Struck by
Falling Object
Critical Controls:
Task: ................................................................................................
Are controls in place to prevent personnel entering the drop zone? Yes No N/A
Where there is a risk of dropped objects, an exclusion zone been established? E.g. for
every 4 metres in height barricade 1 metre out from the vertical to allow for deflection?
Exclusion zone shall be danger taped’ with information tags attached at each level where
there is a dropped object risk?
Are rated lanyards used and attached to tools or equipment that could fall from height?
Rubber stoppers or safety collars are fitted to Crow / Podgy / Pry Bars?
Drop mats are in place at the work area to cover any gaps where objects may fall from one
level to another?
Loose items have been secured in containers, tool bags or tool boxes and not left near open
edges?
Handrails have infill protection fitted? I.e. Shade cloth, plastic mesh?
Work shall STOP by everyone if there is a requirement for entry into the drop zone. Work
will not continue until the area is clear?
Other:
If I have answered NO to any questions on this Checklist I will correct any issues or contact my Supervisor before proceeding