GB1036 803243482 01 00 01
GB1036 803243482 01 00 01
GB1036 803243482 01 00 01
Contractor
Subcontractor Stamp
Project PKZ/PC
KKS / Reg.
UNID 803243482 DCC &MDC080 Content code 11H No. 203842
Wijnands Revision
Updated with Client mark-ups
Digitally signed by Wijnands Han
Description
Check 2 - - Title
van
Check 1 2019-Nov-21 PPAA Paassen
van Paassen Peter
cn=van Paassen Peter, o=Siemens,
email=peter.van_paassen@siemens.com
Peter
- A4
Document No. TC ID. Revision
GB1036-H-&MDC080-203842 1/3
ECCN N AL N US-content No
These items are controlled by the U.S. Government (when labeled with “ECCN” unequal “N”) and authorized for export only to the country of ultimate destination for use by the ultimate consignee or
end-user(s) herein identified. They may not be resold, transferred, or otherwise disposed of, to any other country or to any person other than the authorized ultimate consignee or end-user(s), either in
their original form or after being incorporated into other items, without first obtaining approval from the U.S. Government or as otherwise authorized by U.S. law and regulations. Items labeled with "AL”
unequal "N” are subject to European / national export authorization. Items without label, with label "AL:N" / "ECCN:N" or label "AL:9X9999" / "ECCN: 9X9999" may require authorization from responsible
authorities depending on the final end-use, or the destination.
TYPICAL FIELD QUALITY PLAN - FIELD ASSEMBLY - EXPANSION BELLOWS
MRIR : Material Receiving Inspection Report 11 : Work Method Statement by Erection Company
CLOSING OF FQP - FINAL CHECK OF DOCUMENTATION & RELEASE FOR COMPLETENESS AT CONSTRUCTION SITE
Org. Erection Contractor Site Management (1) Siemens Site Management (2) Notified Body (NoBo) (3) Owner / Client (4)
Name
Date
Sign.
Unrestricted
TYPICAL FIELD QUALITY PLAN - FIELD ASSEMBLY - EXPANSION BELLOWS
INSPECTION
No. DESCRIPTION REFERENCE DOCUMENTS IR REMARK
1 Sign Date 2 Sign Date 3 Sign Date SSE Sign Date 5 Sign Date
1. DOCUMENTS
Material Receiving Reports for material required in place (including
1.01 Release Note / MRIR H R - R 1 / 10
assembly materials)
Material stored / preserved as per storage and preservation Storage and handling instructions
1.02 H Ri - Ri 10
instructions 60011-730-05-001
General FQP PP & NPP
1.03 Reviewed Procedures H H - Ri 8
60011-730-12-001
General FQP PP & NPP
1.04 Reviewed Qualifications / Certification H H - Ri 6
60011-730-12-001
1.05 Method Statement Expansion Joints Erection Manual / Supplier documents H H - Ri 11 Release for start erection
2.05 Final inspection for Mechanical completion Drawing / Supplier installation procedure H H - W 3 / 9 Inspection report with(out) outstanding points
3.05 Final inspection for Mechanical completion Drawing / Supplier installation procedure H H - W 3 / 9 Inspection report with(out) outstanding points
NOTE 1 : It's a strong recommendation to have a Supplier representative supervise the installation
NOTE 3 : Insufficient insulation can cause burning of the bellows when in operation.