Professional Documents
Culture Documents
CE Standing Orders
CE Standing Orders
1. No hot work is to be carried out anywhere on the vessel without permission from Master or C/E.
2. Hot work permit / checklist to be completed prior commencement of hot work and filed. Always
follow company policy.
3. Chief Engineer to be informed prior entry and after completion of work.
4. All E/Room personnel are to be in proper working clothes including full-sleeved boiler suits, safety
shoes, ear protection, helmet and working gloves whilst at work.
5. Proper protective gear should be used while handling chemicals, welding, checking batteries,
grinding, chipping etc.
In case any urgent assistance is required due to malfunction of any equipment or emergency, all engineers
should be called immediately using the Engineers call alarm.
All engine room personnel should be familiar with the location and operation of all safety equipment on
board.
1. Tests and checks to be carried out on all equipment as per PMS and recorded.
2. Any defects observed in the safety equipment should be attended to on priority basis.
Prior using any lifting equipment always check weight of object to be lifted and confirm that the equipment
is designed to handle that load.
1. Check all wire slings, eye bolts, shackles etc. are in good condition and suitable for load to be lifted.
2. Never stand under a suspended load while it is being lifted / moved.
3. Lash objects properly taking into account the centre of gravity and v/l’s list and trim prior to lifting.
4. Do not suspend lifting tackles from pipeline or weak supports as these may give way causing severe
damage to personnel and machinery.
1.2 ARRIVAL / DEPARTURE PORT
1. Inform chief engineer when notices are given.
2. Carry out all checks and tests as per concerned checklist.
3. Notify chief engineer immediately in case any equipment defect or malfunction.
4. Positively ensure that steering gear, aux engines, maneuvering equipment and air compressor are in
good orders.
1.4 INVENTORY
1. Promptly update receipt and consumption of spares / stores to maintain an accurate inventory.
2. Store all spares safely and take precautions to avoid corrosion and damage.
2. Periodically inspect spares to check for any signs of deterioration and damage and rectify.
3. Inform chief engineer of low levels and anticipated consumption to plan requisitions.
1.5 MAINTENANCE
1. Always inform C/E prior isolation any equipment for maintenance.
2. Carry out all checks necessary prior restarting any machinery after maintenance .avoid short cuts.
3. PMS routines of all equipment to be followed.
4. A defect list is to be maintained by the 2nd engineer for all defects which cannot be rectified
immediately. This list is to be kept in the engine control room and all E/R staff to be encouraged to
fill in the defects and update the book when the defects are rectified.
Confirm with the bridge that all fire alarms zones are in normal operations and none are isolated.
2.0 GENERAL
1. All engineers should be familiar with the operation of all machinery in the engine room in normal as
well as in emergency mode.
2. All E/R personnel should be familiar with E/R Procedures and checklists and comply with them.
3. Boiler water and cooling water tests should be carried out and recorded regularly.
4. Do not always rely on high levels alarm when filling tanks, check level physically.
5. Chief engineer / 2nd engineer will supervise all shore assisted maintenance. Never rely completely on
the technicians.
6. All personnel to inform second engineer before proceeding ashore.
7. Never hesitate to call the chief engineer at any time in any doubt whatsoever.
CHIEF ENGINEER