Purpose:
Assurance of application of design and normative requirements to welding constructions.
2. Applicable Documents
DIN EN 1090-2 Execution of steel structures and aluminium structures
Quality requirements for fusion welding of metallic materials – comprehensive
DIN EN ISO 3834-2
quality requirements
DIN EN ISO 14731 Welding coordination – Tasks and responibilities
Welding and allied processes - Nomenclature of processes and reference
DIN EN ISO 4063
numbers
DIN EN ISO 6947 Welding and allied processes - welding positions
Welding – Fusion-welded joints in steel, nickel, titanium and their alloys – Quality
DIN EN ISO 5817
levels for imperfections
DIN EN 287-1 Qualification testing of welders – Fusion welding Part 1: Steels
DIN EN ISO 9606-1 Qualification testing of welders – Fusion welding Part 1: Steels
Welding Personnel – Qualification testing of welding operators and weld setters
DIN EN ISO 14732
for mechanized and automatic welding of metallic materials
DIN EN ISO 8501-1 Preparation of steel substrates before application of paints and related products
LH 10224956 Non-destructive testing of steel structures
LH 10227842 Visual Inspection of steel structures
LH 11234132 Welding consumables – storage and handling
LH 10336465 Joint types - Overview
LH 11931865 WPS transformation list
LH 11242627 Welding consumables - Overview
LH 10558005 Flame straightening of plates, profiles and plate structures
LH 10558004 Tack welding
LH 10558003 Recordable indications on welded joints or in base material during fabrication
LH 982500914 Control of non-conforming products
LH 11912085 Welding categories
Process 0000325968 Control of Non-conforming products
Design drawings, welding and inspection plans, test documents according to parts lists
In case of contradictions between the accompanying documents and this standard the requirements of this
standard shall be applied.
Dieses Dokument darf ohne Genehmigung weder kopiert, noch vervielfältigt werden. Liebherr-Norm_DE_V002.dot
Dieses Dokument wurde elektronisch erstellt und ist ohne Unterschrift gültig.
1/5
Artikelcode 982816814
- Norm Version 002
3. General requirements
3.1. Bevel preparation, material preparation
In general raw material and semi-finished products shall be shot blasted prior to cutting. For welding-related
processing all raw material shall be in shot blasted condition. (surface quality: ISO 8501 - Sa 2½). Welding
preparation shall be performed according to drawings. All cut edges performed by thermal cutting shall be
cleaned and deburred in order to be free from slag, scale, etc.
- welding process
- welding position
- joint type
- base material, material dimension, product form
Independently on the welding task the basic qualification for internal permitted welders and metal workers
consists of the following qualifications:
If any welder or metal worker is engaged only for fillet welding the basic qualification is:
- Welding process
- Joint type and
- Material combination,
Dieses Dokument darf ohne Genehmigung weder kopiert, noch vervielfältigt werden. Liebherr-Norm_DE_V002.dot
Dieses Dokument wurde elektronisch erstellt und ist ohne Unterschrift gültig.
2/5
Artikelcode 982816814
- Norm Version 002
All valid WPS are stored in document archive LIDA (QW > Schweißen) and are to be made available for any
welder and steelworker by the welding supervisor. All necessary Information for execution of weld seams are
included in the respective WPS, especially:
If any WPS required by the welding and inspection plan does not exist in the document archive the welding
engineer shall be informed immediately before welding is carried out.
If root and filler/top of a weld seam are to be welded by different welding process the welding process for root
welding is specified additionally in brackets in the welding and inspection plan. Following combinations of
processes are possible:
Dieses Dokument darf ohne Genehmigung weder kopiert, noch vervielfältigt werden. Liebherr-Norm_DE_V002.dot
Dieses Dokument wurde elektronisch erstellt und ist ohne Unterschrift gültig.
3/5
Artikelcode 982816814
- Norm Version 002
picture 2 welding constructions without welding and inspection plan but with welding symbols
IdNo. temperature
884150114 150°C
884150414 100°C
11236868 180°C
4.12. Marking
Any welding construction is to be identified and marked at any time during production. Until release of the
welding construction for painting it is to be ensured that any weld seam can be assigned to the respective
welder. NDT-welds shall be hard-stamped by the welders.
Dieses Dokument darf ohne Genehmigung weder kopiert, noch vervielfältigt werden. Liebherr-Norm_DE_V002.dot
Dieses Dokument wurde elektronisch erstellt und ist ohne Unterschrift gültig.
4/5
Artikelcode 982816814
- Norm Version 002
Material grade
LH355-40, LH355-60, LH690-40, LH690-60, LHR770-40, LH960-40
LHR355-20, LHR355-40, LHR690-40, LHR690-50, LHR770-50,
LHR355-50, LHRW355-40 LHRW690-40 S890QL
135, RT RT RT 48h
135(141)
12*, RT 24h - -
12*(135)
For defined minimum waiting times (24h, 48h) the effective waiting time shall be documented in the welding
and inspection plan. The required waiting time for NDT-Testing may be increased by the responsible welding
engineer in case of need.
5. Changes
Complete revision