CEYLON PETROLEUM CORPORATION


Page 21 of 123

PMN-117258-010

Construction of a Jet A-1 Transfer Pipeline from Muthurajawela to BIA Katunayake &
Project Title: Construction of Jet A-1 Storage Tanks and Associated Facilities with Modifications to the Existing
Terminal Facility at Muthurajawela.
Technical Scope of Work for EPC/Turnkey Contractors
Document Title:
Part-[A]: Jet-Al Fuel Pipeline

5 PROJECT DESIGN BASIS

The design basis of t he PROJECT is depicted in the following table named as "Basic Engineering and
Design Data (BEDD)" containing all necessary technical data used in the FEED studies and
ca lculations of t he Jet A-1 Fuel Pipeli ne System. This data shall be checked, verified and validated
during the FEED review stage of the CONTRACT. In the following table, the design basis items and
the values of the design related parameters for the main components of the PROJECT are
presented.

Design Basis Item Descriptions and Values


Jet A-1 physical characteristics Temperature 10° [C]
Specific gravity 0.843
Viscosity 2.7 [cP]
Pipeline Length 21[km], approximately
Nominal Pipeline Size (NPS) 10" / 273.1 [mm] , seamless pipes
Pipe Wall Thickness 9.27 [mm]
Material design code API SL
Wall thickness calculation code ASME B31.4 & API RP 1102
Material type Grade B
Minimum cover (trench) 1.0 - 1.5 [m] (depending on detail design
consideration)
Design Factor 0.72
(ASME B31.4, paragraph 402.3)
Protection Internally epoxy coated and Externally 3 layers
polyethylene (3LPE) coated pipes

u Specified Minimum Yield Strength


(SMYS)
241 [MPa]

Internal pipe design pressure 4246.3 [kPa]


Internal pipe operating pressure 3280 [kPa]
Installation temperature 20° [C]
Maximum pipeline temperature 68° [C]
Pipeline System U-2000: Muthurajawela 10" Scraper Station
Units numbering (pig launcher)
U-2500: belowground 10" pipeline section
U-3000: BIA 10" Scraper Station (pig receiver)

Basic Engineering and Design Data