Method Statement For CCTV System Testing & Commissioning
Method Statement For CCTV System Testing & Commissioning
Method Statement For CCTV System Testing & Commissioning
© TAD-CNP-MST-EL-0008-R01 Page 1 of 26
Submission Details
Contract, Agreement, or
2 As per Contract
Specification Reference(s)
Revision History
Changes List
Section Page
Change No. Change Description
Number(s) Number(s)
- - - -
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 2 of 26
Table of Contents
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
7.0 PROCEDURE
8.0 ATTACHMENTS
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 3 of 26
1.0 PURPOSE
This method statement covers the Guidance of testing & commissioning of CCTV System that includes:
Field Camera (Indoor/Outdoor) and Power Supply
Client / Server Workstation
Connection to LAN
Integration with Access Control system
1.1 This procedure is to be read in conjunction with relevant Operators Manual & User’s guide
1.2 Suppliers Engineer will carry out the testing and commissioning of the CCTV system along with the sub-
contractor commissioning team.
1.3 Purpose of this manual to ensure the methods used for Testing & Commissioning of CCTV described above are
correct, acceptable and in line with the consultant quality system procedures to achieve the optimum results.
2.0 SCOPE
This document details the CCTV system testing and commissioning procedures, as follow:
3.0 REFERENCE
4.0 DEFINITIONS:
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 4 of 26
MIR : Material Verification Record.
MAR : Material Approval Request
ACS : Access Control System
CCTV : Closed Circuit Television
PIN : Personal Identification Number
LAN : Local Area Network
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant steps
in the procedure:
- Project Manager.
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 5 of 26
5.4 QA/QC Engineer (MEP):
- The monitoring of executions of works at site and should be as per the approved shop drawings and project
specifications.
- Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the Consultant.
- Check and ensure that all activities / work done / completed prior to offer for consultant inspection.
- He will follow and carried out all the relevant tests as per project specifications.
- Obtain the required clearance prior to Consultant’s inspections.
- Should acquire any necessary civil works clearances and coordination.
- Coordinate with site construction team.
- One who will assist the Consultant Engineer / Inspector during inspection.
- The carrying-out of work and the proper distribution of all the available resources in coordination with the
Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
- Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer
immediately.
- The implementation of all safety measures in accordance with the HSE plan and that the whole work force is
aware of its proper implementation.
- The implementation of safety measures is adequate to maintain a safe working environment on the work
activity.
- Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the
Construction Manager and the Project Manager.
- The site is maintained in a clean and tidy manner.
- Ensure only trained persons shall operate the power tools.
- Ensure all concerned personals shall use PPE and all other items as required.
- Ensure adequate lighting is provided in the working area at night time.
- Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders.
- Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
- Ensure safe access to site work at all times.
- Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in
suitable area that will keep the material in safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned
Engineer.
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 6 of 26
- The carrying-out of work and the proper distribution of all the available resources in coordination with the
sub-contractor Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
- Complying with the sub-contractor basic design practices, particularly those related to safety and engineering
- Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer
immediately.
Tool Box
Measuring Wheel.
Ladders.
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 7 of 26
Commissioning Laptop
Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent vest, and
safety gloves to ensure maximum ability of safe work and dust mask when required.
7.0 PROCEDURE
- Persons engaged with Testing have to be skilled and have received proper and adequate training on safety and
should be maintained in safe condition and the Testing methods not to create danger either for the operator or
for other persons or livestock.
- Necessary PPE to be worn while working in energized to be worn while working in energized circuits.
- Ensure adequate lighting is provided in the working area at night time and if inside the building area to be
well illuminated.
- Ensure service area/work area openings are provided with barricade, tape, safety nets and warning signage to
be provided.
- Emergency evacuation plan and procedure to be developed prior to start of testing.
- PTW to be applied and obtained to start work on the required area.
- Calibrated Instruments only to be used.
10. Connect the Server to the LAN (Server located in the Security Control Room).
11. Ensure all the Storage (NSM), Encoder, Video Console Display and System Managers are placed inside
the 42U RACK
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 8 of 26
12. Ensure the 42U Racks are provided by the 230VAC Power Supply sockets
13. Ensure all the Cisco CORE & EDGE switches are placed in the Racks as per the approved Schematic
Diagram.
14. Focusing of the camera to be adjusted by proper positioning to obtain optimum result/image.
15. Ensure that the camera Enclosure power supply installed properly.
16. Ensure that Power supply outlets for CCTV system to be fed by UPS (Optional).
7.2.B. Power up
- Check Mains (PE, N, L) cables
- Check Mains Voltage.
- Check all cable termination.
- Energize the incoming Mains Supply to Master Rack (where the CCTV Head End
Equipment’s placed)
4. Ensure that all the cables from Camera to the Network Switch are properly terminated and clearly
tagged.
5. Ensure that distribution of cameras to Network Switch is to be done as per approved drawing.
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 9 of 26
6. The Termination will be identified and checked as per the Manufacturer’s Instructions and also
check the right power supply provided.
7. Check the Network continuity from the Workstation to the Field Cameras.
8. Check the Encoder and its connection for the Analog Cameras.
9. Connect the Workstation, System Manager, Video Console Display, PCs and Encoder to the
LAN.
10. Connect the Server to the LAN (Server located in the Security Control Room).
11. Ensure all the Storage (NSM), Encoder, Video Console Display and System Managers are placed
inside
the 42U RACK
12. Ensure the 42U Racks are provided by the 230VAC Power Supply sockets
13. Ensure all the Cisco CORE & EDGE switches are placed in the Racks as per the approved
Schematic Diagram.
14. Focusing of the camera to be adjusted by proper positioning to obtain optimum result/image.
15. Ensure that the camera Enclosure power supply installed properly.
16. Ensure that Power supply outlets for CCTV system to be fed by UPS (Optional).
- After the successful completion of testing & commissioning the system will be ready to be demonstrated to
the facility management team and all concerned parties.
- During this period SUPPLIER engineer will assist the involved parties to operate and familiarize with the
system.
- All operations will be carried out by the operators and facility team in this period until they are able to
handle the system without any doubts.
- One day demonstration will be provided by SUPPLIER engineer and next 3 days will be assumed as
familiarization period to the concerned parties. Any doubts or clarifications they may require to be clarified
in these days will be done by SUPPLIER engineer
- After completion of commissioning, all test certificates of Commissioning will be submitted in hard copy.
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 10 of 26
8.0 ATTACHMENTS
Risk Assessment
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 11 of 26
TAD-CNP-MST-EL-xxxxxxxxxxxx Page 12 of 26