Ite
m
No. Description Qty Unit Unit rate Total
GENERAL REQUIREMENTS 22,788.36
Mobilization/Demobilization including hauling
of materials and disposal of waste 1 lot 22,788.36 22,788.36
EXTERIOR AREA 268,738.00
1 Earthworks
a. Soil compaction 91.75 sqm 100.00 9,175.00
b. Gravel bedding 5 cu.m 900.00 4,500.00
Structural works (Supply of materials and
2 labor for floor concreting)
a. Parking area 4.44 cu.m 10,000.00 44,400.00
b. Laundry area/dirty kitchen 3.58 cu.m 10,000.00 35,800.00
c. Path walk 0.82 cu.m 10,000.00 8,200.00
d. Patio (below balcony) 1.63 cu.m 10,000.00 16,300.00
Payment terms:
PRICE STILL NEGOTIABLE
Respectfully yours,
50% DOWN PAYMENT
40% PROGRESS BILLING
10% PAYMENT UPON COMPLETION
Engr. Francis Jane O. Mejias
Duration: 20-30 days from the receipt of down payment Contractor