acceptance as continued acceptance.
44
Workability of concrete shall be measured by compacting factor. The Contractor
shall provide a compacting factor apparatus conveniently accessible to each concrete
mixer and shall measure the compacting factor by the method described in B.S.1881 at
frequent intervals or as frequently as the Engineer's Representative may direct, but in
any case, tests shall be carried out at least once every halfhour during which concrete is
being mixed. Whenever the compacting factor varies from that of the approved mix the
quantity of water added to the mix shall be immediately adjusted to counteract the
variation. The successive values of the compacting factor and the quantity of water
added shall be recorded on a suitable quality control chart, which shall be kept near the
mixer and submitted to the Engineer's Representative for his inspection as he may
direct. Notwithstanding the foregoing, the "V-B" consistometer test may be used in
place of the compacting factor test and in such cases tests shall be carried out in
accordance with the recommendations of the manufacturer of the "V-B" Consistometer;
see B.S 882 part 19.
The Contractor shall ensure that all their concrete mixer operators are aware of
the importance of maintaining uniform controlled quality of the concrete and that they
are experienced in detecting variations in concrete quality and workability and in rapidly
correcting the same.
The gradings of all aggregates must be within the respective limits specified in
Clause 2004; failing which the Engineer or his Representative shall instruct the
Contractor to make such modifications to the proportions of aggregate in the mix as will
allow for such difference, and the Contractor shall immediately do so.
Should the amount of clay, fine silt and fine dust exceed 4% by volume, then the
Contractor shall refrain from using the aggregate until he satisfies the Engineer's
Representative of its suitability for making concrete of the quality required.
45
(5) PROTECTION OF CEMENT
Works Cubes, whether required for the normal method or for the
special method of quality control described respectively hereunder, shall
be made and cured in the manner described in B.S.1881. Where the
concrete is vibrated, the cubes shall be compacted by similar means in
such a way that full compaction of the concrete with neither segregation
nor excessive latex is obtained. Samples of concrete from which works
test cubes shall be made shall be taken in accordance with B.S.1881 and
in particular at the time and place of deposition of the concrete and at
such other times and places as the Engineer's Representative will direct.
(III) The frequency of sampling for each concrete mixing plant used for the
Contract shall be as follows:-
(1) When each mix is first made for use in the works, batches shall be
sampled at the rate of 8 batches per day for the first 5 days of using that mix or
at such other times as directed by the Engineer's Representative until a total of
40 batches have been sampled, with a minimum requirement that
(i) one batch shall be sampled each day particularly when any
concrete of a particular mix is made.
(2) Thereafter one sample shall be taken on each day any grade of
46
concrete is made.
From each sample of concrete and at the place where the sample was taken six
test cubes shall be made; 3 shall be tested at an age of 7 days and 3 at an age of 28
days. The test cubes shall be made cured and tested in accordance with B.S.1881. If
cured at a mid point temperature of 270C, then the 200C strengths will be assumed to
be 0.80 times the 270C strength.
For the strength of concrete to be acceptable to the Engineer, the following shall
be achieved:
(1) Each test cube shall have compressive strength of not less than that
specified on the drawings.
(2) Notwithstanding the provision of sub-clause (1) above, should the 200C
compressive strength of a test cube or cubes tested at an age of 7 days
be below the minimum specified strength, then if the other test cubes of
the set tested at 28 days comply with the Specification, the concrete shall
be deemed to have passed the tests.
∑x )²
∑ ( x - N
N-1
(∑x )²
∑( x)² - N
N - 1
47
where N = Number of cubes tested
x = 28 day compressive strength
of 150mm cube in N/mm²
S= Standard deviation in N N/mm²
Notwithstanding the foregoing, the standard deviation shall not be calculated for
a mix until there are at least 40 sets of 3 test cube results available.
(6) Workability
(9) Individual and average compression strengths of the 3 test cubes and
assumed 200C values if different
(11) Average compressive strength and standard deviation for which the mix
has been designed
(13) Overall average compressive strength from (12) minus 1.64 multiplied by
deviation from (12).
If results of the cube tests do not comply with the Specification, such remedial
works as the Engineer may accept or direct shall be carried out.
If results of cube tests do not comply with the Specification and/or if the
48
figure from item (13) of the test report is less than the specified minimum 28 day
compressive strength, then either the quality control at the relevant mixing plant shall
be improved to the satisfaction of the Engineer's Representative or the mix shall be
redesigned to the satisfaction of the Engineer's Representative. If directed by the
Engineer, redesign of the mix shall include carrying out further preliminary laboratory
tests in accordance with the Specification with the redesigned mix.
Should either the test cubes crushed at 7 days or those crushed at 28 days or
both, fail to satisfy the specified requirements, the Contractor shall, on the Engineer's
Representative instructions, take one or more of the following steps:
(A) He shall alter the design of the mix to increase its average compressive
strength
(B) He shall alter the method of making the concrete and controlling its
quality to reduce the variability of the concrete.
(C) He shall cut out and replace concrete placed in the works on any day in
which a cube (was made and failed if, in the opinion of the Engineer's
Representative, such concrete is likely to be incapable of fulfilling its
purpose.
The Engineer may require the Contractor to cut out defective concrete from the
works even though test cubes made from that concrete have not failed. This
may arise if the concrete failed to meet other salient features and quality
standard like the following:
49
(i) Honey combing
(ii) Cold joint
The Contractor shall bear the cost of carrying out and supplying all labour,
materials and equipment for the sieve, silt, organic impurities, bulking, compacting
factor and slump tests mentioned above and any other tests required by the Engineer or
the Engineer's Representative to ensure proper quality control of the concrete. He shall
also bear the cost of supplying all labour, materials and equipment necessary for the
preparation of the compression test cubes and their subsequent storing, curing, packing,
transportation and testing. All costs arising out of modifications to the concrete mixes,
cutting out and replacing of defective concrete and all other work carried out in
accordance with this Clause shall be borne by the Contractor.
Concrete shall be taken from the place of mixing to the place of deposition by
methods which will prevent the drying out and consolidation of the concrete, the
segregation and loss of the ingredients, and which are sufficiently rapid to ensure that
the concrete does not commence to set before it is finally compacted in position. During
transportation, the concrete shall be protected from all adverse effects of sun, wind and
rain. The concrete shall be deposited as near as possible to its final position in the
works, and no concrete shall be dropped freely or deposited by means of chutes
through a depth exceeding 3 metres. All mixers, barrows, spades and other mixing and
distributing equipment will be thoroughly clean before commencing each period of use
and shall be kept free of partly set concrete which shall not be used in the works. No
concrete shall be transported over or near to new work that has insufficiently hardened,
in order to prevent harmful vibration of the new work and no planks or ways for skips,
etc., shall be supported on either formwork or reinforcement for the same reason.
No concrete shall be placed in any part of the works until written permission to
do so has been obtained from the Engineer's Representative. Well in advance of the
intention to place concrete, the Contractor shall forward to the Engineer's
Representative for his approval full information about the order in which he proposes to
place concrete in the various parts of the works, the height of each lift of concrete,
details of the shuttering which he proposes to employ with relevant calculations, and
positions of all construction joints.
All construction joints shall be formed as specified in Clause 2019 and there shall
50
be no stoppage of the placing of concrete except at such proper construction joints.
For members involving "vertical" placing of the concrete, (e.g. piers) each lift
shall be deposited in layers extending for the full width between shuttering and of such
depth that each layer can be easily and effectively incorporated with the layer below by
the means of compaction being employed. The layers shall be placed horizontally,
sloping beds not being permitted unless particularly so specified.
For members involving "horizontal" placing of the concrete (e.g. deck slabs), the
concrete shall be placed along the line of the starting point, in such quantities as will
allow the member to be cast to its full depth along the full width between side
shuttering and then gradually brought towards the finishing point along its entire front,
parallel to the starting line, the tampers for giving the required surface and compaction
following as closely behind as practicable.
All members shall be concreted at such a rate as will eliminate any possibility of
fresh batches of concrete being deposited immediately adjacent to batches which have
commenced to set, and all members shall be poured in one continuous operation until
completed, no interval being allowed to lapse while the work is in hand.
Care shall be taken to ensure that the process of placing concrete does not
cause any harmful vibration to adjacent work that has insufficiently hardened.
No concrete for work which will present a large exposed surface (e.g. deck slab)
shall be placed in the direct rays of the sun and the Contractor shall erect shades to
protect such work therefrom.
51
taken to ensure that neither hand pounders nor mechanical vibrators come into contact
with the formwork, reinforcement, or any embedded fittings and to prevent the
operation of compaction from transmitting any harmful vibrations or shocks to concrete
which has not yet hardened sufficiently.
Compliance with the conditions of this clause may require working longer hours
than usual and the Contractor must allow for this in his schemes for concreting and in
the rates for the work inserted by him in the Bill of Quantities.
Concrete shall be placed under water only where particularly so specified and
approved by the Engineer's Representative. The quantity of cement in any concrete
placed under water shall be increased by at least 25 per cent above the cement content
of the appropriate approved mix. Concrete shall be placed in still water only and every
precaution shall be taken to prevent the cement and fine materials from being washed
out of the concrete. Concrete shall be placed either with a tremie or a bottom opening
box of a type approved by the Engineer's Representative. Bottom opening boxes shall
not be opened until they are resting on the work and the lower ends of tremie pipes
shall always be kept below the surface of the wet concrete already deposited. No
concrete shall be allowed to fall through water at any time. Concrete shall be placed
evenly over the whole area enclosed by the shuttering and must not be raked over, only
the minimum of screeding being allowed once the concrete has been replaced.
Concrete under water shall be placed in accordance with the provisions of the
British Standards Code of Practice 2004 (8.2.2.3 or 8.2.2.3.4).
During all concreting operations, the Contractor that a competent joiner and a
competent shall ensure steel fixer (in the case of reinforced work most especially in
work in which fittings are embedded) are in attendance on each concreting operation. It
shall be their duty to ensure that the formwork is maintained in accordance with the
specification, temporary construction joints inserted as necessary, and reinforcement
and fittings maintained in place as the work proceeds.
52
All construction joints in all classes of work shall be formed by inserting stopping
off boards normal to the work to form a tongue and groove joint as detailed on the
drawings and against which the concrete can be properly compacted. They shall be
formed in the position shown on the drawings or as directed and approved by the
Engineer's Representative. There shall be no construction joints in precast members nor
in the reinforced concrete deck slabs of minor spans. In the case of tee beams the rib
and slab shall be cast together in one continuous operation. In other work, construction
joints shall be located at points where shear stresses or tensile concrete stresses are a
minimum and at place where they will least affect the appearance and properties of the
finished works, but no construction joint may be inserted without the written approval of
the Engineer's Representative. All reinforcement required by the Engineer's
Representative as a consequence of the position selected for any proposed construction
joint shall be provided by the Contractor at his own cost, unless, in the opinion of the
Engineer's Representative, the joint is absolutely necessary and there is no alternative
position for such joint.
All costs incurred in complying with the requirements of this clause shall be
deemed to be included in the tendered rates for concrete.
53
joint, there must be not less than two thicknesses of approved waterproof building
paper. Concreting operations and pounding etc., shall be carried out carefully to ensure
that no damage shall be done to the paper.
All concrete surfaces not requiring shuttering shall be smooth finished with
approved floats to give a dense surface with a minimum of cement and fine materials
being brought to the surface. The top surface of deck slabs shall be tamped to a smooth
finish, aided by floats if necessary, to the levels, falls and cambers shown on the
drawings or as instructed. The tamping shall not be done to the extent of bringing an
excess of fine materials to the surface.
Shuttered surfaces of work in mass concrete which will always be in contact with
the ground and more than 0.5 meter below finished ground level on the external
surfaces of abutments and piers may be cast against sawn timber shuttering. All other
surfaces, including all reinforced work and all precast and prestressed, shall be cast
against steel or planed timber formwork. Any surfaces, irrespective of the shuttering
employed, which show honeycombing or voids shall be made good by cutting back the
concrete to behind the reinforcement in the case of reinforced work or to such depth as
the Engineer's Representative may specify in the case of mass work, and in either case
to sufficient depth to remove all defective concrete, but no repair work shall be started
until after the defective surfaces have been inspected by the Engineer's Representative.
The cut shall be slightly belled to ensure that the new surface will be keyed to the sound
concrete, and the new surface will be cast in accordance with the requirements of this
specification and against shuttering which has been carefully aligned with the sound
concrete on either side and tightly secured in position by wedging etc.
All exposed concrete surfaces shall be fair finished to the entire satisfaction of
the Engineer's Representative.
All concrete surfaces shall be protected from damage and disfigurement due to
the subsequent pouring of concrete or the carrying out of other work in the vicinity or
any cause whatsoever, and the Contractor shall remove all blemishes and repair all such
damage to the satisfaction of the Engineer's Representative.
All costs for making good honeycombed and defective concrete and repairing
damaged surfaces shall be deemed to be included in the rates for concrete and
shuttering inserted in the Bill of Quantities.
During curing of the concrete, all precautions shall be taken to ensure a slow
heat evolution and the absence of cracks. The temperature of the hot concrete surfaces
should not be subjected to sudden changes by spraying of cold water and the concrete
must be protected from sunshine and wind. Freshly placed concrete must be protected
from rain.
54
If low heat portland cement is preferred, the cement shall conform to the
requirements of B.S.1370.
Very great importance is attached to the proper curing of the freshly placed
concrete and the Contractor must ensure that is effectively done. All newly placed
concrete shall be protected from the effects of rain, drying winds and the sun by
suitable screens of damp hessian, or damp sand after the concrete has hardened
sufficiently to support them directly without marking. The ends and sides of the screens
shall be held down at the edges to prevent draughts from getting underneath. As soon
as the concrete has hardened sufficiently to support the coverings without marking. It
shall be covered with clean sacks, hessians, or a 50mm thick layer of clean sand or
other approved material which shall be kept continuously in a wet condition by frequent
spraying with fresh clean water. Where the concrete to be cured is enclosed by
shuttering, the shuttering shall be covered with clean sacks or hessian which must be
kept continuously in a wet condition When the shuttering is removed, the damp hessian
or sacks shall be hung directly around the concrete member and kept continuously wet
by spraying with clean fresh water. Providing that the shuttering has been covered with
approved mould oil which will prevent the timber from absorbing water from the
concrete, the time that the concrete remains in formwork under the conditions herein
specified shall count as part of the curing period. Curing of all concrete shall continue
for at least 7 days, or as directed by the Engineer's Representative, or as otherwise
specified. On no account must the surrounding sacks, hessian, etc., be allowed to dry
out during the curing period. The cost of curing shall be deemed to be included in the
tendered rates for concrete
All Formwork shall be adapted in every respect to the structure and to the
required surface finish for the concrete. It shall be fixed in perfect alignment and
securely propped and braced so as to withstand without displacement, distortion or
movement of any kind the weight of construction and the movement of persons,
materials and plant.
It shall be sufficiently watertight to prevent any loss of liquid from the concrete
55
and shall be capable of being removed without shock, vibration or damage to the
concrete.
Where wrot shuttering is specified, the faces to be in contact with the concrete
shall be planed perfectly smooth and true, to form in all the surfaces, curves or shapes
specified and joints shall be planed and perfectly watertight.
All Formwork for new lifts of concrete shall be tightly and accurately fitted
against the concrete already cast to ensure that the surface of the new work will be
quite flush and in line with that of the old.
Wedges and clamps shall be used wherever practicable instead of nails and
where it is proposed to employ mechanical vibration the formwork shall be strengthened
accordingly by increasing the number of bracing and props, nailing wedges in position
and using screws instead of nails where necessary. Particular care shall be taken to
ensure that joints remain tight during the process of vibration.
All forms for beams and kindred members shall be designed and constructed so
that the sides may be removed without disturbing the bottom boards or supports
thereto. The bottom of each form shall be set with a camber of l/300th of the span or as
otherwise specified or required according to the dimensions of the beams. The
supporting struts shall be adjusted and securely fixed in position by approved means.
Formwork for encasing steel joists shall be suspended from the joists to relieve
the concrete of dead load stresses.
Unless otherwise specified, fillet strips shall be fixed in the shuttering to form a
chamfer 12mm by 12mm on all external corners of the finished work.
Should the Contractor wish to erect the formwork by passing ties through the
work, or embedding bolts therein, he must first obtain the approval of the Engineer's
Representative and when seeking such approval, shall forward full details of the type of
fitting proposed for use, and show how it will be employed in the work. No type of
fitting will be permitted which cannot be removed easily after use or which does not
allow easy and effective making good of the concrete surface. The use of wires, etc.,
requiring subsequent cutting into, and plastering over, of the concrete will not be
permitted.
56
If metal forms are used, the metal shall conform to the provisions of the
B.S.4360. For prestressed units the additional 10KN/m² shall be added to the weight of
the wet concrete in the design of horizontal areas of the formwork.
All side forms for the prestressed units shall be eased as early as possible and
the soffit forms shall permit deformation of the member when the prestress is applied.
The formwork should be designed to withstand the additional forces due to the
vibrations during concrete placing. The soffit shutter should be adequately supported to
prevent any settlement which might cause cracking of the concrete. On the soffit
shutter, provision should be made for the elastic shortening of the concrete under
prestress.
An upward camber shall be given to ensure that the girders do not sag under
working loads. The Contractor shall make measurement before and after concreting
each section, and submit the results to the Engineer.
The Contractor shall notify the Engineer in advance of the time he proposes any
adjustments to the forms prior to concreting next section, should any adjustments be
needed.
All surfaces of the formwork which will come into contact with the wet concrete
shall be painted with an approved non-staining mould oil, to prevent adhesion between
concrete and formwork. The mould oil shall be insoluble in water, unharmful to the
concrete, non-flaking and shall not be removable by rain or wash water. The Contractor
shall ensure that the oil shall be kept from contact with the reinforcement or embedded
fittings.
Before placing any concrete, all shavings, loose binding wires, soil, rubbish and
all foreign matter shall be removed from the formwork and the formwork shall be
carefully and thoroughly washed with water. Loose planks shall be incorporated in the
bottom of panels of shuttering to facilitate the removal of rubbish from the section to be
concreted, as necessary.
No concrete shall be placed until the Engineer's Representative has inspected the
formwork and props and given his approval to do so.
(2) STRIPPING
57
CONCRETE
SLABS SOFFIT BOARDS 5 DAYS
PROPS 14 DAYS
BEAMS SIDE BOARDS 3 DAYS
BOTTOM BOARDS 14 DAYS
PROPS 28 DAYS
COLUMNS 7 DAYS
WALLS, MASS CONCRETE 3 DAYS
PIERS AND REINFORCED 7 DAYS
ABUTMENTS CONCRETE
Where props are to be left in position under slabs and beams the formwork shall
have been made in such a fashion that it can be removed without disturbing the props
in any way, otherwise it must be left in position for the full period that the props are left
in position.
The formwork shall be removed by gradual easing without jarring and only under
competent supervision. Before removal of the shuttering, the concrete shall be
examined and removal shall only be proceeded with if the concrete has attained
sufficient strength to sustain all the loads to which it will be subjected. The Contractor
shall be responsible for any injury or damage to the work caused by or arising out of the
removal of formwork and props and any advice, permission or approval given by the
Engineer's Representative, relative to the removal of formwork and props shall not
relieve the Contractor of this responsibility.
All timber or metal moulds inclusive of all necessary supports and stagings
(unless billed separately), bolts, nuts, straps, clamps, wedges and other fixings also all
cutting and waste and cost of all labour and materials in making, erecting and removing
the formwork and for any other work required to construct the forms to shapes and
dimensions shown on the drawings or as directed by the Engineer, shall be included in
the rate for formwork.
Formwork shall be measured as the nett area in contact with the finished
concrete surface. No measurement will be allowed for formwork for temporary
construction or day-work joints.
REINFORCEMENT SCHEDULES 2024.
58
works. Where new schedules are required or existing ones require to be amended, the
Contractor shall prepare such new or amended schedules in accordance with B.S.4466
(1969) and forward three copies of each to the Engineer's Representative well in
advance of placing reinforcement in the works. The Contractor shall be responsible for
his own ordering sheets.
The cost of checking all new and amended schedules as specified above shall be
deemed to be included in the tendered rates for reinforcement.
All reinforcing bars shall be carefully bent with an even and gradual motion to
the correct dimensions by experienced steel benders and in a manner which will not
injure the material. In particular, no reinforcement shall be heated before bending.
Unless stated to be otherwise in the schedules, all bends and bending shall be in
accordance with B.S. 4466.
Unless otherwise directed or authorized by the Engineer, the number, size, form
and disposition of all reinforcing bars shall be strictly in accordance with the drawings.
Bars generally must be of the required lengths and lapping and welding of main bars will
not be permitted unless so indicated on the drawings.
Details of the chairs showing their size, bending and disposition in the work shall
be forwarded to the Engineer's Representative for his approval before incorporation into
the work. The use of temporary supports will not be permitted.
Any parts of metal supports that are left in place within 50mm of an exposed
surface of the concrete shall be non-rusting metal or coated with non-rusting metal.
Galvanizing of such parts will be acceptable provided the weight of the zinc coating per
1000cm² of actual surface shall average not less than 56 grams and no individual
specimen shall show less than 50 grams.
59
reinforcement shall be assembled as rigid cases before placing in the formwork.
Concrete blocks shall be used to maintain the correct distance between the
reinforcement and the formwork i.e. to maintain the correct concrete cover to the
reinforcement. Such blocks shall not exceed 50mm in width nor 50mm in length and
their thickness shall be exactly that required to give the cover specified on the drawings.
Binding wires shall be securely embedded into each block to permit adequate fastening
to the reinforcing bars. The number and location of the blocks used in the work shall be
to the satisfaction of the Engineer's Representative.
All reinforcement shall be perfectly clean and free from loose scale, rust, oil,
grease and any other matter which might reduce the bond between the steel and the
concrete. Loose pieces of binding wire and other foreign matter shall be removed.
Electric Arc Welding may be permitted for joining bars, provided the approval of
the Engineer has been obtained, and for work of this type the use of electrodes of the
covered alloy or shielded arc type will be permitted, provided that they conform to the
requirements for Class A electrodes, as described in B.S.639 "C"Covered Electrodes for
Metal Arc Welding Wrought Iron and Mild Steel". Workmanship shall conform to the
general requirements of B.S.693 (1960), 1856 (1964) and 2642 (1965) as applied to
general building construction. All such connections shall be butt
welded with standard Double V or Double U welds.
PART C - PRECAST CONCRETE UNITS 混凝土预制件
(NOT TO BE PRESTRESSED)
The requirements of the foregoing clauses for concrete will apply to all precast
work where applicable and in addition the following special clauses are to be observed.
Rapid hardening portland cement shall conform to the requirements of B.S.12 and may
only be used with the approval of the Engineer or his Representative.
60
(1) FORMWORK
All formwork is to be such as to ensure true arris and sound surfaces and metal
lining formwork will generally be required by the Engineer.
(2) DIMENSIONS
Units are to be formed to the dimensions and tolerances shown on the drawings.
(3) MOULDS
Units are to be made in strongly constructed moulds which are closely jointed,
perfectly smooth and true in alignment. The moulds must be constructed so that no
bulging or distortion can occur during consolidation of the concrete, and should be fitted
with suitable fastenings to facilitate easy removal without injury to the units.
(4) MANUFACTURE
The Contractor shall provide facility for the Engineer or his Representative to
carry out any tests or inspection during all stages of manufacture as may be required to
ensure the quality and soundness of the units. The proposed method of manufacture is
to be approved by the Engineer before production of the units commences. All units
shall have impressed upon them in some convenient position the date of manufacture
and such distinguishing letters as the Engineer may direct.
(5) CURING
The moulds will be struck at such a time so that the units are not subject to risk
or damage or distortion. All concrete shall be kept damp for seven days and protected
from the direct rays of the sun for a further period of 14 days. This can be achieved by
covering roof or tent.
Concrete surfaces and moulds shall be protected during casting and for 14 days
thereafter from the effects of sun, wind and rain etc., and the concrete shall be cured
for a period of 7 days after casting, all to the satisfaction of the Engineer's
Representative. The striking of moulds shall be without damage to or distortion of the
concrete surfaces.
(7) REJECTED UNITS
(8) STACKING
61
and arranged so that they are available for use in order of age.
Precast concrete goods, whether they have been purchased for use in the
works, or manufactured by the Contractor shall be in accordance with the
requirements of the following British Standards, as applicable:
Should any portion of the work give evidence, in the opinion of the
Engineer or his Representative that the concrete is of inferior quality,
insufficiently compacted, segregated or improperly deposited and
rammed in the forms or that any of the reinforcement or fittings has been
omitted, incorrectly placed or subsequently displaced or that it suffers
from any defect, omission or injury from any cause whatsoever which
may adversely affect the strength or durability of the construction, the
Contractor shall, on the written instructions of the Engineer, remove and
reconstruct that portion of the work in such manner as the Engineer shall
direct or approve to ensure that the requirements of this specification are
fulfilled.
No repairs shall be made to any faulty work until it has been inspected by
the Engineer's Representative and his permission to proceed obtained. All costs
involved in the reconstruction of faulty work shall be borne by the Contractor.
62
Mortar and Grouts shall be composed of portland cement, sand and water
satisfying the requirements of this specification and mixed together in the proportions
indicated in Tables II-5 and II-6. The cement and sand shall be measured by volume in
gauge boxes of approved size. The common size is 0.03m³. The gauge boxes shall be
filled with the respective materials without compaction, and struck level, proper
allowance being made for any bulking of the sand due to moisture content. Mixing shall
be done in an approved mechanical mixer, the amount of water added being just
sufficient to give the consistency and workability desired by the Engineer's
Representative for the use to which the mortar is to be put. Mixing shall be carried out
as specified for concrete.
Hand-mixing of mortar will only be permitted where very small quantities are
required and the approval of the Engineer's Representative has been obtained. In such
cases, the dry sand and cement shall first be mixed together by turning over with a
clean shovel or trowel on a clean steel platform or other approved surface until a
mixture of uniform colour has been obtained.
Water shall then be added, a little at a time, the mixture being turned over after
each addition, until a homogeneous paste has been obtained. This process shall be
repeated until the required consistency has been obtained. Only perfectly clean
implements and surfaces shall be used in hand mixing and care shall be exercised to
ensure that no cement is washed away during the addition of the mixing water.
All mortar must be in its final position in the works within 30 minutes of the
initial mixing together of the sand, cement and water.
All foundations, bolts, fittings, kerbs, etc., are to be built into the work as
concreting proceeds by supporting them either from the formwork in their correct
position or grouted into recesses cast in the work as specified or directed by the
Engineer or his Representative. Recesses to accommodate such item shall be cast
63
against properly constructed formwork and in no circumstances shall they be formed by
cutting out green concrete. Similarly, no fittings shall be positioned in the works by
inserting into concrete which has commenced to set.
The Contractor shall set the metal work which is to be embedded into position
before concreting. All items shall be carefully cleaned, placed and firmly secured to
ensure that it will not be displaced during concreting operations. Anchor bolts shall be
placed by means of templates supplied by the Contractor. All threads shall be carefully
greased after the bolts are firmly in position, but prior to concreting. The position of all
embedded items shall be carefully observed during and at the completion of concreting
operations to ensure they are in the proper position upon completion of the work.
The grade of concrete, mortar or grout to be used in the various parts of the
work shall be as specified on the drawings. Where no specification is given on the
drawings as to the grade of concrete, mortar or grout to be used, it shall then be as
given in the following Table II-6 below.
The materials shall be mixed to a consistency suitable for the purpose intended.
All mortar shall be used within 30 minutes after the mixing water has been added.
64
PART E - GRANOLITHIC CONCRETE FLOOR FINISHED
CEMENT 2030.
All cement used in the works shall be from an approved source, and shall comply
with the latest appropriate Nigerian Industrial Standards or British Standards.
AGGREGATES 2031.
All aggregates fine and coarse shall comply with the requirements for aggregates
for concrete work and shall be subject to the approval of the Engineer's Representative.
The Granolithic Topping shall be laid and floated on a new concrete sub
floor within 12 hours of laying the latter. Where the sub-floor consists of an existing
concrete surface, this shall be hacked, thoroughly cleaned, wetted and brushed over
with cement grout prior to laying granolithic topping.
65
LAYING 2034.
The Contractor shall ensure that successive trowellings are applied at appropriate
times by skilled workmen.
The topping shall be rendered with a wood float and struck off with a steel
trowel after the set has commenced. The topping shall be laid to a thickness of 25mm to
40mm Slightly increased thicknesses are necessary when the topping is laid on matured
concrete sub-floors.
The toppings shall be divided into bays not larger than about 3.5m. x 3.5m. laid
alternately or as directed.
CURING 2035.
Granolithic topping shall be cured for a period of seven days after laying all as
for normal concrete.
Concrete shall be laid to finished level and while it is still wet and soft shall be
sprinkled with a mixture of 1 part of chippings to 1 part of high alumina portland cement
mixed together in a dry state and applied at a rate of spread of 8Kg/m² of surface. The
chippings shall consist of a suitably graded material 6mm to dust with not more than
20% content of fine material.
This mixture shall be tamped in with a wooden float and twice trowelled with a
steel trowel to a smooth and fine finish. After the topping is dry it shall be treated with
one application of 10% solution of silicate of soda.
66
DAMP PROOFING 2039. MISCELLANEOUS
The surface to be damp proofed shall be primed and then thoroughly mopped
with waterproofing asphalt.
The mastic asphalt shall be laid in two courses in the manner described in British
Standard Code of Practice CP 144 Part 2. Joints shall be staggered at least 150mm
between courses.
When the first mopping of asphalt has set sufficiently, the entire surface shall
then be mopped with a second coating of hot asphalt. Special care shall be taken to see
that there are no skips in the coatings and that all surfaces are thoroughly covered. The
two sides of all joints shall be intimately bonded. The surfaces of any gullies and other
features with which the waterproofing will be in contact shall be clean and painted with
bitumen.
The cost of all materials, labour, tools, equipment and incidentals, and for doing
all the work involved in applying the damp proofing, complete in place as shown on the
drawings or as directed by the Engineer, shall be deemed to be included in the tendered
rates for concrete.
67
SPECIFICATION
68
SECTION III - PRESTRESSED CONCRETE 预应力混凝土
GENERAL 3000.
In addition to any other relevant clause of this Specification, the following shall
be deemed to apply in particular to prestressed concrete work, and shall be read in
conjunction with all other relevant clauses (especially those referring to mass and
reinforced concrete) of the conditions of Contract and this Specification.
This work shall include the furnishing and installation of any appurtenant items
necessary for the particular prestressing system to be used, including but not limited to
sheaths, anchorage assemblies and grout used for pressure grouting sheaths.
The Contractor shall submit to the Engineer for his approval plans and working
drawings. The working drawings, of the prestressing system shall contain details and
substantiating calculations of method and materials the Contractor proposes to use, in
the prestressing operations including any additions or rearrangement of reinforcing steel
from that shown on the drawings. Such details shall outline the method and sequence of
stressing and shall include complete specifications and details of the prestressing steel
and anchoring devices, working stresses, anchoring stresses, type of sheaths, and all
other data pertaining to the prestressing operation, including the proposed arrangement
of the prestressing steel in the member.
Working drawings shall not exceed 594mm x 841mm in size and each drawing
and calculation sheet shall include the job site, name of the structure as shown on the
contract drawings.
Throughout the prestressing work the Contractor shall employ on the works at
least one suitably qualified engineer who shall be experienced in the systems of
prestressing being used. His duties shall be as follows:
69
(6) Such other duties as the Engineer's Representative may direct.
All personnel operating the stressing equipment shall have been properly trained
in its use. In addition to the normal precautions against accident which should be taken
at all times for the whole of the Works, special precautions shall be taken when working
with the tendons which have been tensioned or are in the process of being tensioned.
The personnel should not stand in line with the tendons, their anchorages or
jacking equipment. Simple protective measures such as stout timber shields sheathed
with steel should be placed in line with tendons and behind the jacks to protect
personnel passing in the usual course of their duties, if applicable.
CEMENT 3001.
The Cement shall be rapid hardening portland cement in accordance with the
latest B.S. 12 with all latest amendments or portland blast furnace cement conforming
to the requirements of B.S.146 with all latest amendments. The use of high alumina
cement will not be permitted.
AGGREGATE 3002.
Materials which are rejected from the grading process may be used up in 10
N/mm² grade concrete in other parts of the works at the discretion of the Engineer's
Representative. Any rejected material is to be removed forthwith from the site by the
Contractor at his own expense.
70
Fine Aggregates shall consist of naturally occurring sand obtained from fresh
water river deposits approved by the Engineer's Representative. The grading of sand
particles shall satisfy the percentages stated for Zones 1 or 2 in B.S. 882, and as given
in Table III-1
Coarse Aggregate shall consist of natural gravel or crushed granite rock obtained
from a source to be approved by the Engineer or his Representative. The grading of
coarse aggregate particles shall strictly satisfy the percentages for l9.0mm - 4.76mm
nominal size stated in B.S. 882 as given in Table III-1 with a content not exceeding 1%
passing the 2.36mm sieve size.
PERCENTAGE PASSING
AGGREGATE
SIEVE SIZEZ
150 300 600 1.2 2.4 4.76 9.5 19.0 38.
µm µm µm mm mm mm mm mm 1
m
m
FINE
AGGREGA 0-10 5-20 15-34 30-70 60-95 90- 100 - -
TE 100
ZONE 1
(3) TESTS
Samples of the chosen aggregates shall be delivered to site and prepared by the
Contractor at his own expense. Methods of testing shall be in accordance with Clause
2003 (3) of these specifications. Samples of each aggregate are to be submitted by the
Contractor to a testing authority approved by the Engineer or his Representative. The
Contractor shall obtain from the Engineer or his Representative written approval of the
tests and types of aggregate chosen, together with the proposed arrangement for use
71
on the works.
WATER 3003.
The Water to be used for concrete manufacture shall be clean water free from
chemical or organic impurities and dissolved salt solutions, which may have a harmful
effect on the concrete. The Ph value shall range from 6.8 - 7.5. Periodic test on water
used for concrete should be carried out on site in accordance with B.S. 3148.
(I) Plain hard-drawn steel wire complying with the requirements of B.S.2691,
"Steel for prestressed concrete, Part 1 Plain hard drawn steel wire".
(III) High tensile steel bars of open hearth steel with sulphur and phosphorus
contents each below 0.05 per cent.
Bars whether plain or deformed should have a tensile strength of not less
than 926 N/mm2 with a 0.2 per cent proof stress of not less than 75 per
cent or more than 92 per cent of the actual ultimate strength. For
methods of testing see B.S. 18, "Tensile testing of metals".
(IV) Such other wires, strand, or bars having properties not inferior to those
laid down in B.S. 2691 or Sub Clause (III) above respectively.
Seven wire steel strand for prestressed concrete shall comply with B.S. 3617.
72
(1) It shall contain no welds
(2) It shall be at least low relaxation strands complying with Section 3 of B.S.
3617.
MINIMUM
NOMINAL BREAKING ELONGATION
PRSTRESSED
DIAMETER LOAD KN TO FRACTURE REMARKS
STEEL IN GAUGE
mm (1000kgf)
LENGTH
Wire 7 65 (6.63) to 69(7.038) 6% Tensile Testing is
to be carried out
35 (3.57) to 38(3.876) as per
5 6%
25 (2.55)
4 6%
Strands 8 67 (6.834) 10% BS 5896
Mechanical
10 94 (9.588) 10% Testing of Steel
Wires.
13 160 (16.320) 10%
22 480 (48.960) 10%
Bars 25 650 (66.30) 12% Additional
Mechanical
28 800 (81.60) 12% Properties which
are not specified
in this Table shall
be subject to the
approval of the
Engineer.
All bars in any individual member shall be of the same grade. When bars are to
be extended by use of couplers, the assembled units shall have a tensile strength, of not
less than manufacturer's minimum guaranteed ultimate tensile strength, when tested in
accordance with Test Method No. California 641, or equal. Failure of any sample to
meet this requirement will cause for rejection of the heap of bars and lot of couplers.
The location of couplers in the member shall be subject to approval by the Engineer.
(V) The Engineer may permit the use of prestressing steel manufactured to
standards equivalent to those mentioned above provided that minimum
strength requirements are complied with, as indicated in this
specification.
(2) CERTIFICATES
73
furnished by the Contractor and given to the Engineer or his Representative for each
consignment of prestressing steel reinforcement. These certificates must be submitted
to and approved by the Engineer or his Representative before the prestressing steel
reinforcement is used in the works.
(3) DELIVERY
All prestressing steel shall be protected against physical damage and rust or
other exposures that will result to corrosion at all times from manufacture, to grouting
or encasing in concrete. Prestressing steel that has sustained physical damage at any
time shall be rejected. The development of visible rust or other results of corrosion shall
be cause for rejection, when ordered by the Engineer.
The shipping package and the form shall be clearly marked with a statement that
"PACKAGE CONTAINS HIGH-STENGTH PRESTRESSING STELL, PLEASE HANDLE WITH
CARE." The type, kind and amount of corrosion inhibitor used, including the date when
placed, safety orders and instructions for use shall be indicated.
(4) STORAGE
Coils and bundles of prestressing steel shall be stored flat on a floor raised off
the ground and under full cover from the weather. They shall be protected from
damage, oil, corrosion or any deleterious matter, and shall not be opened until required.
Before being manufactured into prestressing cables, the wire shall be cleaned free from
loose rust and any deleterious matter, and inspected by the Engineer's Representative
for approval. Prestressing steel reinforcement which shows signs of pitting or has any
surface defects such as splits, roughness or necking is not to be used, and any lengths
of wire or strand so affected are to be cut out of the coil and rejected.
(5) TESTS
74
SHEATHING 3006.
After installation of the forms, the ends of sheathings shall at all times be
covered as necessary to prevent the entry of water or debris.
The Contractor shall demonstrate to the satisfaction of the Engineer that the
sheathings are free of water and debris immediately prior to installation of the steel.
All sheathing for continuous structures, shall be vented over each intermediate
support, and at additional locations as shown on the drawings. Vents shall be 12.5mm
minimum diameter standard pipe. Connections to sheathings shall be made with metallic
structural fasteners. The vents shall be mortar tight, taped as necessary, and shall
provide means for injection of grout throughout the vents and for sealing the vents.
Ends of vents shall be removed 25mm below the roadway surface after grouting has
been completed. Grout vents shall be provided at crests and valleys in the duct profile
and at intervals of not more than 15 metres in straight ducts.
All sheathings for continuous structures, except sheathings in bent or pier caps,
shall consist of rigid galvanized ferrous metal. Transition couplings connecting the rigid
sheathings to anchoring devices need not be galvanized. At the Contractor's option,
such rigid sheathings may be used in simple spans prestressed members. Rigid
sheathings may be fabricated with either welded or interlocked seams. Galvanizing of
the welded seam will not be required.
Rigid sheathings shall have sufficient strength to maintain their correct alignment
during placing of concrete. Joints between sections of rigid sheathings shall be positive
metallic connections, which do not result in angle changes at the joints. Waterproof
tape shall be used at the connections.
Corrugated sheathing is to be stored on site under cover from the weather, and
shall be protected from rusting, damage, oil or any other deleterious matter and shall be
clean and free from all such matter before being used in the works.
PART B - WORKMANSHIP
75
CONCRETE PROPORTIONS 3007. (1) PRELIMINARY TESTS
(2) PROPORTIONS
(3) PROCEDURE
The results of these preliminary tests shall give cube strengths of not less than
10% more than those stated in Table II-3 Clause 2009 in the case of cubes made under
laboratory and at least the values stated in Table II-3 Clause 2009 in the case of cubes
made under site conditions.
All cubes shall be 150mm x 150mm x 150mm and made in standard steel moulds
according to the procedures described in B.S. 1881 and shall be vibrated. As a result of
these tests, the mix proportions for the prestressed concrete work shall be chosen and
approved by the Engineer. Thereafter these proportions shall be adhered to throughout
the works and may be varied only on instructions given by the Engineer's
Representative.
The Water Cement Ratio shall be chosen from the laboratory tests, and shall be
taken as the total weight of water added to the mix using completely dry aggregates,
divided by the total weight of cement. The amount of water to be added to each batch
of concrete under site conditions, shall be calculated from the results of moisture tests
on the aggregates and the weight of cement used for each batch, using the same total
water cement ratio as used in the laboratory tests. No deviation from this water cement
ratio shall be made except with written approval of the Engineer's Representative. Strict
76
adherence to established water cement ratio can be maintained during the manufacture
and placing of concrete by using slump value established during mix design exercise.
The Contractor is to provide the following apparatus on site for the testing of
aggregates and concrete mixes which, where applicable, shall comply with the
requirements of B.S. 1881 and 812.
12. Apparatus for testing contents of silt, clay, organic impurities in fine aggregates.
Size
mm
25
12.5
10
5
Цm
2.8 Цm
1.25 Цm
77
600 Цm
300 Цm
150 Цm
15. Complete apparatus for gamma-ray inspection of grout in ducts for pre
stressing tendons.
17. Load cell for directly reading tension in prestressing tendons during stressing.
All the equipment listed as above shall be supplied and maintained in perfect
condition by the Contractor at his own expense for the duration of the works. After
completion of the works all equipment shall remain the property of the Contractor.
From these results the weights of wet aggregates and water to be used in mixing
shall be calculated for the chosen quantity of cement to be used for each mix, using the
dry weights proportions determined from the preliminary concrete mix design.
During the casting of each beam strict control shall be maintained at the mixer to
ensure that the correct weights of materials are consistently used for each mix of
concrete. The workability of the concrete shall be frequently checked using the
compacting factor test so that the consistency of the concrete is kept uniform. Mixes
which show large variation from the workability aimed at, due to varying aggregate
conditions or errors in batching, will be rejected and the necessary corrections are to be
made to the mix immediately after this is observed. Stockpiles of aggregates at the
mixer must always be maintained so that no fresh aggregates are fed in while casting of
the beam is taking place. The mixer and adjacent aggregate stockpiles shall be placed
under temporary roofing so as to be fully protected from the direct rays of the sun and
rain. Where compacting factor test apparatus is not available, slump test may be used
to control the consistency of the concrete being produced and placed.
78
(1) VIBRATION
When a design mix has been approved by the Engineer's Representative, the
Contractor is to allow for a preliminary casting of a short length of beam complete with
prestressing cables and reinforcement, using the proposed methods of vibration for the
whole works.
(3) CASTING
CURING 3011.
Curing of the prestressed components shall ensure a slow heat evolution in the
concrete so that shrinkage cracks may be avoided.
The prestressed components shall then be cured in air for a further period of
seven days or enough time to achieve the necessary strength before being erected into
position on the bridge.
FORMWORK 3012.
Formwork shall be of purpose made steel moulds or plywood panels, and shall
be rigidly fastened together so that no displacement can take place during casting.
Formwork shall be designed so that it can be removed without shock or damage to
concrete, and must be braced and held in position so as to avoid any holes or fastenings
through the prestressed component.
Moulds shall be of such a nature as not to allow the concrete member to deform
when the prestress is applied. The bottom portions of the moulds shall be prevented
from adhering to the concrete.
79
Subject to the approval of the Engineer's Representative, stripping of side
formwork may take place 24 hours after casting or as soon as is convenient after the
concrete has reached its final set. Stripping of bottom formwork shall not be carried out
until after transfer of prestress to the prestressed component.
TOLERANCE 3014.
The tolerance for lack of straightness on plan or variation in camber shall also be
of the same order as shown above for the respective lengths of the components.
PRESTRESSING 3015.
(1) GENERAL
80
In order that any applied force may be maintained after the tensioned tendons
have been anchored, an allowance must be made in assessing the value of the applied
force for loss of stress due to the yield in the anchorages and for slip when the tendon is
wedged after tensioning. At transfer of the prestress, the concrete shall have the cube
strengths as shown on the drawings, or as specified. These requirements shall be
ascertained from works tests on three cubes manufactured and cured under the same
conditions as the concrete member.
Sufficient cubes shall be made so that if the stipulated strength is not achieved,
further cubes will be available for such additional testing as may be required.
At transfer of prestress, the measured deflection of the beam shall not exceed
the limits given on the drawings, or as specified.
(I) The system of prestressing and the magnitude of the post tension in a
structural component shall be as shown on the drawings.
(III) SHEATHING
81
(V) PLACING OF ANCHORAGES
All anchorage devices for post-tensioning shall hold the prestressing steel
at a load producing a stress of not less than 95 percent of the guarantee
minimum tensile strength of the prestressing steel, when tested in
accordance with Test Method No. California 641 or equal.
When headed wires are used, the outside edge of any hole for
prestressing wire through a stressing washer or through an unthreaded
bearing ring or plate shall not be less than 5mm from the roof of the
thread of the washer or from the edge of the ring or plate.
The load from the anchoring device shall be distributed to the concrete
by means of approved devices that will effectively distribute the load to
the concrete.
(VII) JOINTS
82
provided and steps taken to ensure that the jointing material does not
enter the duct or press against the prestressing steel. The holes for the
prestressing steel shall be accurately made and meet one another in true
alignment at the ends and shall permit unobstructed passage of the
grout.
The stressing operation shall not take place until the filling material in the
joint has attained a strength equal to at least 1½ times the stress at
transfer of prestress. The time lag is to be established during design
process.
(VIII) TENSIONING
(2) Tensioning shall be carried out with the approved type of jacks.
(9) The prestressing force should be applied from one or both ends as
83
specified on the drawings.
(10) Each wire, pair of wires, cables, strand, or bar shall be attached in
such a manner as to ensure that the elongation is uniform
throughout its length. Should any tensioned steel or anchorage
break or be damaged, it should be replaced if so ordered.
Throughout all tensioning operations a spare jack capable of
maintaining the designated load should be available.
(12) Immediately before tensioning, the Contractor shall prove that all
tendons are free to move between jacking points and that
members are free to accommodate the horizontal and vertical
movements due to the application of prestress.
(13) The Contractor shall establish the datum point for measuring
extension and jack pressure to the satisfaction of the Engineer.
(14) The tendons shall be stressed at a gradual and steady rate until
they attain the force described in the Contract.
(15) The Contractor shall keep full record of all measured tensioning
operations, including the extensions, pressure gauge or load cell
readings and the amount of pull in at each anchorage. Copies of
records shall be supplied to the Engineer within 24 hours of each
tensioning operation.
(IX) GROUTING
(1) After tendons have been tensioned and anchored they shall be
grouted up solid throughout. Suitable outlet with plugs being
provided to prevent air locks unless otherwise specified. Grouting
trials shall be undertaken when required by the Engineer.
(2) Grout shall be either a neat cement grout with a water cement
ratio not exceeding 0.4 or cement mortar (1:1 by weight). An
expanding plasticizing admixture should be used. All ducts and
holes shall be thoroughly washed out with water, immediately
84
before grouting and after the stressing operation has been
completed. Grouting is to be carried out continuously, the
discharge from consecutive air holes being observed throughout.
The mixer shall be thoroughly cleaned before grouting is
commenced. A complete spare grouting plant for immediate use
in case of emergency or breakdown of the equipment operation
shall be available.
(3) Care shall be taken to avoid lumps in the cement, and sieving
shall be carried out before mixing the grout. It is essential to mix
up a quantity of grout sufficient for a particular duct immediately
prior to its injection and to use only this batch on the duct.
(8) The pressure gauges shall be calibrated before they are first used
in the works and thereafter as required by the Engineer. All
85
equipment shall be thoroughly washed with clean water at least
every 3 hours during the grouting operations and at the end of
use for each day.
After grouting, the ends of the anchorages and any protecting ends of cut
off tendons shall be covered over by a 1:1 mix mortar packed hard into the recesses on
the beam.
(2) PRE-TENSIONING
(I) GENERAL
(II) JOINTING
Joints between precast concrete units are to be made in accordance with the
drawings or instructions from the Engineer's Representative. They shall consist of dry or
wet joints. In the case of dry joints they shall be filled with dry concrete quality 50
N/mm² which shall be mechanically rammed into position and in the case of wet joints
they shall be filled with wet concrete quality 50 N/mm² and fully vibrated into position.
In both cases joints shall be finished flush with, the pre-cast concrete faces. During
jointing, protection and continuation shall be given to the transverse cable holes, using a
method to be approved by the Engineer's Representative.
86
(III) TRANSVERSE CABLES
Where grooves are provided in which tendons have been placed, they shall be
cleaned before the mortar is inserted.
Mortar shall consist of one part by weight of cement to three parts of sand with
a water cement ratio not exceeding 0.4 and shall be thoroughly compacted in the
grooves, preferably by the use of vibrators, and subsequently cured.
Any tension and retensioning procedure when allowed for offsetting losses shall
be strictly in accordance with the instructions of the Engineer's Representative.
The procedure to be adopted for all operations, using large diameter single
strands used as prestressing tendon shall be specially approved by the Engineer.
87
LIFTING AND HANDLING 3017
The Contractor shall furnish the Engineer's Representative with full details of the
proposed method of transporting and erecting, prestressed beam for his approval,
before commencing this work. Should any cracking or other damage to components
during transport or erection render the components unfit for use the Contractor shall
replace the same at his own expense.
The method of lifting and handling prestressed beams is to ensure that the design dead
weight bending moment is not exceeded at any point in the beam throughout the whole
operation. Lifting from casting beds shall not take place until grouting is completed and
at least 24 hours old. Erection of the beams on to the bridge spans shall not take place
until the concrete has attained a cube strength as specified on the respective drawings.
The lifting of the beams shall be made using temporary lifting devices provided by the
Contractor to the Engineer's Representative's approval. Initial lifting from casting beds
and final lowering on to bearings shall be carried out using hand operated chain blocks
so as to avoid sudden shock in the beam.
(2) STORAGE
The contract lump sum price paid for prestressing precast members shall include
full compensation for furnishing all labour, materials, tools, equipment and incidentals
and for placing and tensioning the prestressing steel in precast concrete structures,
complete in place, as shown on the drawings, as specified in these and the special
provisions and as directed by the Engineer.
88
Full compensation for furnishing and placing additional deformed bar reinforcing
steel required by the particular system used, ducts, anchoring devices, distribution
plates or assemblies and incidental parts, for furnishing samples for testing, working
drawings and microfilms, and for pressure grouting ducts shall be considered as
included in the Contract Lump Sum Price paid for in prestressing cast-in-place concrete
or in the contract price for furnishing precast members, and no additional compensation
will be allowed therefore.
(CLAUSES 3019 - 3999 INCLUSIVE NOT USED)
SPECIFICATION
SECTION IV - PILING
89
SECTION IV – PILING 桩
GENERAL 4000.
In addition to any other relevant clause of this specification, the following shall
be deemed to apply in particular to piling works, and shall be read in conjunction with
all other relevant Clauses of the Conditions of Contract and this Specification.
(I) Type "A": Precast reinforced concrete bearing and sheet piles.
(II) Type "B": Cast-in-place reinforced concrete bearing piles formed driving a
steel shell which is filled with concrete and left in place.
(III) Type "C": Cast-in-place reinforced concrete bearing piles formed by driving a
steel pipe casing, inserting a permanent steel shell, filling it with
concrete and then withdrawing the driving casing.
(IV) Type "D": Cast-in-place reinforced concrete bearing piles formed by driving a
heavy steel pipe casing, filling the casing with concrete and
withdrawing the casing during or after concreting.
(V) Type "E": Prestressed concrete cylinder bearing piles driven in.
(VI) Type "F": Prestressed concrete cylinder bearing piles bored in.
(VII) Type "G": Steel sheet piles.
The Contractor shall submit to the Engineer for his approval, details of all the
types of piles intended for use in the works. These details shall comprise complete
detailed drawings and specifications, a comprehensive list of the equipment to be used
and a full description of the methods to the employed.
90
Should the Contractor elect to carry out the pile drive or boring from his own
resources he will be required to satisfy the Engineer that the personnel he intends to
employ in the operation have had sufficient experience in similar installations under like
sub-surface conditions.
SUB-CONTRACTOR 4004.
Should the Contractor elect to employ a Sub-Contractor for the piling, he shall
satisfy the Engineer that the Sub-Contractor is sufficiently experienced in similar
operations under like sub-surface conditions.
In addition to the particular requirements of this part of the specification, all the
relevant clauses of the specification shall apply to the manufacture of reinforced or
prestressed concrete piles.
CEMENT 4006.
The Contractor shall be responsible for the correct location of all piles and the
establishment of all lines and levels.
ALIGNMENT 4008.
Piles shall be driven with a drop hammer or with a single acting steam hammer. The
91
weight of the hammer and the drop to be used shall be subject to the approval of the
Engineer and shall conform to the recommendations of CP 2004 and will depend on the
type of pile to be used. In general the energy per blow will be of the order as follows:-
(I) For piles types "A", "B", "C" and "D" - at least 26,500 Joules or 35,000 Joules
depending upon cross-sectional dimensions of the piles, the lighter hammer
being used up to 300mm diameter piles and the heavier from 300mm diameter
to 400mm diameter.
(II) For piles of type "E" at least 54,300 Joules with a ram weight of not less than
6,800 Kg.
Double Acting steam hammers may be used when driving piles to refusal but
shall not be used for other piles except with specific permission of the Engineer.
Suitable anvils or cushions, depending on the type of the pile, shall be used to
prevent damage to the pile butts.
Unless otherwise specified or directed driving shall be done using fixed leads
which will hold the pile firmly in position in axial alignment with the hammer.
Raking piles shall be held in position during driving right down to the level at
which the piles enter reasonably solid ground and to the satisfaction of the Engineer's
Representative.
When the driving of any pile commences it shall be continued without cessation
for any avoidable cause until the pile has been driven to the required set or level as
directed by the Engineer's Representative. Where levels or sets are indicated on the
drawings these may be varied, at the Engineer's discretion, in accordance with the
results of test piles driven in representative areas.
JETTING 4014.
Where water or air jetting is contemplated to assist the driving of the piles, the
permission of the Engineer must be obtained. The jetting shall be carried out in a
manner to the satisfaction of the Engineer's Representative and must be discontinued
92
when the toe of the pile is 3 metres short of the estimated final depth of penetration.
Driving shall be completed by hammer only, without jetting, to the required set or as
indicated by the Engineer's Representative. Where it is intended to employ water or air
jetting to assist the driving of a number of piles in a group, the jetting of piles in the
group must be completed before the driving of any pile to its final penetration is
commenced.
All piles shall be driven to the specified final set in the presence of Engineer's
Representative.
A record of the driving of each pile shall be kept in the form of the "Daily Pile
Driving Record" as set out in the British Standard Code of Practice No. 8004. Four copies
of each of these records shall be forwarded to the Engineer's Representative for his
retention.
Observations and measurements shall be made in the field during the process of
driving piles, by any suitable method satisfactory to both the Contractor and the
Engineer to determine whether a driven pile has been lifted from its original seat during
the operation of driving adjacent piles. The Contractor shall provide the necessary tools
such as tell tale pipes and instruments, to make these measurements. Such
measurements shall be properly corrected for any temperature variations that might
exist in the case of the pile shell or instrumentation.
Broken or shattered piles will not be accepted. Should any pile be damaged
by over driving or not conform to the tolerances of the specification, an extra pile or
piles shall be driven in its place, at the Contractor's expense unless in the opinion of the
Engineer the pile is out of place or plumb as the result of an underground obstruction.
Piles rejected after driving may remain in the ground at the descretion of the
Engineer, in case of shell piles the shell shall be filled with concrete, and be cut off as
directed. When rejected piling is withdrawn, the space, if another pile is not driving into
it, shall be filled solid with gravel or broken stone without payment thereof.
OBSTRUCTIONS 4018.
93
the location shown and to the proper bearing strata, the Contractor shall resort to all
usual methods to install the pile or steel pipes as required, including spudding, jetting,
or other feasible means. If, in the judgement of the Engineer, the Contractor is unable
to complete the pile driving properly by resorting to such methods, the Engineer may
order an additional pile or piles driven for which the Contractor will be paid in
accordance with the tendered rates. Piles abandoned because of obstructions
encountered before reaching the accepted bearing strata shall be left in position or
shells filled with concrete and be paid for as a complete pile for the length driven.
The tops of piles shall be cut off true and level at the elevations indicated on the
drawings, all to the satisfaction of the Engineer's Representative. All portions which are
battered, split, wrapped or buckled, or damaged or imperfect in any way shall be
removed.
Shells and casings shall have sufficient excess length to allow the complete
removal of working tops.
The method of boring steel casing or pipes into the ground shall be subject to
the approval of the Engineer.
PAYMENT 4021.
Payment for piling shall be made as detailed hereunder in the parts of this
section of the specification dealing with the particular types of piles.
GENERAL 4030
(i) Test piles shall be driven or bored as appropriate and loaded in the manner
detailed hereunder in the numbers and locations indicated on the drawings
and/or in the contract documents and/or as directed by the Engineer.
(ii) Unless otherwise directed the test piles shall remain as working piles
under the completed foundations.
(iii) Test piles shall be driven or bored using the equipment and methods
94
approved by the Engineer for the remaining working piles.
(iv) Before any load test is made, the proposed apparatus, structure and
method to be used, in making the load test, shall be approved by the
Engineer. All load tests shall be made under the supervision of the
Engineer's Representative.
The results of all piles loading tests shall be set out in a report the form of which
shall be as directed by the Engineer. This report shall include a description of the pile
and its driving record; type and size of hammer used, a tabulation of the load time,
settlement and rebound data; and remarks concerning unusual circumstances during the
driving or boring or loading of the pile and any other information which the Engineer or
his Representative may require.
The following procedure shall be adopted for the testing of piles referred to
above as types "A", "B", "C" and "D"
(i) Piles shall be load tested to twice the design load with the test load applied in
seven increments equal to 0.5, 0.75, 1.0, 1.25, 1.5, 1.75 and 2.0 times the
design load with a minimum of two hours between the addition of load
increments. Increments shall not be added until the rate of settlement is less
than .25mm per hour, or if each increment thereafter for the test load shall
remain in place until there is no settlement in a 2 hr. period.
(ii) If the full test load can be applied without failure of the pile, this load shall
remain on the pile for 48 hours, after which the test load shall be removed in
four equal decrements with a minimum of one hour between decrements.
(iii) Readings of settlements and rebounds shall be made with a minimum of two
dial gauges mounted on an independent framework and positioned on opposite
corners of the test plate. Readings shall be recorded to the nearest 250 μm and
shall be made every 30 minutes during the loading cycle and every hour during
the application of the full test load. Readings of rebound shall be made before
and after each decrement and 24 hours after entire load has been removed.
(iv) The load test shall be considered satisfactory provided that the net settlement
(after rebound) does not exceed 10% of the pile diameter.
(v) Piles to be load tested will be contract piles driven in their proper location.
During the load testing of piles, the driving of contract piles may be continued at
the Contractor's option provided the testing process is not affected by the pile
95
driving. Should the results of the load test indicate that longer piles are
necessary, the Contractor will be required to further drive piles driven during the
load testing operation without additional cost to the owner except for the added
pile length. Piles driven during the testing operation shall not be filled with
concrete until the required length and/or resistance has been determined by load
test.
The following procedure shall be adopted for the piles referred to above as types
"E" and "F":-
The information obtained from the driving of the test piles shall be applied to a
suitable dynamic pile formula or formulae. The formula or formulae to be employed shall
be as selected by the Engineer. The results of this application or these applications shall
be considered in conjunction with the results obtained from the loading test and lengths
of the remaining piles in a particular area or group shall then be agreed between the
Contractor and the Engineer.
Payment for the fabrication and driving or boring of the test piles shall be made
at the tendered rates and prices for working piles of the same type entered in the bills
96
of quantities.
Payment for the pile load tests shall be made at the unit price quoted for load
test on the particular type of pile in the bills of quantities, except where the Contractor
should have made any kind of guarantee as to safe bearing capacity of any particular
type of pile in any location, payment for load test shall only be made for tests which are,
in the opinion of the Engineer, successful.
The price by the Contractor for the carrying out of a load test shall be deemed to
be inclusive of all the cost involved in the carrying out of the load test and also of the
cost of obtaining the stipulated information during the driving of the test pile.
GENERAL 4050.
The piles shall be manufactured at the site of the work in which they are to be
used and in an area entirely free from the harmful effects of shock and vibration. They
shall be cast in lengths as determined by test.
The moulds shall be so supported that the pile is not distorted during or after
casting and shall be such as to ensure that the resulting pile is straight and true on each
face. The sides of the moulds shall be capable of being removed without shock or
jarring of the pile. Shoes, reinforcement, links, toggle hole tubes and all other fittings
shall be fixed accurately in the positions shown on the drawings. Shoes shall be of the
type shown on the drawings and of approved manufacture. They shall weigh not less
than as shown on the drawing, and shall have chilled hardened cast iron bases and mild
steel straps cast in, i.e. The straps shall run continuously through the cast iron bases.
All castings shall be of clean, grey, tough metal, free from sand, honeycombing, porous
places, air holes or other defects and shall be delivered to the site without being
painted, stopped or plugged in any part, otherwise they will be rejected. Shoes shall be
fixed accurately to the piles with the points truly on the longitudinal axis and the lower
ends of the reinforcing bars shall bear on the top of the shoe. Forks for retaining the
longitudinal reinforcing bars in position shall be of cast iron or pressed steel and of
approved shape and length.
Each pile shall be poured in one continuos operation. During concreting and
97
subsequently, the pile shall be protected from the effects of sun, wind and rain by
covering with screens of clean, damp sacks or hessian, care being taken to prevent
contact with the wet concrete until it has hardened sufficiently to prevent marking.
When so hardened, the concrete and moulds shall be intimately and completely covered
with the damp sacks or hessian and these shall be kept in a continuously wet condition
for a period of not less than 10 days after casting.
The sides of the moulds shall not be removed before two days after casting and
the piles shall not be disturbed on the bottom boards for at least 10 days after casting.
The piles shall be removed from the bottom boards only by canting sideways and shall
be rolled carefully to the stacking ground for final curing. The runners and other
supporters upon which the piles are canted and rolled shall not be more than 2 metres
apart and shall be perfectly level one with the other so that during the operations of
canting and rolling each pile shall be fully supported at each interval of 2 metres along
its length. Each pile shall have the date of manufacture painted on one side and this
date shall determine the sequence in which the piles are driven. The piles must on no
account be lifted at this stage and, until ready for driving, must be adequately supported
at each 2 metres interval throughout their length. The Contractor shall keep the piles in
a continuously wet condition until a period of at least 14 days has elapsed since
manufacture.
Otherwise than as aforesaid, the piles shall not be handled, lifted, slung, pitched
or driven before 6 weeks after manufacture and then shall be slung only from the toggle
holes provided in the positions shown on the drawings or as approved by the Engineers
Representative.
Should the Contractor wish to use rapid hardening cement he shall first obtain
the approval of the Engineer's Representative. Where approval has been given, and
rapid hardening cement used in the manufacture of the piles, the sides of the moulds
shall not be removed earlier than 2 days after casting, and the piles shall not be
disturbed on the bottom boards for at least 4 days after casting. Curing shall continue
for the full period of l4 days, and the piles shall not be driven before three weeks after
manufacture.
98
after it has been driven, the head of the pile shall be cut off to expose the reinforcement
for a length not less than 1.2 metres below the top of the steel reinforcement. The joint
shall be made by butting the lengthening bars to the pile bars with the addition of a
supplementary bar to every pile bar and of equal area. These supplementary bars shall
extend at least 1.2 metres on each side of the joint and shall be secured to both pile
and lengthening bars by No. 16 S.W.G. wire, links being provided as directed. The
extension shall be carried out vertically so as to form a true continuation of the pile. Butt
welding of reinforcement may be allowed by the Engineer's Representative and where
so allowed shall be carried out in strict compliance with the instructions of the Engineer's
Representative.
STRIPPING HEADS OF PILES 4054.
After the piles have been driven, the concrete shall be cut away from those
portions of the piles extending above a level of 75mm minimum above the bottom of the
pile cap, without damaging the reinforcement and leaving exposed a minimum length of
0.90m of the main bars. The binders, links, forks and toggle hole tubes within this
portion shall be removed and the main bar reinforcement shall be bent into the base of
the foundation as shown on the drawings.
Payment for precast reinforced concrete bearing and sheet piles shall be made
on the basis of the length of the pile per linear metre measured from the tip to the cut
off elevation at the tendered rates and prices entered in the bills of quantities for the
sheet piles particular type and dimensions of pile.
The tendered rates and prices shall be deemed to include for all materials,
equipment, labour and supervision involved in the completed pile driven and in place.
No payment shall be made for withdrawn or ejected piles.
ln addition to any other requirements of any other parts of this section of the
specification the following requirements shall be complied with in respect of cast
place reinforced concrete piles of types "B" and "C".
These piles shall be formed by driving a shell to the required bearing, leaving the
shell permanently in place, and filling it with concrete. Shells shall have sufficient
strength and rigidity to permit their being driven and not to be distorted by soil pressure
or the driving of adjacent piles; they shall be sufficiently watertight to exclude water
during placing of concrete. No concrete is to be placed until all piles in a cluster have
been driven and approved.
99
CAST-IN-PLACE REINFORCED CONCRETE PILES TYPE “C” 4061.
These piles shall be placed by driving a heavy steel pipe casing with an interior core or
point to the required depth, removing the core and inserting a permanent steel shell,
filling it with concrete, and then withdrawing the driving casing. Shells shall have
sufficient strength and rigidity not to be distorted by soil pressure or the driving of
adjacent piles and they shall be sufficiently watertight to exclude water during placing of
concrete. Shells shall be cylindrical with a minimum diameter of 315mm.No driving
casing shall be withdrawn until all piles within 3 metres centre to centre, have
been driven.
Pile shells may be step tapered, cylindrical or a combination of such shapes and may be
plain or corrugated. Plain cylindrical shells and shells driven without an internal mandrel
shall have a minimum diameter of 325mm. and a minimum wall thickness of 8mm. with
steel meeting respective B.S. requirements. Piles driven with an internal mandrel shall
have a minimum top diameter of 255mm. and a minimum butt diameter of 355mm. For
the step taper portion of any pile, the maximum distance between changes of diameter
shall be 3.6 metres for shells driven with an internal mandrel, the Contractor shall
assume responsibility for providing shells of sufficient strength and thickness to
withstand proper driving without injury, to obtain proper penetration and to resist
harmful distortion and/or buckling due to soil pressure.
The lower end of each pile shell shall be closed by a butt steel plate or shoe
firmly welded to the shell.
EQUIPMENT 4062.
Pile driver leaders shall be of the rigid or fixed type to insure accurate alignment
of the pile and hammer during driving. The use of swinging leads will not be permitted.
The cushion block used shall be a one piece hardwood block with grain parallel
to the pile axis and enclosed in a close fitting steel housing, except that subject to the
approval of the Engineer, a cap block of other materials may be used providing the
hammer energy transmission characteristics of the proposed capblock are equal to or
greater than the wood capblock specified herein. The use of wood chips, small wood
blocks, rope or other material which permits excessive loss of hammer energy shall not
be permitted. The introduction of fresh capblock material just before or during the final
driving of the pile shall not be permitted.
Observation shall be made during driving to determine whether or not the soil
and/or water is rising inside the pile. If this occurs to such an extent that soil and/or
water is trapped in the pile under the follower, provision shall be made for the escape or
removal of such soil and/or water before driving is continued.
CONCRETE 4064.
100
No concrete shall be placed in any pile shell until the shell has been inspected
and found to be free of water, debris or other foreign matter.
Concrete for cast-in-situ piles shall have an ultimate compressive strength of not
less than 20 N/mm² at the end of 28 days and shall be composed of approved portland
sulphate resisting cement, clean sharp sand and gravel or crushed stone of maximum
25mm diameter. Care shall be taken to ensure that the concrete is thoroughly
compacted and that the minimum cover of 38mm to the main reinforcing bars is
maintained throughout.
After driven shells have been inspected and found satisfactory, approximately
0.03 cu.m. of 1:2 cement grout shall be deposited in each pile followed by concrete of
100 to 125mm slump deposited in the pile in a continuous operation through a funnel
hopper having a discharge opening not greater than 200mm. in diameter.
Concrete strength shall be determined from Standard Cube Test made from each
day's pour as specified for reinforced concrete.
Payment for Cast-In-Place Reinforced Concrete Piles of Types "B" and "C" shall
be made on the basis of the length of the pile per linear metre, from the tip to the cut-
off elevation at the tendered rates and prices entered in the Bill of Quantities for the
particular type and dimension of pile.
The tendered rates and prices shall be deemed to include for all materials,
equipment, labour and supervision involved in the complete pile driven and in place.
101
GENERAL 4070.
Cast-in-place reinforced concrete piles of type "D" are formed by the driving of a
heavy steel pipe casing closed at the lower end by a cast steel pointed shoe firmly fitted
to the casing so as to provide a watertight joint. Reinforcement steel is then placed
within the casing and concrete poured, the casing may be removed whilst the concrete
has being poured or may be removed after the concrete has been poured. Alternatively
the casing may be filled with the concrete aggregate mix and cement sand grout
injected after the casing has been removed.
Where this type of piling is proposed for the works, the Contractor shall submit,
in detail, his proposed method of carrying out the piling, to the Engineer for his
approval, and shall carry out the work strictly in accordance with the method as
approved by the Engineer.
Payment for cast-in-place reinforced concrete pile of type "D" shall be made on
the same basis as for piles of types "B" and "C" at the tendered rates and prices.
In addition to any other requirements of any other parts of this section of the
specification the following requirements shall be complied with in respect of prestressed
concrete cylinder piles of types "E" AND "F".
GENERAL 4080.
Prestressed concrete cylinder piles of type "E" shall have outside diameter and
minimum dimensions as indicated on the drawings or as approved by the Engineer.
Prestressing cables of the composition, number and type as indicated on the drawings
or approved by the Engineer, shall be uniformly placed in the wall of the piles.
MANUFACTURE 4081.
(I) All materials shall be as stated in the relevant parts of the specification.
(II) Metal forms shall be used and they must be well braced and stiffened
against deformations under pressure of the wet concrete. They shall have
102
smooth joints and inside surfaces accessible for adequate cleaning. The
portions of the form which form the end surfaces of the pile (or sections)
must be a true plane and perpendicular to the axis of the pile with the
following tolerances: Maximum allowable deviation for abutting end
surfaces 3mm, for head end surfaces, 13mm and for the point end 76mm
Forming tubes for the longitudinal holes for the prestressing cables shall
be 35mm nominal diameter and shall be positioned so that there will be a
minimum cover of 38mm to the outside finished surface of the pile, shall
be inside the spiral steel reinforcement and shall be uniformly spaced
around the pile circumference.
HANDLING 4082.
Piles shall not be handled or moved in any manner that would result in cracking
or permanent damage to the concrete or to the grout surrounding the wires.
EQUIPMENT 4083
Piles shall be driven with an approved hammer which shall develop a rated
energy per blow of not less than 54,300 Joules and which shall have a ram weight of
not less than 6,800 Kg. A solid hardwood cushion block, at least 150mm thick, shall be
used in the base of the hammer between the hammer ram and the follower. A
laminated ring
shaped cushion block at least 150mm thick made up of 25mm hardwood boards and cut
to fit the head of the pile, shall be used between the follower and the top of the pile.
Both cushion blocks shall be inspected periodically during driving and blocks that have
been unduly worn and compacted with use shall be replaced before driving is continued.
Piles may be driven without guides or leaders except that the hammer shall be
kept in accurate alignment with the axis of the pile.
Each pile or pile section shall have a cage of non prestressed reinforcing steel of
the size, dimension and arrangement shown on the contract drawings or as approved by
the Engineer. This reinforcing cage shall be securely held in position during the casting
and spinning of the concrete. The spiral steel reinforcement shall have a minimum
concrete cover of 25mm to the outside surface of the finished pile.
CONCRETE 4085.
Concrete used shall be not leaner than Grade 35 N/mm2 or as indicated on the
Contract drawings. The concrete mix shall be such as to give the most uniform possible
distribution of the aggregates across the wall of the pile. The fine and coarse
aggregates shall be as nearly as possible of the same specific gravity.
CASTING 4086.
103
Piles shall be centrifugally cast and shall be cast in convenient sections as
approved by the Engineer.
CURING 4087.
Piles or pile sections may initially be steam cured. After removal of forms,
membrane curing may be applied to all surfaces except abutting end surfaces and core
holes.
The Method of Handling piles or pile sections shall be such that no permanent
damage to the concrete will occur. If piles are made up of sections, any section which
has more than 10% of the end surfaces spalled to a depth of more than 3mm shall be
rejected.
In making up the full length pile, the abutting surface of each section shall be
covered by a sealing material of sufficient thickness to fill all voids (except at the cable
holes) when the sections are brought together under compression as later specified.
This sealing material must attain a minimum ultimate strength of at least equal to or
greater than that of the concrete and must be as resistant to exposure and weathering
as is the concrete. After the sealing material is applied, the pile sections shall be
brought into contact and held together by a force equivalent to not less than 0.79
N/mm2 on the gross concrete area while the sealing material sets. The individual
sections shall be lined up so that the maximum deviation in the alignment of the outside
surfaces of two adjacent sections at the joint will not exceed 6mm and the maximum
deviation in the alignment of the prestressing cable holes at the joint will not exceed
6mm
Piles shall not be stressed until the compressive strength of the concrete is at
least 30.0 N/mm2 after the prestressing cables have been threaded through the cable
holes to make up cables of the required number of wires; the cables shall be tensioned
to an average cable unit stress as indicated on the drawings or approved by the
Engineer. This tension shall be measured by the elongation of the wires and checked by
the jack pressure. The tension in the wire shall be transferred to mechanical end
locks or anchors. Aggregate stress losses through transfer of the stressing force from
the jack to temporary anchorage shall not exceed an average of 10% on one cable or an
average of 5% on all cables in any one pile.
104
All cables holes shall be grouted with a mixture of cement and water in such a
manner that the interstices are completely filled with the grout material. The cable
tension shall be maintained by the mechanical anchors while the holes are grouted and
until the grout attains sufficient strength to hold permanently the tension in the cables.
During this period, the piles shall not be moved or handled in any manner that would
result in permanent damage to the grout. The grout curing period must be sufficient to
permit the removal of the temporary anchors without slippage of the wires in the grout
except that the stress loss through transfer shall not exceed an average of 10% on one
cable or an average of 5% on all cables in any one pile. During removal of end anchors,
if the wires do not part under stress with a "Cup and Cone" fracture, but can be burned
completely through with a cutting torch, no slippage is considered to have occurred.
Piles shall not be driven until the concrete has attained the minimum strength as
specified on the drawings.
When the point of the pile is passing through soft soil so that there is little or no
resistance to penetration at the bottom of the pile, the stroke of the hammer shall be
reduced to approximately 600mm
Observation shall be made during driving to determine whether or not the soil
and/or water is rising inside the pile casing. If this occurs to such an extent that soil
and/or water is trapped in the pile under the follower, provision shall be made for the
escape or removal of such soil and or water before driving is continued.
PRE-EXCAVATION 4095.
The Contractor may use any combination of driving and drilling approved by the
Engineer to obtain the required pile embedment. Jetting or pre excavation shall be done
below the pile tip elevation and the final seating of the pile shall be done by driving only
for the last 3 metres.
TOLERANCE 4096.
Piles may be driven with the use of template or other method approved by the
Engineer. The top of each pile shall not vary more than 150mm from the required plan
location.
105
CUT-OFF 4097.
Where piles are required to be cut off, cuttings may be performed with
pneumatic tools, sawing, or other method approved by the Engineer. In no case shall
explosives be used for cutting off piles.
If pile tops are driven below the established cut off elevation, or if pile tops are
damaged below the cut off elevation, the pile shall be built up to the required elevation
using a cast-in-place concrete extension of the cylinder or by use of an acceptable
length of cylinder pile section. The pile splice shall consist of a poured plug or
reinforced concrete extending at least l.4 metres into the original pile and, where
possible, the same length into the added section as detailed on the drawings. This
concrete plug may be an extension of the plug connecting the pile to the cap.
PAYMENT 4100.
Payment for prestressed concrete cylinder piles of type "E" shall be made on the
same basis as for piles of types "D" or "C" at the tendered rates and prices.
In addition to any other requirements of any other parts of this section of the
specification the following requirements shall be complied with in respect of prestressed
concrete cylinder piles of the types "F"
GENERAL 4110.
Prestressed concrete cylinder piles of type "F" are formed by the forcing into the
ground of heavy steel casing and the removal of the earth from its inside. After the
casing has been installed to the required depth a precast prestressed concrete cylinder
pile is inserted into the casing either in sections and stressed insitu or as a complete
106
unit. The space between the steel casing and the prestressed concrete shall be grouted
with sand-cement grout as directed and approved by the Engineer.
Where prestressed concrete cylinder piles of Type "F" are proposed for use in the
works, the method of manufacture and construction shall be as approved by the
Engineer and the Contractor shall comply strictly with this approved method.
PAYMENT 4112.
The payment for prestressed concrete cylinder piles shall be made on the same
basis as for piles of type "E".
All steel sheet piles shall be of an inter locking section as shown on the drawing
and shall be a type and manufacture approved by the Engineer.
Steel sheet piles, tie rods, rivets, and bolts shall conform to the minimum
requirements of B.S. 4360, Parts 1 & 2 and B.S. 449. If cofferdams for foundation
construction are used, the steel sheet piling for the cofferdams shall be carried well
below the bottom of the footings and shall be well braced and as watertight as
practicable.
The interior dimensions of cofferdams shall provide sufficient clearance inside the
walls for constructing forms and driving pile and to permit pumping outside the forms.
107
When permitted by the Engineer, cross struts or bracing may extend through
foundation concrete. Such struts or bracing below low water will be permitted to remain
in place, or when specified in the special provisions or shown on the drawings, to be
removed. Struts or bracing above low water shall be removed and the resulting space
filled with concrete of the same mix as that specified for the surrounding concrete.
The Contractor shall submit to the Engineer, for approval, drawings showing his
proposed method of cofferdam construction and other details left open to his choice or
not fully shown on the drawings. The drawings shall be submitted at least two weeks in
advance of the time the Contractor begins construction of the cofferdams.
After completion of the substructure, the cofferdams with all sheeting and
bracing shall be removed at least to 1 metre below the level of the stream bed, by the
Contractor at his own expense, and such removal shall be performed in a manner that
will not disturb or mar the finished concrete or masonry.
Electrodes used for welding shall comply with B.S. 639 or B.S.693 depending on
the type employed.
Where directed on the drawings or in the specifications, steel sheet piles shall be
coated before driving with two coats of an approved bituminous paint, in a manner as
directed by the Engineer's Representative.
The piling shall be driven either singly or in pairs vertically and to true lines and
even planes in the position shown on the drawings and to the levels indicated thereon.
Should there be any defect in the horizontal or vertical alignment of the piling or should
a break, through any cause whatsoever, occur in the continuity of the piling, the
Contractor shall withdraw such defective pile or piles and drive such further piles as may
be necessary to remedy the defect. Should any distortion, fanning or creep occur in the
alignment of the piling the Contractor shall immediately take steps to rectify the defect
and shall, where necessary, supply and drive suitable tapered piles to the satisfaction of
the Engineer's Representative. All costs incurred by the Contractor in carrying out the
necessary remedial measures shall be at his own expense.
Should any tapered piling have to be manufactured locally they shall have along
the joint 22mm diameter rivets at 150mm pitch except for a length of 600mm 150mm at
each end the pitch shall be 75mm
All necessary holes for tie rods shall be neatly drilled and for drains they shall be
neatly burnt out, all in the positions shown on the drawings.
108
THE RODS AND ROPES 4124.
The steel sheet piling shall be connected to the anchor piles by mild steel tie
rods or ropes as approved by the Engineer. They shall be in lengths as indicated and
coupled together with forged steel coupling boxes or turnbuckles. Each end of each rod
shall be threaded for a distance of 230mm with standard whitworth right and left
handed threads as the case may be. Mild steel bearing plates and washers of approved
sizes shall be provided for the outer end of the tie rods, the washers being tapered. The
tie rods and ropes coupling boxes or turn buckles and other fittings shall be cleaned
with wire brush or other approved means to remove all millscale, rust, etc., and shall
then be given one coat of the bituminous solution and the tie rods and ropes shall, after
fixing in position, be wrapped in approved hessian and, with all fittings, be given a
second coat of the approved solution. Where possible the coupling boxes or turnbuckles
shall also be wrapped in hessian.
PAYMENT 4125.
The quantity of sheet piling to be paid for under this item in this section except
for cofferdams, will be the number of square metres of sheet piling placed in its final
position. The unit price bid for this item shall include the cost of furnishing all labour,
materials and equipment necessary to complete the work, including the cost of
furnishing and placing, if necessary removing, all wales and braces. No separate
payment will be made for providing cofferdams unless it is called for on the drawings.
When Cofferdams are called for on the drawings they shall be paid for at the
contract lump sum price bid for the item COFFERDAM in the proposal.
109
SPECIFICATION
SECTION V - BRIDGEWORKS
110
SECTION V - BRIDGE WORKS 桥梁工程
GENERAL 5000.
In addition to any other relevant clause of this specification, the following shall
be deemed to apply in particular to bridge works, and shall be read in conjunction with
all other relevant clauses of the conditions of contract and this specification.
GENERAL 5001.
The Contractor shall himself obtain full and accurate information in connection
with the existing structures, traffic, periods of flow and non-flow in the waterways,
normal water levels, whether above or below ground level, flows and frequencies,
floods, nature and condition of soils and sub-soils etc., And generally acquaint himself
with all factors influencing the construction and maintenance of the works as shown on
the drawings and specified herein, and shall be deemed to have allowed for all such
conditions in the rates inserted by him in the bill of quantities.
Where the use of temporary bridge spans is involved the Contractor shall submit
complete and detailed drawings and calculations for the scheme to the Engineer's
Representative. The Engineer's decision on whether such methods may be adopted or
not shall be absolutely final.
111
obligations and risks in regard to such works specified or implied in the contract and he
shall reinstate the same at his own cost should any mishap or accident occur causing
damage or injury thereto subject to such provisions of the conditions of contract as may
be applicable.
Payment for all such diversions including for temporary bridging or converting as
necessary shall be deemed to be included in the tendered rates and prices, unless
elsewhere expressly allowed for.
5003.
The site of the works shall be cleared completely to the satisfaction of the
Engineer's Representative. Generally, the waterway shall be cleared of all obstructions
to the flow of water. All fallen trees, bushes and accumulations of debris shall be
removed and deposited as directed. Trees which are to be retained shall be indicated
by the Engineer's Representative.
Such details of training works and protective works to the banks and protection
beds of waterways as may be shown on the contract drawings are schematic only.
Exact details of the training and protective works shall be supplied by the Engineer's
Representative after consideration of the final disposition of the works, local site
conditions etc.
Excavations shall be of the widths and lengths necessary for the construction of
the works and shall be taken down to the depths shown on the drawings. Or as
otherwise specified hereafter or to such other depths as the Engineer's Representative
may require. When the final level of the excavation has been reached, the Contractor
shall so inform the Engineer's Representative, and together they shall inspect, measure
and agree in writing all particulars on which measurements of the works are to be
based. No back filling or construction shall be undertaken until after the final levels and
dimensions of the excavation have been surveyed and agreed. Failing such surveys and
agreements being signed by the Contractor, the surveys of the Engineer's
Representative, shall be final and binding on the Contractor.
112
Contractor shall remove such damaged, softened or loosened materials and replace
them with concrete grade 10 N/mm² or as directed by the Engineer's Representative, at
the Contractor's own expense. Sumps dug in the bottom of excavations shall be cleaned
out, all soft and puddled material removed, and the hole made up with approved
material as described above. Should excavations be taken to a depth greater than that
required by the Engineer's Representative such extra depth shall be made up at the
Contractor,s expense with concrete grade 10 N/mm² or as directed by the Engineer's
Representative.
The Contractor shall not leave any item or temporary works in position in the
excavations after back-filling, without the permission of the Engineer's Representative.
Permission will only be given in cases where the Engineer's Representative is satisfied
that no adverse effect will result to the finished works. No payment shall be made to
the Contractor for any item of temporary works so left in position, unless such item was
left in on the explicit instructions of the Engineer's Representative.
Earth and other material taken from excavation shall be set aside for selection
for re-use as filling materials, and materials unsuitable for this purpose shall be disposed
of by the Contractor at his own expense, as directed by the Engineer's Representative.
50mm 100
25mm 60 - 100
1.1mm 20 - 100
500m 10 - 70
255m 8 - 40
75m 5 - 10
When tested for bearing capacity, selected material shall have a California Bearing Ratio
(CBR) of not less than 20% when compacted to 95% of maximum density, using BS
compactive effort up to a depth not more than 600mm to formation level; there after
compaction shall be 100% MDD of the material using BS effort.
113
not less than 1x 10-2mm/sec.
Before driving piles, the common embankment material shall be placed and
compacted to the top elevation of the prism of selective material.
No payment for placing of selective material will be made, but the cost thereof
shall be included in the price bid for the item "Excavation and Backfill" scheduled in the
proposal.
(B) ROCK
The term "solid rock" shall mean rock found in ledges or masses in its original
position, which would normally be removed by blasting and pneumatic tools or by
wedges and sledge hammers if removed by hand, and all solid boulders or detached
pieces of rock exceeding 0.2 Cubic metres in size trenches and 0.3 Cubic metres in size
in general excavations, to the classification of which the Engineer's Representative is
satisfied. Should any difference of opinion arise between the Contractor and the
Engineer's Representative as to whether any material is rock, the Engineer's decision
shall be final and shall be made before the material is disposed of or covered up. Should
the Contractor wish to use explosives for the excavation of rock, he must obtain the
permission of the Engineer's Representative. When permission is granted the Contractor
shall proceed as directed in, and satisfy all the requirements of, clause 99 of the
conditions of contract and clause 5010 of this specification.
Excavations for foundations shall be paid for on the actual quantities measured
on site by multiplying the horizontal area of the base of the foundations by the mean
depth from surface level, and at the appropriate rates for excavation inserted in the bill
of quantities. The rate shall include for all shoring, pumping, backfilling and
compactions, and for all pumping, digging, backfilling of sumps and for all other things
necessary to allow the proper placing of the foundations. No payment shall be made to
the Contractor for any item of temporary works left in position unless it has been left on
the instruction of the Engineer's Representative. No item of temporary works shall be
left in position without the approval of the Engineer's Representative.
Where excavations have to be made and foundations formed below water level,
suitable arrangements shall be made to exclude the water from the site, and the
Contractor shall, when tendering, submit a full and clear description, supported by
drawing and sketches, of the methods he proposed to use in respect of each foundation
where these conditions will be encountered. The methods proposed shall be directed in
all cases to permit the execution of the whole of the work in the dry unless this is shown
in the method statement to be entirely impracticable or uneconomical. The Contractor
must satisfy himself absolutely as to what water levels may be experienced at and
during the period of construction, whether such water levels be above ground level or
below and as to what flows and water levels will be attained during flood and high tide
114
periods and as to the condition of soils and subsoils and all other matters pertaining to
the adequacy of the temporary works and the efficient and proper construction of the
works themselves. The Contractor shall take all precautions to prevent flooding of the
works and shall make good any loss or damage to the temporary works and the works
themselves caused thereby at his own cost and to the satisfaction of the Engineer's
Representative.
If Contractor chooses to use steel cofferdams for the below water level
foundation excavations, the materials shall conform to SECTION IV, Clause 4120 "STEEL
SHEET PILES."
No separate payment for cofferdams will be made, but the payment shall
conform to the applicable portion of the SECTION IV, Clause 4125 "PAYMENT."
It is the intention that all concrete shall be placed in the dry, and the Contractor
shall direct all his efforts towards this end.
115
REMOVAL OF EXISTING STRUCTURE 5009.
Before any part of any existing structure is removed the Contractor shall forward
to the Engineer's Representative for approval, full details of the method by which he
proposes to dismantle the structure and provide an alternative way for traffic during the
subsequent works. (See also clauses 90 of the conditions of contract and 5002 of this
specification).
EXPLOSIVES 5010.
116
Should the Contractor wish to demolish any part of the existing structure by
using explosives, he must first satisfy the Engineer's Representative that this is the most
economical and satisfactory way of performing the work and obtain his permission to
proceed. The Contractor shall provide proper buildings or magazines in suitable positions
for the storage of the explosives in a manner and in quantities to be approved.
He shall also be responsible for the prevention of any un-authorized issue or improper
use of any explosive brought on to the works, and shall employ experienced and
responsible men by whom only shall explosives for the purpose of the works be handled,
all to the satisfaction of the Engineer's Representative and in conformity with the
statutory regulations. During blasting, the greatest care shall be taken by the Contractor
that no injury be done to persons or property or to any finished work or any work which
is to remain untouched. The shots shall be properly loaded and covered and only
moderate charges shall be used, and where directed by the Engineer's Representative,
the Contractor shall provide heavy mesh blasting nets. Blasting shall be restricted to
whatever hours the Engineer's Representative shall prescribe. If, in the opinion of the
Engineer's Representative, blasting would be dangerous to persons or adjacent
structures, or is being carried on in a reckless manner he may prohibit it, and order that
the demolition be carried out by other means see also clause 99 of the Conditions of
Contract.
Before dismantling any part of any structure which is to be re-used either wholly
or in part either by the Contractor in another part of the works or by the Engineer
elsewhere under another contract, the Contractor shall mark each part of the structure
with a distinguishing mark which shall be assigned to it in a marking plan to be prepared
by him, in figures or letters not less than 50 mm. high and in such a manner that the
pieces may be readily identified and put together again in their proper positions when
required. The figures and letters shall be painted on, in at least two places on each
member, and on a surface which has first been thoroughly cleaned and freed from all
rust, loose paint, grease, dirt and other deleterious coatings and given one coat of
protective paint. The colour of the paint to be used for the letters and figures shall be
such as to make them readily visible against the background of protective paint. Where
more than one bridge is to be marked in any contract, the Contractor shall ensure that
no combination of figures and letters employed in the marking of one bridge is repeated
in the marking of another. All markings shall be to the approval of the Engineer's
Representative and dismantling of the structure shall not be proceeded with until the
Engineer's Representative has checked and approved the marking on the structure and
117
compared them with those on the marking drawings and given his permission to
proceed. The drawings showing the markings shall conform to the requirements of
Clause 5020 hereinafter.
The Contractor shall forward to the Engineer's Representative one set of hand-
made negatives on best quality linen, one set of velograph negatives on best quality
linen and one set of prints on linen showing black lines on a white ground, of the
marking drawings and the cost of producing and supplying all these negatives and prints
shall be deemed to be included in the rates for dismantling.
Troughing, joists, trusses, trestle, piers, cylinders, etc., shall be dismantled with
great care. Temporary supports, horses, jacks, wedges, stiffening, bracing, etc., being
provided to ensure that there will be no overstraining or buckling of any member or
connection during the operation. Bolts and other fastenings shall be removed without
causing damage to or elongation of the holes from which they are withdrawn.
Where required for re-use by the Engineer under another contract the Contractor
shall, after dismantling and satisfying the requirements of clause 5009, scrape, clean
and free all parts of the dismantled structure from all loose paint, grease and other
deleterious coatings. Areas of rust should be cleaned down to the bare metal and all
thick edges, fins, blistering etc., due to previous coats of paint removed. The surfaces,
when thoroughly dry, shall be given one coat of protective paint, particular attention
being given to surfaces which have been in contact or inaccessible whilst the structure
was erected. Care shall be taken to ensure that the distinguishing marks are not
obliterated during this operation. Surfaces which have been galvanized shall be
examined by the Engineer's Representative who shall direct whether the whole is to be
cleaned thoroughly, freed from all deleterious matter and given one coat of protective
paint or whether only the bad spots are to be touched up with an approved proprietary
galvanizing commodity (aluminium paint is not to be used for this purpose). All bright
and machined surfaces shall be cleaned and well coated with a mixture of white lead
and tallow free from acid, or with other approved coating which will not readily melt
when exposed to the sun in the tropics. Exposed machined surfaces shall be further
protected by timber casings or other approved means. Free ends of members shall be
stiffened to prevent distortion during transit, and the ends of members with turned bolts
connections suitably protected. A full set of new bolts, nuts and washers, rivets and all
other fastenings should be supplied together with spares in accordance with clause 5066
of this specification, and in addition a complete set of erection tools (drifts spanner,
screw-drivers etc., but not riveting apparatus) in accordance with clause 5065 of this
specification. Turned bolts, nuts and washers shall be covered with a mixture of white
lead and tallow free from acid and black bolts, nuts and washers, and field rivets shall
be thoroughly cleaned, heated to about the melting temperature of lead and whilst hot
dipped into boiled linseed oil.
Straight bars and plates shall be bundled and temporarily bolted together. If this
is not possible they shall be bound in at least three places with annealed steel wire of
not less than 6mm diameter which must be tightly fastened. All rivets, bolts, nuts,
washers, screws small plates and small article generally shall be packed in bags. A
separate bag being used for each diameter and length of rivet, bolt etc., and each bag
118
having a metal label wired on indicating its contents. The bags shall be packed into
strong wooden cases or casks whose gross weight shall not exceed 300 kilograms. Each
case, cask etc., shall be clearly marked with its weight and an indication of its contents.
Bundles shall have a metal label, stamped with similar information, attached to each
end, the label being secured at each of the end by a separate wire so that it lies flat
with the bundles. All marking and labellings shall be to the satisfaction of the Engineer's
Representative.
All parts of the structure protected, marked and packed as above specified shall then be
stacked in a position indicated by the Engineer's Representative to await collection by
him and transport to his store, and all operations mentioned in this clause up to and
including this final stacking shall be deemed to be included in the rates for dismantling
the structure. Should the Engineer require the Contractor to transport the structure to
his store, the Contractor shall do so without delay and payment shall be made in
accordance with the rates in the day work schedule referred to in the bill of quantities
or as mutually agreed before transporting.
Where the structure is to be incorporated elsewhere into the works, either wholly
or in part, the Contractor shall proceed as follows. On the marking drawings specified
above, he shall indicate
(i) Those parts of the structure which are not required for incorporation into
the works and which will be stacked in readiness for transport to the
Engineer's store, and
(ii) Those parts of the structure which will be required for incorporation
elsewhere into the works.
Those parts covered by (i) shall be treated entirely as specified above for
structure required for incorporation elsewhere into the works.
Those parts covered by (ii) shall be treated entirely as specified above for
structures required by the Engineer for re-use under another contract, with the following
amendments. After dismantling, the required items shall be spread out and the
Contractor shall inform the Engineer's Representative that they are ready for inspection.
The Engineer's Representative shall then examine the items with respect to length,
quality weight and condition and shall pronounce upon their suitability for incorporation
into the works and shall advise the Contractor as to what cuts etc., should be made to
permit their proper fitting, and they shall together agree as to where such work shall be
carried out. The items shall then be transported to that part of the works unto which
they are to be incorporated and the Contractor shall then proceed as directed in clause
5071 of this specification. The cost of all operations involved in complying with these
requirements shall be deemed to be included in the rates for dismantling and re-
erection.
All paint and painting shall be in accordance with clause 5049 of this
specification.
119
REMOVAL OF EXISTING SUPER STRUCTURE AND SUBSTRUCTURE: ALL
TIMBER 5012.
Existing decks, trestles, mud sills, piles etc., in timber shall be removed as
carefully as possible. The use of explosives is forbidden. Timber piles shall be withdrawn
completely, or sawn off, as directed by the Engineer. All timber, fastenings etc.,
shall be cleaned and stacked neatly as directed in a place to be indicated by the
Engineer's Representative.
Unless particularly so mentioned in the drawings no distinguishing marks,making plans,
painting or protective coatings will be required.
The demolition of existing abutments, piers and landing will be permitted only
after the superstructure has been removed to the satisfaction of the Engineer's
Representative. The demolition shall be carefully carried out and the use of explosives
will be subject to the approval of the Engineer's Representative. Generally, abutments
and piers which are specified in the drawings to be completely removed, shall be
completely removed above the lowest level of the ground in contact with the abutments
or piers as approximately indicated in the drawings and in the bill of quantities, or as
directed by the Engineer's Representative, below this level only so much will be removed
as is required for the proper construction of the new abutments and piers. Reinforced
concrete piles shall be completely withdrawn or cut away above the levels stated in the
drawings or as directed by the Engineer's Representative.
Abutments, piers and landings which are required to be only partially demolished
in a manner which will ensure that no damage whatever will be caused to that portion
or the structure which will remain. The use of explosives for this work will not be
permitted. The demolitions shall be carried out to the lines and levels shown on the
drawings or to such lines and levels as the Engineer's Representative may determine
after examination of the material exposed. The surfaces remaining after demolition shall
be freed from all loose stones, rubble, mortar or other material and left in a perfectly
sound condition, to the satisfaction of the Engineer's Representative. Under no
circumstances shall any new work be constructed upon or against any part of the
structure that remains until the Engineer's Representative has inspected it and given his
permission to proceed.
All concrete and masonry rubble and all other such material resulting from
demolition shall be tipped as directed. No debris shall be allowed to block, interfere with
or hinder the flow of water under the new structure, or along any part of the
watercourse or through any drain, gully or water course, in the vicinity of the work, nor
shall any debris be allowed to obstruct the passage of traffic or cattle or other animals
120
along recognized paths. The rubble may be re-used as plums in the construction of the
new abutments and piers should these be of mass concrete, at the discretion of the
Engineer's Representatives.
After demolition operations have been completed the surfaces of the remaining portions
of the substructures which are to receive new concrete shall be thoroughly hacked and
freed from all loose plaster, mortar and other material and random stones shall be
removed in the case of masonry walls as directed by the Engineer's Representative to
provide an efficient key between the new work and the old. Immediately before
concreting begins, the surfaces shall be thoroughly washed with clean fresh water to
remove all deleterious matter, all surplus water being then removed. The wet
horizontal surfaces shall be covered with a 12mm layer of stiff, freshly mixed mortar
class M1 which shall be thoroughly worked into all interstices to ensure intimate contact
with the old structure and the fresh concrete shall be poured and carefully pounded into
it without delay. The fresh concrete shall be carefully worked into all corners, crevices
and interstices in the wet vertical surfaces to ensure complete bounding with the old
structure.
Where the drawings require a non-bonding joint or a gap to be left between the
surfaces of the remaining portions of the existing substructure and those of the new
work, the relevant surfaces of the existing structure shall be thoroughly cleaned and
freed from all loose material. Irregularities in the surfaces shall be filled in with concrete
Grade 10 N/mm² or the whole rendered with a minimum 12 mm thickness of plaster of
a grade to be approved by the Engineer's Representative, to give a smooth surface over
the whole area of the joint. The non-bonding joint shall then be constructed as directed
by the Engineer's Representative or a gap left as directed in the drawings.
The Engineer may instruct that a loading test be made on the works or any part
thereof if, in his opinion, such a test is deemed necessary for one or more of the
following reasons:-
(a) The site made concrete tests cubes failing to reach the specified strength,
121
(c) Overloading during construction of the works or part thereof,
If the loading test be instructed to be made solely or in part for the reason (a)
the test shall be made at the Contractor's own cost. If the test be instructed to be made
for one or more of the reasons (b) to (e) inclusive, the Contractor shall be reimbursed
for the cost of the test if the result thereof is satisfactory. If the test be instructed to be
made for the reason (f) the Contractor shall make the test and shall be reimbursed for
all costs relating thereto unless the result of the test is unsatisfactory in the opinion of
the Engineer.
The test load shall not be applied within eighty-four days of the completion of
placing of the concrete in the part of the structure to be tested, and the latter shall not
be supported during the test by the shuttering or other non-permanent support. Means
shall however be taken to ensure that in the event of failure under the test, temporary
support of the loaded members shall be immediately available. The test shall proceed
strictly as directed by the Engineer.
If the result of the loading test is not satisfactory in the opinion of the Engineer,
the Engineer shall instruct that part of the works be taken down or cut out and
reconstructed to comply with this specification, or that other remedial measures be
taken to make the work secure.
All remedial measures shall be carried out expeditiously by the Contractor at his
own expense.
The test load to be applied shall be a series of tractors, lorries, or road rollers
equivalent to the 1.10 times the design load of the particular structure, disposed of in
one or more arrangement so that the maximum bending moments, thrusts, tensions and
shear forces due to the test load are produced at the critical sections. During the test a
record of the sequence of all cracks and deflections at mid-span will be kept together
with any other observations which the Engineer may elect to record. The residual
deflection if any shall be recorded and if required by the Engineer the test will be
repeated. The period of loading shall be one hour in any particular case or as otherwise
directed by the Engineer.
122
affected, the Engineer shall order such tests to be carried out as shall indicate the real
strength of the structure. The test may follow that specified above for reinforced
concrete structures or any other form that the Engineer may consider desirable.
If in the opinion of the Engineer, the result of the test is not satisfactory the
Engineer shall order such remedial measures to be carried out as may be necessary in
his opinion, and the Contractor shall carry out such remedial measures without delay
and at his own expense.
Under no circumstances shall any part of any structure included in the works be
loaded in any way until permission to do so has been obtained in writing from the
Engineer's Representative.
The Contractor shall arrange his programme of construction so that the loads of
subsequent construction shall not be imposed upon work already completed until, in the
opinion of the Engineer's Representative, that work has developed sufficient strength to
withstand safely the resulting stresses.
(iii) No earth shall be backfilled against the walls, nor placed on top of the
roof slab, of a reinforced concrete culvert until at least 28 days have
elapsed since the pouring of the last concrete in the complete structure,
including wingwalls should these be monolithic with the barrel, and the
results of the 28 days compression cube tests have been studied and
proved acceptable. No earth shall be placed on to the roof slab unless
this is so specified on the drawings, and then strictly within the limits
shown thereon.
123
(c) Backfilling of all excavations for abutments, piers, culverts, etc., shall be brought
up equally and simultaneously on all sides to eliminate unbalanced earth pressures,
filling to open-type abutments shall likewise be brought up equally and simultaneously
around supporting columns, walls, etc., to eliminate unbalanced earth pressures. All
backfill shall be done in layers not exceeding 150mm compacted thickness, and in
accordance with the requirements of all relevant clauses of this specification.
During backfilling operations, the Contractor shall take every care to ensure that
no undue loads shall be imposed upon the structure and he shall furnish the
Engineer's Representative in advance with full details of his proposed method of
performing the task, showing that the structure will not be overstressed in any
way.
In no case shall any structure be used for the passage of constructural traffic,
storage of materials etc., without the written permission of the Engineer's
Representative, whose decision in these matters shall be final.
AS-MADE-DRAWINGS 5020.
On completion of the work, and after it has been approved by the Engineer's
Representative, the Contractor shall prepare as-made drawings of each bridge, showing
complete, fully dimensioned details of the foundations, material on which they are
founded, ground levels, road levels, protection works, superstructure and all other work
carried out under the Contract. The drawings shall be originals prepared from records
taken as the work progresses and agreed with the Engineer's Representative, and shall
not be merely amended prints of the contract drawings. Draughtsmanship shall be of a
high standard, to the satisfaction of the Engineer's Representative. The drawings shall
be by CAD (Computer Aided Designed) or handmade drawing ink, on best quality tracing
linen and shall be 594mm by 841mm overall including a margin of 50mm on the left
hand side, and a margin of 10mm on the other three sides and the title box shall follow
the form shown on the contract drawings. These original tracings together with one
black and white print of each on linen shall be forwarded to the Engineer for his
permanent retention.
The cost of preparing and supplying all these negatives, velographs, prints etc.,
shall be deemed to be included in the rates for carrying out the works to which they
refer.
(a) The return to site and carrying out of a survey of settlement of bridge
and approaches at a time just prior to the completion of the maintenance
period and the submission of a report of the results of this survey to the
Engineer. The cost of this survey shall be deemed to be included in the
tendered rates and prices.
124
(b) The carrying out of any jacking operation or other remedial works
deemed necessary by the Engineer as a result of this settlement to re-
establish the bridge and approaches to the proper levels. The cost of any
such operation shall be deemed to be included in the tendered rates and
prices.
BEARINGS 5022.
Metal bearing shall comply in all respects with the requirements of B.S 5400 and
as specified on the drawings.
The masonry plates shall be set level. The expansion devices shall be set to
conform to the temperature at the time of erection or to the setting specified.
When masonry plates are shown on the drawings to be placed (not embedded)
directly on concrete, the concrete bearing area shall be constructed slightly above grade
and shall be finished by grinding or other approved means to a true level plane which
shall not vary perceptibly from straight edge placed in any direction across the area. the
finished plane shall not vary more than 3mm from the elevation shown on the plan.
Elastomeric bearing pads shall conform to the requirements of B.S. 1154 and the
special provisions.
Where elastomeric bearing pads are shown on drawings, the concrete surfaces
on which pads or packing are to be placed shall be wood float finished to a level plane
which shall not vary more than 1.5mm from a straight edge placed in any direction
across the area. The finished plane shown on the drawings.
Pads 12mm and less in thickness may be either laminated or all elastomer.
Pads over 12mm in thickness shall be laminated. Laminated pads shall consist of
alternate laminations of elastomers and metal or elastomer and fabric bonded together.
The outside laminations shall be metal or fabric. The outside and edges of
metal laminations shall be coated with elastomer not more than 3mm in thickness.
125
The total out to out thickness of pad shall not be less than the thickness shown
on the drawings nor more than 6mm greater than that thickness. Variation of total
thickness within an individual pad shall not exceed 3mm.
The length and width of a pad shall not vary more than 3mm from the
dimensions shown on the drawings.
Pads containing metal laminations shall be fully moulded. Pads of all elastomer
or with fabric laminations may be cut from large sheets. Cutting shall be performed in
such a manner as to avoid heating of the material and to produce a smooth edge with
no tears or other jagged areas and to cause as little damage to the matter as possible.
Corners and edges of moulded pads may be rounded at the option of the
Contractor. Radius at corners shall not exceed 9mm and radius of edges shall not
exceed 3mm.
The bond between elastomer and metal or fabric shall be such that, when a
sample is tested for separation, failure shall occur within the elastomer and not between
the elastomer and metal or fabric.
Metal laminations shall be rolled mild steel sheets not less than 1.0mm thick.
Fabric laminations shall be either (1) a long chain synthetic polymer containing at
least 85 percent of polyester from ethylene glycol and terephthalic acid or (2) a long
chain synthetic polymeric amide from hexamethylene diamine and adipic acid. Each ply
of fabric shall have a breaking strength of not less than 12.5 N/mm². Fabric laminations
shall be single ply at top and bottom surfaces of the pad and either double ply or double
strength within the pad.
The sole polymer in the elastomeric compound shall be neoprene and shall be
not less than 60 percent by volume of the total compound.
Where elastomeric bearing pads over 12mm in thickness are shown on the
drawings, such pads may be manufactured as a moulded laminated pad, or at the
option of the Contractor, may be made up by stacking individual laminated pads.
Individual laminated pads used for stacking shall be normally 12mm in thickness. When
laminated parts are stacked, their contact surfaces shall be cleaned prior to stacking and
a positive method shall be used to hold the individual parts in the stack in proper
alignment.
The quantity of Elastomeric Bearing pads for which payment will be made, will
126
be the number of pads actually constructed and installed as prescribed.
Payment for the Elastomeric Bearings pads shall be made for the quantities as
above determine, at the unit price shown in the Bill of Quantities, which price shall
include the cost of bearing pads, dowels, hardware, setting, all material, equipment,
labour, and all else necessary thereof and incidental thereto.
Before any part of the work is put in hand, the Contractor shall prepare working
drawings in accordance with clause 1010 of this specification.
As soon as possible after the signing of the contract, the Contractor shall prepare
schedules of all parts which go to make up the work, including bought-out material, and
shall forward a copy, to the Engineer's Representative, the duly authorized inspector for
guidance during inspection.
Unless otherwise specified in the contract, structural steelwork shall comply with
the provisions of B.S 4360 (1990) "Weldable Structural Steels" and shall be of the grade
indicated on the drawings. All sections shall conform to British Standard dimensions.
Steel for rolled steel pins, knuckle pins, rollers etc., shall be of the minimum
tensile strength as specified on the drawings and finished as indicated. (Not rivet steel)
127
Steel casting for bearings shall comply with the requirements for B.S. 3100: and
shall be Grade A steel except where noted on the drawings.
Patterns of all castings are to be submitted to the Inspection Engineer, and shall
be approved before moulding is commenced and the casting are run. Where this cannot
be done on account of their large size the pattern shall be kept available at the
manufacturer's works for approval by the Inspection Engineer.
Gunmetal for girder bearing strips etc., shall be made of the following mixture:
Copper 88 per cent, tin 10 per cent, zinc 2 per cent, and shall show a tensile
strength of not less than 215 N/mm² with 7.5% elongation on 50mm.
FORGINGS 5038.
Forgings shall comply with B.S.29 and the steel shall have a minimum tensile
strength of 430 N/mm² or as indicated on the drawings.
RIVETS 5039.
Steel for high tensile steel rivets shall comply with the requirements of B.S. 548
"High Tensile Structural Steel for Bridges, etc., and General Building Construction",
Amendments CE 52, May 1936; CE6854 February 1938: CG 715 June 1942 and current
amendments.
Steel for mild steel rivets shall comply with the requirements of B.S. 15 1948
"Structural Steel", Amendment PD 3346, April 1959 or latest edition.
128
BOLTS 5040.
All bolts must comply with the requirements of B.S. 1083: 1965 (Precision
Hexagon Bolts, Screws, Nuts and Plain Washers), and of B.S. 1968: 1963 (Unified
Precision Hexagon Bolts, Screws, Nuts (Unc and Unf Threads) and Plain Washers Normal
Series), Amendment PD5706 November 1968 and PD 6623 or latest edition.
High strength bolts and nuts washers for high strength bolts shall comply with
B.S. 3139 and B.S. 3294, part 1.
High Tensile Steel to be used for plates and rolled sections that are specified to
be welded must comply with the requirements of B.S. 4360 with the following
additional requirements:
(C) The high tensile steel (welded quality) for plates shall be subjected to the
V-Notch Charpy 2 millimetre impact energy test. The average of three
test specimens and the average impact energy at 00C shall not be less
than 35 joules
(D) As a result of the V-Notch Charpy test the crystalline area in the fractures
of the high tensile steel (welded quality) test pieces shall be measured. In
general the average crystalline area in the fractures of the test pieces
shall not be greater than 80 per cent of the original area of the test piece
below the notch.
(E) The high tensile steel (welded quality) for plates shall be subjected to the
Vicker's test for hardness. For the hardness control test of the steel; a
single welded bead shall be deposited on the outer surface on the plate
with 4mm diameter welded electrode, and a cross section of the bead
and the plate shall be cut and etched. The hardness in the heat affected
129
zone shall be measured by the Vickers method and shall not exceed 350
Vickers.
(F) The frequency of the tests described in (C), (D) and (E) above shall be
the same as those for tests for the control of tensile strength, yield point
and elongation as specified in B.S. 4360.
(G) Should the results of the tests described in (C), (D) and (E) above not
reach the requirements specified then the steel may be re-normalized
and re-submitted for inspection. The cost of re-normalizing the steel
shall be borne by the manufacturer.
If the steel is re-normalized then all the tests required under this
specification shall be repeated if after re-normalizing the results of the
tests do not reach the requirements specified then the inspection
Engineer will reject the steel and the costs of the rejected shall be borne
by the manufacturer
High Tensile Steel to be used for plates and rolled sections and welding will not
be permitted except where shown on the drawings.
All High Tensile Steel shall be marked strictly in accordance with the
requirements of B.S. 4360. All steel not correctly marked and identified may be rejected
by the Inspection Engineer.
Steel castings are to be true and clean and shall comply as regards quality and
tests with the requirements of B.S. 3100 for Steel Castings for General Engineering
Purposes, 1967. The casting shall be thoroughly annealed and stress relieved and tested
as per the above for cracks. They are to be well fettled and dressed where necessary to
remove roughness or inequalities. All holes for bolts shall be drilled unless shown on the
drawings to be cored.
Cast Iron shall comply with the requirements of B.S. 1452: (1961) for Grey Iron
Castings. All holes in cast iron for bolts shall be drilled unless shown to be cored.
ELECTRODES 5047.
The Electrodes to be used for welding steel must be of the best heavily coated
type and of such make as the Inspection Engineer may approve. They shall be kept in a
130
dry store in unbroken packets and shall be accompanied by the Maker's Certificate of
date of manufacture and guarantee that they fulfil in all respects the requirements of
B.S. 639, B.S 1856 and B.S 2642 depending upon the grade of steel employed in the
Contract.
2. The Contractor shall submit to the inspection Engineer the name(s), and
all relevant particulars of the electrodes he proposes to use.
3. The quality and type of the electrodes to be used for the submerged arc
welding of high tensile steel must be approved by the Inspection
Engineer and will depend on the submerged arc welding process that will
be used.
Grease for bearings shall be such as will ensure adequate lubrication of the
bearings under tropical conditions. The following is the approximate analysis of a
suitable grease:-
The melting point of the grease shall be not less than 1380C
The grease shall be packed for shipment in strong airtight metal drums.
All paint used in the works, whether applied in the shop or in the site shall be the
best of its kind and all ingredients used in its manufacture shall comply with the
appropriate British standards. In any paint system (viz: primer, undercoats and
finishing coats) each coat of paint shall be compatible one with the other, and to ensure
this, all paint shall be obtained from the same approved manufacturer with a guarantee
of compatibility. The paints shall be used as specified for the various parts of the work.
131
protective paint, such paint shall be of priming paint, as
specified by the Engineer's Representative. Where the
paint has to be applied to a surface already painted with a
bituminous paint, the protective coat shall be of
bituminous paint of best approved quality and colour.
Prior to shop painting all surfaces of steelwork shall be cleaned and de-sealed to
bare metal by steel grit or sand blasting.
132
PREPARATION OF EDGES AND ENDS 5051.
When single universal plates are used with their edges flush with heels of angles
or channels, as in box girders, end posts etc. the edges shall be planed. The edges of
universal plates shall also be planed when used as web plates of riveted plates girders
and there are flange plates. Where two or more universal plates or flats of the same
nominal width are used in tier (excluding covers to a single plate) the edges shall be
machined to make them straight and flush.
All holes for rivets and black bolts shall be 1.5mm larger than the nominal
diameter of the cold rivet or bolt as manufactured and all hole shall be drilled, or drilled
small and reamed. Punching and sub-punching and reaming shall be permitted only for
floor plates and troughing and only when these do not exceed 12 millimetre in
thickness.
Holes for turned bolts shall first be drilled at least 3.0mm small in diameter and
afterwards when the structure is assembled, they shall be reamed or drilled to the
correct size through all thicknesses in one operation. Sub-punching will not be
permitted.
Rivets shall be heated uniformly to "light cherry red colour" and shall be driven
while hot. Any rivet whose point is heated more than the remainder shall not be driven.
When a rivet is ready for driving, it shall be free from slag, scale, and other adhering
matter. Any rivet which is scaled excessively, will be rejected.
All rivets that are loose, burned, badly formed or otherwise defective shall be
removed and replaced with satisfactory rivets. Any rivet whose head is defective, in size
or whose head is driven off centre, will be considered defective and shall be removed.
Where required, rivets shall be cut for examination by the Engineer's Representative and
afterwards replaced free of charge. Stitch rivets that are loosened by driving of adjacent
rivets shall be removed and replaced with satisfactory rivets. Caulking, recupping, or
double gunning of rivet heads will not be permitted.
WASHERS 5054.
All bolts shall be provided with washers, those for turned bolts being bright
finished. Round washers shall not be less than 6mm thick for turned bolts and not less
than 3mm thick for black bolts. Tapered washers of the correct angle shall be provided
under all heads and nuts bearing on bevelled surfaces and where tapered washers are
required for turned bolts, round washers shall also be supplied. Tapered washers shall
133
be not less than 5 mm mean thickness. All washers shall comply with the requirement
of B.S 3410.
WELDING 5055.
Unless otherwise described in the Contract, metal-arc welding shall comply with
B.S 1856 and B.S.2642 as appropriate except for tack welds and temporary attachments
for which the procedures laid down in B.S. 2642 shall be followed.
The temperature of steels welded in accordance with B.S 2642 shall be not less
than 10°C when welding is commenced.
The general welding programme for shop; and site welds, including particulars
of the preparation of fusion faces, the method of pre-heating where required, the
methods of making the welds, and the types of electrodes shall be submitted to the
Engineer for his approval before the work is put in hand. No departure from the agreed
welding programme or from the details shown on the drawings shall be made without
the agreement of the Engineer. Electrodes and fluxes shall be so chosen that the
properties of the deposited metal are not inferior to those of the parent metal.
The position of welds required for temporary attachments shall be agreed by the
Engineer before the work commences.
The cost of furnishing materials, labour, equipment and all else necessary
thereof and incidental thereto.
JOINTS 5056.
Joints shall not be made in any plate or section or in any part of the
bridgeworks, except where shown on the drawings. Abutting joint in compression
members and girder flanges and where shown on the plans shall be faced and brought
to an even bearing.
134
When the flanges or webs of any member have to be cut or notched to enable
the section to be trimmed into another member,a hole of suitable diameter shall first be
drilled through the flange or web so as to leave a fillet at the intersection of the cut
lines.
Members shall not be riveted up until the parts have been thoroughly scraped,
cleaned and freed from all scale and other deleterious matter. Thereafter, surfaces
which will be in permanent contact after shop assembly shall be given one coat of
priming paint on each face and the parts drawn firmly together with bolts whilst the
paint is still wet. All rivet holes shall be thoroughly brushed out and all burrs and
exuded paint removed before rivets inserted and riveting commenced. Surfaces not in
contact but which will be inaccessible after shop assembly shall receive the full
protective painting treatment before assembly viz one coat of priming paint, one
undercoat and assembly viz: one coat of priming paint, one undercoat and one finishing
coat. All paint and painting shall be in accordance with requirements of clause 5049 of
this specification. All reamering of holes shall be carried out in the manufacturer's
works and the edges of all holes on the outside faces of members shall be slightly
arrised.
MACHINING 5060.
The bearing surfaces of bearing plates etc., shall be planed level, the cut being
made in the direction of expansion of the girder. Surfaces which require machining
shall be indicated on the drawings.
Before being despatched, all bridge spans shall be temporarily erected complete
in the manufacturer's works so that the Inspection Engineer can be satisfied as to both
the alignment and fit of all connections.
After the work has been passed by the Inspection Engineer and before it is
dismantled, each part shall be stamped with the distinguishing mark, assigned to it on
the marking drawings, in figures not less than 16 mm high, in such a manner that the
pieces may be readily identified on arrival at site and put together in their proper
positions. The marking shall also be stencilled on each part in one or more places after
it has received the coat of paint mentioned in Clause 5062 and a circle of white paint
shall be placed round each stamped erection mark. No marking other than that
specified shall be put on the steelwork.
135
The drawings showing the markings shall be as set forth in Clause 5020. The
Manufacturer shall forward to the Engineer one set of hand made tracings on best
quality polyester or tracing linen, one set of mechanical copies on tracing linen (e.g.
velograph) and one set of prints showing black lines on white background of the
marking drawings. The cost of producing and supplying all these tracings and prints
shall be deemed to be included in the rates for steel work.
After approval by the inspection Engineer but not before, the whole of the work
shall be thoroughly wire brushed, scraped, cleaned and freed from all scales, grease and
coatings. Areas of rust shall be cleaned down to the bare metal. The surfaces shall be
thoroughly dried and given one coat of priming paint. All paint and painting shall be in
accordance with requirements of clause 5949 of this specification. See also clause 5059
for the treatment of surfaces which will be in permanent contact or inaccessible after
shop assembly.
All machined surfaces, turned bolts, nuts and washers, and all bright surfaces
shall be well coated with other approved coating which will not readily melt when
exposed to the sun in the tropics. Exposed machined surfaces shall be further protected
by timber casings or other approved means.
Field rivets, black bolts, nuts and washers shall be thoroughly cleaned, heated to
about melting temperature of lead, and whilst hot, dipped in boiled linseed oil.
GALVANIZING 5063.
Items which are shown on the drawings to be galvanized shall first be cleaned by
pickling and then galvanized by the hot process. The smelter used in this process shall
comply with B.S 222 and the manufacturer shall produce evidence to the satisfaction of
the Engineer's Representative that this is so, and at his own cost. In addition, samples
of metal from the batch may be taken by the Inspection Engineer for independent
analysis and if found to contain less than 98.5 percent of pure zinc, the galvanized parts
represented will be rejected. The cost of this independent analysis will be borne
according to clause 36 (4) of the conditions of contract.
The galvanized surfaces shall be evenly covered, clean and free from drops or
spelter, spots and blemishes of every kind. After coating, all traces of flux shall be
removed. The coating shall weigh not less than 34 grams per square metre of surface
treated.
All cutting, holing, threading etc. shall be carried out before galvanizing. Cutting,
holing, threading etc., after galvanizing will only be permitted where the written
136
approval of the Inspection Engineer has been first obtained. Where such permission has
been given, the cut edges shall be protected by an approved proprietary galvanizing
commodity, aluminium paint must not be used for this purpose.
All materials shall be stored for a period of 7 days after galvanizing in such a
manner that air comes freely in contact with the surfaces. At the end of this period each
article will be examined by the Inspection Engineer and those showing signs of acid
spot, cracks, blisters or other defects will be rejected.
At the discretion of the Inspection Engineer the quality of the galvanizing may be
tested by the copper sulphate test as described in B.S 729: 1961 and the ductility and
adhesion of the zinc coating tested by bending or otherwise. For the purpose of these
tests more than 1 per cent of the articles will be selected for testing and the cost of the
tests and replacement of the articles thus destroyed shall be borne by the Contractor.
Drifts for rivets and bolts shall be supplied to the extent of one per cent (with a
minimum of six for each size) of the net number of rivets or turned bolts used in the
work. Drifts for use with turned bolts shall be turned to suit the holes. Spanner, the
handles of which shall be made in the form of a podger and joggled, shall be supplied
in the proportion of 1 in every 500 or less for each size of bolt and nut. Where
necessary, brace spanners, screw drivers etc., shall also be supplied. The Contractor
shall ensure that an adequate number of all tools necessary for the proper and efficient
erection of the work at site are provided; the above requirements are regarded as a
minimum.
The full number of rivets, bolts, nuts, washer etc., required to complete the work
shall be supplied and in addition, the following spares shall be provided for each span:-
Rivets 15 per cent of the full number of each size when the
number is 250 or less plus 10 per cent of the number of
each size in excess of 250.
Service bolts complete with nuts and washers shall also be supplied equal to 25
137
per cent of the net number of site rivets for all girder work and 10 per cent of the net
number of site rivets for trough and plated floors.
There shall be no reduction in any of the above number in the case of multiple
spans.
The bolt lists including all lengths of rivets to be provided shall be submitted on
acceptable reproduced prints, and all costs involved in suppling them shall be deemed to
be included in the rates for steelwork.
Payment for steelwork shall normally be made on the computed weight of the
structure as determined from the dimensions given on the drawings, on the basis given
in B.S. 5400, if however the weight of any materials falls short of the calculated weight
by more than 2½ per cent, but nevertheless be accepted, the actual weight of such
material only shall be paid for. If there is any difficulty in obtaining the B.S. section
specified or shown on the drawings, the nearest B.S. section may be submitted for
approval. Should the weight of the substituted section differ from that of the specified
section the weight to be taken for the purpose of payment shall be the lighter of the
two.
For the purposes of payment and unless otherwise shown on the drawings,
castings, forgings, special alloy steels, wrought iron and all structural shapes and plates
of expansion joints, pier protection, access manholes, steel deck drains and other
miscellaneous steel members, shall be considered as structural steelwork except that
when specific items of the above are called for in the Bill of materials, the weight or
unit of measurement of each selected item as specified therein, will be paid at the
respective contract unit price as named in the bid schedule.
All works shall be protected from damage in transit, full allowances being made
for handling under difficult conditions. Particular care shall be taken to stiffen free ends
and to prevent distortion and to adequately protect all machined surfaces, the ends of
members with turned-bolt connections etc.
Straight bars and plates, when bundled, shall be temporarily bolted together. If
this is not possible they shall be bound in at least three places with annealed steel wire
of not less than 6 millimetre diameter which must be tightly fastened. All rivets, bolts,
nuts, washers, screws, plates and small articles generally shall be packed in bags, a
separate bag being used for each diameter and length of rivet, bolt, etc., and each bag
having metal label wired on indicating its contents. The bags shall be packed into
strong wooden cases or casks, whose gross weight shall not exceed 300 kilograms.
Each case, cask, or drum, shall be clearly marked with the shipping marks, and
indication of its contents and its weight. Bundles shall have a metal label, stamped with
138
similar information, attached to each end, the label being secure at each of its ends by a
separate wire so that the label lies flat with the bundles.
All marking and labelling shall be carried out to the satisfaction of the Engineer's
Representative:-
The steelwork shall be erected at site in accordance with B.S.153: with the
following amendments and additional requirements.
All lines and levels shall be as shown on the drawings or as specified by the
Engineer's Representative. The Contractor shall be responsible for all setting out and
shall give all necessary assistance and facilities for checking by the Engineer's
Representative (see clause 1013). Any stakes or marks set out by the Engineer's
Representative on site shall be carefully preserved.
In addition to the requirements given under clause 7 of B.S. 153, the Contractor
shall comply with the requirement of Clause 1012 of this specification relating to
drawings and calculations for temporary works and stagings etc. The Contractor shall
obtain the prior approval from the Engineer for the method of erection and he shall
forward to the Engineer's Representative complete details, drawings and calculations
for the proposed method of erection at the time of seeking such prior approval.
Surfaces which will be in permanent contact after site assembly or erection shall
be thoroughly clean and freed from all scale, loose paint, grease and other deleterious
coatings. Areas of rust shall be cleaned down to the bare metal. The surfaces shall be
thoroughly dried and one coat of priming paint applied to each face. The parts shall
then be drawn firmly together whilst the paint is still wet. All rivet holes shall be
brushed out and exuded paint removed before the rivets are inserted. Similarly for
bolts and bolt holes.
Care shall be taken to ensure that no paint shall be applied to or allowed to foul
any reinforcement or other steelwork which is to be embedded in concrete. In the case
of steel joists which will be so embedded and steel troughing which will be concrete
filled, and all other such surfaces, those surfaces which will be in contact with the
concrete shall be thoroughly cleaned and freed from all rust, scale, loose paint, grease
and other deleterious coatings before the concrete is poured against them.
Where concreting or any other operation likely to foul the steelwork has to be
139
carried out (e.g. pouring of concrete deck slabs supported on R.S.Js.), preparation
and painting of surfaces shall not be undertaken until such time as the cause of likely
fouling or damage no longer exists.
All paint and painting shall be in accordance with clause 5049 of this
specification.
he proposes to employ to carry out the work. Such details shall be accompanied
by drawings and calculations showing that no part of the existing structure shall be
overstressed or likely to suffer any damage during the strengthening operations and to
ensure that this will be so, the Contractor shall provide temporary supports, bracing,
struts etc., as necessary. In no case shall any part of an existing bridge be removed to
facilitate strengthening until a temporary substitute has been fixed in place to the
complete satisfaction of the Engineer's Representative. The Contractor shall amend his
proposals for undertaking the strengthening of the bridge as required by the Engineer's
Representative and shall not commence the work until the Engineer's Representative
has given his approval to the scheme and his permission to proceed.
Before ordering the additional steelwork, the Contractor shall completely satisfy
himself in all respect as to the dimension and positions of all fastenings and members
of the existing structure and shall be responsible for ensuring that all new plates, joists
etc., required for the strengthening shall avoid or accurately pick up all such existing
fastenings and members as the case may require. The Contractor shall also check
existing spans as indicated on the drawings to ensure that the lengths of new joists
etc., are adequate for the work proposed, and before ordering any such material shall
inform the Engineer's Representative of the dimensions, weights etc., which he proposes
to obtain and obtain his approval therefore. Any indications of the sizes or positions of
any part of any existing structure as are shown on the drawings are of a general
nature only and the Contractor must on no account regard such indications as accurate.
The Contractor shall be deemed to have inspected each and every structure and to have
taken all necessary information and measurements required for the proper carrying out
of the work, and to have allowed for such in his rates.
140
permanent contact with the existing steelwork, the contact surfaces of both shall be
thoroughly scraped and cleaned and freed from all loose paint, scale, grease and other
deleterious coatings. Areas of rust shall be cleaned down to the bare metal. The contact
surfaces shall then be given one coat of priming paint and brought together and
fastened whilst the paint is still wet. Surfaces of both existing and additional steelwork
which will be inaccessible after strengthening measures are complete shall be prepared
as described above and given the full protective paint treatment viz:- one priming coat,
one undercoat and one finishing coat, before assembly is begun. Where site welding is
to be employed, paint and other coatings shall be removed from the areas to be welded
for a suitable extra distance to ensure that the quality of the welds will not be impaired.
When strengthening is complete, the surfaces of all added steelwork, and those of the
existing steelwork which have been damaged during the operation shall be prepared as
above and given one coat of priming paint, one undercoat and one finishing coat. All
paint and painting shall be in accordance with the requirements of clause 5049 of this
specification.
The cost of fulfilling all the requirement of this clause shall be deemed to be
covered by the rates for supplying, fixing and painting additional steelwork.
Girders, joists etc., from a dismantled structure which are to be re-used in the
strengthening or reconstruction of another structure are thus indicated on the drawings.
The Contractor shall check the dimensions of such girders, joists etc., against those of
the structure into which they are to be incorporated and obtain the approval of the
Engineer's Representative as to their suitability for such use before commencing any
cutting, drilling etc., that may be necessary. (See also clause 5011).
All work shall be carried out strictly in accordance with the drawings or as
directed by the Engineer's Representative, and in compliance with this specification.
When the work on the girders, joists etc., has been completed, and before they are
incorporated into the structure, they shall be submitted to the Engineer's
Representative for approval and when this has been obtained and not before, the
Contractor shall forthwith incorporate them into the works as directed on the drawings.
The Contractor shall ensure that during fabrication, assembly and subsequent
incorporation into the works, the girders, joists etc., are given the paint treatment
specified in clause 5069.
The base plate, etc., shall first be located accurately with respect to both line
and level, by careful tapping, levering, wedging etc., as approved by the Engineer's
Representative. Care shall be taken to ensure that no damage is done to any item,
especially machined surfaces. Immediately before the operation of grouting in, the
entire area covered by the bearing, including pockets for holding down bolts, and a
sufficient extra area around to prevent contamination, shall be thoroughly cleaned by
141
washing with water from hose pipes, compressed air etc., and all dust,loose and
deleterious matter shall be removed. All surplus matter shall then be dried off by
mopping and the use of compressed air and the surfaces left damp. Freshly mixed
mortar, as directed and of suitable consistency shall then be introduced to fill the
pockets for the holding down bolts, and the space beneath the bearing plates. the
mortar shall be well pounded into the space, working from one side with suitable
pounders until the mortal appears on the opposite side and every care should be taken
to ensure that the mortar appears on the opposite side and every care shall be taken to
ensure that the entire void is filled, giving complete support to the bearing over the
entire area, without air holes etc. To ensure this, wooden screed shall be introduced
around the edges of the grouting space to contain the mortar during the pounding
operations. Any mortar which may foul the threads of bolts, nuts, or affect their bearing
on washers and plates shall be carefully removed without disturbing the mortar already
placed, and on completion of the operation, the edges of the mortar shall be trimmed as
shown on the drawings. The whole shall then be covered with wet sacks or hessian
which shall be kept continuously damp for a period of not less than 7 days, after which
they shall be removed and all loose, adherent or projecting mortar liable to reduce the
efficiency of the bearings carefully removed. After 28 days all holding down and other
bolts shall be tightened as directed.
Expansion joints shall be provided where shown on the drawings and be of the
type specified.
The size of the gap shall be compatible with the mean bridge temperature at the
time of installation. This temperature shall be determined in accordance with
arrangements agreed with the Engineers.
142
The position of all bolts cast into concrete and holes drilled in plates shall be
accurately determined from templates.
The mixing, application and curing of all proprietary materials shall comply with
the manufacturers requirements.
During the placing and hardening of concrete or mortar under expansion joint
components, relative movement shall be prevented between them and the supports to
which they are being fixed.
When one half of the joint is being set, the other half shall be completely free
from longitudinal restraint. In particular where strongbacks or templates are used to
locate the two sides of a joint, they shall not be fixed simultaneously to both sides.
Screw threads shall be kept clean and free from rust. Ramps shall be provided
and maintained to protect all expansion joints from vehicular loading. Vehicles shall
cross the joints only by means of the ramps until the Engineer permits their removal.
143
SPECIFICATION
SECTION VI - ROADWORKS
144
SECTION VI ROADWORKS 道路工程
GENERAL 6000.
In addition to any other relevant clause of this specification, the following shall be
deemed to apply in particular to roadworks, and shall be read in conjunction with all
other relevant clauses of the conditions of contract and this specification.
除本规范其他有关条款外,下列内容应特别适用于道路工程,并应结合合同条
件和本规范的其他有关条款进行阅读。
PART (A): DESIGN AND CONSTRUCTION STANDARDS
For new roads, the horizontal alignment must be carefully chosen as this is cost
related. A good alignment shall provide good drainage, minimum and balanced
earthworks and must avoid swampy and high water table areas, where this is possible.
A good horizontal alignment allows straight portions of the road on the horizontal plane
to be connected with horizontal curves which may be circular or transitional.
For the rehabilitation of roads in general, the proposed new alignment shall
follow closely on that of the existing road, except where necessary to effect realignment
to conform with the current standards of the Federal Ministry of Works and Housing or
to effect the most economical sitting of new bridges. It shall consist of a series of
straights joined by circular curves. All gradients, vertical and horizontal curves, sight and
passing distances, rate of super-elevations etc., shall conform with the accepted
standards of the Ministry for the particular terrain and adopted design speed as follows:-
ADOPTED DESIGN
SPEED, KM/H 100 80 60
145
HORIZONTAL CURVES AND SUPER-ELEVATION
Radii of horizontal curves and super-elevation rates shall comply with the
following formula:-
E = V²/2.25R
DEFINITIONS:-
(I) TANGENT RUN-OFF That distance in which the level of the outer edge of the
pavement is brought to the level of the crown of the road section.
In cases where the inside edge of the curve may be easily drained, then the
super- elevation shall be achieved by the rotation of the pavement about the centre-line
profile. The sequence of operations is as follows:-
(a) The outer half of the pavement width is brought to the same horizontal
plane with the crown of the cross section. This is done within the
distance called the tangent run-off.
(b) The outer half of the pavement is then brought to the same inclined
plane as the inner half of the pavement.
(c) (i) For rotation about the inner edge, the pavement shall then be
finally rotated about its inner edge to the required full super-
elevation. No cut is involved along the inner edge in this
operation.
(ii) For the rotation about the centre-line, the pavement shall be
rotated about its centre-line to the required full super-elevation.
This operation involves "cut" along the inner edge of the
pavement.
146
DESIGN SPEED KM/H 100 80 60
MAXIMUM GRADIENT OF SUPER-ELEVATION
RUN OFF RELATIVE TO CENTRE-LINE OF ROAD 0.45 0.5 0.57
(PERCENT)
MINIMUM LENGTH OF SUPER-ELEVATION RUN-
55 45 40
OFF (METRE)
MAXIMUM RATE OF CHANGE OF SUPER-
0.05 m/m PER 30 METRE
ELEVATION RUN OFF
LENGTH OF SUPER-ELEVATION RUN-OFF
20%
WITHIN THE CURVE (CIRCULAR)
The straight portions on the vertical plane which are connected by vertical curves
are called gradients. Two cases of vertical curves occur with gradients either meeting at
summits or meeting at sags. The choice of gradient will affect construction costs, vehicle
operation cost, road capacity and passenger's comfort. With these considerations, the
vertical alignment shall conform with adopted standards of the Ministry. The finished
work shall be to even gradients joined by vertical curves. The lengths of vertical curves
shall be calculated using the formula:-
L = K(G1-G2) = KA
TABLE VI-2 DESIGN SPEED FOR VERTICAL, SUMMIT OR SAG CURVES WITH
CORRESPONDING K VALUES
147
The level of any point along the vertical curve shall be equal to the level at the
tangent point plus
G1X/100 + AX2/200L
ROLL-OVER 6003.
Roll Over is the algebraic difference in cross falls of two adjacent lanes of
pavement area. The Roll Over shall be in accordance with the details as shown on the
DRAWINGS or as directed by the Engineer's Representative.
The Contractor will be responsible for working out all levels of the pavement,
shoulders, ditches etc., that are necessary for the setting out of the works and will, if
required to do so, furnish the Engineer's Representative with lists of these levels for his
approval prior to setting out. The Contractor shall locate and preserve where directed all
concrete land markers, beacons, benchmarks etc.
(I) WIDTH 宽度
The base course of the carriageway, which may be continued over the hard
shoulders or extended a minimum of 300mm at either side of the surfaced width as
shown on the drawings or as directed by the Engineer shall be constructed of approved
148
material having a finished compacted thickness of not less than 150mm and complying
in all respects with this specification. The base course to the hard shoulders if different
from that of the carriageway, shall be constructed of such other approved material as
directed by the Engineer's Representative, but also having a finished compacted
thickness of not less than 150mm.
The Subbase Course of the carriageway, which may be continuous over the hard
shoulders as shown on the drawings or as directed by the Engineer's Representative,
shall be constructed of approved material having a finished compacted thickness as
shown on the drawings, or as directed by the Engineer depending on the C.B.R. value of
the subbase in question.
(IV) GEOMETRY 几何
The horizontal and vertical alignments, superelevations and cambers of the road
shall be constructed in accordance with the DRAWINGS or as directed by the Engineer.
The surfacing of the roadway shall be two coat bituminous surface dressing or
hot asphaltic concrete pavement as shown on the DRAWINGS or as directed by the
Engineer.
Unless shown otherwise on the drawings the invert of the side drains shall be not
less than 900mm below the finished level of the crown of the road. All side drains
shall, where shown, be excavated to the profile and dimensions shown on the drawings,
but the Engineer's Representative may direct that the side drains be constructed to such
lesser profiles consistent with drainage capacity as he may think fit due to the existence
of rock or other obstruction. Where the height of the embankment exceeds 900mm
above the existing ground, and the natural gradient of the surrounding area is towards
the roadway, then catch water drains shall be constructed as shown on the drawings or
as directed by the Engineer's Representative.
(VIII) CULVERTS
Generally culverts shall consist of precast concrete pipes laid either as single or
multiple culverts, and where shown shall be bedded and haunched with a minimum of
150mm of concrete. In cases where sufficient cover is not available the Engineer's
149
Representative may direct that culverts be surrounded with a minimum of 150mm of
concrete.
A Minor Roads 小路
At all junctions with minor roads where shown on the DRAWINGS or directed by
the Engineer's Representative, bell mouth shall be constructed carrying the construction
and drainage to a minimum of 15.0 metres from the edge of the proposed roadway
along the minor road as shown in details on the DRAWINGS or as directed by the
Engineer's Representative.
B. Major Roads 大路
All junctions with major road culverts shall be constructed as shown on the
DRAWINGS or as ordered by the Engineer's Representative.
Where the roadway passes through villages and at recognized lorry halts, the base
course and the asphalt concrete pavement shall be widened. Concrete side drains shall
be constructed. All as shown on the DRAWINGS or as directed by the Engineer's
Representative.
(XIII) SUBGRADE
A. Cuts
The subgrade of the road shall be shaped to the dimensions, formations and
levels as shown on the Drawing or as directed by the Engineer's Representative and the
top 150mm subgrade shall be watered and compacted to 100% B.S. standard
compaction at optimum moisture content (OMC).
150
B. Embankments
The subgrade of the roadway shall be shaped to the dimensions formations and
levels as shown on the DRAWINGS or as directed by the Engineer's Representative.
(1) MATERIAL
GENERAL 6100.
The materials used in the works shall be new and/or of the qualities and kinds
specified, and no materials shall be used in the works unless approved. Materials
delivered to the works shall be equal to the approved samples. Deliveries shall be made
sufficiently in advance of constructional requirements to enable samples to be selected
by the Engineer's Representative for testing before using the materials in the works.
No material shall be used until it has been approved by the Engineer or his
Representative. Permission to use any material shall not be construed as an approval of
its source nor any acceptance as continued acceptance.
Material for filling in the embankment shall be obtained from sources approved
by the Engineer's Representative and no slurry, mud, soft or otherwise unsuitable
materials shall on no account or under any circumstances be placed in embankments.
Large pieces of rock, or other materials shall be properly broken up and beaten down
and no accumulation at the foot of side slopes of embankments of boulders or lumps
having no cohesion will under any circumstances be permitted. The Engineer's decision
regarding the suitability of any material shall be final, and any material of which more
than 35% passes the No 75µmsieve may be rejected depending on the plasticity
characteristics of this material, provided good quality fill materials are available,
otherwise such material may be modified for use.
151
The material to be used for the forming of embankments shall generally be
obtained from cuttings which may be widened as agreed with the Engineer's
Representative.
The material shall be spread evenly over the area of embankment and
compacted in uniform layers to the specified density and moisture using B.S. compactive
effort. Each compacted layer shall not be greater than 150mm.
The seed, or the grass used for sowing or planting on the verges, the slopes of
embankments and cuttings shall be daub grass (cynodon dactylion) or bahama grass.
Tall, quick growing or tussock grasses shall not be used without the consent of the
Engineer. The Contractor must anticipate the requirements for the supply of suitable
grass.
Stones for filling behind retaining walls or walls of culverts shall be angular and
graded from 12mm to 75mm with a fine content below 12mm not exceeding 20%
stones, for pitching the inverts and sides of ditches embankment slopes and culvert
inlets, and outlets, shall be of durable natural broken rock of approximate cubical shape
225mm x 225mm x 225mm or 150mm x 150mm x 150mm as appropriate.
(II) WORKMANSHIP
The Contractor shall fell, grub-out roots and clear from the site all trees
occurring within the boundary of the works as directed. In addition all bushes, ant hills,
ants' nests, grass, stumps and other vegetation shall be cleared from the site and roots,
grubbed up, holes made in grubbing up, removing the ant hills, roots, stumps and the
like shall be backfilled and compacted to a density at least equal to that of the
surrounding ground except that all holes, cavities, and wells within the road width shall
be backfilled with approved soil which shall be thoroughly compacted throughout by
power rammer to a density not less than the dry density of the surrounding ground.
152
Outside the above limits, on the inside of bends, bushes and trees shall be felled
and their roots grubbed up as directed to give an unobstructed sight distance of 150
metres. For purposes of measurement, the girths of the trees shall be taken 900mm
above ground level except that where a tree has a buttress the girth shall be taken
immediately above the buttresses. No economic trees or crops shall be removed prior
to their enumeration and valuation for compensation purposes.
The Contractor shall remove gates, gate posts, manhole covers, kerbs, signs,
water mains and other items to the extent directed by the Engineer's Representative.
Foundations shall be broken up and removed to a depth of 900mm below natural
subgrade level or finished grade level, whichever is lower.
Pits, tanks, underground chambers and the like shall be demolished to a depth of
900mm below Natural Subgrade Level or finished grade level, whichever is lower and
the remainder shall be properly cleaned out.
Clearing limits for this Contract shall be the entire length of the project within
widths as hereinbelow defined.
Any and all existing compound walls located within the Right Way limits shall be
cleared and removed as part of the appropriate item in the Bill of Quantity. Also
included as part of this item shall be the reconstruction of all such walls, equal to
the removed wall, along the Right Way line connecting to the points at the start
and end of the removed section. The cost of such reconstruction shall be
considered included in this item. Reconstruction of compound walls may be
required anywhere along the alignment.
III. Wells
Working wells within the limits of grading shall be filled as herein above
required. Replacement wells equal to the existing wells shall be constructed outside the
limits of grading. The cost of all replacement wells shall be considered as included in
Item "Clear Site as specified..... etc;."
153
Non-working wells within the Right Way lines, shall be filled as hereinbefore
required.
All trees shall be cleared within a strip fifty (50) metres wide, (25 metres to each
side of the centre line). To ensure that future falling trees do not clog road side drains,
all trees outside this 50 metre strip whose height is such that, if they fell would reach to
the nearest roadside drain, shall be cleared.
All other erosion resisting vegetation shall be cleared only within the limits of
grading.
Outside the above limits and within the Right of Way lines all vegetation shall be
selectively thinned and/or trimmed.
A. Selective thinning shall include the removal of live and dead trees both standing
and fallen, shrubs, and other vegetation and debris in the areas shown on the Drawings
and designated for removal by the Engineer.
B. Trimming existing trees shall include the complete removal of all defective or
undesirable limbs and the repair of all injuries or wounds on existing trees as directed by
the Engineer's Representative.
All diseased, dead, broken and seriously injured branches shall be removed.
Healthy low branches shall not be removed except as otherwise directed by the
Engineer's Representative. All wounds over 25mm diameter shall be painted with tree
paint. The bark around all wounds and other injuries shall be traced and treated in
accordance with approved arboricultural practice. All pruning tools and methods
employed shall be in accordance with arboricultural practice and shall be subject to the
approval of the Engineer.
All trees to remain within the areas designated for selective thinning shall be
trimmed to remove all dead and undesirable limbs up to a height of 5m above ground.
The Engineer will determine which live limbs are undesirable.
The Contractor shall load, transport, unload and stock materials designated for
154
delivery to the owner's thereof.
Other materials resulting from clearing operations shall become the property of
the Contractor as soon as he takes possession of the land for the Works. The Contractor
shall remove and dispose of such materials.
Payment will be made under this for the net areas cleared and shall include for
the satisfactory removal of anthills and ants' nests and for any backfilling and
compacting required and for disposal of material, but shall not include any areas of
grass on the road vergers or otherwise, which is subjected to periodic cutting and
maintenance.
EARTHWORKS 6122. 土方
In the Contract the following words and expressions shall have the meanings
hereby assigned to them except where the context otherwise requires:-
(1) "Existing Ground Level" means the ground level shown on the Drawings as
existing at the start of the Works.
(2) "Finished Ground Level" means the ground level after the completion of the
Works.
(3) "Natural Subgrade Level" means the level at the completion of excavation for
155
roadworks.
(4) "Formation Level" means the level at the completion of earthworks for roadworks
prior to top soiling.
(5) "Stripped Ground Levels" means the ground levels after the completion of
clearing operations.
(6) "Specified Finished Excavation Levels" means the levels of the completed
excavation after trimming, compacting and preparation of the surface of the
excavation as calculated from the levels shown on the Drawings, or the levels
directed by the Engineer's Representative.
(7) "Specified Finished Fill Levels" means the levels of fills after trimming,
compacting and preparation of the surface of the fill (excluding top soiling)
placed in accordance with the Drawings or as directed by the Engineer's
Representative.
(2) Peat, logs, stumps, roots and other perishable or combustible material.
(4) Clay having a liquid limit exceeding 80% or plasticity index exceeding 55.
Suitable material shall exclude the foregoing unsuitable materials and shall
comprise all other natural material acceptable for use in the Works, whether obtained
from within or without the Site.
Top soil shall mean soil which can be seen to have been broken down by
agricultural cultivation and/or is seen to be capable of supporting vegetable growth. It
shall include turf.
Solid rock shall mean rock found in ledges or masses in its original position,
which can only be loosened by blasting or by pneumatic tools, or excavated by hand, by
using wedges and sledge hammers. Rock which is in a shattered condition and/or is
capable of being loosened by rippers or earthmoving plant is excluded from the
definition of solid rock. Boulders or detached pieces of rock each exceeding 2 cubic
meter size in trenches or 6 cubic meter size in general excavation, shall be regarded as
solid rock.
156
Where embankments are to be constructed on steeply sloping ground, including
the side slopes of existing embankments, existing sloping surfaces shall be excavated to
form benching as shown on the Drawings or as directed by the Engineer's
Representative.
General fill shall consist of suitable material as defined herein. Subject to the
requirements regarding the forming of embankments isolated boulders not
exceeding 3 cubic metres in size may be included in general fill.
Rock fill shall consist of sound igneous rock or other sound rock acceptable to
the Engineer's Representative or such strength that when compacted an excess of fines
will not be produced. It shall be free draining and reasonably well graded and shall
have a maximum size of 3 cubic metres. The percentage of material by weight passing
a 5mm sieve shall not exceed 30%. It shall be free from silt, clay and organic material.
Such material may be deposited below water without the associated use of compaction
plant.
Granular fill shall consist of an approved granular material of maximum, size not
greater than 38mm which is inert in water and which on analysis by sieving complies
with the following requirements.
10mm up to 100
Special granular fill shall be hard and durable and shall consist of broken rock or
gravel. It shall be well graded with a maximum size of 38mm. The percentage
of material by weight passing 75m sieve shall not exceed 10. It shall be free
157
from silt, clay and organic material.
Granular bedding shall consist of crushed rock or gravel having a smooth grading
curve within the limits specified for l9mm nominal size all in aggregate to Table 3
of B.S 882. The fraction passing the 425μm sieve shall be non-plastic when
tested in accordance with B.S 1377 (1975) Sections 2, 3 and 4 unless such
fraction constitutes less than 2 per cent of the whole by weight.
Payment for earthworks shall be made once on the basis of the total quantity of
measured fill by the Contractors together with the quantity of unsuitable material and/or
of excess cut placed to spoil, all as determined from the cross sections referred to in
clause 6122. The depth of unsuitable material, if any, to the placed to spoil shall be
agreed between the Contractor's Agent and Payment for this material will be on the net
volume as measured in situ.
(i) The net volume of suitable material excavated from cuttings or side drains shall
be determined by deducting the quantity of unsuitable material placed to spoil
from the total quantity of cut as determined from the cross sections.
(ii) The total volume of filling placed in embankment shall be found from the cross
sections.
158
(iii) The volume of suitable excess cut placed to spoil shall be taken as the volume
found in (i) above less the volume found in (ii) above with an adjustment made
to the latter to allow for compaction.
The adjustment which shall be made for compaction shall be based on the ratio
of the maximum dry density of the filling at 100% B.S. Compaction to the in situ dry
density of the material in the cutting or side drain.
Haulage rates will he assessed on the basis of the use of the nearest acceptable
road making materials to the section of work under construction.
Soils shall be obtained from areas of cut including ditching or from approved
borrow pits. All grass and vegetation shall be removed from the surface of the areas of
cut or borrow pits before excavation of the fill material is commenced and no such grass
or vegetation shall be included in the fill. In borrow pits the top soil, shall be carefully
removed and stockpiled.
Topsoil shall not be removed from any area until excavations or filling operations
are about to start in that area. Topsoil on the sites of cuttings and embankments shall
be excavated to the average depth directed by the Engineer's Representative or as
specified hereinafter.
The Contractor shall, at his own expense and to suit his own convenience, make
arrangements for and provide such temporary storage sites as may be required for
heaps of topsoil.
If any materials suitable for subbase, base or aggregates as specified herein are
encountered in material removed as roadway excavation, and the Contractor elects to
use such material for constructing items, payment for the various items shall be as
follows:
If the Contractor elects to use materials removed from cuttings for constructing
items of subbase, base or aggregates, payment will be made for such material
excavated under the appropriate roadway excavation item and for such material so
placed under the appropriate item of subbase or base, provided that the Contractor
furnishes and places borrow excavation material, in embankment without cost, in an
amount equal to the value of the material used in the base, subbase or as aggregate in
place prior to excavation.
The Contractor shall at his own expense, make arrangements for and provide
159
such spoil dumps as may be required for the disposal of excavated materials which are
not to be incorporated in the Works.
The spoil dumps shall be located and shaped in accordance with the Contractor's
proposals as and shall be finished with neatly trimmed slopes, adequately surface soiled,
all to the satisfaction of the Engineer's Representative.
During the course of the excavation from an area of cut or borrow pit or other
approved source of fill material, the Contractor shall provide adequate supervision to
ensure that only soil of a type approved by the Engineer's Representative is excavated.
Care shall be taken during such excavations to avoid any pockets of heavy clay,
vegetation or other unsuitable material and if any such unsuitable material or soil of an
unapproved type is included in the fill it shall be dug out and made good with approved
material where directed by the Engineer's Representative and at the Contractor's own
expense.
Where a sandy soil is encountered in the excavation of a cut or borrow pit, the
Engineer's Representative shall have the power to instruct the Contractors to place this
sandy soil to the top layer of fill.
Any material which in the opinion of the Engineer's Representative is not suitable
for fill shall be tipped to spoil as and where directed.
After removal of fill material from borrow pits etc., The area shall be levelled and
top soil replaced all to the satisfaction of the Engineer's Representative.
The Contractors shall arrange and pay for any compensations and other
payments whatsoever required for their access to and occupation and use of the borrow
areas for fill material.
COMPACTION 6125.
Compaction of all material shall be carried out at a moisture content optimum for
the compaction effort of the plant used. The Engineer's Representative may, however,
direct that the moisture content at compaction be further controlled in order to reduce
as far as possible any subsequent consolidation or swelling.
Where it is necessary to add water to the material to achieve the dry density
specified, the cost of obtaining, transporting or pumping, spraying and mixing sufficient
160
water must be allowed in the Contractor's prices for compaction. Water shall be added
as and where necessary by a water carrier fitted with an approved sprinkler and the
uniform wetting of the layer to be compacted shall be achieved. Under no
circumstances will compaction solely by construction or other traffic be accepted.
Fill materials shall be placed, spread and levelled in layer of loose depth not
exceeding 230mm of general fill, 460mm of rock fill, 230mm of special and granular fill.
Notwithstanding the foregoing, where rock fill or granular fill is placed below water level
there shall be no restriction on the depth of layers.
The material of each layer, of whatever type, shall be uniform throughout the
layer. Except as otherwise necessary to conform to the zoning of the various types of
materials, each layer of material shall extend over the full width of the filling. No layer
of fill material shall be placed until the Engineer's Representative is satisfied that the
underlying layer is properly compacted.
Rock fill (including solid rock excavated from cuttings) shall be placed, spread
and levelled by a track laying tractor, and large voids shall be filled with broken
fragments before compaction.
Isolated boulders and isolated large fragments of solid rock forming part of
general fill shall be evenly distributed throughout each layer, but no stone exceeding
150mm in size shall be placed within 300mm of formation level.
During the construction of embankments the Contractor shall control and direct
construction traffic uniformly over the full width. Unless permitted by the Engineer's
Representative, fill materials shall not be stockpiled on embankments.
All compaction equipment must operate over the whole area to ensure uniform
compaction by it. All filling including the subbase course and base course shall be
compacted in layers of a compacted thickness of 150mm or such other thickness as may
be found necessary to achieve the required density. Longitudinal and transverse joints
in any two successive layers shall be staggered to a minimum distance of 3 metres.
At the beginning of the Works and from time to time as may be necessary in the
161
opinion of the Engineer's Representative, the Contractor shall carry out, to the
satisfaction of the Engineer's Representative, field trials, supplemented by any necessary
laboratory investigations to determine types of compaction equipment, suitable layer
thickness and moisture contents all within the requirements of the specification for the
placing and compaction of the various materials to be used in the earthworks. The sites
of trials shall be agreed between the Contractor and the Engineer's Representative.
Copies of the full records of all such trials shall be provided promptly to the Engineer's
Representative. If compaction trial fill is placed as part of the permanent work, such fill
shall conform to the requirements of the specification and if it does not it shall be
removed or reworked until it does conform. Extra work required either to rework or
remove the trial section shall be at the Contractor's expense.
The Contractor shall not modify the agreed methods without the consent of the
Engineer's Representative.
Work in compaction of fill materials shall be carried out only when the moisture
content is within the range shown by the field or by laboratory tests whichever is
appropriate on that material to be suitable for the attainment of the densities specified
below.
(i) For material which is within 600mm Formation Level or in the filling adjacent to
structures (including backfilling), not less than 100 percent of the maximum dry
density for the material obtainable by B.S standard compaction.
(ii) For all other material, not less than 95 per cent of the maximum dry density for
the material obtainable by B.S standard compaction.
The foregoing compaction requirements shall also apply to the subgrade material
which is within 600mm of formation level in cuttings.
The Contractor and the Engineer's Representative shall from time to time agree
upon field compaction methods and relevant plant for the various materials such that by
correlation using the relative density and ISO CBR control tests, the need for the
extensive tests on the finished road section may be reduced.
The Contractor and the Engineer's Representative shall also agree on procedures
for determining the areas of fill to which particular sets of test results should be deemed
to be applicable. Such areas shall include clay or peat deposit where consolidation test
may be necessary.
162
All sections of the works shall be protected from damage by plants, rainstorms or
other cause. All such damage should it occur, shall be made good by the Contractor at
his own expense.
In particular the exposed surface of each lift of fill or sub base course or base
course material, after compaction, shall be protected by a cambered surface from
excessive moisture content changes due to rainstorms until the next lift is placed. If
such changes in moisture content do take place and the surface of the compacted layer
softens, the Contractor shall, if required by the Engineer's Representative, remove and
replace the material affected at his own expense. Should the material used for subbase
or base course be prone to drying from the surface the Contractor shall from time to
time keep the finished surface slightly dampened. This process will continue until
another layer is placed.
Should there be patches of unsound ground, excessive sand or clay, which are,
in the opinion of the Engineer's Representative unsatisfactory, then such areas shall be
rectified by admixture of suitable materials or by cutting out and replacement to ensure
a uniformly compacted formation.
Tests for the control of compaction shall be carried out at regular intervals as
directed by the Engineer's Representative. If any test result from a particular area falls
below the minimum specified, then the Contractor shall at his own expense scarify,
water and recompact that area to the satisfaction of the Engineer's Representative,
provided the constituency of the material will not be adversely affected as double
compaction may increase percentage passing 75m sieve to more than 35% thus
reducing the strength of the material.
The Contractor shall allow in his construction programme time for such tests and
for the results to be made known, before the next stage of the works.
The Contractor shall at his own expense clear bush, topsoil and other inferior
materials from the site of borrow pits. The Contractor shall also bear the cost of
compensation for borrow pits outside the area of the site. Borrow pits for road
materials shall be excavated only where the natural slope of the ground is away from
the road, except that where he considers it essential for the proper execution of the
works the Engineer's Representative may approve the excavation of borrow pits in
ground above road level.
Generally in rural areas the nearest edge of the pit shall be not less than 15
metres from the centre line of the road. The Contractor shall so plan his method of
execution of the works that the haul of road materials from borrow pits is reduced to a
minimum. The Contractor may be allowed to form "side borrow trenches" for fill material
wherever it is required providing such trenches are self draining, having a minimum fall
along the line of the road of 1 in 120. All other pits shall be properly drained to the
satisfaction of the Engineer's Representative by the construction of turnouts or other
approved methods.
163
In build up areas, the Contractor shall submit to the Engineer, his proposals for
obtaining fill materials and shall furnish details regarding the locations, sizes and owner
of all borrow areas, together with his proposed method of working and all measures
proposed to eliminate damage or nuisance to persons or property. He shall be required
to submit his proposed method for the reinstating such borrow areas at the same time.
The Contractor shall obtain the Engineer's written approval for the above before
commencing work on any borrow area. In addition the Contractor shall comply with all
other relevant clauses of the conditions of contract and this specification.
No borrow pit shall be abandoned until the area has been levelled, topsoil
replaced and the sides battered to a slope of 1 in 1½ so that no animals may be
trapped, all to the satisfaction of the Engineer's Representative. The cost of all
operations detailed under this clause shall be deemed to be included in the tendered
rate for earthworks.
The quality of the material intended for use as sand fill shall be subject to the
approval of the Engineer. For hydraulic sand fill the grading of the material shall be
such that not more than 15% passes the 75μm sieve and in no case will isolated
pockets or layers of silt, clay or other organic impurities be accepted. For sand fill
placed by any method other than the hydraulic, the grading shall be such that not more
than 15% passes the 75μm sieve, and in no case will isolated pockets or layers of silt,
clay or other organic impurities be accepted.
Sand fill placed by any method other than the hydraulic shall be compacted in
layers by a method approved by the Engineer's Representative to a density of not less
164
than 100% of the maximum dry density obtained in the British Standard Compaction
Test. Vibrative system of compaction is recommended.
In the case of hydraulic sand fill the Contractor shall construct all drains, ditches,
spillways, marginal bonds necessary for the proper protection of the works. Such drains,
marginal bonds etc., shall be constructed sufficiently in advance of the deposit of the
sand fill, so as to effectively drain and retain the sandfill and to prevent any of the
material from flowing into any harbours, creeks, canals, drains etc., or from causing any
damage or nuisance to persons or property. The Contractor shall be responsible for any
slip or settlements which may occur during the construction of the sand fill or the bunds,
drains, etc., and shall also be responsible for same during the maintenance period. The
Contractor shall make good such slips and settlements to the satisfaction of the
Engineer's Representative.
The Contractor shall be responsible for the full and efficient drainage of water resulting
from the hydraulic sand fill operation and shall construct such open drains as may be
necessary to drain all surface and rainwater, so as to avoid all ponding. The Contractor
shall make due allowance for settlement and drying out of the sand fill and for the
making good of same.
Before any hydraulic sand fill is commenced, the Contractor shall, in conjunction
with the Engineer's Representative, survey the site and mutually agree the surface
levels, and such agreement shall be recorded in writing by both parties. The levels shall
be taken on a grid with points at not exceeding 15 metres centres and the Contractor
shall construct concrete pilot pillars to the satisfaction of the Engineer's Representative
to enable the grid lines to be located during the filling operations. The Contractor shall
construct sufficient tell tales, consisting of 50mm x 50mm x 10mm angle of adequate
length with a flange of 900mm in diameter fixed at one end, all in non corrosive metal,
to the satisfaction of the Engineer's Representative, to enable any subsidence of the
original ground level to be measured. The method of measurement of hydraulic sand fill
shall be on the basis of the volume of material placed as determined from the area filled
and the depth of fill to the finished level from the original ground level or the subsided
original ground level, as applicable. Should any dispute arise as to the subsided original
ground level, as indicated by the tell tales, then the same shall be determined by the
taking of borings or by the digging of trial pits. Payment for trial pits shall be from the
appropriate item, in the bills of quantities. Where no such item is included, payment will
be from appropriate provisional sum. If option of trial pit is chosen shuttering shall be
provided to check the collapse tendencies of sand fill.
Hydraulic sand fill shall be deposited in layers as directed by the Engineer, but in
any case the thickness of such layers shall not exceed the limits stipulated as follows:
(A) First Layer not exceeding 450mm in thickness
165
Contractor and the Engineer's Representative. A tolerance of 75mm above or below
the finished level may be permitted during pumping operations, but the same shall be
made good by subsequent grading or dozing to the satisfaction of the Engineer's
Representative and to the tolerances stipulated for the sub grade. Without limiting his
commitments under the terms of the contract, the Contractor shall not be required to
make good any normal expected settlement of the original ground levels after
completion of the sand fill. The Contractor shall be deemed to have allowed for all the
foregoing provisions in his rates and prices for sand filling. Should the Engineer so desire
the Contractor shall place stock piles of material in quantities and areas as directed.
Payment for theses stock pile shall be made at the tendered rates and prices for
hydraulic sand fill.
The Contractors shall keep all excavations free from water and shall at their own
expense construct such temporary grips and ditches and provide and maintain pumps as
may be found necessary for this purpose. Excavation free from water may be possible
if underground design formation level is not close to the water level.
SLIPS 6129. 滑坡
During the carrying out of excavations the Contractors shall limit vertical and
other temporary faces to such heights as are suitable to the nature of the soil exposed.
If in the course of the works, any slips, slides, or subsidences occur and such slips,
slides or subsidences extend beyond the lines and slopes and below the levels shown
on the drawings, the excess excavation will not be paid for and the Contractors shall at
their own expenses carry away such materials and make good in a manner satisfactory
to the Engineer's Representative and without extra charge.
Payment shall be made under this clause for any material removed as unsuitable
soil only on the written direction of the Engineer's Representative provided such
unsuitable material could not have been discovered during the tendering period.
Measurement for this item shall be on the compacted backfill only and payment
for this work will be at the rates entered in the bill of quantities for earthworks.
Certain existing swampy areas on the proposed line of reconstruction may have
166
been delineated on the drawings.
The attention of the Contractor is particularly drawn to the fact that, under the
provisions of this specification, he is responsible for the safe passing of traffic in such
areas and that the cost of any diversions which may be required for this purpose are
deemed to be included in the tendered rates and prices.
The Contractor shall programme and execute his earthmoving operations such as
to complete the embankments in swamp areas prior to initiating work or other
embankments and to allow minimum settlement periods as specified in volume III, or as
agreed by the Engineer to elapse between first raising the embankments to the specified
finished surface level in the area or such other level as may be required and the start of
the construction of any part of the pavements, drainage or other permanent works in
the area.
Prior to, during and subsequent to the settlement periods specified above the
Engineer's Representative will carry out investigations in filled sections of swamp areas
to collect information on which to base predictions of the magnitude and rate of
settlement which will occur after completion of the works. Such investigations will be
undertaken, to ascertain, inter alia, the strength, compressibility of ground beneath
embankment, ground water levels and vertical settlements and they will be made by
means of various measuring devices. The results of such tests shall be used by the
Engineer's Representative to predict the equitable surcharge to facilitate early maximum
settlement.
The measuring devices shall be supplied and installed by the Contractor using
methods approved by the Engineer. They shall be read by the Engineer's
Representative. The Contractor shall supply such skilled and unskilled assistance as the
Engineer may direct.
The Contractor shall be deemed to have allowed for any reduction in the
efficiency of his operation and for any delays or stoppages caused thereto by the
installation, testing and reading of the various measuring devices and the avoidance of
damage or disturbance thereto.
As a result of the investigations described above, The Engineer may direct the
Contractor to take measures to reduce or to compensate for settlements which will
occur in filled sections of swamp areas after completion of the Works. Such measures
167
shall consist of :
(ii) providing settlement allowances in the finished levels of the pavements, drainage
and other permanent works constructed in the filled sections of swamp areas.
The Contractor shall be deemed to have allowed for any reduction in the
efficiency of his operations and for any delays, stoppages or inconveniences caused
thereto (directly or indirectly) by the operation of this Clause.
The formation level shall be the level of the embankment or cutting in its final
168
shape after completion of the earthworks and before the superimposition of the sub
base course, base course, or hard shoulder, and before the surface material is applied.
All earthworks shall be graded to provide the required formation profile. The
Contractor may elect to leave sufficient material above formation level to protect the
formation and to delay the excavation of this material until preparation of the formation
can follow immediately. The subsequent removal and disposal of such material shall be
at the Contractor's expense. Cuttings other than those in rock shall not be excavated to
formation level in wet weather. If suitable material below formation level is damaged by
any cause such material shall be removed and replaced by properly compacted general
fill and such operations shall be at the expense of the Contractor.
Not less than 150 metres of completed subgrade shall be maintained in advance
of the paving operations at all times. Failure to comply with the provisions of this
paragraph will be deemed sufficient cause for stopping the paving operations until this
provision is met.
During the preparation of the formation, suitable motor graders shall be used
and shall be operated by highly experienced operators. Payment for work done under
this clause will be deemed to be included in the tendered rates for earthworks.
All slopes of cuttings and embankments shall be trimmed to the batters specified
by the Engineer's Representative with a permissible tolerance of plus or minus 50mm
measured at right angles to the batter. Payment shall be deemed to be included in the
tendered rates for earthwork.
When solid rock is encountered in excavations, the Contractor shall excavate and
dispose of such material as directed by the Engineer's Representative. The Contractor
shall not use explosives for excavations in rock without the prior written approval of the
Engineer. Where such approval is given, the Contractor shall provide proper magazines
in suitable positions for the storage of explosives and take all necessary precautions to
prevent any unauthorized issue or improper use of any explosives, to the satisfaction of
the Engineer's Representative. The Contractor shall comply with any regulations
regarding the times for blasting, sizes of blasts, loading of shots, provision of blasting
nets, etc., that the Engineer's Representative may prescribe.
"Solid Rock" shall mean any material having a volume greater than 0.30 cubic
metres that, in the opinion of the Engineer's Representative, can only be removed by
the use of sledge hammers and wedges (if removed by hand) or explosives and
pneumatic tools (if removed mechanically). Soft or decomposed material or boulders in
169
excess of 0.30 cubic metres which can be removed by dozing, pushing, rooting, ripping,
scarifying or by the use of other normal earth
moving plant shall not be classified as "Solid Rock".
Payment will be per cubic metre of "solid rock" excavated and disposed of as
directed by the Engineer's Representative. Should any difference of opinion arise
between the Contractor and the Engineer's Representative the matter shall be referred
to the Engineer, whose decision shall be final and shall be obtained before the material
is disposed of or covered up. If the Contractor is still not satisfied, the matter may be
referred to an Arbitrator.
Any material having a volume of less than 0.30 cubic metres or material, which
in the opinion of the Engineer's Representative can be removed by dozing, pushing,
rooting, ripping scarifying or by the use of other normal earthmoving plant shall be
classified as earthworks, and the cost of such operations shall be deemed to be included
in the tendered rates and prices for earthworks.
Existing borrow pits adjacent to the roadway shall be backfilled as and where
directed by the Engineer's Representative.
Such areas shall be backfilled with approved soil which shall be thoroughly
compacted throughout by power rammers or other approved methods, to a density not
greater than insitu density of the soil to promote vegetation growth as obtained in the
British Standard Compaction Test.
Measurement for this item shall be on the compacted backfill only, based on
initial and final levels, and payment under the relevant items of the bill of quantities,
shall include for benching and providing, placing, watering and compacting the material
to the required density as specified herein.
The Contractor shall bring to the notice of the Engineer’s Representative cases
where embankments are required to be sited over swamp or unstable ground. Where
such conditions exist the Engineer's Representative may direct that the first lift of fill
material before compaction can be increased to 450mm in order to establish firm ground
for the compacting plant. This may not be done without the written approval of the
Engineer's Representative and even if such approval is given, the Contractor is not
relieved of his responsibility to provide a well compacted stable embankment of the
same standard as the rest of the works.
BACKFILLING 6138.
170
inspected and passed the culverts and other structures which will be covered up.
When existing pipes and conduits have insufficient earth cover during
embankment construction, the Contractor shall protect them against damage by his
equipment and operations. The embankment above and for a distance of not less than
600mm each side of such facilities shall be compacted by such means as the Contractor
may choose so as to prevent damage to such facilities. The Contractor shall repair or
make good any damage to such facilities that may be caused by his operations.
Any space over the culverts and between the sides of the culvert and the walls of
the excavations shall be filled with selected material in a damp state approximating to its
optimum moisture content. The material shall be thoroughly compacted by hand or
power rammers to not less than the dry density specified in Clause 6125. The cost of all
backfilling as specified herein shall be deemed to be included in the tendered rates and
prices.
Except where otherwise directed, the Contractor shall keep grassed areas
mowed or cut until the commencement of the period of maintenance. The grass shall
be cut three times during the growing season, or as often as it may be necessary.
Roadside drainage ditches shall be constructed to the lines, grades and levels
171
shown on the drawings or as directed by the Engineer's Representative. Where ditches
collect surface water along their length and if he considers it necessary, the side at
which the water enters the ditch shall be protected by constructing a bund and by
allowing the water to enter the ditch only at specific points through the bund.
Where the gradient of the road is flatter than 1 in 120 the ditch shall be
deepened to provide an adequate drainage slope. All ditches with a gradient steeper
than 1 in 120 shall be paved in the invert with small stones embedded in the bottom of
the ditch and for a height of 150mm up the sides. Pitching with small stones if ordered
by the Engineer' Representative shall be paid for separately.
Payment for roadside drainage ditches is covered under earthworks and shall
include for all trimming, shaping and bunding required.
Spoil excavated from drains shall, where suitable be incorporated in the filling,
and the quantity so used shall be deducted from the quantity of fill. No spoil shall be
placed within 2 metres of the drain.
Use shall be made of suitable roadside ditches at the discretion of the Engineer's
Representative.
Concrete drains shall be constructed to the lines and levels shown on the
drawings, or as directed by the Engineer's Representative and shall comply in all
respects with the requirements stipulated for mass and reinforced concrete. The grade
of concrete and quantity and size of reinforcement to be used shall be as shown on the
drawings or as directed by the Engineer. The invert of drains shall be trowelled to a
smooth finish and the inside face of walls shall be left with a fair finish as obtained from
wrot shuttering.
Where possible, spoil excavated for the construction of the drains, if suitable,
shall be incorporated in the filling and payment will be made, once only, under the
appropriate item for earthworks in the Bill of Quantities. Otherwise, the material
excavation shall be disposed of as directed by the Engineer's Representative, and paid
for under the appropriate item in the Bill of Quantities.
All water appearing on the formation as surface water held in depressions and
potholes and sub-soil water which in any way affects the stability of the formation or
pavement shall be carried to the side drains in rubble or stone filled drains, to the
approval of the Engineer's Representative.
Graded stone filling shall be hard and durable and shall consist of broken rock or
gravel. It shall be well graded with a maximum size of 75mm and the percentage
passing a 38mm sieve shall not exceed 5%. Graded stone filling shall be placed in layers
not exceeding 225mm loose depth and shall be well rammed as filling proceeds. Stone
filled drains on side slopes shall be constructed prior to any surface soiling and grassing
172
Pipes for sub soil drains shall be mainly slotted flexible PVC pipes or perforated
concrete pipes with ogee joints or perforated corrugated metal pipes. They shall be laid
with dry joints. The pipe trenches shall be filled with graded stone filling which shall be
carefully placed and packed in layers not exceeding 225mm in loose depth.
Stone filled pipe drains on side slopes and margins shall be constructed prior to
any surface soiling and grassing. Payment for work done under this clause shall be at
the rate entered in the Bill of Quantities.
Once the formation has been prepared water should be pumped out of the
section to allow perforated pipes to be laid across the section in close proximity to
enable water flow into it, and get channelled out of the roadway. Thereafter the pipes
are to be covered with specially selected granular materials which will serve as weep
holes over and above the perched water level, before approved fill is laid and compacted
to not less than 95% MDD at a moisture not less than 2% above OMC using sheepsfoot
(Taper-foot) roller up to a depth of 600mm below formation level, thereafter 100%
compaction at OMC of compactive effort will apply. Compaction depth shall not be
greater than 150mm per layer.
may be necessary particularly if the crown of the road is within one metre from
the level of the perched water table.
Cut-off ditching, metre drains turn-outs and culvert outfalls, including bunding as
and where required by the Engineer's Representative shall be constructed where shown
on the drawings or as directed by the Engineer' Representative and will be paid for
under the appropriate items of the bill of quantities. Payment shall include for all
trimming, shaping and bunding.
Excavation for drainage works shall be carried out to the lines, levels and depths
shown on the drawings or as directed by the Engineer's Representative and in such a
173
manner that the stability of the sides and bottom of the excavation is ensured.
Excavation shall be kept from water until, in the opinion of the Engineer's
Representative, concrete or other works therein are sufficiently set and any filling has
been completed.
Trenches shall be excavated through natural ground, or, where pipe culvert
structures are to be placed under embankment, the Contractor shall, unless otherwise
directed, complete the construction of the embankment to a minimum elevation of
300mm above the elevation of the top of pipe. The pipe trench shall then be excavated
and the pipe placed in the trench. The width of trenches at any point below the top of
the pipe shall not be greater than the outside diameter of the pipe at the bell or bank
plus 900mm to permit satisfactory jointing and thorough tamping of the bedding
material under the pipe. Sheeting and bracing, where required, shall be placed within
the trench width as specified. Care shall be taken not to over excavate. Where trench
widths are exceeded, redesign with a resultant increase in cost of stronger pipe or
special installation procedures will be necessary. Cost of this redesign and increased
cost of pipe or installation shall be borne by the Contractor.
The width of trench for structural concrete pipe culverts shall not exceed the
widths shown on the Drawings or as specified above, and these widths shall be
maintained to a height of at least 300mm above the top of the barrels of the pipes.
Rock encountered in trenches for pipes shall be excavated to the depths shown
on the Drawings. Where no depths are shown it shall be excavated to a depth 150mm
below the intended level of the bottom of the pipes and replaced with granular bedding
or concrete grade 10 N/mm2 as directed by the Engineer's Representative.
The rate for excavation shall include for any extra width over the net width
which the Contractor may consider to be necessary. The rate for excavation shall also
include for any timbering, shoring, strutting, or pumping if required, backfilling and
compaction and for the disposal of surplus material as directed by the Engineer's
Representative to a distance not exceeding 1.6 kilometres. Soft yielding material shall
be dug out and replaced with approved selected material compacted to 100% of its
maximum dry density obtained in the West African Compaction Test. All backfilling shall
be compacted to 100% of its maximumdry density obtained in the West African
174
Compaction Test.
The Contractor will be required to excavate and demolish existing culverts as and
where directed by the Engineer's Representative. Materials from the demolition will be
disposed off as directed by the Engineer's Representative. Where the culvert has been
demolished the area will be backfilled with suitable material as specified in the relevant
clause of the specification.
Payment will be made under the appropriate items in the Bill of Quantities, and
shall include for excavation, demolition and disposal of materials and backfilling, all as
specified herein.
Where specified on the drawings, all pipe culverts shall be bedded on and
haunched with a minimum of 150mm thickness of Grade 15 N/mm² Quality Concrete.
(a) Unreinforced concrete pipes shall comply with B.S 556. They shall be
unreinforced standard pipes and the following shall apply:-
(4) Tests other than the manufacturer's quality control tests will not be
required.
Unreinforced concrete pipes shall be surrounded with concrete and the pipe
trenches shall be filled to natural subgrade level with special granular fill.
No concrete shall be placed around any length of pipe until the Engineer's
Representative has approved the laying and jointing of same.
Special granular fill shall be placed and thoroughly compacted in layers not
exceeding 250mm loose depth.
175
(b) Structural concrete pipes shall comply with B.S 556. They shall be reinforced
extra strength pipes of the Class specified on the Drawings and the following
shall apply:-
(1) Joints shall be flexible spigot and socket type with rubber gaskets and
performance data will not be required.
(4) Tests other than the manufacturer's quality control tests will not be
required.
Pipes shall be laid true to line and level and each pipe shall be separately boned
between sight rails. Immediately prior to laying, pipes shall be examined for defects
and no defective materials shall be incorporated in the Works. Where non
standard lengths of unreinforced concrete pipe are required at catch pits, headwalls,
outfalls and the like, the pipes shall be cut and the ends made good. Where it is
necessary to cut structural concrete pipes, they shall be sawn and the cut end shall be
cast into the manhole catch pit headwall etc. so that at least 75mm concrete cover is
provided.
Ogee joints shall be thoroughly cleaned before laying and 1:2 cement sand
mortar shall be evenly applied to the ends so as to completely fill the joint. The pipes
shall then be properly drawn together, the outside of the joint shall be neatly pointed
and any surplus mortar on the inside of the joint shall be removed.
Structural concrete pipes shall be laid and joined in accordance with the
manufacturer's recommendations and the methods recommended for flexible jointed
pipes in National Building Studies Special Report 35 'Pipe Laying Principles'.
Care shall be taken to ensure that excess cement mortar and earth or other
material is thoroughly cleaned out of the pipes. Cleaning shall be carried out during the
laying of the pipes by drawing a timber badger through the pipes at a distance of 2
pipes lengths from the last made joint or by other means acceptable to the Engineer's
Representative. The timber badges shall be not less than 450mm long and shall have a
diameter 12mm less than the internal diameter of the pipe. The badger shall only be
removed from the pipe in the presence of the Engineer's Representative.
If for any reason, the invert level of a pipe culvert is such that the depth of cover
at the edge of the pavement is less than 600mm or the diameter of the pipe, then, on
the instruction of the Engineer's Representative the culvert shall be given a complete
176
surround 150mm thickness, of Grade 15 N/mm² quality concrete in place of a concrete
haunch, and payment shall be made for same at the appropriate rates in the Bills of
Quantities.
The outlets of pipe culverts shall be pitched with stone to a minimum length of 2
metres from the face of the culvert or as directed, and the level of the pitching shall be
at least 75mm below the culvert invert. The width of pitching shall be decided on site
by the Engineer's Representative. The inlets of culverts shall be pitched only where
directed by the Engineer's Representative. In cases where pitching is unobtainable the
Engineer's Representative may order a 150mm thick apron of Grade 15 N/mm² concrete
to be constructed.
a. Backfilling trenches: After the bedding has been prepared and the pipe
installed, selected material from excavation or borrow pit, at a moisture content that will
facilitate compaction, shall be placed along both sides of the pipe in layers not
exceeding 150mm in compacted depth. The backfill shall be brought up evenly on both
sides of the pipe for its full length. Care shall be taken to ensure thorough compaction
of the fill under the haunches of the pipe. Each layer shall be thoroughly compacted
with mechanical tampers or rammers. This method of filling and compacting shall
continue until the fill has reached an elevation of at least 300mm above the top of the
pipe. The remainder of the trench shall be backfilled and compacted by spreading and
rolling, or compacted by mechanical rammers or tampers in compacted layers not
exceeding 150mm. Tests for density will be made as necessary and directed by the
Engineer, at no expense to the Contractor.
b. Backfilling pipe in fill sections: The fill material shall be uniformly spread
in layers longitudinally on both sides of the pipe, not exceeding 150mm in compacted
layer and shall be compacted by rolling parallel with pipe or by mechanical tamping or
ramming. Prior to commencing normal filling operations, the crown width of the fill at a
height of 300mm above the top of the pipe shall extend a distance of not less than twice
the outside diameter on each side of the pipe, or 4m whichever is less. After the
backfill has reached at least 300mm above the top of the pipe, the remainder of the fill
shall be placed and thoroughly compacted in layers not exceeding 150mm.
177
EXTENSION OF EXISTING PIPE CULVERTS 6147.
Existing pipe culverts shall be extended to the lengths shown on the drawings or
as directed by the Engineer's Representative. The extension shall be of a similar
diameter to the existing culvert, and constructed in a like manner. Where existing
headwalls occur within the carriageway width they shall be removed to a minimum
depth of 300mm below new road level and the new road constructed to the profile
shown on the drawings.
The existing culvert and the new extensions shall be cleaned out and flushed as
necessary on completion to clear all dirt, cement mortar and other obstruction to allow
the free passage of water through its full internal area.
If so directed by the Engineer, the existing culverts which are to be retained and
do not already have a complete surround or haunch of concrete as required, shall be
dug out and the surround or haunch completed by 150mm of concrete as specified for
new culverts.
Access culverts shall if sufficient cover is not available for pipe culverts, be
constructed in the form of a small slab or box culverts to the grade, sizes and
dimensions shown on the drawings or as directed by the Engineer's Representative.
The roof and floor slabs shall consist of grade 25 N/mm² concrete reinforced as shown
on the drawings. The walls shall consist of grade 10 N/mm² mass concrete.
Construction shall comply with all relevant clauses of the specification or such
modifications as the Engineer may decide. The headwalls shall be constructed of
precast concrete blocks with a 6:1 sand cement mix.
Box culverts shall be constructed to the grades, sizes and dimensions shown on
the drawings, or as directed by the Engineer's Representative, and the finished surface
shall be smooth and regular free from flaws, air holes and excrescences and with a
constant grade.
The grades of concrete and quantity and size of reinforcement to be used shall
be as shown on the drawings and shall comply in all respects with the requirements
stipulated for mass and reinforced concrete.
Culvert construction shall comply in all respects with the requirements of this
specification or such modification thereof as the Engineer may decide.
The Engineer shall provide the Contractor with additionaldrawings for the
construction of the extensions to the existingsmall section box culverts. Measurement of
the works incorporated in these extensions shall be as for new reinforced concrete box
178
culverts.
The existing culvert and the new extensions, shall be cleaned out and flushed as
necessary on completion to clear all dirt, cement mortar and other obstructions to allow
the free passage of water through its full internal area.
For multiple structures, the minimum clearance between each pipe or pipe arch
shall be not less than half of the maximum cross
sectional width of the pipe or pipe arch. The minimum depth of compacted cover
(excluding the base course) over any pipe or pipe arch shall be at least 300mm. The
maximum depth of fill over any pipe or pipe arch shall not exceed the manufacturer's
recommendation for the particular gauge of culvert used.
Corrugated metal pipes culverts and channels shall comply with the materials
section Standard Specification for Corrugated Metal Culvert Pipe, Designation M36
60 of the American Association of State Highway and Transportation Officials except
that:
(i) The pipes culverts and channels shall be manufactured from steel
complying with B.S 1449: Part Al, or Part l B with copper content when
required at 0. 2 per cent minimum.
(ii) The pipes culverts and channels shall be coated with spelter complying
with B.S 729: Part l, alternatively the pipes may be manufactured from
steel sheet complying with B.S 2989.
(iii) The pipes and culverts shall be bitumen coated in the course of
manufacture as specified hereinbelow.
Where available, all culverts shall be factory coated with a double layer of
protective bitumen. Where the culverts are not factory coated, i.e. in the case of the
large diameter or multiple culverts, the Contractor shall apply two coats of approved
bitumen, as a protective measure, to the satisfaction of the Engineer's Representative,
179
and the Contractor shall be deemed to have allowed for this in his tendered rates and
prices. If for any reason, such as the acidity of the sub soil water, the Engineer
considers any further protective measures to be necessary, the Contractor shall carry
out same as directed and shall be paid at rates to be mutually agreed between the
Engineer and the Contractor.
The Contractor shall take every precaution to ensure that the protective
coatings, including galvanizing, are not damaged in any way during transporting,
storing, assembling or laying of the culvert, and he shall make good any such damage to
the satisfaction of the Engineer's Representative and at his own expense.
(1) Bitumen - Bitumen for coating shall have the following properties: as
in Table VI -3 below:
The positions, lengths, dimensions and levels of all culverts including aprons shall
be as shown on the drawings or as directed by the Engineer's Representative. The
culvert shall be cleaned out and flushed as necessary on completion to clear all dirt, and
other obstructions to allow the free flow of water through its full internal cross
sectional area.
The outlets of all culverts shall be protected from erosion by stone pitching or
concrete to a minimum length of 2 metres from its face. The width of the pitching or
concrete shall be decided by the Engineer's Representative and a toe
wall 450mm deep shall be constructed at the edge of such pitching or concrete. The
inlets to culvert shall be similarly protected, only where directed by the Engineer.
Where the gradient of the roadside drainage ditch would be excessive if the ditch
180
were graded to the invert level of culverts, catchpits or balancing ponds shall be
constructed as and where directed by the Engineer's Representative. The catchpits shall
be constructed of mass concrete to such dimensions as required by the Engineer's
Representative.
Before any drain or culvert is brought into use the Contractor shall ensure to the
satisfaction of the Engineer's Representative that it is free from all extraneous material,
all such material being completely removed from the site.
During the period of maintenance the Contractor shall ensure that the drains and
culverts shall be kept clear of all obstructions and before the maintenance certificate is
granted all drains and culverts must be cleaned out to the satisfaction of the Engineer.
All costs incurred shall be deemed to be included in the tendered rates and prices.
PITCHING 6154.
Pitching shall be measured per square metre of complete pitching and payment
will include for the supply of all materials, labour etc., and the construction of the
completed pitching shall be as specified in this Clause. Catchpits where required may
also be constructed in pitching stone laid in cement mortar as directed on site by the
Engineer's Representative, and measurement shall be per square meter of wall.
Payment for toe walls shall be based on the length of wall constructed and shall include
for excavation and backfilling.
The Contractor shall not commence work on the sub grade, sub base course,
base course or surfacing until he has obtained the Engineer's Representative's approval
of the plant, materials and methods that he proposes for clearance, excavation, mixing,
transporting, heating, spreading, grading and compacting the same as appropriate
compaction tests will be required before such approval is granted.
181
The foregoing provisions shall not prevent the Engineer from requiring the
Contractor to vary his plant, material or methods at any time during the execution of the
works, should he considers this essential for carrying out the contract. The Contractor
shall not vary plant, material or methods which have been approved by the Engineer's
Representative without previously obtaining his approval of such variation.
The Contractor shall ensure that the passage of any vehicle or plant over the
partially completed pavement or over the sub grade, sub base or base does not occasion
any rutting or other damage or disturbance to the partially completed works, and should
such rutting or other damage or disturbance occur, the Contractor shall make the same
good as directed by the Engineer's Representative at his own expense.
Vehicles and plant passing repeatedly over the partially completed pavement or
over the sub grade, sub base or base shall not be allowed to travel in a single track, but
such traffic shall be spread out over as great a width as practicable. There shall be no
storage or stockpiling of materials on top of partially completed pavements or on the
base, sub base or sub grade.
The Contractor shall provide all water necessary for the construction of the sub
grade, sub base, base and pavement surface. Such water shall be clean and free from
organic matters, waste matter or other harmful or deleterious substances, and shall be
obtained from an approved source.
The Contractor shall provide all plant necessary for conveying and distributing
water. Where it is necessary to increase the moisture content of materials comprising
the sub grade, sub base or base, the water shall be evenly sprinkled on the surface of
the soil by spraying machine of a type or types to be approved by the Engineer's
Representative, such machines being capable of uniformly distributing the water at a
known predetermined and constant rate.
ROLLERS 6158.
182
expressed dividing the total load of the roller by the foot area (square centimetre) in
contact on hard ground.
The distribution of wheels on any roller shall be such that the whole of the
ground surface within the width of the roller is loaded during each pass of the roller.
Where vibratory compactors or power rammers are used on the works they shall
be of the type approved by the Engineer's Representative and shall be capable of
obtaining the specified degree of compaction approved.
Measurement shall be based on sections taken before and after excavation of the
trenches but payment shall not be made for excavation in excess of that specified and
required to receive the specified pavement.
The maximum amount of trench excavation shall be placed to fill and payment
shall be made once only as decided above.
The sub grade whether in trench excavation or construction shall be graded and
compacted to such level as will permit the works to be constructed to the required
thickness and specified finished levels and tolerances.
183
All loose pieces of stone or other material exceeding 75mm in size in any
dimension shall be removed from the surface of the subgrade before compaction is
commenced and disposed of as directed by the Engineer's Representative.
The Contractor shall then compact the whole of the subgrade by the use of
approved smooth wheeled, sheepsfoot or pneumatic tyred rollers, static or vibratory
type as approved by the Engineer's Representative.
Final compaction shall be by smooth wheeled roller. The density required shall
be 100 per cent of the maximum dry density obtained in the British Standard
Compaction Test.
Payment for compaction of sub grade will be made once only either through
earthworks items, or other appropriate items in the Bill of Quantities.
Immediately before the construction of the subbase course, the upper surface of
the sub grade shall be tested for smoothness and accuracy of formation and if any areas
are found to lack the required smoothness or accuracy, such areas shall be scarified,
reshaped, re-compacted as specified, or otherwise treated as the Engineer's
Representative may require until the required smoothness and accuracy is obtained.
The finished surface of the sub grade shall be left as smooth as possible and the
accuracy of finish in the longitudinal direction shall not vary at any point by more than
12mm from a 50 metre straight edge, placed in any position on the finished surface
parallel to the centre line. The transverse profile shall conform to the same accuracy
using a correctly shaped template instead of the straight edge. The level of any point
on the aforesaid surface shall not vary by more than 12mm from the finished level of
the pavement less the specified thickness of the pavement construction. Payment for all
of the work required by this clause shall be deemed to be included in the tendered rates
and prices.
The requirements of this clause shall not be held to apply to the existing
bituminous surfacing scarified, shaped and recompacted on lengths of strengthening of
the existing alignment. Payment for all of the operations required under this clause
shall be deemed to be included in the tendered rates and prices.
On completion of the carriageway and hard shoulders, the verges and medians
shall be brought to finished level, shaped to the cross falls as shown on the drawings
and compacted so that the upper 150mm has a dry density of not less than 100% of the
maximum dry density as determined by the West African Standard Compaction Test.
Where the material forming the verges or medians is of such a nature that it is
liable to erosion, the Engineer may direct that the top 75mm of the verges or medians
be formed of cohesive lateritic soil, or other approved material, and the 75mm of filling
184
material below it shall be compacted in one operation to 100% of the maximum dry
density as determined by the West African Compaction Test. The selected lateritic soil
for the verges or medians shall be preferably a well graded lateritic soil with a plasticity
index of not less than 10 and not more than 20. Payment for this selected compacted
75mm of topping to the verges or medians shall be made under the appropriate item in
the Bill of Quantities.
The verges or medians shall be cleared of any windrows or heaps of material and
shall be graded evenly, as directed, so that water drains in the required manner. The
verges and medians shall be grassed, sealed or paved where directed by the Engineer.
Before grading work is commenced the vegetation and underlying topsoil within
excavation and embarkment areas shall be stripped off to a depth of not less than
100mm and not more than 150mm below the existing ground surface. Stripped material
which is or may be made suitable for topsoiling shall be stored and used therefore if
needed. Stripped topsoil in excess of the quantity required for the Project topsoiling
shall be stored at locations specified for future use of the Engineer. Topsoil shall not be
stored in areas where it will interfere with surface drainage or with the conservation of
trees, shrubs and other vegetation that are to remain.
Excavation not occupied by the catchpit cascade or by adjacent pipe drains shall
be backfilled with the excavated material which shall be placed and compacted in layers
not exceeding 225mm loose depth to a dry density equivalent to that of the surrounding
ground. Should the excavated material become unsuitable for backfilling due to any
cause, the Contractor shall provide other suitable material for filling at his own expense.
TESTS
The following tests shall be carried out on all material proposed for use as fill:
185
(I) PLASTICITY TESTS
Unless otherwise stated to the contrary, these tests shall be carried out as
described in section 1 of this specification.
The tests listed below will normally be required to be carried out for each 2
kilometres of sub grade or each layer of fill. The numbers and types of tests listed
however, are given only as a guide to the Contractor for tender purposes and the actual
number and type of tests which will be carried out during the construction of the works
will be determined entirely at the discretion of the Engineer.
Except where otherwise stated to the contrary, these tests shall be carried out as
described in section 1 of this specification, or where no such description is given in
accordance with the appropriate British Standard, AASHTO and ASTM Standards.
The sieve analysis shall be carried out in accordance with the standards laid
down in the latest amended report of the "Lagos materials testing Conference", a copy
of which shall be made available to the Contractor on request, or as per the latest B.S
1377.
186
The Contractor's attention is particularly drawn to the necessity for carrying out
trial sections with each type of proposed filling material prior to the start of the main
construction for the particular type of material, to determine the most efficient
technique, the most suitable compacted thickness of each layer and the suitability of the
proposed materials and plant, all as described in the Clause 1052 of this specification.
(1) LATERITE
GENERAL 6200.
MATERIALS
All materials for the sub base course, base course and hard shoulders shall be
selected by the Contractor. Where a preliminary soil survey has been carried out by the
Engineer, a copy of the report on the soil survey shall be made available to the
Contractor. Where no such soil survey has been carried out the Contractor shall make
his own arrangements for the location of borrow pits and sources of materials, and the
cost of any survey shall be deemed to be included in the tendered rates and prices. The
soil survey report of the Engineer, when available, shall be used for guidance only, and
shall not relieve the Contractor of his responsibility for executing the works in
accordance with the Conditions of Contract and this Specification. All selected material
shall be free of roots, vegetable matter, and other deleterious material and shall be
approved by the Engineer's Representative before its incorporation into the works.
Normally the minimum strength of such base course material shall not be less
than 80% C.B.R. value being determined at maximum dry density and optimum
moisture content unsoaked with either West African or Modified A.A.S.H.T.O.
compaction. However, where the Engineer's Representative considers it necessary on
account of perched water table or any other reasons, he may specify that a C.B.R. value
of 80% be obtained after at least 24 hours soaking. For construction on perched water
area see clauses 6142 and 6142A.
Base Course
187
The requirements below in Clauses 6250, 6251, and 6252 shall apply herein.
Sub-base Type 1
The sub-base material shall consist of pit run laterite, sand, or screening, and soil
of other similar binding or filler material and shall be obtained from approved sources.
The maximum dimensions of any particle shall not be greater than two thirds of the
compacted thickness of the layer in which it is to be placed. Oversize material shall be
removed by screens, grizzlies or by hand picking.
The gradation and soil constants shall comply to the requirements specified herein. The
material shall be free from vegetable matter, and excessive amount of lumps of clay,
and other objectionable or foreign substances.
75mm 100
600µm 25-60
425µm 10-40
75µm 5-20
The percent by weight passing the No-75µm sieve shall be less than but
not greater than 35%. The material passing the 425µm sieve shall have a liquid
limit of not more than 35% and a plasticity index of not more than 12, as
determined by American Society for Testing Materials methods, serial designation D
432-39 and 424-39 respectively or as determined by test No 2 or 2A and test Nos 3 of
B.S 1377 (1975). Prior to approval of the subbase material a test section shall be
constructed to the thickness shown on the typical pavement section and compacted to
100 percent of maximum density. When the test section is compacted to 100
percent maximum density at optimum moisture content, the subbase material shall be
of such quality that it shall have the minimum CBR of 30% after at least 24 hours
soaking. Once established that the subbase meets the CBR quality requirement at 100
percent maximum density it shall be placed and compacted in the field to that density.
The minimum strength of material for Subbase Course type 2, shall not be less than
20% CBR after at least 24 hours of soaking, for light traffic.
The C.B.R. values shall be assessed in the same manner as for base course, at the
optimum moisture content and maximum dry density of the West African Compaction
Test.
At the Engineer's Representative discretion material with a liquid limit greater than 35%,
and a plasticity index greater than 12 may be disallowed for use as subbase course or
188
base course.
If the Engineer's Representative is satisfied that good materials for base or subbase
course are not available, sub standard materials may be used adopting the following
guide lines.
Class A Materials
These are materials rejected either due to too much fine, silt, or clay content but slightly
fall short of strength specified.
(i) The material may be used by compacting it to a dry density slightly less than
maximum at moisture content slightly greater than OMC, to contain the tendency
for such material to swell or shrink due to cycle of weather. To make up for
strength deficiency, a ratio of strength proportion of the material to what is
specified shall be worked out and the depth of the subbase/base course
adequately increased to account for the deficiency.
(ii) On the other hand, where sand is available at economical rate, mechanical
stabilization shall be used to reduce the fines content thus increasing the
strength of the material.
It will be necessary to determine economic percentage of the sand required before the
method is put into use.
The gravels as excavated from the pits may contain oversize material and such material
must be broken down so that all material used in base course shall pass a 25mm sieve;
and that used in subbase shall pass a 50mm sieve. The work of breaking down or
disposal of such oversize material shall be deemed to be included in the tendered rates
and prices.
ROCK LATERITE FOR SUB-BASE COURSE AND BASE BASE COURSE 6202.
Rock Laterite for base course shall be hard and durable and shall be from a
source approved by the Engineer’s Representative. Samples of the stone shall be
submitted to the Engineer’s Representative for his approval and shall be tested by
soaking the specimen in water for 96 hours to ensure they do not disintegrate. The
stone shall not be less than 225mm deep, and shall be not less than 230 sq.cm. base
area, where the thickness of the course is 225mm. The percentage of wear shall not
exceed 50% as determined by ASTM C131-51 procedure.
189
Rock Laterite for blinding shall be clean crushed laterite aggregate graded from
5mm to dust from the same source as material for pitching, free from excessive clay or
silt.
WORKMANSHIP
The pavement construction for the roadway shall consist of the following as specified
herein and shown on the drawings:
(C) The laying and compacting of the sub base course and base course.
(D) The providing of prime and first coat bituminous surface dressing to the base
course of the carriageway if applicable.
The Contractor shall arrange and pay for any compensations or other payments
whatsoever required for access to and occupation and use of the borrow pits for course
and selected shoulder materials. The Contractor shall clear subbase, base the areas and
remove and stockpile overburden to such depths as may be required by the Engineer's
Representative. Under no circumstances will payment be made for removal of
overburden. Materials used which may include the incorporation of suitable overburden
as directed shall be taken only from such areas and to such depths and in such a
manner as the Engineer's Representative shall direct. The Contractor shall at his own
expense remove and dispose of all unsuitable materials, the removal of materials may
require prior rooting and scarification and the Contractor shall be deemed to have
allowed for this in the tendered rates and prices. The material as excavated may not fall
within the required limits of grading for the completed pavement and the Contractor
shall be deemed to have included in the tendered rates and prices for any additional
work which may be required to bring the material within the specified limits when laid
and compacted in the road bed.
Borrow pits shall be worked and drained so as to obtain the maximum quantities
of available suitable materials and shall be finally drained, levelled, and topsoil replaced
all as specified and to the satisfaction of the Engineer's Representative.
190
The width of the subbase course and base course shall be as shown on the
drawings or as directed by the Engineer. The compacted thickness of the subbase
course and base course is dependent on the C.B.R. values of the Sub
grade and that of the material used, and shall be as shown on the drawings or as
otherwise directed by the Engineer's Representative in accordance with the following
provisions:-
The specified combined thickness for the subbase course and the base course
has been derived from the pavement design diagram, curve E(RRL.RN/2503) based on
an anticipated minimum C.B.R. value (after at least 48 hours soaking) for the compacted
Sub grade. Where a C.B.R. value in excess of the anticipated value is achieved, then
compacted thickness of the Sub base course may be reduced at the discretion of the
Engineer's Representative and in accordance with curve E(RRL.RN/2803). Under no
circumstances shall the combined compacted thickness of the pavement be reduced to
less than 150mm.
Before compaction, the subbase course and base course material shall be
brought to the optimum moisture content for the compaction effort of the plant to
achieve the density specified. Where the existing moisture content of the material is
higher than this, the soil shall be allowed to dry out by aeration; where it is lower
sufficient water shall be added to the soil such that uniform wetting of the material to
optimum moisture content is achieved.
Compaction of the subbase course and the base course shall be carried out
separately, and shall begin immediately the soil has been brought to the required
moisture content and shall be carried out rapidly until completion. The compaction of
the subbase course and base course shall be carried out to a dry density not less than
100% of that achieved in the West African Standard Compaction Test at optimum
moisture content, but the compaction of the base course may be carried out to a dry
density of not less than 100% of that achieved in the Modified A.A.S.H.O. Compaction
Test at optimum moisture content, if so directed by the Engineer.
The base course shall be finished to camber or cross fall as shown on the
drawings or as otherwise directed by the Engineer's Representative.
Immediately before the construction of the base-course, the Sub base course
shall be tested for thickness, surface finish, and accuracy, and if any areas are found to
lack the required thickness surface finish, or accuracy or specified density, such areas
shall be scarified, recompacted to the specified density or otherwise treated as the
Engineer's Representative may require until the required thickness smoothness accuracy
or density is obtained.
The finished surface of the Sub base course shall be left as smooth as possible
and the accuracy of finish in the longitudinal direction shall not vary at any point by
191
more than 12mm for a 5 metre straight edge, placed in any position on the finished
surface parallel to the centre line.
The transverse profile shall conform to the same accuracy using a correctly shaped
template instead of straight edge. The level of any point on the aforesaid surface shall
not vary by more than 12mm from the finished level of the pavement less the specified
thickness of the base construction.
The thickness of the Sub-base course at any point shall not be less than the
specified thickness by more than 12 mm The Contractor shall include in his rates the
digging of trial holes, and making good same, to the satisfaction of the Engineer's
Representative.
Immediately before the application of the surfacing the base course shall be
tested for thickness, smoothness and accuracy as specified below and if any areas are
found to lack the required thickness, smoothness and accuracy or the specified density,
such areas shall be scarified, reshaped and recompacted with additional approved
material added where necessary or otherwise treated as the Engineer's Representative
may require until the required thickness smoothness, accuracy or density is obtained.
The finished surface of the base shall be left as smooth as possible and the
accuracy of finish in the longitudinal direction shall not vary at any point by more than
5mm from a 3.0 metre straight edge, placed in any position on the finished surface
parallel to the centre line. The transverse profile shall conform to the same accuracy
using a correctly shaped template instead of the straight edge. The level of any point
on the aforesaid surface shall not vary by more than 5mm from the finished level of the
pavement. The thickness of the base course at any point shall not be less than the
specified thickness by more than 12mm and the average thickness over a length of 0.4
kilometres shall be equal to, or in excess of the specified thickness. The Contractor shall
include in his rates for digging necessary trial holes, and making good same, to the
satisfaction of the Engineer's Representative.
The base course for the carriageway shall consist of approved rock laterite as
specified, laid to the required total thickness after compaction. The lumps of rock
laterite shall be tightly wedged across the prepared formation and interstices shall be
filled with approved spalls from the same source as the rock laterite before thoroughly
rolling. Rolling shall be carried out with a roller weighing not less than 58 kilograms per
centimetre width of roll and any depression or surface irregularity which occurs during
rolling shall be corrected with approved crushed quarry fines as specified, watered and
192
again rolled with a roller weighing not less than 58 kilograms per centimetre width of
roll.
No blinding shall be done until the rock laterite bottoming has been inspected and
approved by the Engineer's Representative. When completed the surface of the base
course shall be smooth and even, free from irregularities or loose material and true to
cross section, line and level as shown on the drawings.
If any clay or mud appears to the surface of the foundation, the Contractor shall
without additional charge dig out the affected areas of such depth as directed and make
good the foundation and finish in conformity with the adjacent surface.
The base course of the carriageway shall, where applicable, be provided with a
prime coat and other surfacing as specified in the relevant clauses of this specification.
The surfacing shall be laid as soon as possible after the construction of the base course.
Immediately before spraying of the prime coat, the surface of the base course
shall be swept clean, and all loose dust, dirt and the like removed. The Engineer’s
Representative may also direct that any very smooth surface to which the surfacing is
unlikely to adhere, be roughened with wire brushes or other approved means.
If any weak areas are found they shall be cut out and refilled with base course
material and rolled to correct cross-section and gradient.
The surface shall be slightly damped before the application of the prime coat
surface.
TESTS
TESTS FOR THE SELECTION OF LATERITE SUB BASE COURSE AND BASE
COURSE MATERIALS 6215
The following tests shall be carried out on all material proposed for use as
subbase course and base course:-
1. Plasticity Test.
2. Grading Test.
193
These tests shall be carried out as described in Section I of this specification.
The tests listed below will normally require to be carried out for each 2
kilometres of subbase course and base course. The numbers and types of tests listed
are, however, given only as a guide to the Contractor for tender purposes and the actual
number and type of tests which will be carried out during the construction of the works
will be entirely at the discretion of the Engineer's Representative:
CLASSIFICATION TESTS
CONTROL TESTS
20 No. Insitu dry density tests per 2 km in an alternate manner, i.e. Right, Centre,
Left, Centre, Right, etc.
Except where otherwise stated to the contrary these tests shall be carried out as
described in Section I of this specification or where no such description is given, in
accordance with the appropriate B.S.
The sieve analysis shall be carried out in accordance with the standards laid
down in the report of the "Material Testing Conference, February 1963" A copy of which
shall be made available to the Contractor on request.
ISO CBR is introduced because of the known factors that our pavement elements
i.e. subgrade, subbase and base courses are usually compacted at a higher moisture
content than the plant optimum moisture content (OMC). The word ISO means equal.
The procedure for establishing the control data with the working system is as follows:
When borrow pit is approved for fill after passing all necessary tests, as carried
194
out in the laboratory, three sets of moisture/density CBR tests shall be performed on the
specimen using the following levels of compactive efforts: (a) Sub-B.S., (b) B.S. and (c)
West African Standard. Each set of tests will have a minimum of five specimens. All
specimen shall be soaked ideally for 48 hours, however the following soaking periods
are recommended: for the southern part of the country 96 hours soaking whilst for the
north 48 hours to 24 hours soaking.
NOTE:- For Sub - BS compaction, the following shall apply:- Use CBR
mould, number of layers shall be three using 2.5kg rammer.
Height of fall = 300mm, Number of blows per layer shall be 25.
After determination of the dry density, moisture and CBR of each set of tests,
relevant graph of density/moisture of each shall be plotted. Thereafter the values of CBR
for compacted specimen so obtained shall be plotted as individual points on the
compaction curve of each set of specimen using corresponding dry density points.
Typical method of plotting ISO graph is shown in Fig. VI-1 while the completed
specimen of an ISO-CBR graph is show in Fig. VI-1A.
The above test will be performed on the materials approved for use as either
subbase or base course using the following compactive efforts: B.S., WAS and Modified
A.A.S.H.O. The results will be treated as above and relevant graphs with ISO CBR
plotted.
In our present day control system we have no method of checking whether the
compacted layer meets the specified CBR criteria, we are only concerned with 100%
relative density and moisture content relative to the laboratory design moisture and
invariably the laboratory determined OMC do not often tally with the plant OMC. We are
aware that maximum CBR can only be obtained around OMC if this moisture is not
achieved on site the strength of the pavement will be less than specified, if plant OMC is
less than laboratory OMC: meaning that the section is compacted to a moisture over and
above the plant OMC, thus producing a compacted pavement with weak strength.
When the density and moisture of compacted layer is determined, same is plotted on
the control graph and the field CBR is read from the ISO CBR line, this being the CBR
value of the pavement. This is a surer way of ascertaining that both the density,
moisture and required CBR are obtained on site.
The Contractor shall carry out trial sections with the proposed materials
prior to the start of the main construction to determine the most efficient compaction,
technique, layer thickness and suitability of the proposed materials and plants, as
described in the relevant clause of this specification. See clause 1052A for a rolling test
method.
195
(CLAUSES 6218 - 6219 INCLUSIVE NOT USED)
DESCRIPTION 6220.
Soil cement shall consist of a course or courses composed of soil stabilized with
portland cement. It shall be constructed on prepared and accepted subgrade, subbase
or existing pavement in accordance with these specifications and in conformity with the
lines, grades and typical cross sections as shown on the drawings and compacted to a
specified finished thickness to the satisfaction of the Engineer.
FIGURE VI-1
FIGURE VI-1A
The materials used for soil-cement stabilization shall comply with the following
specifications:-
(A) CEMENT The cement used shall be ordinary portland cement and
shall comply with B.S 12 or with the latest British standard specification
for the cement specified, or NIS 11 of 1974 or NIS 15 1980.
(B) WATER: The water shall be clean and free from harmful amounts of
alkalis, acids or organic matter. No water shall be used for stabilization
without the approval of the Engineer's Representative. The Contractor
may be required to collect samples of water in an approved manner and
to arrange for an analysis of the water by an approved testing agency.
(C) SOIL: The soil shall be free from roots, vegetable matter or other
deleterious substances. It shall be the nearest available approved
material which when stabilized with 3% - 7% cement shall meet the
design criteria specified in clause 6228 of this specification.
APPROVAL 6222.
Representative samples of all materials proposed for use in the soil-cement shall
be submitted to the Engineer by the Contractor at the Contractor's expense. The
Engineer will test the proposed materials and inform the Contractor if the tests indicate
compliance with the specifications. No material shall be used until it has been approved
by the Engineer. Permission to use any material shall not be construed as approval of
its source nor any acceptance as continued acceptance.
All materials to be tested shall be selected according to the method laid down in
the appropriate British Standard Specification and "Amended Decisions of Material
196
Testing Conference" or where there is no such standard by a method to be mutually
agreed between the Engineer and the Contractor.
Trial pits in a proposed borrow pit area shall be dug from original ground level
and not from the bottom of any existing borrow pits. Trial pits shall be at least 1.2 x 1.2
metres in size and dug to such a depth that the full extent of the material intended for
incorporation in the works is exposed.
Materials for testing shall not be taken from the spoil of the trial pit but shall be
made up of increments taken from each face of the pit after the overburden soil has
been removed. The four increments shall be mixed three times and quartered or riffled
down to the size required for testing.
Soil samples shall be taken by digging trenches across the full width of the
proposed pavement to the depth of processing so that soil sampled shall be the soil that
will be actually used ins oil-cement construction.
The tests are to be performed in accordance with the relevant B.S as modified by
the latest "amended decisions of Materials Testing Conference".
The stabilized soil shall meet the following specification for C.B.R test results.
The specimens shall be cured with a wax cover for 6 days and soaked for 24 hours
before testing, after allowing the specimen to drain for 15 minutes.
197
TABLE VI-5 DESIGN CBR VALUES FOR SOIL CEMENT MIX-IN-PLACE OR PLANT
MIX
METHOD OF CONSTRUCTION
DESCRIPTION OF TEST
MIX-IN-PLACE PLANT MIX
LABORATORY TEST ON MATERIAL MIXED IN
180% 160%
THE LABORATORY
LABORATORY CONTROL TEST ON MATERIAL
MIXED EACH DAY IN THE FIELD OR ON
100% 100%
CORED SPECIMENS FROM COMPLETE SOIL-
CEMENT PAVEMENT (AVERAGE)
LABORATORY CONTROL TEST ON MATERIAL
MIXED IN THE FIELD OR ON CORED
80% 80%
SPECIMENS FROM COMPLETED SOIL-CEMENT
PAVEMENT (MINIMUM)
(A) Classify the soil according to U.S public road Administration system
(B) The estimated range of cement content is determined using the A.A.S.H.O soil
group (shown in table VI-6 below)
(D) Perform B.S. compaction on the material to establish M.D.D and O.M.C using the
middle cement content e.g. (4.5)% cement for A-2 as shown in table VI-6 etc..
The C.B.R and U.C.S specimens shall be moulded to this density and moisture
content.
(E) Establish the relationship between cement content vs C.B.R. and U.C.S
(unconfined compression shear) for soaked and unsoaked specimens.
(i) Moulding 3 C.B.R specimens and 6 U.C.S. at each cement content, with a
minimum of three cement contents. e.g. for A-2 3%, 4.5% and 6%.
(ii) Wax and cure all specimens for 6 days (Except 3 U.C.S specimens at each
cement content which should be cured for 7 days and tested without
soaking).
(iii) Testing all C.B.R Specimen and the 3 U.C.S specimens at each cement
content after 24 hours soaking by complete immersion in water and
allowed to drain for 15 minutes.
198
Establish the required cement content at 180% C.B.R for site mix or
160% for plant mix and the corresponding U.C.S. values soaked and
unsoaked for quality control in the field.
ESTIMATED
PERCENT OF PERCENTAGE
CEMENT CEMENT
USUAL RANGE IN AMENDED
USED IN CONTENT BY
AASHO CEMENT CEMENT
MOISTURE / WEIGHT OF
SOIL REQUIREMENT CONTENT BY
DENSITY DRY SOIL
GROUP PERCENT BY WEIGHT OF
DETERMINA- FOR
WEIGHT OF SOIL DRY SOIL
TION BY MOULDED
WEIGHT OF SPECIMEN
DRY SOIL
A-1-4 4-6 2-4 3.0 2-3-4
A-1-B 4-7 2-5 3.5 2-3.5-5
A-2 5-8 3-6 4.5 2-4.5-6
A-3 6-9 4-7 5.5 4-5-6
A-4 7-11 5-9 7.0 5-7-9
A-5 8-12 6-10 8.0 6-8-10
A-6 9-13 7-11 9.0 6-9-12
A-7 10-14 8-12 10.0 8-10-12
Note: Heavy clay soils ranging from A-5 to A 7 should be avoided where practicable.
CONSTRUCTION 6230.
The Contractor shall submit to the Engineer for approval his method of
stabilization which may be based on either the mix-in place or plant mix principle.
Whichever method of mixing is used the maximum period between mixing of the
cement and final roll off of stabilized material shall be 2 hours. The lengths of the
treated sections shall be regulated to ensure that the 2 hours time limit is not exceed.
199
MULTIPASS-MIX-IN-PLACE METHOD 6231.
(A) Level pegs shall be set at 30 metres intervals and the base course
material to be stabilized imported from borrow pits, spread and shaped
to the required cross-section and longitudinal gradient. It may be
necessary to compact the base course material to obtain a fair estimate
to correct grade and cross-section. If the material of the existing
roadbed is to be used the surface shall be graded to required cross-
section and longitudinal gradient. The cross-section and grade shall be
checked by the Engineer's Representative before construction starts.
(B) The material to be treated shall be scarified to the required depth and thoroughly
pulverized (including pre-wetting the soil if necessary to aid pulverization).
Precaution shall be taken to obtain a uniform condition of the material for the full
depth and width to be treated. A pulverization of 80% (i.e. ratio of the weight of
soil mixture passing the 5mm sieve to the weight of the total representative
sample taken exclusive of the gravel retained on the 5mm sieve shall be
achieved before the cement is spread.
(C) Cement shall be spread uniformly over the pulverised soil. Cement may be
supplied in bags or in bulk. If bags of cement are used, the bags shall be placed
at calculated intervals along the verge, the bags opened and the cement spread
evenly on the pulverized soil by shovels and rakes.
(i) Loss of cement due to formation of clouds of cement dust during dry
mixing
The road mixing plant shall have provision for introducing water at the time of
mixing, through a metering device or by other approved method.
The water shall be applied by means of controls that will supply the correct
quantity of water to produce a complete mixture with a uniform moisture content.
Leakage of water from equipment will not be permitted and care shall be exercised to
200
avoid the addition of an excessive amount of water.
The procedure for construction with either windrout type or flat-type travelling
mixing plant shall be as directed by the Engineer.
COMPACTION 6233.
The mixing equipment shall be batch type mixing plant using revolving blade, or
rotating drum mixers or continuous type at the option of the Contractor. The soil, water
and cement may be proportioned either by weight or by volume.
The weights or rates of feeds of soil and water shall be within 5% of the amount
specified by the Engineer and the weights or rates of feed of cement shall be such that
the cement content in samples taken from any part of a mixed batch or from different
batches or from time to time from the product of continuous mixers or from mixtures
spread on the roadbed, shall not vary more than 0.4% above or below the designed
cement content by weight of dry soil.
The mixer shall be equipped with a sufficient number of paddles of a type and
arrangement to produce a uniformly mixed batch. The mixer platform shall be of ample
size to provide safe and convenient access to the mixer and other equipment. Mixer
and batch box housing shall be provided with hinged gates of ample size to permit ready
sampling from each of the plant bins and of the mixture from each end of the mixer.
The mixer shall be equipped with a timing device which will indicate by a definite audible
or visual signal the expiration of the mixing period. The device shall be accurate to
within 2 seconds. The plant shall be equipped with a suitable automatic device for
counting the number of batches. The time of mixing a batch shall begin after all
ingredients are in the mixer and shall end when the mixer is half emptied. Mixing shall
201
continue until a homogeneous mixture of uniformly distributed cement is produced. In
general the time of mixing shall not be less than 30 seconds, except that the time may
be reduced when tests indicates that the requirement for the variation of cement
content (±.4%) is being consistency compiled with.
When weight proportioning is used the discharge gate on the weight box shall be
so arranged as to blend the different sizes of the soil as they enter the mixer. Cement
shall be weighed on scales, separate and distinct from the soil batching scales.
A positive signal system shall be provided to indicate the level of the material in
each bin and as the level of the material in any one bin approaches the strike-off
capacity of the feed gate, the device will automatically close down the plant instantly.
The plant shall not be permitted to operate unless this automatic signal system is in
good working order.
The drive shaft on the soil feeder shall be equipped with a revolution counter
reading to 1/100 of a revolution and of sufficient capacity to register the total number of
revolutions in a day's run. The continuous feeder for the soil may be mechanically or
electrically driven. The continuous mixing plant shall be equipped with a hopper of at
least 0.6 cubic metre capacity which is divided into as many compartments as there are
sizes of soil being proportioned. The hopper shall be suspended under the soil feeders
on a scale frame in such a manner that the discharge from each soil feeder may be
diverted into separate compartments in the hopper when the feeders are in full
operation. The weight of a loaded hopper shall be indicated on a springless dial scale of
2,278 kilograms maximum capacity with 2 kilogram graduations. Each compartment of
the hopper shall be equipped with a gate so that each size may be withdrawn separately
202
on a conveyor below the hopper in order that the total weight of each size of soil may
be determined and representative samples obtained. The material so over withdrawn
may be returned to storage.
SPREADING 6239.
Side forms shall be set to the lines and grade as shown on the drawings. Forms
shall be of steel or stout timber and shall be of sufficient strength to resist springing out
of shape during placing of soil cement.
The mixed material shall be protected by covers against moisture loss while
being transported to the spreading site and each layer shall be spread in one operation
without segregation (not more than 30 minutes shall elapse between mixing and
spreading).
The spreader shall be provided with a screed that strikes-off and distributes the
material to the required width and thickness within 5% of the pre-determined rate. The
screed shall be adjustable to the required cross section. Screed action includes any
cutting, crowding, or other practical motion that produces a finished texture of uniform
appearance. If the spreader leaves ridges, indentations or other objectionable marks in
the surface that cannot be eliminated by rolling, or prevented by adjustments in
operation, its use shall be discontinued.
The use of motor grades, except for final trimming after compaction, will not be
permitted.
The mixed material shall be spread for the full planned width, either by one
spreader or by several spreaders operating in a staggered pattern across the subgrade
or subbase course, unless otherwise permitted by the Engineer or if traffic conditions
require part width construction. Should permission be granted or part width
construction be required, for the use of one spreader operating alternately on
continuous lanes, not more than 30 minutes shall elapse between the time of placing
material in adjacent lanes at any location. If longitudinal construction joints are
necessary they shall fall on lane lines.
Where the required compacted thickness is 150mm or less, the soil cement may
be spread and compacted in one layer. Where the compacted thickness is more than
150mm the soil cement shall be spread and compacted in 2 layers of approximately
equal thickness and the maximum compacted thickness of any one layer shall not
exceed 150mm or as directed.
Work on each layer shall be performed in a similar manner and the surface of
the compacted material shall be kept moist or prevented from drying out by a method
203
approved by the Engineer until covered with the next layer, either by using damp sand
or sacks.
Soil cement base course placed in inaccessible areas may be spread by approved
methods in one course. After spreading the material shall be thoroughly compacted to
the required lines and grades by means of pneumatic tampers or with other compacting
equipment which consistently obtains equal or better compaction than that specified.
Soil-cement shall not be mixed or placed during rain.
COMPACTION 6240.
(A) All rolling equipment shall be self-propelled and reversible and shall produce the
required compaction within the operation time. e.g. from mixing, wetting,
spreading and compaction.
(B) Initial rolling may be performed with smooth wheel steel-tyred rollers weighing
not less than 10,886 kilograms with a compression on the rear wheels of not less
than 58 kilograms of the tyre width, or with other compacting equipment which
consistently obtain equal or better compaction than that specified. Pneumatic
tyred rollers shall be the oscillating type and having a width of not less than 1.2
metres and equipped with pneumatic tyres of equal size and diameter. Wobble
wheel rollers will not be permitted. The tyres shall be inflated to 6.3 kg per sq.
cm. or such lower pressure as the Engineer may direct and maintained so that
the air pressure will not vary more than 0.35 kg per sq. cm. from the designated
pressure. Pneumatic-tyred rollers shall be so constructed that the total weight of
the roller can be varied to produce an operating weight per tyre of not less than
907 kilograms. The total operation weight of the roller shall be varied as
directed by the Engineer.
(C) Rolling tests shall be carried out to establish the plant maximum dry density
(MDD) its optimum moisture content (OMC) and the number of economic passes
to achieve the MDD see Table I-4 for guidance on performance of different
plants relating to MDD, and OMC of different types of soil.
(D) Rolling shall be performed in such a manner that bumps and irregularities are
eliminated and the finished surface shall be true to the required grade and cross
section within the tolerances specified.
Rolling shall commence from the outer edge of the verge to the centre of the
roadway except on super-elevated curves where rolling shall begin on the low
side and progress to the high side.
(E) Areas inaccessible to rollers shall be compacted to the specified density by other
means, approved by the Engineer.
(F) All compaction planes shall be removed. The finished surface shall be smooth,
dense and free of ridges or cracks. The surface shall be kept moist at all times
until the curing seal is applied.
204
FINISHINGS 6241.
The finished surface shall not deviate at any point in a longitudinal direction by
more than 5mm from 3 metre straight edge laid in any position on the finished surface
parallel to the centre line. The transverse profile shall conform to the same accuracy
when tested using a correctly shaped template. The thickness shall not vary more than
± 12mm from the design thickness of base at any point.
If the finished surface exceeds the above tolerance, the excess material shall be
trimmed with the least possible disturbance of the material to remain in place. The
excess material shall be removed and disposed of immediately after trimming and no
loose material shall be left on the base and the area shall be rolled again. Filling low
spots in the cement treated base will not be permitted.
At the end of each day's work or first thing in the morning a transverse vertical
construction joint shall be formed by cutting back 600mm into the compacted
soil-cement, and disposing of the material. Additional mixture shall not be
placed until the construction joint is placed. When starting the work the 900mm
section adjacent to the joint shall be thoroughly hand mixed.
(B) Longitudinal joints shall be constructed by cutting back vertically into the existing
stabilized material for approximately 75mm and the material cut away may be
disposed of in the adjacent lane to be constructed. The face of the cut joints
shall be moistened in advance of constructing the adjacent section.
CURING 6243.
Immediately after compaction the soil cement shall be cured for a period of 7
days by a 50mm layer of damp sand spread evenly over the surface. The
Contractor shall keep the sand damp and shall close the stabilized soil to all
traffic during the curing period.
The curing seal shall consist of liquid bitumen MC-O, or MC-1 unless otherwise
specified. The curing seal shall be applied at a rate between 0.68 - 1.13 litres
205
per square meter of surface and shall provide a continuous membrane over the
soil-cement pavement. The curing seal shall be applied as soon as possible, but
not later than 8 hours after the completion of final rolling.
The surface shall be kept moist until the seal is applied. No traffic or equipment
shall be permitted on the sealed base during the first 6 days after the application
of the curing seal, unless otherwise permitted by the Engineer.
(IV) STRENGTH
The frequency of these tests shall be one test for every 400 square
metres and part thereof of material laid in each layer.
206
compaction of each section. At lease one dry density test shall be carried
out for each 350 square metres of material laid in each layer, using the
sand bottle or other in-situ density testing equipment or the nuclear
gauge testing equipment approved by the Engineer. These tests may be
located where samples for CBR and/or UCS have been taken.
The thickness of the Soil-cement layer shall be measured using the in-situ
dry density holes, the thickness of cored specimens from hardened soil-
cement and any additional holes at the discretion of the Engineer.
CBR and UCS tests shall be carried out on cored specimens taken from
hardened soil-cement. The frequency of these tests shall be at least one
test for each 400 square metres and part thereof of material laid in each
layer. Sampling shall be in staggered pattern.
The results of all the tests mentioned in this section of the specification shall be
carefully recorded in a manner approved by the Engineer. The test results shall be
recorded in triplicate, one copy to be retained by the Contractor and the other two
copies to be handed to the Engineer's Representative.
In addition to these records required under the provision of clause 6245, above
the Contractor shall keep a record for each individual section of soil-cement construction
giving the following details:-
207
(VI) Complete mixing time.
SUPERVISION 6247.
The attention of the Contractor is drawn to the fact that he must provide
adequate experienced supervisory staff during all the stages of soil-cement construction.
GENERAL 6250.
In addition to any other clause of this specification the following shall be deemed
to apply in particular to crushed stoned base course, and shall be read in conjunction
with all other relevant clauses of the conditions of contract and this specification.
Materials for use as Stone base shall be classified under two categories i.e.
Coarse aggregate and Fine aggregate.
1. COARSE AGGREGATE:
Coarse aggregate shall be granite crushed stone sourced from approved Quarry
by the Engineer's Representative and shall have sizes ranging from 50mm and retained
on 5mm sieve. The aggregate shall be free from clay or silty materials, and when
subjected to 10% fine test or aggregate crushing value, the value of the results shall
range from 7.5% to 12.5% for 10% fine and not more than 35% for aggregate
crushing value. It shall also comply with other requirements under clause 2005 (1) and
(2)
208
(2) FINE AGGREGATE
Fine aggregate known as binder materials shall be materials passing sieve 5mm
and retained on 75µm sieve. It may be sourced from river bed at location
approved by the Engineer's Representative or be fines from crushed stone. It
shall be free from vegetation or other objectionable matter. Fine aggregate shall
be clean without any clay content, strong and sharp. It shall be of such grading
characteristic that when combined with coarse aggregate, the composite material
shall conform to the gradation and other requirements specified in clause 2004
(1-3).
(3) Liquid limit and Plasticity Index requirements stated herein shall apply to
any aggregate component that is blended to meet the require gradation and also
to the aggregate in the compacted base course. The portion of fine aggregate
passing the 75µm sieve shall be either non-plastic or shall have a liquid Limit not
greater than 30% and Plasticity Index not greater than 6. This index test will
only be applicable to materials for wet laying.
Firstly, grade the gradation aggregate and plot on the stone base design
envelope, next, grade the fine aggregate and plot in the design envelope. By
simple proportion and physical examination of the two graphs, guided by
experience ,two to three combination trials may produce the required
satisfactory grading that will fall into the envelope, otherwise simple calculation
may be used to achieve the required combination proportion.
Coarse aggregate of different sizes and the fine aggregate shall be placed in
different Bins. Each aggregate sizes and the fines shall be sieved and plotted on
appropriate log chart. Simple arithmetic calculation may be used to determine
the combination proportion. Alternatively, careful study of the graphs, coupled
with experience will enable user to guess the proportion by trial and error. Once
a suitable mix proportion is established, the grading of each size of aggregate
shall be checked from time to time, to ensure that there is no deviation or
variation.
209
(6) ESTABLISHING MIX CONTROL CRITERIA.
Unless directed to the contrary the six specimens will be tested for Dry Density
only. Alternatively 3 specimens may be soaked for 24 hours (complete
immersion in water with 25mm water head above the specimen) tested for CBR
after the specimen is allowed to drain for 15 minutes. The remaining specimens
shall be tested for CBR (strength) unsoaked. The average of two close results
shall be the CBR or Dry Density of the specimen. If CBR of over 100% is
obtained the dry density established with corresponding moisture content shall
be the design criteria and control for the works.
The grading of crushed stone for use in crushed stone base course shall be as
follows:-
210
Gradation requirement specified herein shall apply to the completed base course
after undergoing the mixing, placing, compacting and other operations. The
portion of the aggregate passing No 75µm sieve shall not be greater than one-
third of the portion passing the No. 425µm sieve. The aggregates shall
continuously be well graded within the limits of Gradation A, B. C, D or E as
specified below. The methods of test used will be ASTM Standards C117, C127,
C128, C136 and D422. Sieves shall conform to ASTM Standard E.11 or B. S.
sieve.
TABLE VI-7 GRADING ENVELOPE FOR STONE BASE COURSE WET METHOD
Note:- The table is based on aggregate of uniform specific gravity, and the
percentages passing the various sieves may require appropriate correction by the
Engineer when aggregates of varying specific gravities are used.
WORKMANSHIP
Note:- No subgrade shall be considered as a working platform for the stone base
as this will promote the early collapse of the pavement. This is due to the fact
that the elastic property of the subgrade (of which strain is a part) will not be
able to sustain the wheel load from the crushed stone base to the subgrade
without any intermediate superior layer.
FORMS 6254
211
Where kerb or concrete haunches are not specified, the Contractor shall ensure
that the edges of crushed stone base course, laid by either the wet or dry
process, are true to line and level and properly compacted to the same standard
as the test of the Base course by the use of forms, hunching stones or other
methods approved by the Engineer's Representative.
Crushed stone Base course laid by either the wet or dry method shall be laid in
layers of not less than 150mm compacted thickness to the satisfaction of the
Engineer’s Representative.
When crushed stone Base-course is to be laid by the dry process the method of
laying and compacting shall be as follows:-
(I) The coarse stone 75mm to 12mm or 50mm to 12mm shall be spread in a
manner approved by the Engineer's Representative to an even depth
which, after compaction will produce the specified thickness of layer.
(II) The coarse stone shall then be regulated and compacted by not less than
three passes of an approved roller.
(IV) The surface of the crushed stone shall then be checked transversely and
longitudinally for level and camber and any indicated variations adjusted.
The surface shall then be sprinkled with water from a water bowser and
rolled with a smooth wheel roller having a weight of roll of not less than
58 kilograms per centimetre. Voids in the Base-course which occur
during this process shall be filled by sweeping screenings into them.
The sprinkling, sweeping and rolling shall continue until all voids are filled
212
with grout to the satisfaction of the Engineer's Representative.
(v) The final surface shall be smooth and even, free from irregularities or
loose material and true to line and level having regard to the tolerances
for base course finish specified elsewhere herein.
When crushed stone Base course is to be laid by the dry or wet process the
method of laying and compaction shall be as follows:-
(I) The approved crushed stoned, graded as specified shall be mixed with
between 3% and 5% of water as directed in a mixer of a type approved
by the Engineer's Representative.
(II) The mixed material shall be protected from the rays of the sun during
transit from the mixer to the site in order to prevent loss of moisture due
to evaporation and shall be laid by a self-propelled asphalt finisher or
other approved plant in layers of not less than 75mm or more than
150mm thickness after compaction. During this operation care shall be
taken to avoid segregation.
(III) Water can only be added to any wet laid stone base if it was discovered
that evaporation had taken place during rolling. The finished rolled stone
base shall not have moisture less than 3% or more than 5% by weight
of dry aggregate.
(IV) The final surface shall be smooth and even free from irregularities or
loose material, and true to line and level having regard to the tolerances
for Base-course finish specified elsewhere herein.
Crushed stone Base course, laid by either the dry or wet process shall be
prepared for the addition of bituminous surfacing as specified under the relevant
parts of this section of the specification.
COMPACTION 6259.
213
(IV) CONCRETE CARRIAGEWAY CONSTRUCTION 水泥混凝土路面施工
GENERAL 6260.
MATERIALS
CEMENT 6261.
AGGREGATE 6262.
Fine and course aggregate for use in the manufacture of concrete for
construction of concrete carriageways shall comply with the requirements of all relevant
clauses of this specification regarding aggregates for use in concrete work.
Dowel bars and tie bars shall consist of mild steel complying with the
requirements of British Standard 15, free from oil, paint, dirt and loose rust.
Dowel bars for transverse joints shall be straight, free from burred edges or
other irregularities and shall have their sliding ends sawn, not sheared, unless otherwise
approved by the Engineer.
The length and diameter of dowel bars and tie bars shall be as shown on the
drawings or directed by the Engineer.
214
kinks, and where the top surface of the forms determines the finished level of the
concrete, it shall be accurate in manufacture to within a tolerance of ± 2mm in 3
metres measured in a vertical plane. Repaired forms shall not be used until inspected
and approved by the Engineer's Representative.
Forms to support rails on which the machine is to run shall be sufficiently robust
to support the weight of all plant running on them without deformation.
All rails shall be sufficiently robust to support the weight of all plant running on
them without deformation. They shall be free from warp, twists and kinks and accurate
in manufacture to within a tolerance of ± 2mm in 3 metres measured in a vertical plane.
Preformed joint filler shall be of the thickness shown on the drawings or directed
by the Engineer within a tolerance of ± 2mm. It shall be 25mm less in depth than the
thickness of the slab, within a tolerance of ± 3mm and of the full width between road
forms. Holes to accommodate dowel bars shall be accurately bored or punched out.
The material comprising joint filler shall be of approved quality, such that the
filler can be satisfactorily installed in position at the joint.
1. Class B or C. The joint sealing compound shall have the following qualities:
215
(c) It must be durable etc.
WORKMANSHIP
GENERAL 6270.
Where a concrete carriageway is constructed more than one slab wide, the first
slab or alternate slabs shall be constructed between two forms and the adjacent or
intermediate slabs shall be constructed by replacing the flanged wheels on one or both
sides of the machine with flangeless wheels, which can travel on the surface of the
concrete already completed, or on rails fixed to longitudinal timber laid on the
completed concrete to support the flanged wheels. Concrete slabs shall be at least ten
days old before they are subjected to the weight of the finishing machine, but, in
suitable weather, the Engineer's Representative may permit a shorter period provided
that adequate provision is made for protecting the surface of the slab on which the
wheels of the finishing machine run and provided that the wheels do not run nearer to
the edge of the slab than 150mm and provided further that the Contractor gives an
undertaking in writing to be fully responsible for any damage that may occur and to
repair same at his own expense to the satisfaction of the Engineer's Representative.
The thickness at any point shall be not more than 6mm thinner nor more than
12mm thicker than that shown on the drawings.
Compacting and finishing machines shall be approved by the Engineer and shall
compact and finish the concrete either by the action of vibration or by mechanical
tamping. The machine shall in addition have a strike-off blade or paddle-roller to control
the surcharge and a rear transverse oscillating screed.
216
WATERPROOF UNDERLAY 6274.
(II) Be bedded on a layer, about 50mm thick and for only the width of the form
base, of cement mortar or concrete of the same grade as the slab on a firm
foundation so as to ensure the necessary complete rigidity and stability. The
base on the line of the forms shall be thoroughly compacted before the forms
are set.
(III) Be as specified in Clause 6265 set to line and level and secured by using not less
than three pins for each 3 metres section, one pin being placed at each side of
every joint or as otherwise approved by the Engineer's Representative. Form
sections shall be tightly joined together by a locked joint free from play or
movement in any direction, so as to prevent the extrusion of concrete.
For machine laid concrete the form joints shall be made without any discontinuity
in the top surface of the forms and the levels at the joints between the forms shall,
where form and rail are not integral, be set within a tolerance of ± 3mm of the levels
shown on the drawings.
The wheels of finishing machines shall not be run directly on the top surface of
the side forms but on rails as indicated in clause 6266 or on the finished concrete as
provided in clause 6270.
For concrete to be compacted by vibrating screeds the setting of the forms shall
be such as to provide the accuracy of finish specified in the relevant clauses of this
specification.
217
the construction of the concrete road slabs. Care shall be taken that the concrete and
any projecting rods are not damaged in any way during the removal of the forms. The
concrete or mortar bed used at the longitudinal joint in partial-width construction shall
be removed at the same time if applicable and the subgrade and subbase made good to
the satisfaction of the Engineer's Representative.
(A) Be integral with the forms so that they remain rigidly fixed at all times, or
where independent, be mounted so that they remain rigidly fixed to the
approved mounting during the passage of the spreading and finishing
machines. The surface of rails shall be kept clean at all times.
(B) Be firmly supported along the length in such a manner that the finishing
machine can travel along the line of the carriageway at the correct level.
(E) Be so set that the screed of the finishing machine operates in relation to
the rail, not the form.
Where on checking it is found that any rail or the form on which it rests has been
disturbed or is incorrectly set, the rail shall be reset, and rechecked before placing of the
concrete between the forms is begun.
Rails may be removed in advance of removal of the forms on which they rest
provided that the latter are not disturbed by so doing.
The quantity and distribution of reinforcement shall be as shown on the drawings, with
such modification as may be necessary and approved by the Engineer’s Representative to suit
218
manholes and surface boxes, junctions or slabs of different width or length; or as are directed by
the Engineer's Representative. No loose rods or small pieces of fabric other than as provided for
in the specification shall be permitted in any portion of the work.
Steel fabric reinforcement for carriageways shall be as pecified in B.S. 1221. All
reinforcement shall be so placed that after compaction of the concrete it is in the
positions shown on the drawings and shall terminate 40mm from the Sedges of all joints
in the concrete unless otherwise specified.
Manholes shall be housed in separate small slabs, which shall be the size of the
exterior of the shaft and shall be formed by casting the main slab against boxes of this
size, made from formwork and accurately placed vertically above the exterior of the
shaft. This formwork shall be removed at the same time as the remainder of the
formwork for the slab. Expansion joint filler 10mm wide shall be placed against the
exposed edges of the slab, and reinforcing bars if shown on the drawings or specified
shall be placed accurately in position so as to give the required final cover, concrete
being placed by hand in the space intervening between the slab and the manhole frame.
This concrete shall then be compacted to the same density as that of the adjoining slab.
A sealing groove shall be formed and filled at the top of the joints with the
surrounding slab, in accordance with Clause 6283 the top arises of both slabs being
rounded to a radius of 6mm.
Dowel bars shall be provided at one end with a closely fitting sleeve 100mm
long, consisting of cardboard or other approved material. A loose plug equal in
219
thickness to the width of the expansion joint, and consisting of cotton waste or a disc of
expansion joint filler, shall be inserted within the sleeve at the end of the dowel bar.
The free half of each dowel shall be greased or painted with joint priming compound as
specified or directed. The method of assembling and securing joints shall be approved
by the Engineer.
Where contraction joints are required, these shall be formed by a groove sawn in
the surface of the hardened concrete and a timber fillet cast into the base of the slab, all
as shown on the drawings. The sawn groove shall be located vertically above the
timber fillet to within a tolerance of ± 12mm. Dowel bars shall be provided as for
expansion joints. Construction joints shall be installed only under the conditions detailed
in Clause 6287. They shall be formed by means of a drilled and split cross form which
shall allow tie bars to be inserted and which shall permit the reinforcement to project
through the joint for a distance of at least 400mm. On recommencing work the cross
form shall be removed and the vertical face of the concrete roughened. The next
reinforcing mat shall completely overlap the projecting reinforcement.
Joints shall be formed in a straight line at right angles to the longitudinal axis of
the carriageway except where this cannot be achieved as at road junctions and
roundabouts and corresponding joints on either side of a longitudinal joint shall be in
line with each other. Where possible all transverse joints shall be staggered.
When slabs are constructed to multi lane widths, tie additional reinforcement as
shown on the drawings shall be bars or provided as specified in clause 6264. The
longitudinal joints shall be placed symmetrically about the middle of the slab in the form
of a dummy joint, as shown on the drawings, or as directed.
For slabs of single lane width, tie bars shall be provided as above and as shown
on the drawings. Provision shall be made for maintaining the tie bars accurately in
position during spreading and compacting of the concrete. When the adjoining slab is
constructed, a groove shall be sawn or formed by other approved means to the
requirements of clause 6283.
220
(c) Grooving method
The depth of grooves shall be 40mm. Groove over expansion joints shall
be 6mm wider than the width of the preformed joint filler, and shall be
accurately located over the joint filler. Grooves forming longitudinal or
contraction joints shall be of the width shown on the drawings, or as directed by
the Engineer.
SEALING OF JOINTS 6284.
All dust or grit shall he removed from the grooves which shall first be dried if
necessary for this purpose. Unless an alternative method of sealing is approved by the
Engineer, the dried joints shall then be coated with priming compound, complying with
clause 6268 and an approved sealing compound heated to a temperature not exceeding
180°C, shall be poured in so as to fill the groves completely. When filling grooves in
expansion joints, allowance shall be made for normal variations of ground temperature
in the locality, so as to avoid the extrusion of the sealing compound with an expected
increase in ground temperature.
During the whole progress of concreting, test cubes shall be made in the manner
described for concrete work. Not more than 1 per cent of cubes tested at 28 days shall
show a strength of less than specified.
Cubes shall be made each day in sets at intervals and locations as decided by the
Engineer's Representative. At the start of the work, and until such time as the
Engineer's Representative may order a reduction in the number of cubes required, six
sets shall be made during each day's work, half of each set for testing at 28 days for
determination of the minimum permissible crushing strength and the other half for
testing at seven days for the information of the Engineer's Representative as to quality
of the mix. When the results of the first thirty sets are available and for so long as the
Engineer's Representative is satisfied with the quality of the mix, he may reduce the
number of cubes required to two sets per day.
If the minimum specified crushing strength is not so attained the Contractor may
without expense to the Employer, cut cores from locations selected by the Engineer's
Representative. Where this is done the strength of cores when tested in accordance with
British Standard 1881 methods of testing concrete will be accepted as taking precedence
over the cubes strengths in determining the strength of the concrete and a core
strength of not less than 75 per cent. of the specified crushing strength at 28 days
(tested vertically) will be accepted for a core having a height/diameter ratio of 2. The
method which shall be adopted for correcting the strength of cubes and cores for age
shall be as directed by the Engineer. In order to check the depth of concrete laid, the
state of compaction and the position of the reinforcement, the Engineer's Representative
221
may order cores to be cut, and the Contractor shall carry out same, and repair all holes
so formed at his own expense, and to the satisfaction of the Engineer's Representative.
The unit prices to be inserted by the Contractor in the bill of quantities shall
include for preparing, cutting, packing, any transporting and testing cubes and cores
required by the Engineer or his Representative.
In addition, for cores the price shall include for all costs incurred in connection with
drilling and making good to the satisfaction of the Engineer's Representative.
The Contractor shall make trial mixes using the aggregates proposed for the
work to ensure that the concrete mix is sufficiently workable and that segregation of the
mix during transportation and placing does not occur. The composition of the trial mixes
shall comply with the requirements of the specification in all respects.
The Contractor shall construct a trial slab of the same thickness as that to be laid
in the work, to the full width of the finishing machine, and at least 30 metre long. The
slab shall be constructed with the approved mix to be used in the work, and in a
position as shown on the drawings or directed by the Engineer's Representative.
Construction of the trial slab shall be commenced sufficiently in advance of the main
construction to enable cores to be cut from the trial slab. Six cores shall be cut
therefrom and shall be tested at 7 days, to ensure that the mix as designed and the
equipment proposed to be used are both suitable to achieve a fully compacted concrete
of the specified strength, workability and surface finish.
The placing, compacting and finishing of the concrete shall be carried out as
rapidly as possible and operations shall be so arranged that in any vertical section the
concrete shall be fully compacted throughout the whole depth and finished within 1 hour
from the time of the completion of the mixing of the first batch of concrete in that
section.
222
REINFORCED CONCRETE ROAD SLABS 6288.
For concrete slabs of 200mm, thickness or less the concrete may either:
When the concrete is spread in one layer a travelling jig or a type approved by
the Engineer's Representative shall be used to hold the reinforcement in position while
the concrete is being placed so after compaction the top cover to the reinforcement is as
specified. When the concrete is spread in two layers the first layer shall be spread to
such a level that after subsequent compaction it will support the reinforcement at a level
which will ensure the specified top cover. The layer of reinforcement shall then be
placed in position and covered with concrete.
Whichever method of spreading is adopted the concrete shall be struck off at the
appropriate surcharge and compacted true to line and level by one or more traverses of
the machine to give the slab the final thickness required. The compaction and surface
finish shall be to the satisfaction of the Engineer's Representative.
For concrete slabs exceeding 200mm. in thickness the concrete may either:
223
finish shall be to the satisfaction of the Engineer's Representative.
Immediately after completion of the finishing process, all exposed surfaces of the
concrete shall be protected from the sun and drying winds by frames covered by canvas
or other approved material until the concrete is sufficiently hard to bear the weight of
other protective material without the surface becoming marked. The sides and ends of
the frames shall be covered to exclude drying currents of air.
Thereafter all exposed surfaces of the concrete shall be protected and kept damp
by covering with suitable matting, sand or other approved material: if sand is to be laid
a minimum depth of 50mm, will be required. The curing material shall be kept wet for a
period of at least seven days or longer as directed by the Engineer's Representative.
Alternatively waterproof paper in accordance with the relevant clause of this
specification, or other approved sheeting may be used, and this shall be laid dry and
kept in contact with the surface of the concrete for at least seven days. The sheets shall
be lapped by at least 230mm and shall be weighted down and well fastened along the
edges to prevent the wind blowing beneath.
The concrete surface shall not show a departure from the true surface greater
than 3mm when tested with a 3 meter straight-edge or template in the manner
described for checking Base course finish.
If at any point tested the tolerance is outside these limits, the Contractor may
224
make not more than two additional passes of the vibrating beam of the finishing
machine and one further pass of the oscillating screed.
The surface shall again be tested in the specified manner whereupon if the irregularity
so measured still exceeds 3mm in 3 meter, the Engineer's Representative shall direct
that the concrete be removed to the level of the top surface of the reinforcement or for
unreinforced concrete to a depth of 50mm.
The area to be removed shall be that represented by the length of the straight
edge in the position of measurement across the full width of the screed.
The concrete so removed, shall not be reused. Where the point of measurement
in default is less than 5 metres from a transverse expansion joint, the whole area up to
the joint shall be removed to the required depth.
The removal of concrete under this clause and its replacement shall be carried
out as directed by the Engineer's Representative to his approval and without extra
charge.
The accuracy of surface required by this clause shall apply also to the surface
across any joint whether formed initially or as a result of replacement of concrete arising
out of the requirements of this clause.
6293. No vehicular traffic shall be allowed on the finished surface within 20 days of its
completion where ordinary portland cement is used or 10 days where rapid
hardening cement is used and until the joints have been sealed unless otherwise
authorized by the Engineer.
TESTS
The selection and control tests to be carried out under this section of this
Specification shall be those specified to be carried out for concrete and reinforced
225
concrete work and shall be conducted in the manner stipulated in all relevant clauses of
this specification.
In addition to the making, curing and testing of concrete test cubes as control tests on
concrete carriageways, the Engineer's Representative may order cores to be cut from
the finished work so as to check the state of compaction, the thickness of the concrete
and the position of the reinforcement. These cores shall be drilled and tested in
accordance with the provisions of B.S. 1881, or any amendment thereto as directed by
the Engineer.
The Contractor's attention is particularly drawn to the necessity for carrying out
trial sections with the proposed materials and plant prior to the start of the main
construction to determine the most efficient construction technique and the suitability of
the proposed materials and plant, as described by the relevant clause of this
specification.
GENERAL 6300.
In addition to all other relevant clauses of the conditions of contract and this
specification, the following shall be deemed to refer more particularly to two coat
bituminous surface dressing work, and shall be read in conjunction with same.
MATERIALS
(
: Either a cut-back bitumen having a viscosity of 100/150 seconds at 40°C as
measured by the standard tar viscometer, or a cutback bitumen having a viscosity
of 300/400 seconds viscosity at 40°C as measured by the standard tar viscometer.
226
(c) STRAIGHT RUN BITUMEN FOR WEARING COAT:
Straight run bitumen for first wearing Coat shall have a penetration grade
of 80/100 at 25°C and a flash point (open) of 107°C (Minimum).
Sand for blinding prime coat surface shall consist of clean sharp sand of
6mm maximum size with not more than 20% passing 600µm. sieve, and
shall be approved by the Engineer's Representative. Alternatively grit
arising from the crushing of the rock may be used provided it is approved
by the Engineer's Representative, and the grading complies with the
specification for sand earlier discussed.
Materials for blinding the first wearing coat surface dressing on the
carriageway, shall consist of clean crushed rock or clean crushed or
uncrushed gravel from an approved source, as specified, graded into
single sizes as defined in B.S. 63 latest edition or any amendment
thereto; "Single Sized Road Stone and chippings", or in B.S. 1984 latest
edition -"Single Size Gravel Aggregate for Roads as appropriate. Two
single sizes l9mm and 12mm shall be used for blinding on the
carriageways, while 10mm single size material may be allowed for non
trafficked surfaces (like verges) but only with the written approval of the
Engineer's Representative.
The different sizes of materials shall be stored in separate stockpiles and shall
not be mixed. If the Engineer's Representative considers it necessary the blinding
material shall be washed before use. The aim of the Contractor shall be to obtain the
maximum production of 19mm and 12mm single sized material from the plant and
either size may be used in blinding a continuous section of surface dressing of not less
than 2 kilometres in length.
The crushing aggregate value of all material used for surface dressing shall not
exceed 30% and its abrasion test result not more than 25%. All samples shall be tested
as described in B.S. 882. Samples of all blinding materials to be used in the works shall
be submitted to the Engineer's Representative for approval prior to being used.
227
Prior to the commencement of surface treatment works the Contractor will carry
out tests under the direction of the Engineer for the purpose of assessing the adhesive
qualities of the materials which are to be used in the works. As a result of these tests
the Engineer may decide that it is necessary to use an additive to the bitumen for the
prevention of strippings of the stone surfacing, and the Contractor shall comply with the
directions of the Engineer in this respect. Strip test is recommended.
Bitumen emulsion shall contain 30% of bitumen and shall comply in all other
respects with B.S. 434 (latest edition and amendment thereto) except that the basic
bitumen used in the manufacture may have a penetration of 80/100. Bitumen emulsion
containing 30% of bitumen may be made by mixing thoroughly together in the correct
proportions emulsion complying with B.S. 434 (amendment thereto) with clean soft
water.
WORKMANSHIP
The cut back bitumen shall be heated in a bitumen heater complying with B.S.
167, which shall have a capacity commensurate with the output required. The heater
shall be so operated that the temperature of the bitumen applied to the road shall be
within the specified range. Accurate thermometers shall be incorporated in the heater to
give a clear indication of the bitumen temperature. Should the temperature be in
excess of that specified, the Engineer's Representative may direct that this overheated
bitumen be disposed off at the Contractor's expense.
The prime coat shall be of a medium curing cut-back bitumen of either M.C.O.
Grade or M.C.1 Grade as specified. The actual grade to be used shall be determined by
the Engineer after carrying out site tests to determine the penetration of each grade.
The bitumen shall be applied strictly in accordance with the provisions of the
relevant clauses of this specification on an approved Base course free from all dust and
loose material and slightly damped prior to applying the bitumen.
After spraying the surface shall be left for a minimum of three hours before
blinding is applied, or longer if considered necessary by the Engineer's Representative to
effect the maximum penetration. Blinding consisting of sand or grit complying with the
provisions of the relevant clauses of this specification shall be applied so that a uniform
covering of sufficient thickness is obtained to ensure that no bare or fat patches of
bitumen are showing. The blinding shall then be rolled in with not more than two
passes of a roller.
228
SPRAYING OF CUT-BACK BITUMEN PRIME COAT 6312.
The prime coat as specified shall be evenly applied to the prepared Base course
by means of an approved presuure feed mobile distributor and complying with the
requirements of B.S. 1707: "Binder distributors". In addition to the special requirements
detailed in section three of B.S. 1707, the pressure feed mobile distributor shall be fitted
with a spray bar through which the hot bitumen can be circulated while the distributor is
not spraying. The jets shall be so arranged in the spray bar that they are effectively
preheated to the same temperature as the circulating bitumen.
Check the initial and final quantity of cut back and record. The difference
between initial and final readings divided by the area sprayed can be used to check
compliance with approved rate of spraying.
Note:- Initial and final reading shall take place at same position.
BITUMEN TEMPERATURE OF
GRADE APPLICATION
The Contractor shall carry out trial sections, as directed by the Engineer's
Representative to determine the most suitable grade and rate of application of bitumen.
229
Immediately before any spraying run is begun, the spray bar shall be tested by
allowing all the jet to discharge simultaneously for about half a minute with a slotted
metal tray placed beneath the spray bar whilst a visual inspection is made. Any jet
which is seen not delivering a uniform spray cone shall be cleaned or replaced. After
testing the spray bar, the distributor shall proceed with the spraying run without delay.
No spraying shall be carried out when rain appears imminent, during rain, or after rain,
until the surface has dried. The Contractor shall ensure that joints between spraying
strips are straight and without excess or deficiency of bitumen which would cause either
fattening up or scabbing along the joint.
The Contractor will be required to respray at his own expense any section which
show deficiency of binder, or to burn off and respray at his own expense any sections
which show an excess of binder and which subsequently fat up.
The wearing course of the surface dressing shall not be laid until at least 10 days
after the application of the prime coat. During this period additional blinding sand shall
be added if directed and brushed over the surface to prevent damage. After such period
all damaged or weak spots shall be cut out, refilled, recompacted flush with the existing
surface, sealed and blinded as specified and rerolled to the satisfaction of the Engineer's
Representative. After all repair work has been allowed sufficient time to harden, the
surface shall be swept clean of all loose material immediately prior to the application of
the wearing coat. Before spraying is begun the surface shall be dry.
Bitumen for the wearing coat of the surface dressing shall be an approved
cutback bitumen or straight run bitumen as specified in the relevant clauses of this
specification. The bitumen as specified shall be evenly sprayed on the surface by means
of an approved mechanical spraying machine as specified. The temperature of the
bitumen at the time of spraying shall be in accordance with the table given below. The
grade of bitumen to de used shall be determined by the Engineer.
BITUMEN TEMPERATURE OF
VISCOSITY APPLICATION
MIN
STV AT 40°C MAX
132°C
100/1500 SECS 160°C
149°C
300/400 SECS 177°C
The rate of spray of the bitumen shall be determined according to the type of base, type
and size of chippings which are to be used as detailed in the table given below, and the
Contractor shall carry out trial sections, as directed by the Engineer's Representative to
determine the most appropriate rate of application of bitumen.
230
TABLE VI-10 SIZE OF CHIPPING AND RATE OF SPRAY OF BITUMEN
Immediately after spraying the surface shall be blinded with approved single size
chippings as specified. The chippings shall be distributed on the sprayed surface by
means of mechanical spreaders or tailboard gritters so that a single layer of closely
packed chippings is obtained. Any bare or lean areas shall be made good by a follow on
gang using hand blinding.
Rolling shall be carried out immediately after the chippings have been spread
with an approved roller weighing not less than 3,629 kilograms or more than 5,443
kilograms. The minimum number of passes of the roller shall be used to press the
chippings into the film of bitumen. Two passes of the roller should generally be
sufficient. Pneumatic tyre rollers are preferable to smooth wheeled rollers.
Prior to the commencement of spraying a section of the road for the first coat, a
2 metres wide paper strip shall be laid over the end of the previous section. The
bitumen sprayer shall then commence its run from over this paper strip.
The finished surface of the carriageway shall be left as smooth as possible and
the accuracy of finish in the longitudinal direction shall not vary at any point by more
than 6mm from a 3 metre straight edge, placed in any position on the finished surface
parallel to the centre line. The transverse profile shall conform to the same accuracy,
using a correctly shaped template instead of the straight edge.
The surface shall be evenly textured and show no lean or fat areas and shall not
have any low or flat spots where water will collect.
No surfacing work shall be done in wet weather or when rain is imminent. Only
dry chippings shall be used.
After laying the prime coat surfacing, barriers shall be erected to keep the area
surfaced free from traffic. It shall remain free from traffic for such a period as the
Engineer’s Representative may direct after which it shall be opened to traffic for not less
than 3 days and for not more than 7 days. During this period additional blinding
231
material shall be added and all damage by traffic made good.
After the application of the first coat surfacing, the area surfaced shall be kept free from
traffic for at least 24 hours.
The section shall then be opened to traffic and suitable traffic notices and
barriers shall be erected for a period of one week restricting traffic speeds to 25 KPH
During this period empty bitumen drums or other obstacles, which shall be well lighted,
or alternatively removed during the hours of darkness, shall be placed on the newly
surfaced areas for the purpose of limiting the speed of traffic, and shall be moved to
different positions from day to day in such a way that the whole width of the surface
receives equal wear and compaction from the wheels of vehicles.
TESTS
The cost of carrying out these tests if required by the Engineer shall be deemed
to be included in the tendered rates and prices.
232
The cost of carrying out these tests if required by the Engineer shall be deemed to be
included in the tendered rates and prices.
This test shall be carried out prior to using the spraying plant for the first time on
the contract and subsequently at the discretion of the Engineer's Representative. In the
event of the quantity of bitumen in any trough or troughs being found to lie outside the
prescribed tolerance from the average, the faulty jet shall be located, cleaned or
replaced and a further test carried out if required by the Engineer's Representative.
The Contractor shall test the rate of application of bitumen at regular intervals,
as directed by the Engineer's Representative by means of the "tray test" as described in
Road Note No.11: "Binder distributors for surface dressing", issued by the Road
Research Laboratory, England.
GENERAL 6330.
In addition to all other relevant clauses of the conditions of contract and this
specification, the following shall be deemed to refer more particularly to bituminous
macadam surfacing work and shall be read in conjunction with same.
MATERIALS
(A) AGGREGATE.
Coarse aggregate shall be hard clean and durable crushed igneous rock from a
233
source to be approved by the Engineer and in accordance with B.S. 812.
Fine aggregate shall be quarry fines produced from the crushing of igneous rock
in a secondary plant. They are to consist of hard non-absorbent moderately sharp
particles and to be free from clay, loam, and other foreign matter.
If filler is used it shall consist of finely ground particles of hydrated lime, portland
cement or crushed rock and at least 75% of the filler shall pass 75µm sieve.
(1st) Binder: The binder shall be a straight-run bitumen with a penetration ranging
from 40/50, 60/70, 80/100 at 25°C.
The grading of the combined aggregate to be used in the respective mix for each
course shall be within the limits stated below and when plotted graphically with the
particle size to a logarithmic scale shall lie on a smooth curve within the envelope of
these limits.
38mm 100
25mm 50 - 100
12.5mm 26 - 50
6mm 18 - 30
2.8mm 12 - 22
1.25mm 8 - 17
600µm 7 - 14
300µm 4 - 11
150µm 2- 8
75µm 0- 5
BITUMEN 4 - 5.5%BY WT.
OF AGGREGATE OR AS PER DESIGN
234
TABLE VI-12 GRADING ENVELOPE FOR BITUMINOUS WEARING COURSE
25mm 100
19mm 95 - 100
12.5mm 70 - 90
9.5 mm 55 – 75
6.4mm 40 - 60
3.2mm 25 - 40
1.25mm 15 - 30
600µm 12 - 24
300µm 8 - 18
150µm 5 - 12
75µm 3 - 6
BITUMEN 4 - 7% BY WT.OF AGGREGATE
OR AS PER DESIGN
The exact job-mix formulae will depend on the nature and grading of the
aggregate and the type of bitumen. The exact job-mix formulae for the respective
courses will be determined by the Engineer.
WORKMANSHIP
The mixing plant shall be maintained in good working condition and shall be
subject to inspection by the Engineer's Representative. The weighing, measuring and
recording apparatus shall be checked at frequent intervals and maintained in perfect
adjustment throughout the contract.
235
Prolonged and excessive heating of the materials is to be avoided and particular
care is to be taken with binders. A dry mixing period of at least 10 seconds shall
precede the addition of bitumen to the mix. Wet mixing shall only continue as long as is
necessary to obtain a thorough blend.
The mixed materials shall be transported from mixing plant to site in clean metal
lined vehicles. Every precaution is to be taken to avoid segregation of mixed materials
and to ensure that they do not become contaminated with dust or foreign matter.
Should any load be wetted excessively by rain, they will be rejected by the
Engineer's Representative.
Before the macadam is laid on the newly constructed based course, the surface
will be inspected by the Engineer’s Representative and testing using an Engineer’s level
3 metre straight edge or any other means to ensure that the surface conforms with the
requirements of this specification. Any irregularities in the surface shall be corrected to
the satisfaction of the Engineer's Representative before surfacing work will be allowed to
proceed.
After mixing the material must not be reheated other than by the means
provided in or on the spreading machine.
Material must not be laid when the surface on which it is to be placed is wet or
when rain appears imminent.
Immediately prior to laying the bitumen macadam, the surface of the Base
course shall be swept clean of all loose and caked dirt. The macadam as specified shall
be laid by approved means to compacted thickness of 50mm binder course and 65mm
wearing course, subject to design.
It is essential that the material is laid at a temperature not less than 107°C and
not more than 149°C. The Contractor is to provide at each spreader and finisher a
suitable thermometer for testing the temperature of the material as it is being spread
and is to take such temperature reading continually and record them hourly throughout
each day's laying. This record shall be available for inspection by the Engineer or his
236
Representative who will himself make such additional temperature checks as he
considers desirable.
The materials shall be laid by approved mechanical spreaders and finishers. The
spreader and finisher shall be in in good mechanical condition and shall be capable of
laying to the required width and profile without causing segregation, dragging, burning,
irregularities or other surface defects and it shall be capable of being operated at a
speed consistent with the character of the mixture and the thickness of the course being
laid, so as to produce a surface having a uniform density and surface texture. When not
operated on side forms the spreader will employ equalizing runner evener arms or other
automatic compensating devices to adjust the profile and confine the edges of the
course to true lines.
The mixer capacity and the operating speed of the spreader shall be so adjusted
as to ensure continuous laying and to avoid intermittent stopping of the spread as far as
is practicable.
Hand spreading will not be permitted for general work, but will only be allowed
for filling localized depressions, or as directed by the Engineer or his Representative.
As soon after laying as conditions permit and when the material is still at a
temperature of not less than 95°C the materials will be uniformly compacted with 3
wheeled smooth rollers by rolling in a longitudinal direction, progressing gradually from
side to centre of work and so lapping the rolling as to obliterate all roller marks on
completion. A sufficient number of rollers shall be employed to ensure that the entire
surfacing as laid is compacted at the correct temperature.
At least two rollers are to be provided, one is to be three wheeled and is to have
a weight per centimetre width of rear wheel of between 44 and 63 kilograms. The
second roller shall preferably be a pneumatic typed roller and shall be of multiple axle,
multiple wheel type with smooth tread pneumatic tyres of equal size staggered on the
axles at such spacings and overlaps as will provide uniform compactive pressure for the
full compacting width of the roller when operating. Oscillation of the wheels, if
provided, shall be in vertical plane only. The pneumatic tyre roller shall be capable (A)
of being ballasted sufficiently to bring its loaded weight to at least 2½ times its own
weight. Gross weight to be preferably 18 - 21 Tonne and (B) of exerting compactive
237
ground pressures of at least 5.6 kilograms per square centimetre (5.6 - 8.4 Kg/sq.cm).
For the pneumatic rollers compaction should be done within 65°C - 80°C range.
All roller wheels are to be kept slightly moist by the use of water tanks and spray
bars attached to the machines to prevent the material being picked up or disturbed.
Rollers must not be left standing on the new surface while there is any risk of it
being damaged thereby.
(b) intermediate rolling with the high pressure tyre pneumatic roller; and
Rolling will continue until the specified density is obtained. This can be checked
by using non-destructive method i.e. Nuclear gauge apparatus.
Density tests of the bitumen macadam surfacing after compaction shall be taken
from the trial area and later at intervals throughout the course of the work and
compared with the density of control specimens taken from the same material before
laying, all in accordance with the following procedure:
(A) A sample of mixed material will be taken from a lorry before the material is
delivered to the spreader, and three control specimens shall be made and their
density measured by the Engineer's Representative by the marshall method.
The average of two close results from the specimens taken as the control density
of that particular batch.
(B) The pavement will be marked with the batch numbers to show where the lorry
load of material (from which the sample was taken) is laid, so that field density
samples can be taken for comparison with the control specimens.
(C) After completion of rolling, two samples are to be cut from each area so marked
in positions indicated by the Engineer's Representative.
(D) The samples shall be taken in accordance with part 1 section 3 of B.S. 598 and
the density calculated by weighing in air and weighing in water in accordance
with part 6 of B.S. 598. The average of two close results will be taken as the
density of the compacted material in that area.
(E) The field density will not be less than 100% of the control density determined as
above.
238
When an approved rolling procedure has been established, each course will be
sampled in accordance with the above at the rate of one sample area for each 1670
sq.m or one sample area every four hours (whichever is the more frequent). Material
which does not achieve the required density will either be cut out and replaced or be
further compacted until the require density is obtained.
The first 30 metres of the approved bituminous macadam which is laid by the
spreader shall be regarded as a trial area in order to establish a rolling procedure which
will produce the required field density.
At least four samples of the material after rolling will be taken in accordance with
part 1 section 3 of B.S. 598 (1958) When the work is at least 12 hours old in order to
determine the degree of compaction.
(A) The surfacing will be finished to the required levels shown on the drawings. The
finished surface shall be of such smoothness that when tested with a 3 metre
straight edge placed anywhere in a longitudinal direction on the surface, there
shall not be a gap greater than 5mm between the bottom of the straight edge
and the surface of the pavement anywhere along the pavement. Any deviation
exceeding 5mm will be corrected at the Contractor's expense by scarifying,
cutting out and removing all loosened materials, adding new materials as
required, reshaping and rolling. No materials loosened by scarifying and cutting
out, will be left in position or otherwise reused. The surface shall be similarly
tested, and corrected if necessary in a transverse direction using a correctly
shaped template instead of a straight edge.
(B) It is essential that the surface of the road is free from waves, any depression
which retain water on the surface are immediately to be corrected as described
above to the satisfaction of The Engineer's Representative.
All joints shall be vertical, properly formed to the correct line and level; if
necessary, they shall be cut back to achieve this. The exposed edges of the bitumen
macadam already laid shall be coated thinly with bitumen emulsion containing 30% to
50% bitumen before laying adjoining work. All joints on completion shall present the
239
same texture, density and smoothness as other sections of the surface.
Surfaces and projections which the new paving will abut shall be thoroughly
cleaned and coated with bitumen emulsion containing 30%
50% bitumen. The new paving shall then be tamped around and against the projection
to such a depth that, on completion of compaction the finished surface of the wearing
course is level with the top of the projection.
Should the new bitumen macadam be dragged, churned up, become soft, show
signs of segregation, show that stripping of the binder from the aggregate has occurred,
or suffer other damage during or after being laid, the Contractor will remove the
damaged or faulty work at his own expense and replace with fresh material, laid and
compacted to the correct level to the approval of the Engineer's Representative.
TESTS
The Contractor shall provide equipment, labour and such trained staff as may be
required by the Engineer's Representative for carrying out the following tests on
materials to be used in the manufacture of bitumen macadam in accordance with the
following standards:
(A) Grading tests on aggregates in accordance with B.S. 812: "sampling and
testing of mineral aggregates and fillers".
Such samples shall be taken either at the place and time of mixing or at the
place of laying both may be necessary as the results will complement one another as
240
directed by the Engineer's Representative. Samples for testing shall also be cut from
the surfacing as laid when directed by the Engineer's Representative.
The frequency of sampling mixed materials shall be at least once per day or once
for each 90 tonne of material mixed whichever is the more frequent. The result of each
test on mixed materials shall be submitted to the Engineer's Representative within 24
hours of the sampling and any adjustments shown to be necessary shall be made
immediately. Until such adjustments have been made and until a certificate to the effect
has been forwarded to the Engineer's Representative no further batches of mixed
material shall be made.
Whenever the Contractor intends to carry out any of the above tests, he shall
give the Engineer's Representative sufficient notice to enable him, should he so wish, to
be present during the test. The Engineer's Representative shall be given the results in
writing of all tests, as soon as they are available, and in any case not later than 24
hours after samples have been taken.
SAMPLES TO BE IN DUPLICATE 6366.
241
Whenever the Contractor takes samples for testing, and where so directed he is
to take duplicate samples and hand them to the Engineer's Representative. Such
samples are to be properly packed and labelled as directed.
The cost of these tests including the provision of samples, will be deemed to
have been included in unit price for bitumen macadam.
GENERAL 6370.
This item consists of hot mixed, hot laid asphaltic concrete composed of mineral
aggregate and asphalt cement thoroughly mixed in an approved plant until all aggregate
particles are uniformly coated with asphalt.
The asphaltic concrete shall be laid in two courses surface and binder courses,
with or without wedge or levelling course or any combination of these as shown on the
drawings. Unless specified in Volume III or on the drawings, the compacted thickness of
each course shall not be less than 60mm for the binder and 40mm for the surface
course. The compacted thickness of any single constructed course shall not exceed
75mm for binder or levelling course or 60mm for surface course.
Priming of untreated base and application of tack coat to existing paved surfaces
shall be done as follows:
MC-O or MC-l shall be used at the rate of 1.0 - 2.0 Litres/ sq.m
Tack coat shall be applied in all areas to take the binder course if warranted by
surface conditions and directed by the Engineer's Representative.
All materials and method of preparation and construction shall conform with the
requirements of these specifications. The finished pavement shall conform in all
respects with the lines, grades, dimensions and cross sections shown on the drawings or
as may be otherwise specified or directed by the Engineer.
MATERIAL 6371.
242
The materials used shall be those prescribed for the several parts which
constitute the finished work and shall conform with all the requirements for such
materials as set out herein.
(A) AGGREGATE
(I) Coarse aggregate shall be the portion of the aggregate retained on the
No. 5mm opening sieve and shall be hard, clean and durable crushed
igneous rock from a source to be approved by the Engineer. The crushed
stone shall be free from dirt or other objectionable matter.
The coarse aggregate when tested by the methods described in B.S 812 shall
have properties not exceeding the following values ON Table VI – 13.
(II) Fine aggregate shall be the portion of the aggregate passing the No. 5mm
opening sieve and shall be quarry fines produced from the crushing of igneous
rock. They shall be composed of clean, tough, rough surfaced and angular
particles, free from lumps, or ball of clay, loam and other deleterious substances.
(III) Mineral filler shall consist of finely ground particles of hydrated lime, Portland
cement or other non plastic mineral matter approved by the Engineer. It shall
be free from foreign or other objectionable material, and shall meet the following
grading requirements:
TABLE VI-14 SPECIFICATION FOR MINERAL FILLER
243
300µm 100
200µm 95 - 100
75µm 85 - 100
(B) BITUMINOUS MATERIAL
SOLUBILITY IN CS2, 99 99
% BY WT … MIN.
DROP IN PENETRATION 20 20
AFTER HEATING %
(C)Bitumen emulsion for tack coat shall be emulsion quick breaking type
containing 30% - 50% bitumen.
244
Representative samples of all materials proposed for use under these
specifications shall be submitted to the Engineer by the Contractor at the Contractor's
expense for test and for the preparation of trial mixes to determine the job mix formula.
The Engineer shall make tests of the proposed materials and inform the Contractor if the
tests indicate compliance with the specifications.
If aggregates are stockpiled prior to their transference to the bins, the stockpiles
shall be formed on concrete floors laid to falls sufficient to permit drainage at the base
of the stockpiles. Aggregates shall be handled to and from the stockpiles in a manner
such that they are not contaminated by the ground or by extraneous matter and also in
a manner such that segregation is prevented. In as much as possible the bins shall be
covered to prevent dampness of aggregate by rain.
Coarse and fine aggregates and aggregates from different sources shall be
stockpiled separately and if aggregates of different gradings or from different sources
are stockpiled in close proximity, the stockpiles shall be separated by partitioning.
Material used as filler shall be stored in dry conditions to the satisfaction of the
Engineer's Representative.
No material shall be used until it has been approved by the Engineer. Permission
to use material shall not be construed as an approval of its source nor any acceptance
as continued acceptance.
The Contractor shall provide equipment, labour and such trained staff as may be
required by the Engineer for carrying out the following tests on materials to be used in
the manufacture of hot asphaltic concrete in accordance with the following standards:
(A) Grading tests on aggregates in accordance with the latest B.S. 812
"Sampling and testing of mineral aggregate and fillers."
245
or
(II) By reflux extractor method.
(2) Aggregates shall be sampled and tested on delivery to the mixing plant
and after each extraction test and the result of each test shall be submitted to the
Engineer or his Representative within 24 hours of the sample being taken.
The number of such tests shall be adequate for proper control of the materials
and shall not be limited to those made on specific instructions of the Engineer or his
Representative. Samples of mixed materials shall be taken and tested during the first
day's mixing and throughout the work to confirm that the gradings and binder contents
are as specified. Such samples shall be taken either at the place and time of mixing or at
the place of laying as directed by the Engineer or his Representative. Samples for
testing shall also be cut from the surfacing as laid when directed by the Engineer or his
Representative.
The frequency of sampling mixed materials shall be at least once per day or once
for each 90 tonne of material mixed whichever is the more frequent. The result of each
test on mixed materials shall be submitted to the Engineer or his Representative within
24 hours of the sampling and any adjustments shown to be necessary shall be made
immediately. Until such adjustments have been made and until a certificate to the
effect has been forwarded to the Engineer or his Representative no further batches or
mixed material shall be made.
(3) Independent sampling and testing may be carried out by the Engineer
throughout the contractor period and for this purpose the Contractor shall grant free
access to the mixing plant and storage depots, supply materials and provide every
facility for the Engineer or his Representative to take samples whenever required.
In particular, throughout the contract, the Engineer will carry out control tests on
the plant mix material using the marshall test apparatus.
(5) If the Engineer so requires, the Contractor shall arrange for the testing in
an approved manner of all materials used throughout the contract to ensure that they
are up to the standard specified, i.e. Aggregates, bitumen and such other materials as
specified or decided by the Engineer. The Contractor shall arrange for the testing of
materials incorporated in the works to ensure that they have been manufactured as
specified, or as ordered by the Engineer.
(6) Whenever the Contractor intends to carry out any of the above tests, he
shall give the Engineer's Representative sufficient notice to enable him, should he so
wish, to be present during the test.
(7) Whenever the Contractor takes samples for testing, and where so
246
directed he is to take duplicate samples and hand them to the Engineer's
Representative. Such samples are to be properly packed and labelled as directed.
(8) The Engineer's Representative shall be given the results in writing of all
tests, as soon as they are available, and in any case not later than 24 hours after
samples have been taken.
(9) The Engineer shall be supplied with all necessary equipment, material
and labour to perform any additional tests he may wish to carry out himself.
(10) The cost of these tests including the provision of samples, will be deemed
to have been included in the bill of quantities under the appropriate item.
% BY WEIGHT PASSING
SIEVE SIZE 40mm – 65mm 40mm – 50mm
BINDER-COURSE WEARING-COURSE
31.8mm 100 100
25mm 90 – 100 100
19.0mm 70 - 90 100
12.5mm 55 – 80 85 – 100
9.5mm 47 - 70 75 – 92
6.4mm 40 – 60 65 – 82
2.8mm 27 – 45 50 – 65
1.25mm 20 – 34 36 – 51
600µm 14 – 27 26 – 40
300µm 8 – 20 18 – 30
150µm 5 – 15 13 – 24
75µm 2-7 7 – 14
Bitumen Content %
By weight of 4.5 – 6.5 5 – 8.0
Aggregate
247
Property Base-Course Wearing-Course
The exact job mix formula will depend on the nature and grading of the
aggregate and the grade of bitumen and will be determined by the Engineer using the
marshall method of mix design. For this purpose the Contractor shall supply to the
Engineer without charge adequate samples (in separate containers) of coarse and fine
aggregates and bitumen which he intends to use. The Engineer will, after testing,
furnish the Contractor with the exact job mix formula, which will be within the specified
limits.
Before any asphaltic concrete is laid, the Contractor shall produce sufficient dry
mixes in the plant and carry out sieve analysis to ensure that the correct grading is
being obtained. In addition he shall produce a number of trial mixes to which the
specified quality of bitumen has been added. He will then carry out extraction tests on
this material and further sieve analysis on the aggregate in accordance with clause 6373
of the specification. The results of these tests on both the dry and wet mixes shall be
approved by the Engineer before any surfacing is laid in the permanent works.
The job mix formula is the single definite percentage of aggregate passing each
required sieve size, a single definite bitumen content to be added to the aggregate, a
single definite temperature at which the mixture is to be emptied from the mixer and a
single definite temperature at which the mixture is to be delivered on the road.
PERMISSIBLE VARIATION
% BY WEIGHT OF TOTAL
MIX
248
Passing sieve 9.5mm - 600µm ± 4%
Notes:
Temperature of Mixture when
emptied from mixer 145°± 5°
Temperature of Mixture
on delivery on the road 130°C ± 5°C
The job-mix formula is liable to alteration by the Engineer throughout the progress of
the work but at all times it will be within the specified limits.
PREPARATION 6375.
(1) PREPARATION OF AGGREGATES
The coarse and fine aggregate shall be separately fed by feeders to the cold
elevator or elevators in their proper proportions and at a rate to permit correct and
uniform temperature control of the heating and drying operation.
The aggregate shall be heated before entering the mixer to a temperature range
of 120ºC - 149°C. All aggregates in the bins of a temperature that will produce a mix
outside the limits stated above or that contain moisture or expanding gases to cause
"Foaming" in the mixture, shall be removed and replaced in their respective stock piles.
All aggregates that have been overheated shall be cooled before being deposited in the
feeder. All unsuitable aggregates that may be in the weigh box or that become
combined in the process of "Pulling" the bins shall be discarded.
The screening efficiency shall be maintained within the limits set forth in Clause
6383. When these limits are exceeded, the material shall be discarded and the cause
for such condition shall be corrected.
The exact proportions within the limits specified for each mix shall be regulated
so as to produce a satisfactory mixture with all particles uniformly coated with bitumen.
249
When batch mixing is used, the aggregate at the temperature specified, shall be
mixed dry for a minimum of 15 seconds; the asphalt cement shall then be added in an
evenly spread sheet over the full length of the mixer. The mixing shall be continued for
a minimum of 30 to 45 seconds for all mixtures.
The "initial time of mixing" shall be the interval of time between the opening of
the weigh box and the opening of the mixer gate. The number of batches produced in
one hour from the mixer shall not exceed 60.
When continuous mixing is used the dry aggregates shall be thoroughly mixed
before the addition of the asphalt cement. The asphalt cement shall then be added in
an evenly spread sheet over the full width of the mixer by means of spray bars. The
mixing shall be continued for a period of not less than 30 seconds. The "total time for
mixing" shall be the ratio of the "dead load" in the mixer to the kilograms per minute
delivered. The kilograms per minute delivered shall be determined by timing and
weighing a load of mixed material. The "dead load" shall be determined by weighing the
"mixer full" of material. The dry mixing shall be the product of the ratio of dry mixer
length to the total mixer length and total mixing time. The Engineer may vary the length
of the dry and wet mixing periods, but under no circumstances shall the total mixing
time be less than 45 seconds.
The mixture shall be loaded into trucks in such a manner that segregation will
not occur.
The mixed materials shall be transported from mixing plant to site in clean metal
lined vehicles. Every precaution is to be taken to avoid segregation of mixed materials
and to ensure that they do not become contaminated with dust or foreign matter.
Covers such as water proof canvas and other insulation shall be provided when directed.
The area to be paved shall be true to line and grade, having a dry and properly
prepared surface prior to the start of paving operations. The area to be paved shall be
free from all screenings, and other loose or foreign material.
When a levelling course is not required, all depressions and other irregularities
shall be patched or corrected in a manner satisfactory to the Engineer. All fatty and
unsuitable patches, excess crack or joint filler, and all surplus bituminous material shall
250
be removed from the area to be paved. Blotting of excessive deposits of asphalt with
sand or stone shall not be permitted.
A tack coat shall be applied when the surface to be paved is an existing Portland
Cement concrete, or dry asphalt pavement. When a tack coat is required, it shall consist
of an application of the asphaltic material indicated, and at the rate specified in clause
6370.
In all cases the emulsion shall be allowed to break before laying. Prior to
application of the tack coat, all loose or objectionable material will be removed from the
surface by brooming or other approved method. After cleaning, the surface shall be
inspected by the Engineer before the tack coat is applied. The tack coat will be applied
evenly and by mechanical sprayer of approved type which is to comply with B.S. 1707.
Where the time between the completion of one surface course and the laying of
the subsequent surface course exceed 72 hours, a tack coat shall be applied to the
preceding course as above but at a rate of spread of 4 - 4.5 square metres per litre.
Such tack coat shall be at the Contractor's expense unless compliance with the 72 hours
limit was impracticable.
Concrete kerbs, channels, and similar objects shall be adequately masked and
protected during the application of tack coats.
The surface of curbs, gutters, vertical faces of existing pavements and all
structures in actual contact with asphalt mixes shall be painted with a thin uniform
coating of asphalt material to provide a closely bonded water tight joint.
The first 30 metres of the approved bituminous mixture which is laid by each
spreader shall be regarded as a trial area in order to establish a rolling procedure which
will produce the required field density.
At least four samples of the material after rolling will be taken in accordance with
part 1 section 3 of B.S. 598: when the work is at least 12 hours old in order to
determine the degree of compaction.
251
If the required density determined in accordance with clause 6381 is not
obtained, the field rolling procedure will be changed so as to achieve the desired field
density and the trial area will be cut out and replaced to the satisfaction of the Engineer.
After mixing, the material must not be reheated other than by the means
provided in or on the spreading machine.
Materials must not be laid when the surface on which it is to be placed is wet or
when rain appears imminent.
It is essential that the material is laid at a temperature not less than 121°C and
not more than 163°C. The Contractor is to provide at each spreader and finisher a
suitable thermometer for testing the temperature of the material as it is being spread
and is to take such temperature readings continually and record them hourly throughout
each day's laying. This record shall be available for inspection by the Engineer who will
himself make such additional temperature checks as he considers desirable.
As soon as the first load of material has been spread, the texture of the unrolled
surface shall be checked to determine its uniformity. The adjustment of the screed,
tamping bars, feed screws, hopper feed, etc., shall be checked frequently to ensure
uniform spreading of the mix to proper line and grade and adequate initial compaction.
Segregation of materials shall not be permitted. If segregation occurs, the spreading
operation shall be immediately suspended until the cause is determined and corrected.
The mixer capacity and the operating speed of the spreader shall be so adjusted
252
as to ensure continuous laying and to avoid intermittent stopping of the spreader as far
as is practicable.
Hand spreading will not be permitted for general work, but will only be allowed
for filling localized depressions, or as directed by the Engineer.
Hand laying of any bituminous material will only be permitted in the following
circumstances:-
(i) for laying regulating courses of irregular shape and varying thickness.
Hand raking of wearing course material which has been laid by a paver and the
addition of such material by hand spreading to the paved area for adjustment of level
will only be permitted at the edges of the layers of materials or where otherwise
directed by the Engineer.
Materials are to be laid to the depths necessary to give the required thickness
after compaction and they are to be finished true to profile.
The Contractor shall break out and remove at his own expense any asphaltic
concrete laid in trial areas if such asphaltic concrete fails to meet the specified
requirements for asphaltic concrete surfacing.
If for any reason the quality, grading or supply source of aggregates or the
quality or source of bitumen is changed, or at any time the cause of variations outside
the permissible limits cannot be corrected for reasons beyond the Contractor's control,
the Engineer may require the Contractor to carry out additional laboratory tests and/or
the construction of additional trial areas depending on the extent of the change or
variation.
253
COMPACTION 6379.
After spreading, the mix shall be thoroughly and uniformly compacted by rolling.
The initial 'breakdown' rolling shall be done with three wheel smooth roller,
followed by intermediate rolling with high- pressure typed pneumatic roller. The final
rolling shall be with a tandem roller. During rolling, the roller wheels shall be kept moist
with only sufficient water to avoid picking up material.
After the longitudinal joints and edges have been compacted rolling shall start
longitudinally at the sides and gradually progress towards the centre of the pavement,
except on super elevated curves where rolling shall begin on the low side and progress
to the high side. Each pass of the roller shall overlap the preceding one by about one
half width of the rear wheel. The roller should move at a slow but uniform speed not
exceeding 8 kilometres per hour. The roller shall be in good condition, and capable of
being reversed without back lash, and the line of rolling shall not be suddenly changed
or the direction of rolling suddenly reversed, thereby displacing the mix. If rolling
causes displacement of the material the affected areas shall be loosened at once with
shovels or rakes and restored to the original grade of loose material before being re
rolled.
The intermediate rolling shall follow the breakdown rolling as closely as possible and
while the mix is still at a temperature of 70ºC 85°C. Rolling shall be continuous until the
mix is thoroughly compacted and the density specified in Clause 6381 is achieved.
Turning of pneumatic rollers on the hot mix which causes undue displacement shall not
be permitted.
The final rolling shall be accomplished with two wheel tandem roller while the
material is still warm enough for the removal of roller marks.
JOINTS 6380.
All joints shall be vertical, properly formed to the correct line and level; if
necessary they shall be cut back to achieve this. A template made to the shape of the
true line and width may be placed at each end of the construction joint to create vertical
254
straight finish. Joints in the surface course should be staggered with those in the binder
course and must be kept straight, when the abutting lane is not placed the same day or
if the edge of the first strip has been distorted by traffic the joint shall be cut back to an
even line and then be coated with bitumen before laying the adjoining strip. All joints
on completion are to present the same texture, density and smoothness as other
sections of the course.
Density tests of the asphalt surfacing after compaction shall be taken from the
trial area and later at intervals throughout the course of the work and compared with
the density of control specimens taken from the same material before laying, all in
accordance with the following procedure:
(a) A sample of mixed material will be taken from a lorry before the
material is delivered to the spreader, and three specimens shall be
made and their density measured by the Engineer by the immersion
method.
The average of the two close specimens will be taken as the control
density of that particular batch.
(b) The pavement will be marked to show where the lorry load of material
(from which the sample was taken) is laid, so that field density samples
can be taken for comparison with the control specimen.
(c) After completion of rolling, three samples are to be cut from each area so
marked in positions indicated by the Engineer.
(d) The samples shall be taken in accordance with part 1 section 3 of B.S.
598 (1974) and the density calculated by weighing in air and weighing in
water in accordance with part 6 of B.S. 598 (1974). The average of two
close results of the samples will be taken as the density of the compacted
material in that area.
(e) This density will not be less than 100% of the control density determined
as above.
When an approved rolling procedure has been established, each course will be
sampled in accordance with the above at the rate of one sample area for each 84
square metres placed or one sample area every 2 hours (whichever is more frequent).
Material which does not achieve the required density will either be cut out and replaced
or be further compacted until the required density is obtained.
The surfacing will be finished to the required levels shown on the drawings. Any
deviation exceeding 5mm from these levels will be corrected at the Contractor's expense
255
by scarifying, cutting out and removing all loosened materials, adding new materials, as
required, re-shaping and rolling. No materials loosened by scarifying or cutting out, will
be left in position or otherwise re-used.
Except across the crown of a camber, the finished surface shall be of such
smoothness that when tested with a 3 metre straight edge placed anywhere and in any
direction on the surface, there shall not be a gap greater than 3mm between the bottom
of the straight edge and the surface of the pavement anywhere along the straight edge.
Should the new asphalt surface be dragged, churned up, become soft, show
signs of segregation, show that stripping of the binder from the aggregate has occurred,
or suffer other damage during or after being laid, the Contractor will remove the
damaged or faulty work at his own expense and replace with fresh material, laid and
compacted to the correct level and density to the approval of the Engineer.
All equipment furnished by the Contractor shall be of approved design and shall
be maintained in its best mechanical condition. Equipment shall be serviced and
lubricated away from the paving site; units that drip fuel, oil and grease shall be
removed from the project until such leakage is corrected to the satisfaction of the
Engineer. This is necessary because fuel leakage can be injurious to newly laid asphaltic
concrete.
The plant site shall have sufficient storage space for separate stock piles; bins or
stalls for each size of aggregate, and the different aggregate sizes shall be kept
separated until they have been delivered by the feeder or feeders to the boot of the cold
elevator or elevators in neat and orderly condition and the separate stock piles shall be
readily accessible for sampling. Samples from each bins shall be graded from time to
time for conformity to design size otherwise adjustment may be necessary.
The plant shall be either the batch mixing type or the continuous mixing type
meeting the following requirements.
256
Tanks for storage of asphalt shall be provided with a device for controlled
heating of the material to temperature requirements set forth in the
specifications. Heating shall be accomplished by steam or oil coils,
electricity or other means such that no flame shall come in contact with
the heating tank. All lines shall be checked periodically under full
pressure for leakage. All line valves shall have clear and permanent
markings to indicate all openable and closable positions. A circulating
system for the asphalt of adequate size to ensure proper and continuous
circulation between storage tank and mixer during the entire operating
period shall be provided. All pipe lines and fittings shall be properly
insulated and heated. The discharge end of the circulating pipe line shall
be maintained below the surface of the asphalt in the tank while the
pump is in operation. Storage tank capacity shall be sufficient for at least
one day's run.
(IV) DRIER
The plant shall include a rotary drum drier that will continuously agitate
the mineral aggregates during the heating and drying process. It shall be
capable of heating and drying all aggregates specified in the necessary
quantities to supply the mixing unit continuously at its operating capacity
and at the temperature and maximum bitumen content specified.
(V) SCREENS
The plant shall have screens of the shaker or vibrating type and be
capable of screening all aggregates to the sizes required for
proportioning. The screens shall have normal capacity slightly in excess
of the full capacity of the mixer or the drier. The plant screens shall have
an efficiency such that when measured by weight there will be not more
than 5% of oversize material in bin No. 1 (fine aggregate), not more than
15% undersize and/or 10% oversize in bin No. 2 and not more than 20%
undersize and/or 5% oversize in bin No. 3, and not more than 20%
undersize and/or 0% oversize in bin No. 4. The Contractor shall expose
the screens for inspection at the request of the Engineer. These screen
tolerances are for general guidance and shall not invalidate the specified
job-mix tolerances.
257
(VI) BINS
Bins shall be divided into at least three compartments for any mix
composition other than a base (binder) composition, and at least four
compartments for a wearing course. They shall be arranged to ensure
separate storage of the appropriate fractions of aggregate. The bin sizes
shall be adequate for continuous operation of the plant at rated capacity.
Adequate additional dry storage shall be provided for mineral filler when
required and provision made for proportioning it into the mix
258
The plant shall be provided with a dust collector, designed to waste, or
return uniformly to the hot elevator, all or part of the material collected,
as directed by the Engineer. Prior to permitting the return of such
collected dust, the Engineer shall examine its characteristics in relation to
the mix requirements, and shall designate the quantity to be returned.
When dust is permitted to be returned to the hot elevator, it shall be
accomplished by mechanical means in a constant and uniform flow. All
plants shall have mixer covers and such additional housing as may be
necessary to ensure the proper collection of dust
Adequate and safe stairways to the mixer platform and guarded ladders
to other plant units shall be provided. All gears, pulleys, chains, sprockets
and other dangerous moving parts shall be well guarded and protected.
Ample and unobstructed space shall be provided on the mixing platform.
A clear and unobstructed passage shall be maintained at all times in and
around the truck loading space. This space shall be free from drippings
from the mixing platform. A ladder, or platform, shall be so located at the
truck loading space to permit easy and safe inspection or sampling of the
mix as it is delivered into the truck. Adequate overhead protection should
be provided where necessary. It is the Contractor's responsibility to
ensure the plant or the plant site shall be free from fire hazard.
All plants shall be equipped with a positive means to govern the time of
mixing.
When scales are of the beam type, there shall be tare beam for balancing
the hopper and a separate beam shall be provided which shall be capable
of functioning when the load being applied is within 45 kilograms of the
weight desired. Each beam shall have a locking device designed and so
located that the beam can easily be suspended or thrown into action.
259
the pointer shall be set close to the face of the dial and shall be free from
excessive parallax. The scale shall be provided with adjustable pointers
for marking the weight of each material to be weighed into the batch
which shall automatically cut off feeder system when the required weight
is attained.
Scales for the weighing of asphalt shall conform to the requirements for
aggregate scales, except that beam scales shall consist of a full capacity
beam and a tare beam. The minimum graduation shall not be greater
than 1 kilogram and there shall be attached a tell tale device which will
start to function when the load being applied is within 10 kilograms of the
weight desired. Dial scales for weighing the asphalt shall read to the
nearest 450g. All scales for weighing the asphalt shall have a capacity of
not more than 15% of the normal capacity of the mixer.
Scales shall be satisfactory to the Engineer and shall be tested and sealed
as often as the Engineer may deem it necessary to ensure their accuracy.
All weighing equipment shall be substantially constructed and of a design
which will permit easy realignment and adjustment. Weighing equipment
that easily gets out of adjustment shall be replaced when so ordered.
The Contractor shall provide and have at hand at least ten 25 kilogram
standard weights for frequent testing of all scales. For each scale, a
suitable cradle, or platform, shall be provided for applying the test load so
that the load is uniformly distributed. The test weights shall be kept
clean and stored near the scales.
(II) BINS
Equipment shall include a means for accurately weighing each bin size of
aggregate in a weigh box or hopper suspended on scales ample in size to
hold a full batch without hand raking or running over. The weigh box or
hopper shall be supported on a fulcrum: with knife edges and shall be so
260
constructed that they will not easily be thrown out of alignment. Gates
on hopper shall be so constructed as to prevent leakage when they are
closed. Proportioning of aggregates and charging of mixer shall be
performed so as to blend the aggregates thoroughly and prevent
segregation in the mixer.
(V) MIXER
The plant shall have a mixer of approved type such as standard twin pug
mill batch type, steam jacketed and a batch capacity of not less than
1000 kilograms. It shall be capable of producing a uniform mix within the
job mix tolerances established by the Engineer. Deviation in size of
batches will be permitted to provide for mixing batches 20% below or
15% above the rated capacity of the mixer, provided the quality of the
261
mix is not impaired. The paddles shall be set in such a manner to ensure
a completely uniform mix. If not enclosed, the mixer box shall be
equipped with a dust hood to prevent loss of dust. The mixer shall be so
constructed as to prevent leakage of contents until the batch is to be
discharged.
The mixer shall have an accurate time lock to control the operation of a
complete mixing cycle by locking the weigh box gate after the charging of
the mixer, until the closing of the mixer gate at the completion of the
cycle. The time lock shall also lock the asphalt bucket throughout the dry
mixing period and shall lock the mixer gate throughout the dry and wet
mixing periods. The dry mixing period is the interval of the time between
the opening of the weigh box gate and the application of asphalt. The
wet mixing period is normally the interval of time between the application
of all asphalt and the opening of the mixer gate for discharge. When
asphalt is applied by a spray system, the wet mixing time shall begin with
the start of asphalt spray.
The Engineer shall, after tests of a few trial mixes, designate the length
of both dry and wet mixing periods to ensure a uniform and completely
coated mix. Excessive wet mixing shall be avoided. Control of the
timing shall be flexible, permitting timed intervals of not less than five
seconds throughout cycles up to three minutes. A mechanical batch
counter, designed to register only completely mixed batches shall be
installed.
(I) BINS
The plant shall include a means for accurately proportioning each bin size
of aggregate either by weight or by volumetric measurement.
262
controlled individual gate to form an orifice for volumetrically measuring
the material drawn from each respective bin compartment. The orifice
shall be rectangular, with one dimension, adjustable by positive
mechanical adjuster and provided with a lock. Indicators shall be
provided on each gate to show the gate opening in millilitres. Mineral
filler, if specified, shall be proportioned separately from a suitable hopper
equipped with an adjustable feed which may be accurately and
conveniently calibrated and which shall be interlocked with the aggregate
and asphalt feeds. The feeder equipment for the mineral filler shall meet
the approval of the Engineer.
The asphalt storage system shall be provided with automatic controls and
signal devices which will warn of low levels of asphalt and which will
automatically stop the entire plant operation when the asphalt storage
level is to the point of exposing the feed end of the asphalt suction line.
263
(V) MIXER
The plant shall have a steam jacketed, twin pugmill, continuous type ixer
of not less than 700 kilograms per minute rated capacity. The mixer shall
be in first class condition equipped with a sufficient number of blades or
paddles and operated at such a speed as to produce a properly and
uniformly mixed composition within the job mix tolerance specified. The
paddles shall be of a type adjustable for angular position on the shafts
and reversible by remote control to retard the flow of the mix. The mixer
shall carry a manufacturer's plate giving the net volumetric contents of
the mixer at the several heights inscribed on the permanent gauge. The
mixer shall have a cut off gate at its discharge and adequately sealed
against leakage between truck loads. The determination of mixing time
shall be by a weight method under the following method unless otherwise
required:
The weights shall be determined for the job from the tests made by the
Engineer.
Pavers shall be equipped with hoppers and distributing screws of the reversing
type to evenly place the mixtures in front of the screeds.
The screed shall be a strike off device operated by cutting, crowding or other
264
practical action which is effective on the mixtures without tearing, shoving or
gouging, and which produces a finished surface without segregation. The screed
shall be adjustable as to level and shall have an indicating level attached thereto
in full view of the operator.
The pavers shall be further equipped with blending or joint levelling devices for
smoothing and adjusting all longitudinal joints between adjacent stripes of
surface course.
The paver shall be equipped with an efficient steering device, and shall be
capable of travelling both forward and in reverse.
ROLLERS
Rolling equipment shall consist of steel wheel and pneumatic tyre rollers, or a
combination of both described as follows:
(B) The pneumatic-tyre rollers shall be self propelled, multiple axle multiple wheel
type with smooth tread pneumatic tyres of equal size and diameter. The tyres
shall be staggered on the axles at such spacings and overlaps as will provide
uniform compactive pressure for the full compacting width of the roller, when
operating. Oscillation of the wheels, if provided, shall be in vertical plane only.
The pneumatic tyred roller shall be capable of:
(I) Being ballasted sufficiently to bring its loaded weight to at least 2½ times
its own weight and
265
(II) Of exerting compactive ground pressures at least 5.6 kilograms per
square centimetre, 5.6 8.4Kg/cm² preferred.
Vehicles used for the transportation of hot mix asphalt from the plant to the site
of work shall have tight metal bottoms and shall be free from dust, screenings,
petroleum oils, volatiles or other mineral spirits which may affect the mix being
hauled. The truck beds shall be painted, or sprayed with a lime water or soap
solution, at least once a day or as often as required. After this operation the
truck bed shall be elevated and thoroughly drained, no excess solution shall be
permitted.
When ordered by the Engineer, trucks shall be suitably insulated and provided
with covers of canvas or other material of sufficient size and weight to protect
the load from adverse weather conditions. When variations in size, speed and
condition of trucks are such as to interfere with orderly and continuous
operation, the Engineer may order suitable substitutions to be made.
For verification of weights and measures, character and quality of materials and
determination of temperatures used in the preparation of the paving mixes, the
Engineer or his Representative shall at all times have access to all portions of the paving
plant, aggregate plant, storage yards and other facilities for producing and processing
the materials of construction. All sampling and testing of processed and unprocessed
material shall be under the control and direction of the Engineer.
The Engineer shall make frequent gradation analyses of the hot aggregate and
of the completed mix to be certain that the materials being used and produced
are within the tolerances of the job-mix formula and the specifications of the mix
number being used.
If the mix is found to be outside of the job-mix formula tolerances, or outside of
the specification limits, corrections shall be made in quantities measured from
the hot bins and suitable changes made at the cold bin feeders.
Stockpiles and bins shall be sampled for gradation analysis, dust coating and for
other purposes, at the option of the Engineer. Gradation analysis of material
from each hot bin shall be performed and a combined analyses computed at
least twice a day - once in the forenoon, and once in the afternoon. A combined
gradation and analyses shall be performed at least twice a day. If materials do
not run uniform, more frequent tests shall be made.
266
or by drawing aggregate from each bin through the mixing chamber (without
asphalt) into a trunk or other receptacle. At least one sample shall be taken from
each 250 tonne of the mix being produced. Samples shall be used to determine
compliance with general and special requirements.
At each plant site, there shall be provided a testing laboratory for joint use of the
producer's quality control and acceptance testing functions, and the Engineer's
Representative, during periods of mix production, sampling, and testing, and
whenever materials subject to the provisions of these specifications are being
supplied or tested.
The bituminous plant testing laboratory shall have a floor area of not less than
14 square metres, with a ceiling height of not less than 2.3 metres. The
laboratory shall be weather tight, sufficiently heated in cold weather, air
conditioned in hot weather, to maintain temperatures, for testing purposes, of
24°C plus or minus 2.5°C degrees centigrade. It shall be so located on the
asphalt plant site as to provide an unobstructed view from one of its windows of
the trucks as they are located with the plant mixed materials.
(2) electrical outlets sufficient in number and capacity for operating the
required testing equipment and for drying samples
(4) work benches for testing with dimensions not less than 0.75 metres by 3
metres.
(7) exhaust fan to outside air, with minimum blade diameter of 300mm to
adequately handle laboratory dust and fumes
(8) telephone
(10) a sink with running water and attached drain-board and drain capable of
handling elutriable material
267
(12) a 2 element hot plate or other comparable heating device, with suitable
dial type thermostatically controlled to adjust the heat, for drying
aggregates
(17) other necessary small hand tools required for proper sampling and testing
of materials
(18) library containing all British Standards referenced herein, ASTM Parts 10
and 11; and AASHTO Tests, Part II.
Approval of the bituminous plant and testing laboratory by the Engineer, will
require all the above facilities and equipment in good working order, during all
periods of mix production, sampling, and testing; and whenever materials
subject to the provisions of these specifications are being supplied or tested.
Failure to provide any of the above shall be sufficient cause for disapproving the
bituminous plant operations.
SECTION VI ROADWORK
Where directed by the Engineer, new precast reinforced concrete kilometre posts
shall be provided to indicate distance in kilometres along the road. The
kilometre posts shall conform with the accepted standards of the Federal Ministry
of Works for kilometre posts on Trunk "A" Roads, as shown on Federal Ministry
of Works Drawing No. 28016, or such modification thereof as the Engineer may
direct. Normally, the new kilometre posts, shall be constructed of Grade 15
N/mm² concrete, be approximately 2.0 metres in length, and shall have a
roughly triangular cross section the back face being 300mm wide with two 50mm
268
perpendicular offsets and the two side surfaces being 400mm wide with the apex
truncated to give a 50mm flat surface. The kilometre posts shall be reinforced
longitudinally with three 16.0mm diameter mild steel rods having 6mm mild steel
stirrups at 250mm centres.
The kilometre posts shall be erected with the apex facing the road and shall be
located on the right hand side of the road(when looking towards the higher
distance in kilometres). They shall be set in a 600mm x 750mm x 380mm
(deep). block of grade 15 N/mm² concrete, and shall project 900mm above the
ground level. The distance between the nearest edge of the kilometre post and
the edge of the ultimate carriageway shall not be less than 3 metres.
All kilometre posts shall be twice painted with a white (non reflective) paint and
have the letters and numbers stencilled on in green reflective paint. The lettering
and distance in kilometre. Origin shall be approved by the Engineer.
Where existing kilometre posts are in good condition, the Engineer may direct
that these be taken down, painted and treated as for new kilometre posts, and
re-erected at the correct chainages.
Where directed by the Engineer, culverts shall be provided with two precast concrete
beacons located diagonally near the ends of the culvert as directed by the Engineer.
The beacons shall be cast of grade 15N/mm² concrete and shall be 230mm, 150mm
thick and 900mm long, and shall project 45mm above the ground level. They shall be
set at the left hand side of the road with the broad face facing the traffic and on this
face shall be stencilled, in two coats of black oil paint figuring 20mm high on a two coat
white painted background, the appropriate mileage and culvert number as directed by
the Engineer.
The beacons shall be located in a readily visible position from the carriageway and as
near as possible to the ends of the culverts, but in no case shall they be nearer than 3.0
metres from the edge of the ultimate carriageway. All markings of culvert beacons shall
be completed before the issue of the completion certificate for the section of road in
question.
Where directed by the Engineer, the appropriate reference marks may be painted on
any flat easily visible and accessible surface of the culvert, such as on the head-walls of
box culverts, in lieu of culvert beacons. In such cases the figuring shall be stencilled as
described above on a white painted rectangular background as directed by the Engineer.
Where directed by the Engineer, road warning signs shall be provided by the Contractor
at approaches to all dangerous curves, narrow bridges, railway level crossings etc.
Warning signs shall be of approved standard design complying with the accepted
standards of the Federal Ministry of Works for use on Trunk "A" Roads. They shall be
269
constructed of plain single sided pressed aluminum, shall be suitably braced at the back,
and shall be painted in the regulation manner. They shall be mounted on 76mm
diameter tabular steel posts when supported from the ground or, where such a support
may not cause an obstruction. They may be suspended as shown on the drawings or as
may directed by the Engineer.
The signs shall be erected in such locations and in such numbers as shown on the
drawings or directed by the Engineer. They shall be erected, painted and completed in
every way prior to the issue of the completion certificate for the section of the works in
question.
Payment for road warning signs shall be made under the appropriate item in the bill of
quantities, or where no such item is included from the appropriate provisional sum.
The Contractor shall provide and erect advance direction signs in such numbers and in
such locations as directed by the Engineer. The signs shall be of approved design
complying in all respects with the accepted standards of the Federal Ministry of Works
for use on trunk A roads. Generally they shall consist of plain single sided pressed
aluminum suitably braced at the back and painted in the regulation manner. The
Engineer shall supply to the Contractor a more detailed specification and drawings for all
advance direction signs required, showing their locations, sizes, structural details, types
of support etc. The signs shall be erected, painted and completed in every way prior to
the issue of the completion certificate for the section of the works in question.
Payment for advance direction signs shall be from the appropriate item in the bill of
quantities or where no such item is included, from the appropriate provisional sum.
On completion of the surfacing of the carriage ways e.t.c., the Contractor shall construct
such carriageway markings as are shown on the drawings or that may be directed by
the Engineer.
For smooth dense textured road surfacing the markings shall consist of an approved
ready coated self adhering thermoplastic material. It shall be suitably reflectorised, be
durable and long wearing containing adequate anti skid properties and the adhesive
shall provide sufficient bond between the markings and the road surface as to prevent
any undue movement either due to traffic action or due to temperature variations.
For coarse textured road surfacing such as surface dressing, the markings shall consist
of an approved quick setting thermoplastic composition applied hot by an approved 'line
laying' machine. The composition shall be suitably reflectorised, have a setting time of
not exceeding 60 seconds, be durable, long wearing and have adequate anti skid
properties. When set the markings shall be sufficiently rigid and provide sufficient bond
with the road surface as to prevent any undue distortion or movement due to traffic
action or temperature variation.
270
The type and colour of markings to be used shall be decided by the Engineer for the
various kinds of usage and road surface, and all markings shall be completed prior to
the issue of the completion certificate for the section of works in question.
Payment for carriageway markings shall be made per linear metres of marking from the
appropriate item in the bill of quantities or, where no such item is included, from the
appropriate provisional sum.
All precast concrete kerbs shall be in accordance with B.S. 340 and shall be of the sizes
and dimension shown on the drawings or directed by the Engineer. The kerbs shall be
manufactured using grade 20 N/mm² quality concrete and shall be cast in steel moulds,
and adequately vibrated or pressed. The kerbs shall pass the tests for transverse
strength and the absorption of water tests as described in the appropriate B.S 340.
After casting they shall be lightly rubbed over with a carborundum stone and later to a
smooth finish but shall not be slurried over with cement.
The kerbs shall be cured for a period of 14 days by protection from the direct rays of the
sun or from drying winds, and for the first 7 days after manufacture they shall be
thoroughly saturated with water. Kerbs shall not be incorporated into the works until
they are at least 28 days old.
The vertical joints shall be filled in with grade M1 mortar and flush pointed. Where
expansion joints occur in the carriageway such jointing shall be extended in the same
plane through the kerbing, and kerb base and ducking when provided.
Kerbs for radius work shall be purposely made to the required internal and external
radii. For radii less than 6 metres they shall be 500mm long. All kerbs for radii work in
excess of 15 metres radius may be straight kerbs and shall be 500mm long for radii up
to 30 metres. Otherwise than above all kerbs shall be 1000mm long.
Where precast concrete edging blocks are specified, such as edging to footpaths, they
shall be of the sizes and dimensions shown on the drawings or directed by the
Engineer, shall be in accordance with B.S. 340 and generally shall comply with the
provisions of the preceding clause for precast concrete kerbs. They shall be
manufactured using 20 N/mm² grade quality concrete and shall be laid as directed true
to line and level to the satisfaction of the Engineer's Representative. Payment shall be
271
made per linear metre of edging under the appropriate item in the bill of quantities.
Precast concrete paving slab shall comply with BS. 368 "Precast Concrete Flags." Except
where otherwise stated to the contrary or directed by the Engineer, the slabs shall be
50mm thick, and except where cutting is necessary, be of a uniform width of 450mm
and a uniform length of 600mm. The paving slabs shall be adequately vibrated or
pressed and shall have a smooth hard wearing non skid finish.
The paving slabs shall be laid and bedded on approved compacted sand filling to the
correct level, grade and cross-fall, so that when tested with a 3 metre straight edge
placed in any position on the paving, the maximum deviation shall not exceed 6mm.
Joints between the paving slabs shall be filled in with a slurry of cement mortar grade
"Ml" brushed over the paving in a circular motion until all the joint cavities are
completely filled in to the satisfaction of the Engineer's Representative. Any excess
slurry shall be removed and as soon as the joints have sufficiently hardened the whole
of the paving shall be washed so as to leave the completed paving in a neat and
workmanlike manner.
The price for paving shall include all cutting, whether straight or curved, laying, bedding,
jointing etc., And payment shall be made per square metre of completed paving from
the appropriate item in the bill of quantities.
As shown on the drawings, or as directed by the Engineer precast concrete gulley kerbs
shall be inserted at intervals in the kerbing to ensure a quick and complete run off of
surface rainwater from the carriageway. Gulley kerbs shall be constructed to the
dimensions shown on the drawings or as directed by the Engineer and shall comply in all
respects with the provisions of the relevant clause for precast concrete kerbs. The
Contractor's attention is drawn to the necessity for accurate gradients of the kerbs and
the edge of the carriageway, especially for flat gradients, to ensure that no surface
water ponds on the carriageway, payment shall be per number of gulley kerbs placed
from the appropriate item in the bill of quantities.
Gulley pipes shall be inserted into all gulley outlet kerbs to convey the surface water to
the side drain or otherwise. The gulley pipes shall consist of approved PVC pipes or
Class B asbestos cement pipe (150mm) in diameter, but the Engineer may direct that
cast iron pipes be used where the pipe is under an access road etc. Where the depth of
cover is less than 300mm on footpaths or less than 900mm on carriageways, the gulley
pipe shall be bedded on a 300mm by 150mm concrete bed and given a 76mm thick
concrete surround in grade 15 N/mm² concrete. Where a concrete bed or surround is
not used the gulley pipe shall be adequately supported and anchored in position at the
kerb and at its outlet by a bed and surround of grade 15 N/mm² concrete at least
300mm long. When completed all gulley pipes shall be flushed with water so as to leave
272
the full internal of the pipe free from any mortar, concrete or other debris. Payment for
gulley pipes shall be per linear metre of pipe and shall include all anchoring, fixing and
necessary joining, but shall not include the provisions of a concrete bed and surround.
Where the outlet of gulley pipes is over an embankment, or where the existing ground is
liable to erosion or otherwise as directed by the Engineer's Representative, precast
concrete half round channels of 225mm diameter or as directed, shall be laid to form a
water course leading from the outlets of the 150mm diameter gulley pipes.
The channels shall be cast in 600mm lengths of grade 15 N/mm² concrete and shall be
accurately laid on a prepared bed, true to line and level and jointed with Grade M.3
mortar to the satisfaction of the Engineer's Representative. Both extremities of the
channel shall be securely anchored and set in a bed of Grade 15 N/mm² concrete
approximately at least 75mm wider than the external width of the channel and 150mm
thick. Prior to the laying of the channels, the soil bed shall be properly shaped and
compacted to provide an even bed for the channels throughout the whole of their
length.
Payment shall be per linear metre of channel laid, including all necessary bedding,
jointing and anchoring, from the appropriate item in the bill of quantities.
If shown on the drawings or directed by the Engineer, the Contractor shall provide and
fix in position approved standard type reflecting road studs known as "cats eyes".
Payment shall be per number of cats eyes provided and fixed. And shall include for all
cutting out of the road surface and making good as necessary to the satisfaction of the
Engineer's Representative.
Where provision for street lighting is included in the bill of quantities forming part of the
main contract, the Engineer shall issue to the Contractor a separate street lighting
specification and drawings for each individual project. The street lighting system shall
be of the electrical type and generally shall comply with the relevant provision of the
British standard code of practice, "C.P. 1004 parts 1 and 2
Street lighting", or such other provisions specified by the Engineer. The types of
cables, controls, lanterns and mountings to be employed shall be specified by the
Engineer and the source and manufacturer's of same shall be approved by the Engineer.
The actual electrical installation shall be carried out by a competent electrical sub-
Contractor to be approved by the Engineer.
Payment for street lighting shall be made from the appropriate items in the bill of
quantities, or, where no such items are included, from the appropriate provisional sum.
The street lighting shall be completed and tested to the satisfaction of the Engineer's
Representative prior to the issue of the completion certificate for the section of work in
273
question.
Where provision for traffic control lights are included in the bill of quantities forming part
of the main contract, the Engineer shall issue to the Contractor a separate traffic light
specification and drawings for each individual set employed. The traffic control lights
shall be electrically operated and the types of cables, controls, lanterns and mountings
shall be specified by the Engineer, and their source and manufacturers shall be
approved by the Engineer. The actual electrical installation shall be carried out by a
competent electrical sub Contractor to be approved by the Engineer.
Payment for traffic lights shall be made from the appropriate items in the bill of
quantities or, where no such items are included, from the appropriate provisional sum.
The traffic control lights shall be completed and tested to the satisfaction of the
Engineers' Representative prior to the issue of the completion certificate for the section
of work in question.
Where illuminated guard posts, such as “keep right” signs at roundabouts etc., are to be
provided, they shall be of the electrically operated, internally illuminated type having a
pressed steel fluted type body with a vitreous enamel finish and rust proofed steel
lantern with a stove enamel finish. For roundabouts etc., the guard post shall be fitted
with a single aspect lantern having one 600mm x 300mm "keep right" glass panel.
The Engineer shall issue to the Contractor a comprehensive specification and drawings
for each individual type of guard post, indicating the types of cables, controls, lanterns
and mountings to be employed and the source and manufacturers of same shall be
subject to his approval. The actual electrical installation shall be carried out by an
approved competent electrical sub Contractor.
Payment for guardposts shall be made from the appropriate items in the bill of
quantities or, where no such items are included, from the appropriate provisional sum.
The guardposts shall be completed and tested to the satisfaction of the Engineer's
Representative prior to the issue of the completion certificate for the section of work in
question.
A. Scope
The work covered by this Clause consists of the construction of beam guard rails
mounted on concrete or steel posts as shown on the DRAWINGS or as ordered
by the Engineer's Representative.
B. Material
274
1. Steel rail elements shall conform to the DRAWING and shall be of Armco
Flex Beam Guardrail of 12 gage, non galvanized or equivalent. The
minimum tensile strength when tested in conjunction with splices and
end connections shall be 40,000 kg/cm², and the bolts attaching the rail
element to posts shall be 15mm in diameter.
3. Steel posts shall conform to the design shown on the DRAWINGS and
shall conform to the applicable requirements of SECTION ll CONCRETE:
MASS AND REINFORCED of the GENERAL SPECIFICATION.
C. Method of Construction
The concrete posts shall be set in excavated holes and the backfill shall be firmly
tamped in layers not more than 150mm thick in a manner satisfactory to the
Engineer's Representative.
All posts shall be plumb, properly spaced and to the prescribed line and grade.
Post holes shall be excavated to such depth that backfill below the posts will be
kept to the minimum and any such backfill shall be thoroughly compacted before
setting the posts.
The rail elements shall be erected to the required grade and line with the top
edge in a straight line or smooth curve, parallel to or concentric with the
roadway. Where a vertical transition is required the top edge of rail elements
shall form the chords of a smooth vertical curve. At each end post, a single
terminal section of rail element shall be erected and lapped in the direction of
traffic.
The Contractor's attention is directed to the details of guard rail transition at the
approach end of the guard railing as shown on the DRAWINGS.
275
No punching, drilling, reaming. cutting or welding of the rail elements or terminal
sections will be permitted in the field unless provided for on the DRAWINGS or
specifically approved by the Engineer.
All bolts and nuts attaching the rail element to the posts shall be hot
dip galvanized in accordance with the current ASTM Designation 153.
All metal parts that are not galvanized shall be thoroughly cleaned and shop
painted with one coat of rust inhibitive primer. Any metal surfaces from which
the shop coat of rust inhibitive primer has worn off, or on which the primer has
become defective otherwise, shall be given a brush coat of the above specified
rust inhibitive primer before the first coat of white paint is applied. All exposed
parts of the guard rail shall be given two field coats of white paint. Paint shall
not be applied over a previous coat which is not thoroughly dry.
D. Measurement
The quantity of beam guard rail for which payment will be made will be the sum
of the overall lengths of all sections of new beam guard rail constructed in
accordance with the DRAWINGS and Specifications or as directed by the
Engineer's Representative, measured along the face of the guard rail, including
the terminal sections of the rail element.
E. Payment
Payment for beam guard rail shall be made at the unit rate shown in the Bill of
Quantities which price shall include furnishing and erecting the guard rail
complete, including excavation, backfilling, furnishing and setting posts, priming,
painting, preservation treatment, the furnishing of all materials, labour and
equipment, and all else necessary therefor and incidental hereto.
The Contractor shall furnish and erect delineators of hermetically sealed acrylic
plastic prismatic reflector housed in embossed aluminum and provided with a
single grommeted mounting hole, mounted on galvanized "U" section channel
post as shown on the DRAWINGS or as directed by the Engineer's
Representative.
1. Materials
a. Prismatic Reflectors
276
expanded within the reflector mounting hole.
The reflector shall be acrylic plastic and the Contractor shall specify the
manufacturer of the raw material and the identification number of the particular
moulding compound to be furnished. Acceptable formulations:
TYPE OF
TRADE
MANUFACTURER MOULDING
NAME
COMPOUND
E.I. DUPONT
DENEMOURS LUCITE MH-140
AND CO INC.
ROHM AND
HAAS CO. OR FLEXIGLASS V
EQUIVALENT
The reflector shall consist of a clear and transparent plastic face with 45.0 sq.
cm. of reflecting area, herein referred to as the lens with a heat resistant plastic
coated back fused to the lens under heat and pressure around the entire
perimeters of the lens and control mounting hole to form a unit permanently
sealed against dust, water and water vapour. The reflector shall be colourless.
The lens shall consist of a smooth front surface free from projection or
indentation other than a central mounting hole and identification with a rear
surface bearing, a prismatic configuration, such that it will reflect total internal
reflection of light. The manufacturer's trade mark shall be moulded legibly into
the face of the lens.
All steel posts shall be mild steel No. 1 quality entirely in accordance with
the requirements of B.S. 15. All sections shall conform to British Standard
dimensions.
277
GENERAL SPECIFICATION.
c. Hardware
Bolts shall be of such length that in no case shall the exposed threaded
length of a bolt extend beyond the tightened bolt more than 10mm
2. Methods of Construction
If posts are set in earth, post holes shall be backfilled with suitable
material placed in layers not more than 150mm in depth and each layer
shall be thoroughly compacted.
The Contractor, at his own expense, shall replace or repair to the satisfaction of
the Engineer's Representative any delineators, removed or damaged in any way
prior to the acceptance of this work.
278
The quantity of delineators for which payment will be made shall be the number
of delineators actually furnished in accordance with the DRAWINGS, the
Specification, and as directed by the Engineer's Representative.
Payment for the delineators shall be made for the quantities as above
determined, at the unit price shown in the Bill of Quantities, which price shall
include the cost of posts, mounting plates, plastic reflectors, hardware,
galvanizing, driving or setting of posts, all excavation and backfilling, drilling in
rock and grouting, all material, equipment, labour, and all else necessary thereof
and incidental thereto.
The Contractor shall furnish and install telephone poles where and as shown on
the DRAWINGS or as directed by the Engineer's Representative.
All work under this Clause affecting the property, right of way and facilities of the
Posts and Telegraphs Department, Ministry of Communication (hereinafter called
as Owners) shall be carried out under joint supervision of the Engineer's
Representative and the said Owners in a manner satisfactory to both.
After approval of the working drawings and/or working plans, the Contractor
shall furnish the said owners, through the Engineer's Representative, with as
many numbers of prints of such drawings as required by the said owners. No
work affecting the safety, operation or maintenance of the utilities shall be
commenced or prosecuted until written approval of the owners has been
obtained.
This provision must be complied with before the Contractor begins actual
construction work.
Payment shall be made at the unit price for this Item tendered in the Bill of
Quantities. Payment shall include all costs for furnishing materials, equipment
and labour, and for all costs for coordination of all construction activities with the
owners. The installation shall be completed and tested to the satisfaction of the
Engineer's Representative and of the owners prior to the issue of the completion
certificate for the work in question.
279
PENETRATION (GROUTED) MACADAM
GENERAL 6500.
MATERIALS 6501.
The materials to be used in penetration macadam shall comply with the following:
(a) The coarse aggregate for the wearing course shall consist of clean crushed rock
dry and free from dust. The aggregate crushing value shall not exceed 23%.
The aggregate shall be graded as shown in the table below.
Percent Passing
Sieve
80mm thick base 50mm thick base
63.5mm 100 -
50.8mm 90 – 100 100
38.1mm 30 – 80 80 – 100
25.4mm 0 – 15 30 – 80
19.0mm - 0 – 15
(b) The 19mm aggregate for keying the penetration layer of coarse aggregate shall
comply with B.S. 63 "Single sized Road Stone and Chippings".
(c) The 10mm aggregate for keying the penetration layer of coarse aggregate shall
comply with the grading shown in the table below:
(d) The 12mm aggregate for the seal coat shall comply with B.S. 63
"Single sized Road Stone and Chippings".
280
(e) The bitumen for grouting the penetration macadam shall be a straight run
bitumen as specified in Clause 6301 (iii).
(f) The bitumen for the seal coat shall be either a straight run or cut back bitumen
as specified in Clause 6301 (ii) or Clause 6301 (iii).
(h) The specification for the various grades of aggregate required is devised so that
the full range of crushed stone produced will be used except for the fines
passing a 5mm screen. Aggregate in the 63.5mm to 19.0mm range will be used
in the base layer. Aggregate in the 19.0mm to 12mm and 10mm to 5mm range
shall be used as key stone. Aggregate in the 12mm to 10mm range shall be used
as chippings in the seal coat. The above will apply provided always that the
efficiency of the screening arrangements is such that the gradings of each range
of aggregate comply with the specifications.
WORKMANSHIP 6502
The coarse aggregate shall be spread by mechanical means on the prepared base in a
uniform loose layer so that after it is fully compacted it shall be of the specified
thickness. The layer of coarse aggregate shall be rolled to the correct shape
longitudinally and transversely by a three wheel steel tyred roller weighing not less than
9 tonne or by a vibratory roller of same capacity and having a minimum weight of 54
kilograms per centimetre width of rear wheel.
Any irregularities shall be corrected by loosening the surface and removing or adding
aggregate as required and re-compact. Rolling shall be continued until thorough
interlocking is obtained and there is no movement under the action of the roller. Rolling
shall be stopped if the aggregate begins to crack or crush. The finished surface shall
show uniform voids and when tested with a 3 metre straight edge placed parallel to the
centre line of the road shall not show any variation greater than 12mm. The transverse
profiles shall conform to the same accuracy using a correctly shaped rigid fabricated
metal template instead of a straight edge. The length of this template shall not be less
than the width of the base.
(2) Straight run bitumen shall then be sprayed as specified in Clause 6313 on the
shaped and compacted layer of coarse aggregate at the rate of 0.71 to 0.89 litres per
sq.m. per centimetre of compacted thickness. The actual rate of application shall be
determined by the Engineer's Representative after tests have been carried out on site,
as described in Clause 6503.
(3) Immediately following the applications of the bitumen and while it is still warm,
the key-stone shall be spread evenly over the surface so as to key the surface voids.
The key stone shall be applied in successive layers. The first layer shall be 19.0mm. Key
stone applied in just sufficient quantity to prevent the roller wheels sticking. As rolling
281
continues further 19.0mm and 10mm key stone shall be spread and lightly broomed
over the surface and rolled until all the voids in the coarse aggregate have been filled
but without having an excess of loose key stone on the surface. Rolling shall continue
until the key stone is thoroughly embedded and the stone layer shows no movement
under the roller. The proportions of 19.0mm and 10mm key stone to be used and the
order in which they shall be used shall be determined after trial sections have been
constructed as described in Clause 6503.
(4) When the spreading and rolling of the key stone have been completed to the
satisfaction of the Engineer's Representative, the road shall be opened to traffic as
specified in Clause 6316.
(5) The seal coat shall not be applied until at least 10 days after the completion of
the wearing course. During this period additional key stone shall be applied if directed
and brushed into any voids which may appear under the action of the traffic. After such
period any irregularities or areas of failure due to workmanship shall be cut out and
made good to the satisfaction of the Engineer's Representative. After all remedial work
has been allowed sufficient time to harden and settle under the action of traffic, the
surface shall be swept clean of all loose material and the seal coat shall be applied as
described for the wearing coat in Clause 6313 except that the bitumen will be sprayed at
the rate of 1.30 to 1.50 litres per sq.m.
(6) On completion of the seal coat the road shall be opened to traffic and speeds
shall be restricted to a maximum speed of 25 km/h for one day following the opening.
TESTS 6504.
(1) The rate of application of the bitumen shall be checked as specified in Clause
6223. When tests are carried out on the rate of application of the bitumen used
in grouting, the test trays shall be provided with lips of sufficient depth to
prevent loss of bitumen through over flowing.
(2) Holes 300mm square shall be cut in the stone layer to the full depth where
directed by the Engineer's Representative who shall determine by visual
inspection the degree of penetration of the bitumen. The Engineer's
Representative may order such variation in the rate of spread or application
temperature of the bitumen as he may consider necessary to obtain the most
uniform penetration of the bitumen through
out the full depth of the stone layer.
282