April Line Walk Report
April Line Walk Report
April Line Walk Report
SL. OBSERVATION RESPONSIBILITY ACTION TAKEN EVIDENCE (BEFORE) EVIDENCE (AFTER) STATUS
NO
1 TBT meeting found getting Good observation NA NA NA NA
conducted at working site.
2 Housekeeping of the Good observation NA NA NA NA
working areas found in
good condition.
3 Non-standard tools are Site in Instructed to all in Rectified
using at site. charge/Site charges for removing
supervisor non-standard tools
and provide standard
tools.
4 Co2 Fire extinguisher was Safety officer Instructed in charge Rectified
hanging unsafely at of mechanical (AKC)
proportioning down area. to provide safe
hanging hook of fire
extinguisher to avoid
any untoward
incident during any
emergency.
Prepared by Checked by Approved By
(Mr Kunal Prasad) (Mr Sanjay Kumar Pati) (Mr Manoj Kumar
Singh)
(CSO, Sinter Plant) (Head Safety, Sinter plant) (HEAD, Sinter plant)
AKC PROJECTS AND CONTRACTS PVT.LTD.
LINE WALK REPORT
DOC.NO-AKCP/JSR/LW/01 REV.NO./DATE: 01/01.04.2022 EFF DT- 06.09.21
5 Belt Guards not available Site in charge Discussed with site in Under
of all Tubler belts at (mechanical) charge of Progress
proportioning down area. mechanical, he
assured it will be
completed before
next Line walk.
SUGGESTION:
Energy drink to be started as heat situation is getting increasing day by day.
DESIGNATION: PROPRITOR