RECAPITULATION BILL OF QUANTITY (BOQ)

PROJECT : THE HILLS


LOCATION : BADUNG - BALI
YEAR : 2023

TOTAL PRICE
No. WORK DESCRIPTION LABOR + MATERIAL
(Rp.)

1 ADDITIONAL CUT AND FILL Rp 113,660,000.00

TOTAL CONSTRUCTION WORK (A) Rp 113,660,000.00


TOTAL BUILDING ONLY Rp 113,660,000.00

COUNTED :

Note :
1. Price of this BOQ With Rupiah Currency
2. Prices Above Do Not Include:
- Interior Furniture Work
- Landscape

Ubud, 08 Maret 2024


Hormat Saya

Agus Adnyana
BILL OF QUANTITY (BOQ)

PROJECT : THE HILLS


WORK : ADDITIONAL CUT AND FILL
LOCATION : BADUNG - BALI
YEAR : 2023

NO DESCRIPTION VOLUME PRICE TOTAL

I ADDITIONAL CUT AND FILL

1 Additional Excavation in basement & Ground Water Tank 813.76 m3 139,680.00 113,665,996.80

2 Filling of crushed excavated material in bulk in the open to form platforms - m3 78,000.00 -
3 Remove excavated material - m3 45,960.00 -
(Assumption we sell the materials to cover remove excavated cost)

GRAND TOTAL CUT AND FILL 113,665,996.80


ROUNDED 113,660,000.00

Note: Heavy Equipment for Excavation Work ( For 2 month )


1 unit PC 200 include Breaker and Bucket
2 unit PC 75 include Breaker and Bucket
1 unit Dump Truck (by third parties)

Ubud, 08 Maret 2024


Hormat Saya

Agus Adnyana