Checklist for Fixing Doors


Site Work Activity
CHECKLIST FOR FIXING DOORS & WINDOWS
Site
Location
Date
Drawing Reference no.
S.No Description Detail
1 Is approved WMS available? (Yes / No)
2 Are all the HSE norms being covered? (Yes / No)
3 Check whether material is approved by client?

Mention the door being installed. (Internal / External)

4 Door Frames :
Is the grouting done for vertical members of the door frames into the
a
floor? (Yes / No)
f Is grouting done for holdfasts into wall? (Yes / No)

g Is fastening of door frames to walls by screws? (Yes / No)


If No, mention max deviation found:
b Is the door frame installed in line and plumb? (Yes / No)

If No, mention max deviation found:


c Check for right angle and diagonal alignment of the door frames.

Mention size
d Check for the size of section is as per the drawing.

5 Door Shutter

a Mention the type of shutter.

b Are all the fixtures being used in shutter available? (Yes / No)

c Check for the provision and proper functioning of the following:


Mention if deviation found:
Has final check for paint,surface finish been done? (Yes / No)
d
No stain marks and any visible damage on surface

Check the Joints and Gaps of the window frame/sub frame w.r.t.
6
masonry opening.
If Yes, mention max deviation found:
Is there any visible gap between frame and wall? (Yes / No)
a
No visible gap is permitted
Are the joints between frame and door leaf neat and consistent?
b (Yes / No)
Deviation shall not be more than 5 mm
Is there any visible gap within the frame? (Yes / No) If Yes, mention max deviation found:
c
No gap shall be permitted
7 Check for paint,surface finish,glazing
Mention if deviation found:
a No stain marks and any visible damage on surface
b No sags, warps on door leaf
Consistent color tone of leaf and frame as per specification
Door joints and nail holes filled up, properly sanded down and with good
c
paint finish and consistency in color (including on top and bottom of door
leaf)
d No sign of corrosion in metal frame
e In glass doors, glazing should be clean and evenly sealed with gasket
f No cracks in glass shutter
Mention if deviation found:
Has the functionality of doors been checked? (Yes / No)
8 a) Ease of opening, closing and locking
b) No rattling sound during swinging/closures of door
Mention if defects found:
Is there any defect/s found in accessories? (Yes / No)
a) Lock sets with good fit, smooth working, rightly aligned and with no
stains
9
b) No sign of corrosion in door fittings
c) No missing or defective accessories
d) All screws levelled and flushed. No missing screws

10 Access Control
Corrective Actions, if any:

Checked by:

Signature: Construction Manager/ Engineer