General Notes

1. Do not scale drawings. Dimensions govern.


2. All dimensions are in millimetres unless noted otherwise.
3. All levels are in metres unless noted otherwise.
4. Foster + Partners shall be notified in writing of any discrepancies.
5. Any area measurements outside of Foster + Partners scope are for
guidance only, subject to final confirmation upon completion of the other
Consultants' Design, which shall be submitted following Foster +
Partners Architectural DD submission
6. Foster + Partners' scope of services is limited to Core & Shell
Architecture services (Signature Architect) only. All representations of
other design / engineering disciplines' design are indicative only - for all
other disciplines' design please refer to their respective Design
submissions.
7. Not for Construction.
8. The Information Models and CAD drawings used as reference in this
submission, represent the documentation available on the 20th of
November 2023 in BIM 360 "L00 Laheq Island Wide" project.
9. The final FFL ground floor levels will vary according to DMP2 V18
topography and villa location on the masterplan.
10.The South Community villas shutter removal follow the solar shading
shoebox analysis by EOC which is based on SHGCgl 0.35 glass and
SBC and 50 W/m2 solar maximum criteria and 0 Hour of Annual
overheating and is compliant in all the villa orientations as per the latest
masterplan DMP2 rev18. The shutter removal has not taken into
consideration the potential ‘relaxation’ of the parameters in the winter
months, which will need to be further assessed by Chapman case-by-
case and Approved by RSG based on EOC’s latest simulation data.
Once confirmed, these relaxed criteria will allow for more shutters to be
521-D removed in all orientations. The final solar response strategy will be
521-06
issued by F+P via a separate matrix / manual once concluded.

RFS-101 RFS-901 RFS-101


07 55 56 07 42 63 07 55 56

Parapet Level
Majlis
Bedroom 01
00-17
00-04
Ensuite 01

FFL 9.480 00-05

Hot Water
Calorifier (PH3)

Entrance Circulation 00-26

00-01 00-02

Circulation

00-16 Lift pump/electrical closet


RFS-901 Closed Kitchen
Media Room

00-03

07 42 63
00-18 Powder Room 01

00-15

Roof
FFL 8.500 Living Room

00 01/12/2023 100% Design Development - EB


Open Kitchen 00-12

00-14

Powder Room 02

00-12
Bedroom 2

00-06
Addendum II
Level 02 Circulation
Rev. Date Reason For Issue Chk

Design Development
00-11

FFL 8.000
Terrace
Dining

00-13 Bedroom 03

00-08

Key Plan.
Ensuite 02

00-07

Ensuite 03

00-09
780

Pool

Makkah

N
3480

Circulation Bedroom 04
2700

2700
2100

2100
SCR-101 SCR-101
3 S52 - Keyplan - Lift + electrical cabinet

03 53 00 03 53 00

Level 01
FFL 4.200
2
L02-R02D01-FOS-00-
XX-DWG-AR-55003

1845
880

CLG-101 CLG-101
09 21 16 09 21 16
4200

1935
Executive Architect/ AOR
Licence number - 1010452878

Olaya District
3000

3000

Riyadh 11625, KSA


T +966 9200 29750
Circulation Bedroom 01 F +966 2900 29750
riyadh@dewan-architects.com

Signature/Design Architect
2100

2100

Riverside, 22 Hester Road © Foster + Partners 2022

London SW11 4AN


SCR-101 SCR-101 T +44(0)20 7738 0455
03 53 00 F +44(0)20 7738 1107
03 53 00 london@fosterandpartners.com www.fosterandpartners.com
Client

1
Level 00 L02-R02D01-FOS-00-
XX-DWG-AR-55003
120

FFL 0.000

Project

Laheq Island L02


Villas South Community

1 S52 - Lift section 1


4 S52 - Lift plan 00 Drawing Title

1 : 20 1 : 20 Details
Lifts and Escalators
Lift Details 03

Model File Reference


L02-R02D01-FOS-00-ZZ-MOD-AR-00001
Drawn By Checked By Approved By

F+P EB SB
Project No First Issue Date Scale at ISO A0
L02R02 01/12/2023 1 : 20
Drawing Number Revision
L02-R02D01-FOS-00-XX-DWG-AR-55003 00