Copies of these two manuals can be obtained through the intra net. Offices
without access to the intranet may contact the MIS Library to obtain a softcopy.
This Order shall take effect immediately and shall supersede Department
Order No. 25, series of 2001.
OGELIO L. SINGSON
Secretary
IIII IIIII1
WIN1 L04120
Department of Public Works and Highways
December 2010
PREFIX
I. Introduction
This section contains the steps on how the Implementing Office will verify the
Consultant’s billing for advance payment. It also includes the procedures in the
preparation of forms to be used.
Advance Payments may be in lump sum or two equal payments depending on what
the Contract between the Department and the Consultant allows. The contract
provision on advance payment must be checked to see to it that the total claim for
each currency does not exceed the amount stated in the contract and the amount
guaranteed on the Surety Bond.
The table below summarizes the steps and actions that need to be done by the
Implementing Office.
STEP ACTION
1 Check the submitted billing with supporting documents for
completeness. The billing for advance payment should have the
following supporting documents arranged as follows:
For the First Release of Payment, these are the needed documents:
1. Letter-Request of Consultant
2. Advance Payment Invoice
3. Advance Payment Security in the form of Bank Guarantee
4. Certified True Copy of Approved Contract
5. Certificate of Availability of Funds
6. Certified True Copy of Resolution of Award
7. Certified True Copy of the Notice to Proceed
For the Final/Lump-sum Release of Payment, the above mentioned
documents are also needed plus the Certification of Mobilization of
Consultant’s Personnel
2 Verify the documents listed below for accuracy. The process of
verification is listed on the next section.
3 If the supporting documents are incomplete and/or the documents
listed above are inaccurate, the billing must be returned to the
concerned Consultant for correction.
STEP ACTION
4 If the supporting documents are complete and accurate, the
Implementing Office must now prepare the required forms. The
procedure for preparation is listed on the Section III. – Preparation of
Forms
5 The Implementing Office must also provide Certified True Copy of the
following documents:
• SAC Certification on the Advance Payment Security in the
form of Bank Guarantee
• Certification on the Validity and Authenticity of the Advance
Payment Security
• Transmittal of contract documents to COA
6 The billing documents must have appropriate approvals before
submitting them to Accounting for processing of payment.
Note:
This section provides the descriptions of the forms that needs to be verified by the
Implementing Office before the preparation of other documents.
• Checking of Entries
• Sample Format
The sample formats of the Letter Request of the Consultant are given on
the next page.
Reference: Technical Consulting Services for the Development and Implementation of the
3 Institutional Capacity Building (ICB) Project for the Department of Public Works
and Highways (DPWH)
Sir:
In accordance with the conditions of the Contract, we have complied with all your guidelines and
requirements, that is; i) the Form of Agreement was executed by and between both parties, ii) the
4 __________________________ in a form and from a bank acceptable to the client in amounts
equal to the Advance Payment was submitted to the Client.
Accordingly, may we request your good office to release the first 50% of the advance payment in
Local Currency – Philippine Peso immediately, as our Notice to Proceed was issued on April 7,
5 1997. 6
8 Attached is an invoice in the amount of ______________________________________________
_______________________________________________ (P_______________). 7
Robert Doe
10 ICB Project Manager
BPR Consultants, Inc.
Reference: Technical Consulting Services for the Development and Implementation of the
3 Institutional Capacity Building (ICB) Project for the Department of Public Works
and Highways (DPWH)
Sir:
In accordance with the conditions of the Contract, we have complied with all your guidelines and
requirements, that is; i) the Form of Agreement was executed by and between both parties, ii) the
4 __________________________ in a form and from a bank acceptable to the client in amounts
equal to the Advance Payment was submitted to the Client.
Accordingly, may we request your good office to release the final 50% of the advance payment in
Local Currency – Philippine Peso as we have substantially mobilized our staff in connection with
5 the implementation of the above-mentioned project. 6
8 Attached is an invoice in the amount of ______________________________________________
_______________________________________________ (P_______________). 7
Please make Peso payments to:
BPR Consultants, Inc.
Account Number: 999-088906-040
9 Singapore & Bangkok Bank
SBB Tower, 8000 Ayala Avenue
Makati, Metro Manila, Philippines
Robert Doe
ICB Project Manager
10 BPR Consultants, Inc.
Reference: Technical Consulting Services for the Development and Implementation of the
3 Institutional Capacity Building (ICB) Project for the Department of Public Works
and Highways (DPWH)
Sir:
In accordance with the conditions of the Contract, we have complied with all your guidelines and
requirements, that is; i) the Form of Agreement was executed by and between both parties, ii) the
4 __________________________ in a form and from a bank acceptable to the client in amounts
equal to the Advance Payment was submitted to the Client.
Accordingly, may we request your good office to release 100% of the advance payment in Local
Currency – Philippine Peso as we have substantially mobilized our staff in connection with the
5 implementation of the above-mentioned project. 6
8 Attached is an invoice in the amount of ______________________________________________
_______________________________________________ (P_______________). 7
Please make Peso payments to:
BPR Consultants, Inc.
Account Number: 999-088906-040
Singapore & Bangkok Bank
9 SBB Tower, 8000 Ayala Avenue
Makati, Metro Manila, Philippines
Robert Doe
ICB Project Manager
10 BPR Consultants, Inc.
• Checking of Entries
• Sample Format
The Implementing Office must see to it that the following documents are submitted
with the claim for advanced payment: (Listed next to the document is the section
where an example of this document can be found).
Please see the sample forms of the above-mentioned documents on the following
pages.
ROGELIO L. SINGSON
Secretary
ROGELIO L. SINGSON
Secretary
• Definition /Purpose
The Summary of charges will be prepared by the Implementing Office once all
the submitted documents for the billing has been verified and checked for
accuracy and authenticity. This will be signed by the Head of the Implementing
Office (i.e. Project Director) and will be approved by the Secretary.
• Procedure
• Format
• Definition/Purpose
The Executive Summary is a brief summary of the status of the Project. The
details of this form are gathered from the Contract Agreement and Letter of
Credit/Bank Guarantee/Surety Bond. The Implementing Office prepares this
document to be signed by the Assistant Secretary or the Undersecretary with
supervision of the Project.
• Procedure
• Format
1
Reference No. _________________
Date: ________________________ 2
3
EXECUTIVE SUMMARY
4
For
For :: Secretary
SecretaryRogelio
GregorioL.R.
Singson
Vigilar
Thru : U/Sec. Angel Malapitan
1. Subject: Invoice for 50% of the Advance Payment for mobilization under the Local Currency
Component (Peso) of the Contract for Consultant’s Services of BPR Consultants, Inc. for the 5
development and implementation of the Institutional Capacity Building (ICB) Project under the
IBRD-assisted Highway Management Project (Loan No. PH 4030) in the amount of SIX
MILLION FIVE HUNDRED SEVENTY SIX THUSAND SIX HUNDRED FIFTY NINE &
00/100 PESOS (P 6,576,659.00).
6
2. Action Recommended: For Approval
7
3. Implementing Office: DPWH - Planning
4. Reviewing Office: CFMS 8
5. Contractor: BPR Consultants, Inc.
6. Contract Amount: P 65,766,590.00 (Local Currency Component) 9
7. Contract Time: 24 Months 10
8. Effectivity of Contract: 14 April 1997.
9. Contract Expiry Date: 13 April 1999. 11
10. Contractor’s Surety for Advance Payment: 12
10.1 Kind: Surety Bond No. G (16) 2544
10.2 Amount: P 13,153,318.00 13
10.3 Issued by: Eastern Assurance and Surety Corporation
10.4 Expiration: Until advance payment is fully paid 14
10.5 Validated by: Chairman, Special Action Committee 15
11. Remarks: First 50% Advance Payment Claim (Peso Component)
JOSE MAKALINTAL 16
Designation
• Definition/Purpose
• Procedure
The Implementing Office must fill up the upper portion of the Disbursement
Voucher with the following information:
• Format
• Definition /Purpose
• Procedure
The Certification per Department Order No. 55 Series of 1988 must contain
the following information.
• Format
The Certification per Department Order No. 55, Series of 1988 must follow
the format given on the next page.
• Definition/Purpose
• Procedures
• Format
The Special Account Withdrawal Application must follow the format on the
next page.
• Definition/Purpose
This document is the prescribed form by the Local Bank where the Special
Account is deposited. This form will be prepared in conjunction with the
Special Account Withdrawal Application in order to transfer the amount of
payment to the Consultant’s Bank Account. This form should only be used if
the advance payment is being paid out of the Special Account.
• Procedures
• Format
The FCDU Fund Transfer Slip must follow the format on the next page.
DATE:
Telegraphic Transfer Demand Draft ; Manager’s Check In Foreign Currency US$ JPY Others UK Pounds Sterling
PAYEE/ADDRESS/TEL.NO. SOURCE OF FUND TRANSFER
BPR Consultants, Inc. - ICB Cash
20 Ayala Ave. cor. Paseo de Roxas On-Us LBP Check No. ________________________________________
4 Salcedo Village, Makati City Debit my/our Savings/Current Account No. ________________________
Philippines
AMOUNT IN WORDS/FIGURES: FOR CHARGES:
V A L I D A T I O N
Payee’s Account No. 999-088906-040 8
Paying Bank’s Name & Address:
In case payment is debited to a joint account, I/We also hereby declare under penalties of perjury
T E L L E R’ S
that my/or co-depositor/s is/are still living.
DPWH-PMO-IBRD NO.
signature appears below to receive the Demand Draft/Traveler’s Check applied for. 11
Third Currency US Dollar Phil. Peso
Face Amount
Exchange Rate PEDRO MAUNAWAIN ANGEL MALAPITAN
US$ Amount UNDERSECRETARY UNDERSECRETARY
Add: Bank Commission SIGNATURE OF REPRESENTATIVE SIGNATURE OVER PRINTED NAME OF APPLICANT
Corr. Bank Charges DD/TC/OTT NO. PREPARED BY: CHECKED BY:
Cable
Others SIGNATURE VERIFIED BY: BALANCE VERIFIED BY: APPROVED BY:
Total
COPY 1 – ACCTG. DIV. 2-CASHIERING DIV. 3-CLIENT (All savings withdrawals must be
accompanied by a passbook. This shall serve as your receipt when machine validated)
• Definition/Purpose
This document is the prescribed form by the Lending Institution if the payment
to the Consultant from the Loan Proceeds will be withdrawn directly from the
Lending Institution (instead of the Special Account). The example provided is
for World Bank Direct Application for Withdrawal.
• Procedures
This application once signed must be sent to the Lending Institution with the
certified true copy of the Summary of Charges, the Executive Summary, the
Invoice Summary and the Invoice.
• Format
The Lending Institution Direct Application for Withdrawal must follow the
format specified by the Lending Institution. The sample format shown on the
next page follows the World Bank Format.
We apply for this withdrawal from the account opened under the Loan or Development Credit Agreement, and hereby
certify and agree as follows:
A. The undersigned has not previously withdrawn from the Account to meet these expenditures. The undersigned
has not and does not intend to obtain funds for this purpose out of the proceeds of any other loan, credit, or grant;
B. The goods and services covered by this application have been or are being purchased in accordance with the terms
of the Agreement;
C. The expenditures have been made or are being made only for goods or services from eligible sources;
D. For those items where reimbursement is being claimed on the basis of a Statement of Expenditures (SOE), all
documentation authenticating these expenditures will be made available for review by auditors and World Bank
missions upon request. These documents have been retained at the location shown on the individual SOE sheet;
E. In the event that all or part of the funds withdrawn from the Account pursuant to this application are returned to
the World Bank, the undersigned hereby authorizes the World Bank to apply the current value of such funds as a
credit to the Account; or if the amount is small, apply such funds to the borrower’s next payment due for interest,
commitment charges, service charges or principal.
6. PROCUREMENT DETAILS
a) CONTRACT OR PURCHASE ORDER
7 NUMBER AND DATE
Consultancy Services - ICB 9. PAYEE NAME AND ADDRESS
b) DATE OF PROCUREMENT NO-
OBJECTION NOTICE (complete for BPR Consultants, Inc.
contracts above prior review limit) 20 Ayala Avenue cor. Paseo de Roxsa 8
Salcedo Village
c)BRIEF DESCRIPTION OF GOODS, Makati City
9 WORKS OR SERVICES
Direct Payment
d) CURRENCY AND TOTAL AMOUNT OF
10 CONTRACT
PhP 65,766,590.00
e) TOTAL AMOUNT OF INVOICES
COVERED BY THIS APPLICATION (net
5 of retention and other deductions)
PhP 6,576,659.00
7. WITHDRAWAL DETAILS 10. If Payee’s Bank is not located in the Country whose
a) CATEGORY OR SUB-PROJECTS NO. currency is claimed, enter the name and address of
their bank’s correspondent in the country whose
currency is to be paid.
b) PERCENTAGE OF EXPENDITURES TO
BE FINANCED: BY THE WORLD BANK
11 SWIFT CODE:
CS = 100% 11. SPECIAL PAYMENT INSTRUCTIONS AND
INVOICE REFERENCES 12
BY COFINANCIER (if any)
The Implementing Office must attach Fund Utilization Report. This ensures that
Implementing Office is monitoring the project’s funding. CFMS will attach
Obligation Request applicable to the billing.
Please see the sample forms of the above-mentioned documents on the following
pages.
IV.2 SAC Certification on the Advance Payment Security in the Form of Bank
Guarantee
CERTIFICATION
This is to certify that Bank Guarantee No. 120/12144097 issued by Midland Bank
plc, 27-32 Poultry, London ECP2P 2BX, Member Hongkong and Shanghai Banking
Corporation, Ltd., on January 15, 1997, in the amount not exceeding ONE MILLION
THREE HUNDRED FIFTY THOUSAND US DOLLARS (USD 1,300,000), for the
account of BPR Consultants, Inc., to guarantee Advance Payment for Consultancy
Services for the development and implementation of the Institutional Capacity Building
(ICB) Project, has been verified valid and authentic, as evidenced by the letter of
Authentication issued by Ms. Andrea Fernandez, Asst. Vice President, Corporate
Relationship Management, Hongkong Bank, dated May 30, 1997, copy attached.
(SGD)
Cesar D.Mejia
Director III, Legal Service
Chairman, Special Action Committee(SAC)
I. Introduction
This section contains the steps on how the Implementing Office will verify the
consultant billing for progress billing. It also includes the procedures in the
preparation of forms to be used.
The table below summarizes the steps and actions that need to be done by the
Implementing Office
STEP ACTION
1 Check the submitted billing with supporting documents for
completeness. The billing for progress billing should have the
following supporting documents arranged as follows:
• Checking Entries
• Sample Format
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Personnel-Project Staff
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
9 Date: February 2, 2000 From: January 1, 2000
10
A
TOTAL 138/21 /////////// P151,571.50 15
11
CERTIFIED CORRECT:
16
DATE:
17 ROBERT DOE
ICB Project Manager 20
18 DATE:
JUAN MATAPAT
19 PMO PROJECT DIRECTOR
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas Personnel- 5
2
Salcedo Village, Makati City Local Consultants
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
9 Date: February 2, 2000 From: January 1, 2000
18 DATE:
JUAN MATAPAT
19 PMO PROJECT DIRECTOR
Location 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Manila X X X X X X X X X X
Location 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Manila X X X X X X X X X X X
Codes: Totals: 21
X = Work Day _______________
H = Holiday
x = Half Day
Blank = Non-work Day
Gregorio Roda
Gregorio Roda
ICB Office Manager
Noted by:
eÉuxÜà WÉx
Robert Doe
ICB Project Manager
• Checking Entries
• Sample Format
Form L-03
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
5
20 Ayala Avenue cor. Paseo de Roxas Per Diem
2
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
9 Date: February 2, 2000 From: January 1, 2000
10
11
TOTAL 172 /////////// P 574,480.00 D
14
CERTIFIED CORRECT:
15 DATE:
ROBERT DOE
16 ICB Project Manager 19
17 DATE:
JUAN MATAPAT
18 PMO PROJECT DIRECTOR
Location 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Manila T X X X X X X X X X X X X
U. S.
Location 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Manila X X X X X X X X X X X X X X X X
eÉuxÜà WÉx
Robert Doe
ICB Project Manager
Juan Matapat
Juan Matapat
Project Director – PMO-ICB
• Checking Entries
Notes:
• Sample Format
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Local Travel & Vehicle
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
01/04/00 ABC Rental Car Car rental, Isuzu(Jan 1-31, 2000) P 43,000.00
01/04/00 ABC Rental Car Car rental, Toyota(Jan 1-31, 2000) P 40,000.00 12
01/04/00 Peso Rent-a-Car Car rental, Terrano(Jan 1-31,2000) P 40,000.00
10
TOTALS P 180,000.00 13 E
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Utilities &
Salcedo Village, Makati City Maintenance
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS P 45,963.33 13 F
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
Form L-06
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Communication Cost
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS 16,703.98 13 G
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
Form L-07
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Office Suplies
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS P 128,087.75 13 H
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
Form L-08
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Communication
Salcedo Village, Makati City Network
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS P 394,596.48 13 I
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
Form L-09
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Contingency
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS P 145,926.00 13 J
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
• Checking Entries
• Sample Format
• Checking Entries
• Sample Format
• Checking Entries
• Sample Format
• Checking Entries
• Sample Format
Form L-13
4 February 2, 2000
Robert Doe
ICB Project Manager
14 BPR Consultants, Inc.
The following section provides description of the forms and the procedures
that must be followed by the Implementing Office for completing them.
• Definition /Purpose
• Procedure
• Format
The Summary of Charges must follow the format given on the next
page.
• Definition/Purpose
• Procedures
• Format
The Executive Summary must follow the format given on the next
page.
• Definition/Purpose
• Procedures
• Format
Form L-16
•
• Definition /Purpose
• Procedure
• Format
The Certification per Department Order No. 55, Series of 1988 must
follow the format given on the next page.
• Definition/Purpose
• Procedures
• Format
Form L-18
Date: _____________________
2
CARP BANK OF THE PHILIPPINES
3 Intramuros Branch
Intramuros, Manila 4
Attention : Mr. ROMEO MANLANGIT - Manager
5
Subject : Account No. 0014-0024-80
SA Highway Management Project
Loan 3430-PH
6
Sir:
Pursuant to the provision of DBM/DOF/COA Joint Circular No. 2-97 dated 21 March 7
1997, please debit the amount of PHP ONE MILLION SIX HUNDRED TWENTY SIX
THOUSAND TWO HUNDRED FORTY NINE & 18/100 ONLY ( P 1,626,249.18) from
Account No. 0014-0024-80 under the working fund for credit to the account of (Manager’s Q
Check).
9
8
PAYEE : BPR Consultants, Inc
ACCOUNT NO. : 999-088906-040 10
BANK : Singapore & Bangkok Bank 11
ADDRESS : SBB Tower, 8000 Ayala Avenue, Makati City
REMARKS :Payment of reimbursable expenses (per diem, local travel and vehicle rental,
communication costs, utilities and maintenance, project personnel, office
supplies, communication networks and others) during the period January 1-
31, 2000 in connection with the Consultancy Services Contract for the
12
Institutional Capacity Building (ICB) Project, under the Highway
Management Project (HMP)
Advise of Allotment No. : ___________________________________
Dated : ___________________________________
Obligation No. : ___________________________________ 13
N C A No. : ___________________________________
JUAN MATAPAT
PMO-ICB, Project Director 14
16 APPROVED:
• Definition/Purpose
This document is the prescribed form by the Local Bank where the
Special Account is deposited. This form will be prepared in conjunction
with the Special Account Withdrawal Application in order to transfer the
amount of payment to the Consultant’s Bank Account. This form should
only be used if the payment is being paid out of the Special Account.
• Procedures
• Format
The FCDU Fund Transfer Slip must follow the format on the next page.
Form L-19
DATE:
Telegraphic Transfer Demand Draft ; Manager’s Check In Foreign Currency US$ JPY Others UK Pounds Sterling
PAYEE/ADDRESS/TEL.NO. SOURCE OF FUND TRANSFER
BPR Consultants, Inc. - ICB Cash
20 Ayala Ave. cor. Paseo de Roxas On-Us LBP Check No. ________________________________________
3 Salcedo Village, Makati City Debit my/our Savings/Current Account No. ________________________
Philippines
AMOUNT IN WORDS/FIGURES: FOR CHARGES:
Cash
ONE MILLION SIX HUNDRED TWENTY SIX 5
THOUSAND TWO HUNDRED FORTY NINE & 18/100
4 PESOS ONLY.
On-Us LBP Check No. ________________________________________
V A L I D A T I O N
Payee’s Account No. 999-088906-040
8 I/We hereby agree to be bound by the terms and conditions on the reverse side hereof.
9
In case payment is debited to a joint account, I/We also hereby declare under penalties of perjury
T E L L E R’ S
that my/or co-depositor/s is/are still living.
• Definition/Purpose
• Procedures
This application once signed must be sent to the Lending Institution with
the certified true copy of the Summary of Charges, the Executive
Summary, the Invoice Summary and the Invoice.
• Format
We apply for this withdrawal from the account opened under the Loan or Development Credit Agreement, and hereby
certify and agree as follows:
A. The undersigned has not previously withdrawn from the Account to meet these expenditures. The undersigned
has not and does not intend to obtain funds for this purpose out of the proceeds of any other loan, credit, or grant;
B. The goods and services covered by this application have been or are being purchased in accordance with the terms
of the Agreement;
C. The expenditures have been made or are being made only for goods or services from eligible sources;
D. For those items where reimbursement is being claimed on the basis of a Statement of Expenditures (SOE), all
documentation authenticating these expenditures will be made available for review by auditors and World Bank
missions upon request. These documents have been retained at the location shown on the individual SOE sheet;
E. In the event that all or part of the funds withdrawn from the Account pursuant to this application are returned to
the World Bank, the undersigned hereby authorizes the World Bank to apply the current value of such funds as a
credit to the Account; or if the amount is small, apply such funds to the borrower’s next payment due for interest,
commitment charges, service charges or principal.
6. PROCUREMENT DETAILS
a) CONTRACT OR PURCHASE ORDER
6 NUMBER AND DATE
Consultancy Services - ICB 9. PAYEE NAME AND ADDRESS
b) DATE OF PROCUREMENT NO-
OBJECTION NOTICE (complete for
contracts above prior review limit)
BPR Consultants, Inc.
20 Ayala Avenue cor. Paseo de Roxsa
7
Salcedo Village
c)BRIEF DESCRIPTION OF GOODS, Makati City
8 WORKS OR SERVICES
Direct Payment
d) CURRENCY AND TOTAL AMOUNT OF
9 CONTRACT
PhP 84,892,756.00
e) TOTAL AMOUNT OF INVOICES
Q COVERED BY THIS APPLICATION (net
of retention and other deductions)
PhP 1,626,249.18
7. WITHDRAWAL DETAILS 10. If Payee’s Bank is not located in the Country whose
a) CATEGORY OR SUB-PROJECTS NO. currency is claimed, enter the name and address of
their bank’s correspondent in the country whose
currency is to be paid.
b) PERCENTAGE OF EXPENDITURES TO
BE FINANCED: BY THE WORLD BANK
10 SWIFT CODE:
CS = 100% 11. SPECIAL PAYMENT INSTRUCTIONS AND
INVOICE REFERENCES
11
BY COFINANCIER (if any)
The Implementing Office must attach Fund Utilization Report. This ensures
that Implementing Office is monitoring the project’s funding. CFMS will
attach Obligation Request applicable to the billing.
I. Introduction
This section contains the steps on how the Implementing Office will verify the
consultant billing for progress billing. It also includes the procedures in the
preparation of forms to be used.
The table below summarizes the steps and actions that need to be done by the
Implementing Office.
STEP ACTION
1 Check the submitted billing with supporting documents for
completeness. The billing for progress billing should have the
following supporting documents arranged as follows:
• Checking Entries
• Sample Format
Form F-01
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Personnel
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-USD-0010 Purpose: US Dollars
8
9 Date: February 2, 2000 From: January 1, 2000
A
10 14
11
B
15
CERTIFIED CORRECT
16
DATE:
17 ROBERT DOE
ICB Project Manager 20
18 DATE:
JUAN MATAPAT
19 PMO PROJECT DIRECTOR
Location 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Manila T X X X X X X X X X X X X
U. S.
Location 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Manila X X X X X X X X X X X X X X X X
Codes: Totals: 29
X = Work Day _______________
T = Travel Day
Blank = Non-work Day
eÉuxÜà WÉx
Robert Doe
ICB Project Manager
Juan Matapat
Juan Matapat
Project Director – PMO-ICB
• Checking Entries
• Sample Format
Form F-02
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 International Travel
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-USD-0010 Purpose: US Dollars
8
Date: February 2, 2000 From: January 1, 2000
C
12
TOTALS $ 2,928.45
CERTIFIED CORRECT
13
DATE:
14 ROBERT DOE
ICB Project Manager 17
15 DATE:
JUAN MATAPAT
16 PMO PROJECT DIRECTOR
• Attachments
January 3, 2000
CERTIFICATION
This is to certify that the airline ticket invoiced to DPWH for Arnold Gore was used
specifically for the Institutional Capacity Building (ICB) Project and was used for no
other purpose. In addition, I certify that the amount invoiced to DPWH for the said ticket
is the actual amount paid.
Arnold Gore
Arnold Gore
ICB Project Manager
BPR Consultants, Inc.
Attachment #2: Certified true copy of the ticket and Original Invoice
– this attachment serves as the official receipt/invoice of the cost of
international travel for reimbursement. The attachments will depend on
the payment information shown in the plane ticket as enumerated below:
Case 1 – the plane ticket will be accepted as the receipt and invoice if
it shows the actual amount paid (e.g. if it was purchased using a credit
card for payment as shown in the Attachment #2-Sample A in the next
page).
Case 2 - if the plane ticket does not show the actual payment made for its
purchase as shown in Attachment #2-Sample B.1, a copy of the Original
Invoice must be added to the attachment (see Attachment #2–Sample
B.2).
• Checking Entries
• Sample Format
Form F-03
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Equipments &
Salcedo Village, Makati City Softwares
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-USD-0010 Purpose: US Dollars
8
Date: February 2, 2000 From: January 1, 2000
10
11
12
TOTALS $ 90,000.00 13 D
CERTIFIED CORRECT
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
Form F-04
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Contingency
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-USD-0010 Purpose: US Dollars
8
Date: February 2, 2000 From: January 1, 2000
11
12
TOTALS $ 5,193.00
13 E
CERTIFIED CORRECT
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
• Checking Entries
• Sample Format
• Checking Entries
• Sample Format
• Checking Entries
• Sample Format
• Checking Entries
• Sample Format
Form F-08
4 February 2, 2000
Robert Doe
ICB Project Manager
14 BPR Consultants, Inc.
The following section provides description of the forms and the procedures
that must be followed by the Implementing Office for completing them.
• Definition/Purpose
• Procedure
• Format
Form F-09
1
INSTITUTIONAL CAPACITY BUILDING (ICB) PROJECT
SUMMARY OF CHARGES
2
3
PERIOD COVERED *** JANUARY 1-31, 2000 ***
JOSE MAGPAYO
PMO Project Manager II 11
JUAN MATAPAT
12 PMO Project Director
• Definition/Purpose
• Procedures
• Format
The Executive Summary must follow the format given in the next
page.
EXECUTIVE SUMMARY
For :: Secretary Gregorio
Rogelio L. 3
For Secretary R.Singson
Vigilar
Thru : U/Sec. Angel Malapitan
1. Subject: Invoice (in US Dollars) for Consultancy charges during the period January 1 - 4
31, 2000 in connection with BPR Consultants, Inc. Consultants’ Services Contract for the
development of the Institutional Capacity Building (ICB) Project.
5
2. Action Recommended : For Approval
3. Implementing Office : DPWH - Planning 6
4. Reviewing Office : CFMS
5. Contractor : BPR Consultants, Inc. 7
6. Contract Amount
(Including SA #2 and 8
SA #3) : P 84,892,756 (Local Currency Component)
$ 5,467,476 (US $ Currency Component) 9
£ 878,301 (UK Pounds Currency Component)
10
7. Contract Time : 38 Months and 17 days.
8. Effectivity of Contract : 14 April 1997. 11
9. Contract Expiry Date : 30 June 2000.
10. Remarks : 12
This Invoice is for Consultancy charges (US Dollar Component) during the
period January 1-31, 2000 13
JOSE MAKALINTAL 15
Designation
• Definition/Purpose
• Procedures
• Format
• Definition/Purpose
• Procedures
• Format
Date: _____________________
Sir:
7
Pursuant to the provision of DBM/DOF/COA Joint Circular No. 2-97 dated 21 March 1997,
please debit the amount of US$ ONE HUNDRED EIGHTY TWO THOUSAND SIX HUNDRED
TEN & 68/100 ONLY ( $ 182,610.68) from Account No. 0025-0024-79 under the working fund
for credit to the account of (Telegraphic Payment).
8
H
PAYEE : BPR Consultants, Inc 9
ACCOUNT NO. : 12345678 SORT CODE: 24 12 27 SWIFT CODE: BANAMGMAA8JA
BANK : Banco Americana 10
ADDRESS : 100 Wilshire Blvd., Los Angeles, CA 90002
11
REMARKS : Payment for Consultancy charges (US Dollar Component) during the period
January 1-31, 2000 in connection with the Consultancy Services Contract for the 12
Institutional Capacity Building (ICB) Project, under the Highway Management
Project (HMP)
14
JUAN MATAPAT
PMO-ICB, Project Director
15 APPROVED:
• Definition/Purpose
This document is the prescribed form by the Local Bank where the
Special Account is deposited. This form will be prepared in conjunction
with the Special Account Withdrawal Application in order to transfer the
amount of payment to the Consultant’s Bank Account. This form should
only be used if the payment is being paid out of the Special Account.
• Procedures
• Format
The FCDU Fund Transfer Slip must follow the format on the next page.
DATE:
; Telegraphic Transfer Demand Draft Traveler’s Check In Foreign Currency ; US$ JPY Others UK Pounds Sterling
PAYEE/ADDRESS/TEL.NO. SOURCE OF FUND TRANSFER
BPR Consultants, Inc. - ICB Cash
4 20 Ayala Ave. cor. Paseo de Roxas On-Us LBP Check No. ________________________________________
Salcedo Village, Makati City Debit my/our Savings/Current Account No. ________________________
5 Philippines 6
AMOUNT IN WORDS/FIGURES: FOR CHARGES:
HUNDRED TEN & 68/100 US DOLLARS ONLY On-Us LBP Check No. ________________________________________
(US $ 182,610.68) ;
H Debit my/our Savings/Current Account No. 0014-0024-80
7
FOR TELEGRAPHIC TRANSFER SPECIAL INSTRUCTION:
V A L I D A T I O N
Payee’s Account No. 12345678 Sort Code: 24 12 27
Swift Code: BANAMGMAA8JA 8
Paying Bank’s Name & Address:
9 BANCO AMERICANA
100 Wilshire Blvd. 10
Los Angeles, CA 90002
I/We hereby agree to be bound by the terms and conditions on the reverse side hereof.
11
T E L L E R’ S
In case payment is debited to a joint account, I/We also hereby declare under penalties of perjury
that my/or co-depositor/s is/are still living.
• Definition/Purpose
• Procedures
This application once signed must be sent to the Lending Institution with
the certified true copy of the Summary of Charges, the Executive
Summary, the Invoice Summary and the Invoice.
• Format
Form F-13
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
IBRD – Project Management Office 1
We apply for this withdrawal from the account opened under the Loan or Development Credit Agreement, and hereby
certify and agree as follows:
A. The undersigned has not previously withdrawn from the Account to meet these expenditures. The undersigned
has not and does not intend to obtain funds for this purpose out of the proceeds of any other loan, credit, or grant;
B. The goods and services covered by this application have been or are being purchased in accordance with the terms
of the Agreement;
C. The expenditures have been made or are being made only for goods or services from eligible sources;
D. For those items where reimbursement is being claimed on the basis of a Statement of Expenditures (SOE), all
documentation authenticating these expenditures will be made available for review by auditors and World Bank
missions upon request. These documents have been retained at the location shown on the individual SOE sheet;
E. In the event that all or part of the funds withdrawn from the Account pursuant to this application are returned to
the World Bank, the undersigned hereby authorizes the World Bank to apply the current value of such funds as a
credit to the Account; or if the amount is small, apply such funds to the borrower’s next payment due for interest,
commitment charges, service charges or principal.
15. _________________________________________
13. ________________________________________
Print Name(s) and Title(s) of Authorized Representative(s)
Date
I. Introduction
This section contains the steps on how the Implementing Office will verify the
additional requirement on the consultant billing for final payment. The
applicable documents and attachments described in the Progress Billing
described in Part B and Part C for local and foreign currency respectively, are
also required in the preparation of the Final Payment. It also includes the
procedures in the preparation of additional forms to be used.
The table below summarizes the steps and actions that need to be done by the
Implementing Office
STEP ACTION
1 Check the submitted billing with supporting documents for
completeness. The claim for final payment should have the following
supporting documents discussed for Progress Billing in Part B and Part
C for local and foreign currency with the addition of BIR Clearance
(Form 2555) and the Inventory and Costing of Turned-over equipment
bought out of project funds and Invoice Receipt for said assets.
2 Verify the documents and attachments for accuracy and authenticity.
The process of verification for documents and attachments shall be the
same with the ones discussed under Part B and Part C. The process of
verification for BIR Clearance (Form 2555) and the Inventory and
Costing of Turned-over equipment bought out of project funds and the
Invoice Receipts is discussed in next page.
3 If the supporting documents/attachments are incomplete and/or the
documents listed above are inaccurate, the billing must be returned to
the concerned Consultant for completion or correction.
4 If the supporting documents are complete and accurate, the
Implementing Office must now prepare the required forms. The
procedure for preparation is listed on the Section III. – Preparation of
Forms of Part B and Part C
5 The billing documents must have appropriate approvals before
submitting them to Accounting for processing of payment.
The steps and processes in verifying the applicable documents in Part B and
Part C submitted by the Consultant will be the same as described in the said
sections.
The Consultant must accomplish and attach the BIR Clearance Form 2555 as
part of the Final Payment requirement. The attachment must be original and
duly received by BIR.
• Checking Entries
• Checking Entries
• Sample Format
• Attachment
The sample format below will be the basis by the Supply and Property
Management Division (SPMD) together with the Inventory in the
issuance of the Property Clearance. If the equipments will be turned-over
to the SPMD at the completion of the project, there is no need for this
document.
The following section provides description of the forms and the procedures
that must be followed by the Implementing Office for completing them.
• Definition /Purpose
The Implementing Office will prepare the same forms described in
Part B and Part C. However, these are not the only forms to be
prepared to process the claims for final payment. These additional
forms are discussed in the next Section.
• Procedure
The information requirement and procedures in the preparation of the
applicable forms in Part B and Part C and its attachments will be the
same as discussed in those Sections.
• Definition /Purpose
This Clearance is a pre-requisite by the Supply and Properties
Management Division (SPMD) for the issuance of the SPMD
Clearance Certificate on Property Accountability. It is issued by the
Head of the Implementing Office (at least a Project Director)
certifying that as per their records the Consultant has no property,
supply and financial accountabilities.
• Procedure
• Format
October 5, 2000
2
CLEARANCE CERTIFICATE
TO W HOM IT M AY CONCERN:
3
This is to certify that as per records of this Office, BPR CO NSULTANTS,
INC., Consultant of the Institutional Capacity Building (ICB) Project under the
IBRD-assisted Highway M anagem ent Project (Loan No. 3430-PH), has no property,
supply and financial accountabilities to our Office in connection with the said project.
4 This Certification is being issued as per request of the ICB in connection with
their claim for Final Paym ent on the above-m entioned project.
5
Juan M atapat
JUAN M ATAPAT
PM O Project Director
• Definition /Purpose
• Procedure
• Format
October 5, 2000
MEMORANDUM
Attached for your reference are the Clearance Certificate from this Office and
copies of the Invoice Receipts of Properties turned-over in connection with the
implementation of the said project.
Juan Matapat
JUAN MATAPAT
PMO Project Director
• Definition /Purpose
• Procedure
• Format
CERTIFICATE OF COMPLETION
2
TO WHOM IT MAY CONCERN:
3
This is to certify that, per records of this Office, and in accordance with the
Contract and the corresponding Terms of Reference for the Institutional Capacity
4
Building (ICB) Project under the IBRD-assisted Highway Management Project
(Loan No. 3430-PH), BPR CONSULTANTS, INC. has satisfactorily completed and
turned-over to the DPWH all contract requirements and deliverables.
Juan Matapat
JUAN MATAPAT
PMO Project Director
• Definition /Purpose
• Procedure
• Format
CERTIFICATION
2
This is to certify further that all requirements and supporting papers pursuant to
Department Order No. 55, series of 1988 have been complied with, reviewed and found 5
to be in order.
Juan Matapat
JUAN MATAPAT
PMO Project Director
IV. Attachment
The Implementing Office must see to it that the SPMD Clearance Certificate
on Property Accountability is provided for inclusion on the Final Payment
claim to be sent to the CFMS.
• Definition /Purpose
• Procedure
• Format
December 2010
PREFIX
The Consultant should exert the utmost care in the preparation of its billing
and ensure that documents and amounts are prepared accurately. Inaccurate
billings will result in delays of payments.
All Claims, documents, forms, etc. must use the name of the principal
Consultant as listed in the Contract.
III. Attachments........................................................................... 14
III.1. Advance Payment Security in the form of Bank Guarantee ............. 15
III.2. Copy of Approved Contract .............................................................. 17
III.3. Certification of Availability of Funds ............................................... 19
III.4. Copy of the Resolution of Award ...................................................... 20
III.5. Copy of Notice to Proceed................................................................. 23
I. Introduction
DPWH shall upon a written request of the Consultant, make an advance payment to
the Consultant in an amount specified in the contract. This can be made in lump-
sum or in two releases as allowed in the contract between the Department and the
Consultant. If the contract allows Advance Payment in multiple currencies, each
currency must have a separate request and set of documents.
This section is divided into two parts: First Release of Advance Payment and the
Final/Lump-sum Release of Advance Payment. If the Consultant wants to claim for
an advance payment immediately upon award of the Contract, 50% of the Advance
Payment can be requested if the Contract allows it using the documents and
procedures for the First Release of Advance Payment. However, if the Consultant
wants to claim 100% of the Advance Payment in lump-sum, follow the documents
and procedures stated in the Final/Lump-sum Release of Advance Payment section.
The Consultant’s billing for advance payment must contain the listed supporting
documents and arranged as follows:
(Listed next to the document is the Section that pertains to preparation of that
document.)
The Consultant upon award of the Contract can request payment equivalent
to 50% of the allowable Advance Payment.
The Security required for the Advance Payment must be equal to or greater than the
amount being requested. The Security instrument includes Bank Guarantee, Letter
of Credit or Surety Bond as specified in the Contract.
This section will be used if the Consultant wants to claim 100% of the
Advance Payment in lump-sum or to claim the remaining 50% of the
Advance Payment (if the Consultant opted for a 50% release of the Advance
Payment upon award of the Contract) upon Certification that the
Consultant’s personnel and staff has substantially mobilized.
The required documents for this section are the same as mentioned in the
First Release of Advance Payment except the Consultant must add the
Certificate of Mobilization of Consultant’s Personnel (A.II.2)
Note:
• Definition/Purpose
The Consultant provides this document for the billing of advance payment.
This letter shall state that the Consultant has complied with all conditions of the
contract and requesting the Department for the release of advance/mobilization
payments. This letter/request is prepared on the Consultant’s letterhead. There
are three formats of the Letter - Request of Consultant (Release of Advance
Payment) exhibited on Section A.II.1 showing each type of request. The same
procedure is followed in preparing each format.
• Procedure
The following are the steps for preparing the Letter-Request of Consultant:
• Format
Letter - Request of Consultant must follow the format given on the next page.
Reference: Technical Consulting Services for the Development and Implementation of the
3 Institutional Capacity Building (ICB) Project for the Department of Public Works
and Highways (DPWH)
Sir:
In accordance with the conditions of the Contract, we have complied with all your guidelines and
requirements, that is; i) the Form of Agreement was executed by and between both parties, ii) the
4 __________________________ in a form and from a bank acceptable to the client in amounts
equal to the Advance Payment was submitted to the Client.
Accordingly, may we request your good office to release the first 50% of the advance payment in
Local Currency – Philippine Peso immediately, as our Notice to Proceed was issued on April 7,
5 1997. 6
8 Attached is an invoice in the amount of ______________________________________________
_______________________________________________ (P_______________). 7
Robert Doe
10 ICB Project Manager
BPR Consultants, Inc.
Reference: Technical Consulting Services for the Development and Implementation of the
3 Institutional Capacity Building (ICB) Project for the Department of Public Works
and Highways (DPWH)
Sir:
In accordance with the conditions of the Contract, we have complied with all your guidelines and
requirements, that is; i) the Form of Agreement was executed by and between both parties, ii) the
4 __________________________ in a form and from a bank acceptable to the client in amounts
equal to the Advance Payment was submitted to the Client.
Accordingly, may we request your good office to release the final 50% of the advance payment in
Local Currency – Philippine Peso as we have substantially mobilized our staff in connection with
5 the implementation of the above-mentioned project. 6
8 Attached is an invoice in the amount of ______________________________________________
_______________________________________________ (P_______________). 7
Please make Peso payments to:
BPR Consultants, Inc.
Account Number: 999-088906-040
9 Singapore & Bangkok Bank
SBB Tower, 8000 Ayala Avenue
Makati, Metro Manila, Philippines
Robert Doe
ICB Project Manager
10 BPR Consultants, Inc.
Reference: Technical Consulting Services for the Development and Implementation of the
3 Institutional Capacity Building (ICB) Project for the Department of Public Works
and Highways (DPWH)
Sir:
In accordance with the conditions of the Contract, we have complied with all your guidelines and
requirements, that is; i) the Form of Agreement was executed by and between both parties, ii) the
4 __________________________ in a form and from a bank acceptable to the client in amounts
equal to the Advance Payment was submitted to the Client.
Accordingly, may we request your good office to release 100% of the advance payment in Local
Currency – Philippine Peso as we have substantially mobilized our staff in connection with the
5 implementation of the above-mentioned project. 6
8 Attached is an invoice in the amount of ______________________________________________
_______________________________________________ (P_______________). 7
Please make Peso payments to:
BPR Consultants, Inc.
Account Number: 999-088906-040
Singapore & Bangkok Bank
9 SBB Tower, 8000 Ayala Avenue
Makati, Metro Manila, Philippines
Robert Doe
ICB Project Manager
10 BPR Consultants, Inc.
• Definition/Purpose
The Consultant needs to secure this document (with the appropriate approvals)
from the Implementing Office in original form prior to the submission of
billing.
• Procedure
• Format
2 Date
CERTIFICATION
This is to certify that Consultant Name has substantially mobilized their personnel
in connection with its contract for the Project Name in Project Location.
5
4
This certification is being issued to support the claim for the Final Release of the
Advance Payment pursuant to Section _________ of the Contract for the above
project.
6
7
Name and Signature
Project Manager
1 Implementing Office
8
Name and Signature
Project Director
1 Implementing Office
• Definition/Purpose
The Consultant provides this document as an Invoice for the billing of advance
payment. This must be prepared by the Consultant and must be countersigned
by the Project Director of the project.
• Procedure
The following are the steps for preparing the Advance Payment Invoice:
• Format
Advance Payment Invoice must follow the format given on the next page.
III. Attachments
The Consultant must secure and submit the following documents with the claim for
advanced payment: (Listed next to the document is the section where an example of
this document can be found).
Please see the sample forms of the above-mentioned documents on the following
pages.
ROGELIO L. SINGSON
Secretary
ROGELIO L. SINGSON
Secretary
I. Introduction
The following are the documents and the information that must be provided by
the Consultant to support his monthly progress payment claims.
The following section provides description of the forms that must be used and
the procedures for completing them.
• Definition/Purpose
• Procedure
• Format
Form L-01
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Personnel-Project Staff
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
9 Date: February 2, 2000 From: January 1, 2000
10
A
TOTAL 138/21 /////////// P151,571.50 15
11
CERTIFIED CORRECT:
16
DATE:
17 ROBERT DOE
ICB Project Manager 20
18 DATE:
JUAN MATAPAT
19 PMO PROJECT DIRECTOR
Form L-02
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas Personnel- 5
2
Salcedo Village, Makati City Local Consultants
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
9 Date: February 2, 2000 From: January 1, 2000
18 DATE:
JUAN MATAPAT
19 PMO PROJECT DIRECTOR
• Attachment
The original Monthly Time Sheet for each personnel must be attached as
supporting document for the Supporting Summary Personnel – Local
Consultant/Project Staff. A sample of the Monthly Time Sheet is shown
below.
Location 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Manila X X X X X X X X X X
Location 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Manila X X X X X X X X X X X
Codes: Totals: 21
X = Work Day _______________
H = Holiday
x = Half Day
Blank = Non-work Day
Gregorio Roda
Gregorio Roda
ICB Office Manager
Noted by:
eÉuxÜà WÉx
Robert Doe
ICB Project Manager
• Definition/Purpose
The Consultant prepares this document as a supporting document for the Per
Diem of Foreign Personnel. The amount would be based on the Daily Rate
specified in the contract and the number of days a particular personnel
stayed in the Philippines. The Per Diem daily rate is usually higher on the
first 60-days stay of the Consultant in the Philippines.
• Procedures
• Format
Supporting Summary Per Diem must follow the format given on the next
page.
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
5
2 20 Ayala Avenue cor. Paseo de Roxas Per Diem
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
9 Date: February 2, 2000 From: January 1, 2000
10
11
TOTAL 172 /////////// P 258,000.00 D
14
CERTIFIED CORRECT:
15 DATE:
ROBERT DOE
16 ICB Project Manager 19
17 DATE:
JUAN MATAPAT
18 PMO PROJECT DIRECTOR
• Attachment
The original Monthly Time Sheet for each foreign personnel must be
attached as supporting document for the Supporting Summary Per Diem. A
sample of the Monthly Time Sheet is shown below.
Location 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Manila T X X X X X X X X X X X X
U. S.
Location 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Manila X X X X X X X X X X X X X X X X
eÉuxÜà WÉx
Robert Doe
ICB Project Manager
Juan Matapat
Juan Matapat
Project Director – PMO-ICB
• Definition/Purpose
• Procedures
The preparation of these supporting summaries will use only one format but
should be done separately for each category as it appear in the Contract or
any Contract Amendment/Supplemental Agreement and must contain the
following information.
Notes:
• Format
Supporting Summaries for Other Recoverable Cost must follow the format
given below and on the next pages. For presentation purposes several Forms
are shown to illustrate different categories as presented in the Invoice
Summary and the Budgeted Balance Summary.
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Local Travel & Vehicle
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
01/04/00 ABC Rental Car Car rental, Isuzu(Jan 1-31, 2000) P 43,000.00
01/04/00 ABC Rental Car Car rental, Toyota(Jan 1-31, 2000) P 40,000.00 12
01/04/00 Peso Rent-a-Car Car rental, Terrano(Jan 1-31,2000) P 40,000.00
10
TOTALS P 180,000.00 13 E
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Utilities &
Salcedo Village, Makati City Maintenance
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS P 45,963.33 13 F
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Communication Cost
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS 16,703.98 13 G
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Office Suplies
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS P 128,087.75 13 H
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
Form L-08
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Communication
Salcedo Village, Makati City Network
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS P 711,076.48 13 I
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
Form L-09
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Contingency
Salcedo Village, Makati City
Tel Nos.: +63 2 988 -0100 Fax Nos.: +63 2 988 -0105 6
3 E -mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-PHP-0012 Purpose: Philippine Peso
8
Date: February 2, 2000 From: January 1, 2000
11
Date Vendor Description Amount
10
TOTALS P 145,926.00 13 J
CERTIFIED CORRECT:
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
• Attachments
The original invoice, delivery receipt and official receipt must be attached
on the supporting summaries for Recoverable Cost and in the order it is
presented. Other original copy of documents that will show proof of
purchase or payments made (e.g. plane tickets, acknowledgement receipts)
or certified true copy of duly notarized Contract of Lease can also be
attached as supporting documents. For contingency, a certified true copy of
the DPWH authorization/approval to use the amount allocated must also be
attached in the supporting summary.
• Definition/Purpose
• Procedures
• Format
• Definition/Purpose
The Consultant provides this document as an Invoice for the progress billing
payments. This must be prepared by the Consultant and must be
countersigned by the Project Director of the project.
• Procedures
The following are the steps for preparing the Progress Billing Invoice and
must contain the following information:
• Format
Progress Billing Invoice must follow the format given on the next page.
• Definition/Purpose
The Consultant prepares this document to monitor the financial status and
the utilization of the Consultant’s time of the project.
• Procedure
• Format
Budgeted Balance Summary Sheet must follow the format provided below.
• Definition/Purpose
The Consultant provides this document as the main cover letter for their
progress billing claims. This letter/request is prepared on the Contractor’s
letterhead.
• Procedures
• Format
The Letter Request must follow the format given on the next page.
Form L-13
4 February 2, 2000
Robert Doe
ICB Project Manager
14 BPR Consultants, Inc.
I. Introduction
The following are the documents and the information that must be provided
by the Consultant to support his monthly progress payment claims.
The following section provides description of the forms that must be used and
the procedures for completing them.
• Definition/Purpose
• Procedure
• Format
Form F-01
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Personnel
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3
E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-USD-0010 Purpose: US Dollars
8
9 Date: February 2, 2000 From: January 1, 2000
11
B
15
CERTIFIED CORRECT
16
DATE:
17 ROBERT DOE
ICB Project Manager 20
18 DATE:
JUAN MATAPAT
19 PMO PROJECT DIRECTOR
• Attachment
The original Monthly Time Sheet for each personnel must be attached as
supporting document for the Supporting Summary Personnel. A sample
of the Monthly Time Sheet is shown below.
Location 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Manila T X X X X X X X X X X X X
U. S.
Location 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Manila X X X X X X X X X X X X X X X X
Codes: Totals: 29
X = Work Day _______________
T = Travel Day
Blank = Non-work Day
eÉuxÜà WÉx
Robert Doe
ICB Project Manager
Juan Matapat
Juan Matapat
Project Director – PMO-ICB
• Definition/Purpose
• Procedures
• Format
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 International Travel
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-USD-0010 Purpose: US Dollars
8
Date: February 2, 2000 From: January 1, 2000
C
12
TOTALS $ 2,928.45
CERTIFIED CORRECT
13
DATE:
14 ROBERT DOE
ICB Project Manager 17
15 DATE:
JUAN MATAPAT
16 PMO PROJECT DIRECTOR
• Attachments
January 3, 2000
CERTIFICATION
This is to certify that the airline ticket invoiced to DPWH for Arnold Gore was used
specifically for the Institutional Capacity Building (ICB) Project and was used for no
other purpose. In addition, I certify that the amount invoiced to DPWH for the said ticket
is the actual amount paid.
Arnold Gore
Arnold Gore
ICB Project Manager
BPR Consultants, Inc.
Attachment #2: Certified true copy of the ticket and Original Invoice
– this attachment serves as the official receipt/invoice of the cost of
international travel for reimbursement. The attachments will depend on
the payment information shown in the plane ticket as enumerated below:
Case 1 – the plane ticket will be accepted as the receipt and invoice if it
shows the actual amount paid (e.g. if it was purchased using a credit card
for payment as shown in the Attachment #2-Sample A in the next page).
Case 2 - if the plane ticket does not show the actual payment made for its
purchase as shown in Attachment #2-Sample B.1, a copy of the Original
Invoice must be added to the attachment (see Attachment #2–Sample
B.2).
• Definition/Purpose
• Procedures
The preparation of these supporting summaries will use only one format
but should be done separately for each category as it appear in the
Contract or any Contract Amendment/Supplemental Agreement and must
contain the following information.
• Format
Form F-03
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Equipments &
Salcedo Village, Makati City Softwares
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-USD-0010 Purpose: US Dollars
8
Date: February 2, 2000 From: January 1, 2000
10
11
12
TOTALS $ 90,000.00 13 D
CERTIFIED CORRECT
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
Form F-04
1
Institutional Capacity Building (ICB) Project
Department of Public Works and Highways
BPR Consultants, Inc.
Supporting Summary
20 Ayala Avenue cor. Paseo de Roxas 5
2 Contingency
Salcedo Village, Makati City
Tel Nos.: +63 2 988-0100 Fax Nos.: +63 2 988-0105 6
3 E-mail: bpr.consultant.com.ph
7
4
Invoice Number ICB-USD-0010 Purpose: US Dollars
8
Date: February 2, 2000 From: January 1, 2000
11
12
TOTALS $ 5,193.00
13 E
CERTIFIED CORRECT
14
DATE:
15 ROBERT DOE
ICB Project Manager 18
16 DATE:
JUAN MATAPAT
17 PMO PROJECT DIRECTOR
• Attachments
• Definition/Purpose
• Procedures
• Format
The Invoice Summary must follow the format given on the next page.
• Definition/Purpose
• Procedures
The following are the steps for preparing the Progress Billing Invoice and
must contain the following information:
• Format
Progress Billing Invoice must follow the format given on the next page.
• Definition/Purpose
The Consultant prepares this document to monitor the financial status and
the utilization of the Consultant’s time of the project.
• Procedure
• Format
• Definition/Purpose
The Consultant provides this document as the main cover letter for their
progress billing claims. This letter/request is prepared on the Contractor’s
letterhead.
• Procedures
• Format
The Letter Request must follow the format given on the next page.
Form F-08
4 February 2, 2000
Robert Doe
ICB Project Manager
14 BPR Consultants, Inc.
I. Introduction
This section will discuss the documents needed to prepare the Final Payment
claim of the Consultant.
The preparation of the BIR Clearance (Form 2555) and Inventory and Costing
of Turned-over equipment bought out of project funds and Invoice Receipt for
said assets are discussed in the next page. If there is no equipment bought out
of project funds a Certification to that effect by the responsible official of the
project (at least by a Project Director) will have to be submitted with the
claim.
The following section provides description of the forms that must be used and
the procedures for completing them.
• Definition/Purpose
The Consultant will use the applicable forms and attachments discussed
in Part B and Part C.
• Procedure
The Consultant must accomplish and attach the BIR Clearance Form 2555 as
part of the Final Payment requirement. The attachment must be original and
duly received by BIR.
• Checking Entries
• Format
• Definition/Purpose
• Procedure
• Format
• Attachment