CONSTRUCTION PROJECT COMMUNICATION PLAN TEMPLATE

PROJECT NAME PROJECT MANAGER CONSTRUCTION LEAD PROJECT ID DATE OF LAST UPDATE

Design and build a new bus stop shelter near the Melbourne Polytechnic
Jordan Kean A0000-9876 Thursday, April 11, 2024
Epping Campus Library, Dalton Road, Epping

DESCRIPTION /
COMMUNICATIO OBJECTIVES / FREQUENC PROJECTED
PURPOSE OF AUDIENCE OWNER CONCERNS COMMENTS
N METHOD KEY MESSAGES Y START DATE
COMMUNICATION

Provide project plan updates, Project Manager,


In-Person Meeting Share updates Weekly Allison Smith 01/20/24 lacks specifics Added details and neat handling
budget status. Contractor Leads

Distributing files,
Stakeholders,
communicating Jay
Email General update Daily Construction 01/21/24 lack of supplies efficiently communicate
decisions, status Occhiogrosso
Managers, Suppliers.
updates

Shared Project plan, designs, Project Team and


Share updates Ongoing Kaliah Fox 02/22/24 wrong drawing efficiently communicate
Documentation blueprints, contracts. Stakeholders

Safety sign and protective compulsory stuff in Project Team and


In-Person Meeting Weekly kean 03/12/24 over budget efficiently communicate
clothes construction Stakeholders

Project Manager,
Email Review project status Share updates Daily Jordan 03/13/24 Lack of workers efficiently communicate
Contractor Leads

Shared discuss potential issues or Share document and


Weekly project sponsor Allison Smith 03/14/24 broken machinery efficiently communicate
Documentation delays report

Skill worker,
Video call General update Status update At milestones Kean 03/19/24 lacks specifics efficiently communicate
stakeholder

Discuss what each team


Project Manager, Jay
Email member did yesterday, any Status update Daily 03/25/24 lack of supplies efficiently communicate
Contractor Leads Occhiogrosso
blockers

Stakeholders,
Present project deliverables, Share document and
In-Person Meeting Daily Construction Kaliah Fox 04/05/24 wrong drawing efficiently communicate
gather feedback report
Managers, Suppliers.

Shared discuss potential issues or Share document and


Weekly project sponsor Allison Smith 04/08/24 over budget efficiently communicate
Documentation delays report

Distributing files,
Stakeholders,
communicating Jay
Email General update Daily Construction 04/11/24 Lack of workers efficiently communicate
decisions, status Occhiogrosso
Managers, Suppliers.
updates

share daily progress made on Share document and Project Manager,


Project review Weekly Kean 04/14/24 broken machinery efficiently communicate
project tasks report Contractor Leads
Assess what worked and
Team standup what did not work and Status update Ongoing project sponsor Jordan 04/17/24 Slow progress efficiently communicate
discuss next steps

Distributing files,
Assess what worked and
Post - mortem communicating At the end of Project Manager,
what did not work and Allison Smith 04/19/24 The project ended late efficiently communicate
meeting decisions, status project Contractor Leads
discuss actionable takeaways
updates
Any articles, templates, or information provided by Smartsheet on the website are for
reference only. While we strive to keep the information up to date and correct, we make
no representations or warranties of any kind, express or implied, about the
completeness, accuracy, reliability, suitability, or availability with respect to the website or
the information, articles, templates, or related graphics contained on the website. Any
reliance you place on such information is therefore strictly at your own risk.