GB1036 803243499 01 00 01
GB1036 803243499 01 00 01
GB1036 803243499 01 00 01
Contractor
Subcontractor Stamp
Project PKZ/PC
KKS / Reg.
UNID 803243499 DCC &MDC080 Content code 11H No. 203843
Wijnands Digitally signed by Wijnands Han
Revision
Approved 2019-Nov-21 RCLA Han
DN: cn=Wijnands Han, o=Siemens,
email=han.wijnands@siemens.com
Updated with Client mark-ups
Description
Date: 2019.11.27 15:02:01 +01'00'
Check 2 - - Title
van
Check 1 2019-Nov-21 PPAA Paassen
van Paassen Peter
cn=van Paassen Peter, o=Siemens,
email=peter.van_paassen@siemens.com
Peter
- A4
Document No. TC ID. Revision
GB1036-H-&MDC080-203843 1/4
ECCN N AL N US-content No
These items are controlled by the U.S. Government (when labeled with “ECCN” unequal “N”) and authorized for export only to the country of ultimate destination for use by the ultimate consignee or
end-user(s) herein identified. They may not be resold, transferred, or otherwise disposed of, to any other country or to any person other than the authorized ultimate consignee or end-user(s), either in
their original form or after being incorporated into other items, without first obtaining approval from the U.S. Government or as otherwise authorized by U.S. law and regulations. Items labeled with "AL”
unequal "N” are subject to European / national export authorization. Items without label, with label "AL:N" / "ECCN:N" or label "AL:9X9999" / "ECCN: 9X9999" may require authorization from responsible
authorities depending on the final end-use, or the destination.
TYPICAL FIELD QUALITY PLAN - FIELD ASSEMBLY - SCR / AIG SYSTEMS
MRIR : Material Receiving Inspection Report 11 : Work Method Statement by Erection Company
2
3
CLOSING OF FQP - FINAL CHECK OF DOCUMENTATION & RELEASE FOR COMPLETENESS AT CONSTRUCTION SITE
Org. Erection Contractor Site Management (1) Siemens Site Management (2) Notified Body (NoBo) (3) Owner / Client (4)
Name
Date
Sign.
Unrestricted
TYPICAL FIELD QUALITY PLAN - FIELD ASSEMBLY - SCR / AIG SYSTEMS
INSPECTION
No. DESCRIPTION REFERENCE DOCUMENTS IR REMARK
1 Sign Date 2 Sign Date 3 Sign Date SSE Sign Date 5 Sign Date
1. DOCUMENTS
Material Receiving Reports for material required in place (including
1.01 Release Note / MRIR H R - R 1 / 10
assembly materials)
Material stored / preserved as per storage and preservation Storage and handling instructions
1.02 H Ri - Ri 10
instructions 60011-730-05-001
General FQP PP & NPP
1.03 Reviewed Procedures H R - R 8
60011-730-12-001
General FQP PP & NPP
1.04 Reviewed Qualifications / Certification H R - R 6
60011-730-12-001
1.05 Method Statement Outlet and Transition Duct Erection Manual / HSE Manual H R - R 11 Release for start erection
3. SCR SKID
NPP bolt torque proc.
3.01 Skid position and alignment H W - W 10
60011-730-01-008 / EN 1090-2 par.8
3.02 Perform grouting of skid Grouting of skid H Ri - Ri 10 Assure "standing water" inside skid is prevented
3.03 Pre-inspection SCR skid Drawing H W - Ri 3 / 9 Inspection report with(out) outstanding points
4. SCR PIPING
See FQP "Piping"
4.01 SCR piping H Ri - Ri 10
60011-730-12-008
4.02 Pre-inspection SCR piping Drawing H W - Ri 3 / 9 Inspection report with(out) outstanding points
Unrestricted
TYPICAL FIELD QUALITY PLAN - FIELD ASSEMBLY - SCR / AIG SYSTEMS
INSPECTION
No. DESCRIPTION REFERENCE DOCUMENTS IR REMARK
1 Sign Date 2 Sign Date 3 Sign Date 4 Sign Date 5 Sign Date
5.04 Pre-inspection SCR catalyst frame Drawing H W - Ri 3 / 9 Inspection report with(out) outstanding points
6,01 Final inspection for Mechanical completion Drawing H H - W 3 / 9 Inspection report with(out) outstanding points
6,02 Review Manufacturing ( Erection ) Data Records for Safety Valves Erection documentation H H - W 3 / 9 Inspection report with(out) outstanding points