TOTAL PRICE
No. WORK DESCRIPTION LABOR + MATERIAL
(Rp.)
COUNTED :
Note :
1. Price of this BOQ With Rupiah Currency
2. Prices Above Do Not Include:
- Interior Furniture Work
- Landscape
Agus Adnyana
BILL OF QUANTITY (BOQ)
1 Additional Excavation in basement & Ground Water Tank 813.76 m3 139,680.00 113,665,996.80
2 Filling of crushed excavated material in bulk in the open to form platforms - m3 78,000.00 -
3 Remove excavated material - m3 45,960.00 -
(Assumption we sell the materials to cover remove excavated cost)