Professional Documents
Culture Documents
Delay in Construction Projects-Types Causes and Effects
Delay in Construction Projects-Types Causes and Effects
Delay in Construction Projects-Types Causes and Effects
1. Introduction
In general, delays are among the most well-known issues that occur in the
building development industry and may happen in basic or complex project.
Delay in building construction project can be defined as the lateness of
completion; it either exceeds the date specified in the contract or the date
decided by the parties for delivery of the project. It slips over its planned
schedule and is considered as a common problem in construction projects
(Ramya et al., 2015).
According to (Zack, 2003), delay is an event that requires more time than the
one specified in the contract to perform or complete works. Delay as a loss of
1
Student, Civil Engineering, KIIT University, Yemen
Email: abdullahtawfeq560@gmail.com
2
Faculty, School of Civil Engineering, KIIT University, Bhubaneswar, Odisha, India
184
Project Management Practices
time, Majid (2006) stated that Time refers to the period needed for the
completion of the construction project. If the project is delay, it means that the
project work cannot be completed according to the original contract schedule.
According to (Kanase et al., 2017), construction delay is classified into critical
delay, non-critical delay, causable delay, non-causable delay and concurrent
delay. According to (Ahmed, 2015), there are many causes that result in
construction project delay. According to (Aibinu and Jagboro, 2002), there are
six effects of delay in construction project: Time overrun, Cost overrun,
Dispute, Arbitration, Litigation and Total Abandonment.
2. Literature Review
Construction sector is one of the most important sectors for the economical
growth of the countries. It creates more job chances. This sector is characterized
by its important products such as buildings, dams, roads, railways, bridges, etc.
Increasing the production rate in construction projects makes a significant
contribution to the growth of any country’s economy. The production rate plays
a major role in the project success. Yet, there are many expected or unexpected
factors which can affect the production rate. Such factors lead to construction
project delay.
Most of construction projects have the same execution process but the causes of
construction projects delay are different from one country to another based on
many factors (climate, construction condition, project location, etc).
2.1. Types of Delay in Construction Projects
Project completion on the specified time in the contract is the main objective in
construction projects. Project delay leads to the negative value of the contract
regardless of the causes of delay or the responsible party of the delay
185
Project Management Practices
Type of
Delay
Non-
Compensable
compensable
Delay
Delay
186
Project Management Practices
187
Project Management Practices
Figure 2: Gantt chart Planned Vs Actual- Delay at Same Time from Owner
and Contractor
Figure 2: above the owner delay and contractor delay happen and finish at the
same time so the contractor is entitled to extension of time without any
compensation.
Figure 3: Gantt chart Planned Vs Actual Delay at different times from Owner and
Contractor
Figure 3 : the owner delay starts first on path-A and then the contractor delay
starts on path -B and both delays finish at the same time so the contractor is
entitled to extension of time and compensation for ( A ) time.
188
Project Management Practices
189
Project Management Practices
190
Project Management Practices
following methods were found much in use to analyze the causes of delay:
Relative Importance Index (RII), Frequency and severity Index (FI and SI),
Friedmann’s test, reliability analysis using SPSS statistical software, etc.
According to the latest trends in construction project delay research, the causes
of delay are various. Though certain causes were identified as major causes, no
single cause was found to be extremely important than the others.
Delay causes can be classified into critical and non-critical delays, excusable
delays and non-excusable. Knowing about the level of impact the delay mainly
caused due to improper schedule of the project that means planning in advance
by identifying which factors cause what kind of delay and so reduce the impact
of delay. The project manager is not only expected the problems created by
these causes but also have the strategy to manage these causes as early as
possible. If delay is expected in the early stages of the project, the cost and time
overruns increase proportionately with delay. So the causes of delay should be
foreseen before of the status of growth of the project and accordingly steps to be
taken to minimize the time and cost overrun. One can easily identified the
causes of delay of the project on and before of the project by studying this
exhaustive study.
References
Aibinu, A. A., & Jagboro, G. O. (2002). The effects of construction delays on
project delivery in Nigerian construction industry. International journal
of project management, 20(8), 593-599.
Al-Najjar, J. M. (2008). Factors influencing time and cost overruns on
construction projects in the Gaza Strip. Master thesis, Islamic
University, Gaza.
Divya, R., & Ramya, S. (2015). Causes, Effects and Minimization of Delays in
Construction Projects. In Proc. Conf. on the Research in
Communication, Computation, Electrical Science and Structures
(NCRACCESS-2015) (pp. 47-53).
Dr. Makarand Hastak, PE CCP, Editor (2015) American Association of Cost
Engineering.
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2015). Factors
affecting schedule delay, cost overrun, and quality level in public
construction projects. Journal of Management in Engineering, 32(1),
04015032.
Muhammed, T. A. (2015). Delays in Construction.
Odusami, K. T., & Onukwube, H. N. (2008). Factors affecting the accuracy of a
pre-tender cost estimate in Nigeria. Cost engineering, 50(9), 32.
191
Project Management Practices
Rao, B. P., Shekar, S. C., Jaiswal, N., Jain, A., & Saxena, A. D. (2016). Delay
Analysis of Construction Projects. Journal of Information Technology
and Economic Development, 7(1), 15.
Society of Construction Law Delay and Disruption protocol (2017). Published
by Society of Construction Law (UK), 2nd Edition.
Sweis, G., Sweis, R., Hammad, A. A., & Shboul, A. (2008). Delays in
construction projects: The case of Jordan. International Journal of
Project Management, 26(6), 665-674.
Thorat, S., Khandare, M., & Kanase, A. K. (2017). Identifying the Causes and
Effects of Delay in Residential Projects.
Zack, J. G. (2003, May). Schedule delay analysis; is there agreement. In Proc.
PMI-CPM college of performance spring conf (Vol. 41).
192