Professional Documents
Culture Documents
Iuac W Sub
Iuac W Sub
Iuac W Sub
Versus
INDEX
Petitioner
New Delhi
through
Dated: .02.2024
Versus
20. It is submitted that the Ld. Arbitral Tribunal also relied upon
objections raised by the Respondent-Claimant that were
raised for the first time by them in written note dated
12.10.2022 before the Ld. Sole Arbitrator provided by the
Respondent, which was not even the case of the Respondent
at any point in time. The Ld. Arbitrator, on the basis of the
written note submitted by the Respondent, proceeded to
pass award under these heads.
23. It is submitted that the Ld. Tribunal has gone by the narrow
technicalities and failed to do substantiate justice. Doing so
is contrary to the public policy of India.
25. It is submitted that the Ld. Arbitral Tribunal has passed the
award only on the basis of the submissions made by the
Respondent- Claimant that was contrary to their own
pleadings and thus the award impugned is perverse and not
sustainable in the eyes of law.
26. It is also submitted that the Ld. Arbitrator completely
ignored the fact that the Respondent made claims for
different amounts at different points of time. Initially, the
Respondent, through its final bill dated 06.12.2017, claimed
an amount of Rs. 2,98,55,145/- out of which an amount of
Rs. 73,94,738/- was paid by the Petitioner. However, the
Respondent claimed an amount of Rs.2,16,68,509/- on
15.10.2022 and Rs. 2,36,40,393/- simultaneously on
15.10.2022 itself. The Ld. Arbitral Tribunal took the figure
of Rs 2,36,40,393/- for the purpose of adjudication and
erroneously awarded a sum of Rs. 1,89,88,685/- which on
the face of it is incorrect as an amount of Rs. 73,94,738/-
already stood paid to the Respondent by the Petitioner. The
Ld. Tribunal completely failed to explain the same.
33. It is submitted that the Ld. Arbitrator even went beyond the
terms of the contract in awarding a sum of Rs. 1,12,740/- on
account of damages due to extra interest recovered on
machinery and T&P advance due to prolongation of the
contract. The same was de hors the provisions of Clause
10(B)(iii) and (iv) of the Contract Agreement. Hence, the
award under this head is also patently illegal.
39. In the view of the submissions made herein above, that the
present Petition deserves to be allowed and the Impugned
Arbitral Award dated 10.08.2023 made by the Ld. Sole
Arbitrator deserves to be set aside.
New Delhi
Date: 04.03.2024