Section 238(1)(a)
Building Regulations 2018
Regulation 126
The design certified by this certificate complies with the following provisions of Building Act 1993, Building
Regulations 2018 or National Construction Code
Act, Regulation or NCC Section, Regulation, Part, Performance Requirement or other provision
National Construction Code Series Volume One and Two (inc. Part 3.2) - Building Code of Australia, 2019
Building Regulations 2018
Part 7 of the Building Act Section 238(1)(b).
AS1170.1-2002 Structural Design Actions (Inc Amendment 1 and 2), AS1170.2-2011
Structural Design Actions (Inc Amendment 1 and 2), AS4100-1998 Steel Structures Code,
Relevant Australian Standards AS1684-2010 Timber Framing Code, AS1720.1-2010 Timber Structures Code Part 1,
AS2870-2011 Residential Slab and Footing Code, AS3600-2018 Concrete Structures Code,
AS3700-2018 Masonry Code, AS3500.3-2018 Plumbing and Drainage Code
I prepared the design, or part of the design, set out in the documents listed above.
I certify that the design set out in the documents listed above complies with the provisions set out above.
I believe that I hold the required skills, experience and knowledge to issue this certificate and can demonstrate this if requested
to do so.
Enio Sciessere
Click Engineering (Aust) Pty Ltd
Address: Level 1, 25-27 Railway Road, Blackburn, 3130
Email: contact@clickeng.com.au
Endorsed Building Engineer and area of Engineering
CERTIFICATE prepared for
Civil Engineer
Endorsed Building Engineer Registration No. PE0000984 BCTA Homes EAST
Date of issue of certificate: 09 November 2021
Melbourne
CLICK ENGINEERING (AUST) PTY LTD level 1, 25-27 railway road, blackburn vic 3130 P 03 9894 4422 E contact@clickeng.com.au ACN 162 735 917
STRUCTURAL COMPUTATIONS
1 October 2021
Being duly qualified Civil Engineers, we hereby certify that the computations and drawings denoted with Our Reference Number,
as shown above, have been prepared by one of us, or under our direct supervision, and comply with the relevant Regulations
under the National Construction Code Series Volumes One and Two - Building Code of Australia, 2019, and the following
Australian Standard Codes:
CLICK ENGINEERING (AUST) PTY LTD level 1, 25-27 railway road, blackburn vic 3130 P 03 9894 4422 E contact@clickeng.com.au ACN 162 735 917
CLICK ENGINEERING
Structural Civil Geotechnical & Land Surveying Sheet 2
First Floor 23-27 Railway Road Blackburn Job No. 2215220
Phone: 9894 4222 Designed: AW
Reactions
Working Ultimate Working Ultimate
Ra DL = 1.80 kN 2.25 kN Rb DL = 1.80 kN 2.25 kN
Ra LL = 1.12 kN 1.67 kN Rb LL = 1.12 kN 1.67 kN
Ra TL = 2.92 kN 3.92 kN Rb TL = 2.92 kN 3.92 kN
Deflection
Defl. (long-term) = 3.27 mm @ 1.80 m Allowable 12 mm ...O.K.
Defl. (live load) = 1.01 mm @ 1.80 m Allowable 9 mm ...O.K.
Dead + Live Load phi = 0.8 k1 = 0.8 Dead + Live Load phi = 0.8 k1 = 0.8
V* = 3.92 kNm N* = 3.92 kNm
phiV = 26.50 kNm ...O.K. phiN = 31.10 kNm ...O.K.
Reactions
Working Ultimate Working Ultimate
Ra DL = 3.23 kN 4.03 kN Rb DL = 3.64 kN 4.54 kN
Ra LL = 0.97 kN 1.46 kN Rb LL = 1.13 kN 1.69 kN
Ra TL = 4.20 kN 5.49 kN Rb TL = 4.76 kN 6.24 kN
Deflection
Defl. (long-term) = 4.59 mm @ 1.55 m Allowable 10.33 mm ...O.K.
Defl. (live load) = 0.70 mm @ 1.55 m Allowable 8.611 mm ...O.K.
Dead + Live Load phi = 0.8 k1 = 0.8 Dead + Live Load phi = 0.8 k1 = 0.8
V* = 6.24 kNm N* = 6.24 kNm
phiV = 26.50 kNm ...O.K. phiN = 31.10 kNm ...O.K.
LOADINGS: (U.D.L.)
DESIGN
P 1 kN P 2 kN
W - ULTIMATE = 16.03 kN/m W kN/m
P 1 - ULTIMATE = 0.00 kN mmmmmmmmmmmmmmm
P 2 - ULTIMATE = 0.00 kN Ra Rb
alpha m = 1.00
alpha s = 0.98
SECTION PROPERTIES
ADOPT 250 UB 37
Date:01/10/2021
CLICK ENGINEERING
Structural Civil Geotechnical & Land Surveying Sheet 5
First Floor 23-27 Railway Road Blackburn Job No. 2215220
Phone: 9894 4222 Designed: AW
LOADING
1.14 KN/m
SECTION PROPERTIES
TOTAL LOAD = 31 kN B1
l/r = 70.6231454
Fac = 149.552411 MPa
Foc = 395.7634 MPa
(1- f ac/0.6Foc)Fbc
P1
LOADING ULTIMATE
F Nc = F k1 x k4 x k6 x k11 x k12 [f'c Ac] DL = 6.79 kN
LL = 3.36 kN
b d TL = 10.15 kN
F = 0.8 Post Size 90 x 90 RB1&RB2
k1 = 0.57 DL ONLY
k1 = 0.8 DL + LL
k4 = 1
k6 = 1 g13 = 0.85 rc = 0.98
k11 = 1 L = 3.1 m
k12 = 0.24 Lax = 3.1 m S3 (1) = 34.444 S4 (1) = 34.444444
f'c = 15 Lay = 3.1 m S3 (2) = 29.278 S4 (2) = 29.277778
Ac = 8100
S3 = 29.278 S4 = 29.277778
LOADING:
33.73 kN/m
Wu = 43.76 kN/m
=> Ast -ve = 160 mm^2 MESH "OR" 201 mm^2 BARS
Ast +ve = 143 mm^2 MESH "OR" 179 mm^2 BARS
CHECK SERVICEABILITY
Lef/d = 13.92
l/d = 7.20 ...OK
CLICK ENGINEERING
Structural Civil Geotechnical & Land Surveying Sheet 9
First Floor 23-27 Railway Road Blackburn Job No. 2215220
Phone: 9894 4222 Designed: AW
Vu = d" AWAY
35.46 FROM
kN CRITICAL SUPPORT
LOADING:
30.88 kN/m
Wu = 41.27 kN/m
=> Ast -ve = 151 mm^2 MESH "OR" 189 mm^2 BARS
Ast +ve = 135 mm^2 MESH "OR" 169 mm^2 BARS
CHECK SERVICEABILITY
Lef/d = 14.71
l/d = 7.20 ...OK
CLICK ENGINEERING
Structural Civil Geotechnical & Land Surveying Sheet 11
First Floor 23-27 Railway Road Blackburn Job No. 2215220
Phone: 9894 4222 Designed: AW
Vu = d" AWAY
33.44 FROM
kN CRITICAL SUPPORT
LOADING:
26.53 kN/m
Wu = 36.01 kN/m
=> Ast -ve = 132 mm^2 MESH "OR" 165 mm^2 BARS
Ast +ve = 118 mm^2 MESH "OR" 147 mm^2 BARS
CHECK SERVICEABILITY
Lef/d = 15.70
l/d = 7.20 ...OK
CLICK ENGINEERING
Structural Civil Geotechnical & Land Surveying Sheet 13
First Floor 23-27 Railway Road Blackburn Job No. 2215220
Phone: 9894 4222 Designed: AW
Vu = d" AWAY
29.18 FROM
kN CRITICAL SUPPORT
Loads = UDL
m m
DL Roof = 5.1 x 1.8 x 0.9 kPa = 8.3 kN
Wall = 5.6 x 1.8 x 2.5 kPa = 25.2 kN
Floor = 2.2 x 1.8 x 1 kPa = 4.0 kN
Slab = 1.2 x 1.8 x 3.2 kPa = 6.9 kN
E beam = 0.31 x 1.8 x 0.3 x 25 = 4.2 kN
DL = 48.5 kN
LL = 11.5 kN
TL = 60.0 kN
DL + LL = 66.0 kN
Loads = UDL
m m
DL Roof = 0 x 0 x 0.9 kPa = 0.0 kN
Wall = 5.6 x 3.6 x 0.35 kPa = 7.1 kN
Floor = 0 x 0 x 1 kPa = 0.0 kN
Slab = 3 x 3.6 x 3.2 kPa = 34.6 kN
E beam = 0.31 x 3.6 x 0.11 x 25 = 3.1 kN
Pile Cap = 0.31 x 0.4 x 0.4 x 25 = 1.2 kN
DL = 45.9 kN
LL = 16.2 kN
TL = 62.1 kN
DL + LL = 68.3 kN
Loads = UDL
m m
DL Roof = 3.3 x 3.1 x 0.9 kPa = 9.2 kN
Wall = 2.9 x 3.1 x 2.5 kPa = 22.5 kN
Floor = 0 x 0 x 1 kPa = 0.0 kN
Slab = 1.7 x 3.1 x 3.2 kPa = 16.9 kN
E beam = 0.31 x 3.1 x 0.3 x 25 = 7.2 kN
DL = 55.8 kN
LL = 15.7 kN
TL = 71.5 kN
DL + LL = 78.6 kN
Loads = UDL
m m
DL Roof = 0 x 0 x 0.9 kPa = 0.0 kN
Wall = 0 x 0 x 0.35 kPa = 0.0 kN
Floor = 0 x 0 x 1 kPa = 0.0 kN
Slab = 2.8 x 3.1 x 3.2 kPa = 27.8 kN
E beam = 0.31 x 3.1 x 0.11 x 25 = 2.6 kN
Pile Cap = 0.31 x 0.4 x 0.4 x 25 = 1.2 kN
DL = 31.7 kN
LL = 21.7 kN
TL = 53.4 kN
DL + LL = 58.7 kN
Loads = UDL
m m
DL Roof = 6.7 x 1.9 x 0.9 kPa = 11.5 kN
Wall = 5.7 x 1.9 x 0.35 kPa = 3.8 kN
Floor = 2.2 x 1.9 x 1 kPa = 4.2 kN
Slab = 2.4 x 1.9 x 3.2 kPa = 14.6 kN
E beam = 0.31 x 1.9 x 0.3 x 25 = 4.4 kN
DL = 38.4 kN
LL = 20.9 kN
TL = 59.3 kN
DL + LL = 65.2 kN
Loads = UDL
m m
DL Roof = 0 x 1.8 x 0.9 kPa = 0.0 kN
Wall = 5.6 x 1.8 x 0.35 kPa = 3.5 kN
Floor = 4 x 1.8 x 1 kPa = 7.2 kN
Slab = 1.8 x 1.8 x 3.2 kPa = 10.4 kN
E beam = 0.31 x 1.8 x 0.11 x 25 = 1.5 kN
Pile Cap = 0.31 x 0.4 x 0.4 x 25 = 1.2 kN
DL = 23.9 kN
LL = 18.9 kN
TL = 42.8 kN
DL + LL = 47.0 kN
Loads = UDL
m m
DL Roof = 2.4 x 1.3 x 0.9 kPa = 2.8 kN
Wall = 5.6 x 1.3 x 0.35 kPa = 2.5 kN
Floor = 0.45 x 1.3 x 1 kPa = 0.6 kN
Slab = 1.8 x 1.3 x 3.2 kPa = 7.5 kN
E beam = 0.31 x 1.3 x 0.3 x 25 = 3.0 kN
B1 P Load = 15.0 kN
DL = 31.5 kN
TL = 55.0 kN
DL + LL = 60.5 kN