Project: Construction of Remaining Works, Roads and Infrastructure in Al Froosh Al Kharitiyat - Package 01 (DN107-P01) (Contract No.

C/2023/3) (the "Contract")) QBS_D2302-P1),


Construction of Remaining Works, Infrastructure FS Gaps for Bani Hajer and Al Rayyan Stadium, Pckg 2 (DN117-P02) (Contract No. C/2023/1) (the "Contract")) QBS_D2302-P2)
Contractor: QBS Construction WLL
Subcontractor : Intelligent Technology Systems Co
Scope of Work : Traffic Signal Works
Period Ending: 31-Aug-23
Payment Certificate : 02

MEASUREMENT SHEET

COMPARISON

SN. Description Unit Quantity Rate INR Ref. Sub-Contractor's Submission QBS Certification Variance Comments

Quantity Amount Quantity Amount Quantity Amount

Construction of Remaining Works, Roads and Infrastructure in Al Froosh Al Kharitiyat Package 1 (DN107-P01) (Contract
No. C/2023/3 (the “Contract”)), QBS_D2302-P1
TRAFFIC SIGNAL WORKS
The scope of works for this subcontract generally relates to the Traffic Signal Works described in the Contract and includes the
engineering, procurement, manufacture, supply, installation, testing, commissioning and maintenance and all other related fixing
accessories.
All the works shall be executed in accordance with QCS 2014, the Project’s drawings and specifications and the requirements of the
PWA for such works.
The scope of works includes, unless specifically excluded, the provision of all certifications, permits, licenses, warranties, shop
drawings, as-built drawings O&M Manuals and obtaining all approvals as required by the PWA and the Contract.
TRAFFIC SIGNALS AT JUNCTION OF ROAD 2 & 33
Traffic signal poles and gantries

1094, 1095,
1 Flange type pedestal traffic signal pole, excluding civil works nr 24.00 2,000.00 1252, 1253, 24.00 48,000.00 24.00 48,000.00 0.00 0.00
3931, 3932

Signal Heads
2 3 aspect, 300mm dia. lens, traffic signal head nr 16.00 3,100.00 2499. 4456 16.00 49,600.00 16.00 49,600.00 0.00 0.00
3 2 aspect 300mm dia. lens pedestrian heads nr 16.00 1,900.00 2500, 4456 16.00 30,400.00 16.00 30,400.00 0.00 0.00

Sub-surface vehicle detector with cables, pvc pipe and all associated ;all in accordance with Drawings and Specification
1636, 1216,
4 Sub-surface vehicle detector at 3m and 30m from stop bar nr 32.00 1,750.00 32.00 56,000.00 32.00 56,000.00 0.00 0.00
3620, 3621
1636, 1216,
5 Joint Kit nr 16.00 220.00 16.00 3,520.00 - - (16.00) (3,520.00) INR not found.
3620, 3621

Traffic system controller, including hardware and software with all accsy complete per drawings & specifications
6 Traffic signal controller; TS-C-1, 8 Signal Group nr 4.00 65,000.00 1925 & 3957 4.00 260,000.00 4.00 260,000.00 0.00 0.00
7 Electrical Service Cabinet nr 4.00 2,650.00 4.00 10,600.00 - - (4.00) (10,600.00) INR not found.

Pedestrian push button; including all associated accsy complete per drawings & specifications
8 Pedestrian push button nr 16.00 900.00 2501, 4458 16.00 14,400.00 16.00 14,400.00 0.00 0.00 INR 4458 under review

Cables
9 4 core traffic signal cable, laid through duct m 581.00 7.00 866.00 6,062.00 581.00 4,067.00 (285.00) (1,995.00) Quantity exceeding the LOA
10 5 core traffic signal cable, laid through duct m 836.00 8.00 160.00 1,280.00 160.00 1,280.00 0.00 0.00
4044, 4045,
11 7 core traffic signal cable, laid through duct m 464.00 10.00 849.00 8,490.00 464.00 4,640.00 (385.00) (3,850.00) Quantity exceeding the LOA
4046 & 4047
12 12C traffic signal cable, laid through duct m 342.00 13.00 440.00 5,720.00 342.00 4,446.00 (98.00) (1,274.00) Quantity exceeding the LOA
13 6P traffic signal cable m 150.00 23.00 1,018.00 23,414.00 150.00 3,450.00 (868.00) (19,964.00) Quantity exceeding the LOA

Reflex internally illuminated "Keep Right" bollard (sign Ref. No. 211), 600mm dia. single aspect translucent GRP motif
panel; allow for concrete base, fixings and power supply connection to the street lighting circuit
14 Illuminated bollard nr 48.00 4,800.00 - - 0.00 0.00
15 Testing & Commissioning (per junction) Junction 4.00 5,000.00 - - 0.00 0.00

A) TOTAL AMOUNT OF DN107 517,486.00 476,283.00 (41,203.00)

ITS PC-02 Summary Page 1 of 3


Project: Construction of Remaining Works, Roads and Infrastructure in Al Froosh Al Kharitiyat - Package 01 (DN107-P01) (Contract No. C/2023/3) (the "Contract")) QBS_D2302-P1),
Construction of Remaining Works, Infrastructure FS Gaps for Bani Hajer and Al Rayyan Stadium, Pckg 2 (DN117-P02) (Contract No. C/2023/1) (the "Contract")) QBS_D2302-P2)
Contractor: QBS Construction WLL
Subcontractor : Intelligent Technology Systems Co
Scope of Work : Traffic Signal Works
Period Ending: 31-Aug-23
Payment Certificate : 02

MEASUREMENT SHEET

COMPARISON

SN. Description Unit Quantity Rate INR Ref. Sub-Contractor's Submission QBS Certification Variance Comments

Quantity Amount Quantity Amount Quantity Amount

Construction of Remaining Works, Infrastructure FS Gaps for Bani Hajer and AlRayyan Stadium Pckg 2 (DN117-P02)
(Contract No. C/2023/1 (the “Contract”)), QBS_D2302-P2

TRAFFIC SIGNALS AT JUNCTION OF ROAD 2 & 33


Traffic signal poles and gantries
16 Signal Pedestal nr 21.00 2,000.00 6659& 5814 6.00 12,000.00 6.00 12,000.00 0.00 0.00
17 Signal Cantilever Gantry, Short: 26 & 13 (arm length up to10m) nr 2.00 25,000.00 - - - - 0.00 0.00
18 Signal Cantilever Gantry, Long: 7 & 20 (arm length up to19.8m) nr 2.00 45,000.00 - - - - 0.00 0.00

Signal Heads
19 3 aspect signal head (vehicle) nr 21.00 3,100.00 6659 6.00 18,600.00 6.00 18,600.00 0.00 0.00
20 3 aspect signal head (left turn) nr 9.00 3,100.00 - - 0.00 0.00
21 2 aspect signal head (pedestrian) nr 18.00 1,900.00 6660 4.00 7,600.00 4.00 7,600.00 0.00 0.00

Detector Loops
22 Sub-surface vehicle detector (2 x 2.5m) nr 20.00 1,750.00 2816 4.00 7,000.00 4.00 7,000.00 0.00 0.00
23 Sub-surface vehicle detector (2 x 4m) nr 9.00 1,750.00 2816 4.00 7,000.00 2.00 3,500.00 (2.00) (3,500.00) Over claim revised
24 Joint Kit nr 28.00 220.00 4.00 880.00 - - (4.00) (880.00) INR not available

Traffic system controller, including hardware and software with all accsy complete per drawings & specifications
25 Traffic System controller 8 Signal Group nr 2.00 65,000.00 - - 0.00 0.00
26 Traffic System controller 24 Signal Group nr 1.00 77,000.00 6661 1.00 77,000.00 1.00 77,000.00 0.00 0.00

Pedestrian push button; including all associated accsy complete per drawings & specifications
27 Pedestrian push button nr 16.00 900.00 6662 4.00 3,600.00 4.00 3,600.00 0.00 0.00

Cables
28 4C traffic signal cable, laid through duct m 280.00 7.00 6663 202.00 1,414.00 202.00 1,414.00 0.00 0.00
29 5C traffic signal cable, laid through duct m 168.00 8.00 6663 40.00 320.00 40.00 320.00 0.00 0.00
30 7C traffic signal cable, laid through duct m 282.00 10.00 6663 126.00 1,260.00 126.00 1,260.00 0.00 0.00
31 12C traffic signal cable, laid through duct m 239.00 13.00 6663 198.00 2,574.00 198.00 2,574.00 0.00 0.00
32 19C traffic signal cable, laid through duct m 173.00 17.00 6663 - - - - 0.00 0.00
33 6P traffic signal cable m 326.00 23.00 6663 247.00 5,681.00 247.00 5,681.00 0.00 0.00

TRAFFIC SIGNALS AT PEDESTRIAN CROSSINGS


Signal Heads nr 32.00 3,100.00 - - 0.00 0.00
34 3 aspect signal head (traffic) nr 32.00 1,900.00 - - 0.00 0.00
35 2 aspect signal head (pedestrian)

Detector Loops
36 Sub-surface vehicle detector (2 x 2.5m) nr 32.00 1,750.00 9662 4.00 7,000.00 - - (4.00) (7,000.00) Over claim, INR not available
37 Sub-surface vehicle detector (2 x 4m) nr 32.00 1,500.00 9662 4.00 6,000.00 - - (4.00) (6,000.00) Over claim, INR not available
38 Joint Kit nr 28.00 220.00 - - 0.00 0.00

Cables
39 4 core traffic signal cable, laid through duct m 1040.00 7.00 - - - - 0.00 0.00
40 5 core traffic signal cable, laid through duct m 1330.00 8.00 - - - - 0.00 0.00
41 7 core traffic signal cable, laid through duct m 938.00 10.00 - - - - 0.00 0.00
42 12C traffic signal cable, laid through duct m 538.00 13.00 - - - - 0.00 0.00
43 6P traffic signal cable m 326.00 24.00 - - - - 0.00 0.00

Traffic signal poles and gantries


44 Signal Pedestal nr 48.00 2,000.00 - - - - 0.00 0.00

Pedestrian push button; including all associated accessories


45 Pedestrian push button nr 32.00 900.00 - - - - 0.00 0.00

Traffic system controller, complete with hardware and software and all accsy
46 Traffic System controller, 8 Signal Group nr 8.00 65,000.00 - - - - 0.00 0.00
47 Testing & Commissioning (11 Junctions) Junction 11.00 5,000.00 - - - - 0.00 0.00

ITS PC-02 Summary Page 2 of 3


Project: Construction of Remaining Works, Roads and Infrastructure in Al Froosh Al Kharitiyat - Package 01 (DN107-P01) (Contract No. C/2023/3) (the "Contract")) QBS_D2302-P1),
Construction of Remaining Works, Infrastructure FS Gaps for Bani Hajer and Al Rayyan Stadium, Pckg 2 (DN117-P02) (Contract No. C/2023/1) (the "Contract")) QBS_D2302-P2)
Contractor: QBS Construction WLL
Subcontractor : Intelligent Technology Systems Co
Scope of Work : Traffic Signal Works
Period Ending: 31-Aug-23
Payment Certificate : 02

MEASUREMENT SHEET

COMPARISON

SN. Description Unit Quantity Rate INR Ref. Sub-Contractor's Submission QBS Certification Variance Comments

Quantity Amount Quantity Amount Quantity Amount

B) TOTAL AMOUNT OF DN117 157,929.00 140,549.00 (17,380.00)

C=(A+B) TOTAL AMOUNT OF DN107 & DN117 675,415.00 616,832.00 (58,583.00)