Professional Documents
Culture Documents
Doncaster Decoy South TMP
Doncaster Decoy South TMP
Doncaster Decoy South TMP
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
Location: Doncaster
This document has been produced in accordance with NR/L2/CIV/177: Monitoring of the track over
or adjacent to Construction Works.
1
OFFICIAL
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
1. Project Details
2. Site Details
ELR
SPD5
Track ID
1100, 2100, 3905
Start (miles & yards)
117.0
End (miles & yards)
117.0004
Line speed (mph)
50 – 1100,2100. 25 - 3905
Track Category
4
2
OFFICIAL
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
Details can be found in the sectional appendix or for track category from the local Track
Maintenance Engineer (TME).
Secondary Contact
Both of the above responsibilities apply for the duration of the monitoring works
3
OFFICIAL
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
4
OFFICIAL
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
6. Baseline Readings
Changes in the gauge, geometry and position of the track need to be determined in accordance with
NR/L2/CIV/177.
Pre and post readings will be taken using a cross level to measure cant and twist. 5 point and offset
ruler to measure vertical alignment. Tape to measure horizontal alignment.
The difference in these values will be compared to the baseline values recorded prior to works
commencing. These are recorded in the table below.
Note: Where specific monitoring is required for the identified assets additional sections should be
added to this TMP and they should be referenced in the table below accordingly.
5
OFFICIAL
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
8. Monitoring Frequency
Following a review of site conditions and the type of works, it is expected that the measurements of
the track and the analysis of the readings will be completed at the following frequency.
Note: NR/L2/CIV/177 identifies the minimum required frequency while works are being carried out.
*Note 8.1 – This frequency is minimum of 4 hours for High Risk sites and every 12 hours for Medium
Risk sites in accordance with NR/L2/CIV/177.
Readings will start from the date at which works with the potential to affect NR assets commence
and, depending on the agreed monitoring requirements for the site, will be carried out during and
continue following completion of works in accordance with NR/L2/CIV/177 (Table 4).
If movement is apparent, any required immediate actions in line with Table 5 will be taken to
maintain the safety of the line'
Where the project is not running to planned dates, monitoring will be carried out at the frequency
appropriate for the stage of the project.
6
OFFICIAL
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
Following a review of the works being undertaken and predicted ground movements the following
trigger levels and mandatory actions have been determined for the duration of the works.
The actions in the table below need to be followed upon reaching the predetermined trigger level.
Note 9.1: Consideration can be given to producing additional trigger levels on top of those detailed in
the table below if they are required for the specific project.
7
OFFICIAL
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
Vertical Alignment
Twist
Fault Fault
Action (3m)
(Top) (Line) Action Required
Limit Limiting
limiting Limiting
value
Values** values**
Within allowable
NO FAULT
No mandated Action
Inform & review with CRE*** should rapid or
limits
8
OFFICIAL
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
Up Main (1100)
SFT: 27°c
CRT(W): 42°c
CRT(30/60): 45 °c
CRT(20): 47°c
Dn Main (2100)
SFT: 27°c
CRT(W): 42°c
CRT(30/60): 45 °c
CRT(20): 47°c
SFT: 24°c
CRT(W): 39°c
CRT(30/60): 42 °c
CRT(20): 44°c
9
OFFICIAL
Ref: NR/L2/CIV/177/TMP
Issue: 2
Date: 06 March 2021
OLE
Structures (Platforms/ foot bridges etc.)
10