Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

RECORD OF REVISIONS

Date Revision Details Revision


Number

07.07.2012 Issued for Implementation 0

13.07.2013 Sec‐2, Sec‐8.3.1 and Attachment‐5 added 1

17.08.2013 Sec‐2 and Attachment‐6 added 2

11.04.2014 Attachment‐5 and Attachment‐6 Revised 3

Page 2 of 22
Contents
1. Purpose........................................................................................................................ 1
2. Scope ........................................................................................................................... 1
3. Cost competitive engineering and design ................................................................... 1
4. Conflicts and Deviations .............................................................................................. 1
5. Definitions: .................................................................................................................. 2
6. Abbreviations: ............................................................................................................. 3
7. Codes and Standards: .................................................................................................. 4
8. Basic Methodology: ..................................................................................................... 6
9. Inspection and Testing: ............................................................................................. 14
10. Vendor Data Requirement: ....................................................................................... 16
11. Attachments: ............................................................................................................. 17
Attachment‐ 1: MANUFACTURING PROCEDURE SPECIFICATION RECORD. ....................... 17
Attachment‐2 : BEND INSPECTION REPORT........................................................................ 18
Attachment‐4 : Bend Qualification Record ......................................................................... 23
Attachment‐5 : Scope of Induction Bending for J3 Program ............................................. 24
Attachment‐6 : Minimum required thicknes (MM) after Final Bending ............................ 27

Page 3 of 22
1. Purpose
This specification has been prepared for freezing the requirements and giving
recommendations for Induction Bends for piping applications in Petrochemical &
Petroleum refining and transportation operations.
2. Scope
The specification defines the minimum technical requirements for induction bending
of seamless pipes for sizes > 3” NPS and straight weld EFW Pipes for sizes > 18” up
to 42” NPS along with the minimum supporting documentation. The following
materials are covered;-

• Carbon Steel Low Temperature Carbon Steel.


• Stainless Steel.
• Low & Intermediate Alloy Steel
• Nickel-Chromium-Alloys and Nickel-Iron-Chromium Alloys.

However scope for J3 program shall be as per Attachment‐5 and attachment‐6.


Attachment‐5 details out the list of Pipe classes along with permissible size
for Induction bending and Attachment‐6 provides the minimum wall thickness
required at intrados, extrados and centerline after the bend is in its
finished form.

3. Cost competitive engineering and design


The engineering team shall maintain the cost focus throughout all phases of the
project. This should be done without compromising any specification and design
requirements. From the perspective of induction bending of pipes, efforts shall be
made to ensure the maximum usage of bends over bought out elbows along with
the optimization of available facilities and resources.

4. Conflicts and Deviations


Process and utility piping shall be fabricated in accordance with codes, drawings,
and other requirements specified herein. Where conflict exists, the order of priority
of documents shall follow in the following sequence:
(i) Local Regulatory and Statutory requirement
(ii) This Specification
(iii) Codes and Standard

Page 4 of 22
5. Definitions:
5.1. Piping Material Classes
The Piping Material Classes specify the material requirements for pipe, fittings
flanges, etc., and design details for branch connections, vents, drains, and pressure
‐ temperature connections by Service Class. Where special or non standard material
for a particular class is required, it will be noted on the drawings.
5.2. Supplementary Table of Wall Thickness and Branch Reinforcement
The Supplementary Table of Wall Thickness will specify by individual pipeline
number the requirements of wall thickness subject to calculation as specified in the
Piping Material Classes.
5.3. Piping Stock Code Index
The Piping Stock Code Index identifies and describes all piping material item codes
in documents related to piping material.
5.4. Some frequently used catchphrases used in the specification:

Centre Line Radius. The arc of the bend, usually taken at the centre line or
(CLR) neutral axis of the bend. Usually referred to in
multiples of the OD.
Intrados The inside arc of the bend
Manufacturer The Construction Group at the jobsite carrying out the
induction bending of the pipe(s).
Manufacturing A document that specifies the properties of the
Procedure starting pipe, bending procedure, post bending heat
Specification (MPS) treatment, results of the destructive and non‐
destructive testing on the on the qualification bend.
Neutral Axis The centerline axis of the pipe along the arc of the
bend.
Ovality The distortion of the cross section of pipe from its
normal (round) shape
Qualification Bend A bend or bend segment produced to be destructively
tested to prove bending process variables.
Positive Material To provide chemical analysis and material properties
Identification to verify material certified components.
P numbers As designated for particular materials in Appendix A of
ASME B31.1 and ASME B31.3

Page 5 of 22
Post Bending Heat Heat treatment that takes place after bending to
Treatment (PBHT) modify the properties on the bend material.
Spool Spool refers to a prefabricated section of a piping
system that includes the pipe, fittings and flanges that
are pre‐assembled in the fabrication facility and
then transported to the field.
Starting Pipe The pipe or rolled and welded cylinder that forms the
raw material for;
Carbon Steel (CS) ‐ with carbon less than 0.3%
Low Temperature A carbon steel pipe with Charpy V Notch properties at
Carbon Steel (LTCS) ‐ temperatures of ‐46o C to 0o C.
Low and Intermediate Steel strengthened with elements such as Chrome,
Alloy steel (LAS) ‐ Molybdenum etc.
Stainless Steel (SS) ‐ A Corrosion Resistant Alloy (CRA) containing not less
than 12% Chromium. This specification covers only the
austenitic grades.
Nickel Alloy (NA) ‐ CRA’s containing nickel quantities greater than 25%
and alloyed with chromium, molybdenum etc.
(includes UNS N08020)
Tangent Points The two points at which the bend starts and finishes
Tangent The straight material at each end of the bend
Thinning The amount of reduction from the specified wall
thickness to the amount of wall thickness remaining in
the extrados of the bend after forming.
Transition zone The area at the tangent points of the bend that covers
the change from the unheated portion of the bend to
the heated portion.

6. Abbreviations:
CLR Centre Line Radius
CRA Corrosion Resistant Alloy
CS Carbon Steel
CVD Crest to Valley Depth
CVN Charpy V Notch
DEC Detail Engineering Contractor
DPE Dye Penetrant Examination
EN European Norm
Extrados The outside arc of the bend.

Page 6 of 22
FL Fusion Line
HAZ Heat Affected Zone
HRB Rockwell Hardness (B Scale ‐ 1/16" Ball Penetrator, 100kgf
Load)
ID Inside Diameter
LTCS Low Temperature Carbon Steel
MDR Material Discrepancy Report
MPS Manufacturing Procedure Specification
MPE Magnetic Particle Examination
MTC Material Test Certificate
NDT Non‐Destructive Testing. (NDT methods to detect surface and
internal flaws.)
NPS Nominal Pipe Size (inches).
OD Outside Diameter
PMI Positive Material Identification.
PPM Parts per Million
PBHT Post Bending Heat Treatment.
RT Radiographic Examination
UT Ultrasonic Examination.

7. Codes and Standards:


7.1. Codes
7.1.1. Local Codes or Regulations
Where local regulations, ordinances, statutes or codes take precedence over ASME
codes, such regulations, ordinances, statutes or codes shall govern.
7.1.2. Refinery Code Piping
Except where specified otherwise, the Process Piping Code ASME B31.3‐2008 (latest
edition) governs fabrication of all piping.
7.1.3. Boiler Code Piping
The Power piping code ASME B31.1‐ 2010 (latest edition) and the Indian Boiler
Regulations 1950 governs fabrication of steam and boiler feed water piping within
the battery limits of the boiler as defined in the code. For steam and condensate
lines outside the battery limit of the boiler the applicable codes are IBR and ASME
B31.3‐2010.

Page 7 of 22
7.2. Associated References
This specification covers piping governed by:
ASME B31.3 “Process Piping.”
ASME B31.1 “Power Piping.”
“Pipeline Transportation Systems for Liquid Hydrocarbons and
ASME B31.4
Other Liquids.”
IBR “Indian Boiler Regulations”
“Materials Resistant to Stress Corrosion Cracking in Corrosive
NACE MR0103
Refinery Environments.”
ASTM E3 “Standard Guide for Preparation of Metallographic Specimens.”
“Standard Specification for Seamless Carbon Steel Pipe for High
ASTM A106
Temperature Service.”
“Standard Specification for Seamless and Welded Steel Pipe for
ASTM A333
Low Temperature Service.”
“Standard Specification for Electric‐Fusion – Welded Steel Pipe for
ASTM A671
Atmospheric and Lower Temperatures.”

ASTM E112 “Standard Test Methods for Determining Average Grain Size.”

“Standard Practices for Detecting Susceptibility to Intergranular


ASTM A262
Attack in Austenitic Stainless Steels.”
ASTM E 340 “Macro etching Metals and Alloys”
“Detecting Susceptibility to Intergranular Corrosion in Wrought,
ASTM G28
Nickel Rich, Chromium‐ Bearing Alloys”
“Pipe Fittings of Wrought Carbon Steel and Alloy Steel for
ASTM A 234
Moderate and High Temperature Service.”
“Seamless, Welded and Heavily Cold Worked Austenitic Stainless
ASTM A312
Steel Pipes”
ASTM A 403 “Wrought Austenitic Stainless Steel Fittings.”
ASTM B366 “Factory Made Wrought Nickel and Nickel Alloy Fittings.”
BS EN 10204 “Metallic products‐ Types of Inspection Documents.”

Page 8 of 22
8. Basic Methodology:
The major activities pertaining to the induction bending of Pipes for the internal
projects in the Petroleum and Petrochemical operations of Reliance shall be in the
following sequence:
I. Initiation
II. Material Selection, Storage, Handling and Control
III. Manufacturing Process
IV. Inspection

8.1 Initiation
Before commencing fabrication of the induction bends, the Manufacturer shall
prepare a quality plan, inspection and test plan (refer attachment ‐3) and an MPS,
all of which shall be subject to the review and approval of the Construction
Manager. These documents should include materials, heat treatment procedures,
dimensional control and non‐destructive testing procedure specifications, together
with supporting qualification records, piping material specifications for which
induction bending has been approved by the concerned DEC for the particular
project and an illustration of their proposed area of application. Inspection and Test
Plans, documentation processes shall also be included.
8.2 Material Selection, Storage, Handling and Control
8.2.1 Product Documentation prior to manufacture
It is the intent of this clause that each bend made can be identified in service and
traced to the starter pipe and individual bending process.
When required the Manufacturer shall submit certification in the form of a
Manufacturing Record Book that shall contain sufficient certification to trace
materials and bending processes to each individual bend. Records shall include;
• Identification number, common to both bend or spool and records.
• Starter pipe material test certificate to BS EN 10420 3.1. (Material
specification, grade, chemical composition, mechanical test results,
dimensions etc.)
• Bend radius.
• Bend Angle.
• Piping isometric, spool number and Bend number.
• Bending operation process and heat treatment variables (refer to items 1 to
6 in Table 1 below) and heat input data.

Page 9 of 22
• Date and time of bending operation.
• Records as required by Attachment‐1 and 2 of this specification.
8.2.2 Starting Pipe
Starting pipe shall conform to the applicable ASTM standard and Reliance standard
specification “10080‐1‐SS‐PP‐004”and shall be free of surface defects,
contamination, cracks, buckles and waves that would affect the successful bending
operation.
• Stainless steel and nickel alloy pipe shall be in the Solution Annealed
condition.
• Mill varnish shall be removed from the area to be bent.
• Water used for quenching stainless steel shall have a maximum of 30 ppm
of chlorides.
• CS and LTCS steel pipe shall have restricted chemistry as shown;
Carbon Equivalent, (product analysis) shall be based on;
% Mn %Cr + %Mo + %V % Ni + %Cu
CE = %C + + + ≤ 0.35%
6 5 15
With C max = 0.20% and Mn max =0.7%

8.2.3 Storage, Handling and Control


Material Receipt, Handling, Storage, Control and Release shall be in accordance with
the requirements of this specification. Storage of austenitic stainless steels and non‐
ferrous materials shall be kept fully separated from ferritic materials to avoid
contamination.
It shall be the responsibility of the Manufacturer to inspect all materials upon
receipt, and to ensure that the correct grade of material has been supplied, and that
the identification, dimensions, material quality, and end preparation are in
accordance with the applicable standards and specifications. Procedures for the
transfer of material identification marks shall be agreed with the Construction
Manager prior to commencement of bending.
Any material which is not readily identifiable shall be removed from the site and
quarantined until its material grade and source can be confirmed. All materials shall
be stored above ground and kept free from all contaminants.
All IBR piping materials shall be verified along with the applicable IBR forms for
compliance.
When any piping material is substituted for NACE, the same shall be verified along
with the MTC for confirming the carbon content, carbon equivalent and hardness

Page 10 of 22
as specified in relevant SER. If any discrepancy observed at any of the stage, MDR
shall be raised by the concerned Reliance Engineer.
8.3 Manufacturing Process
8.3.1 Initial Checkpoints for identifying the bendable pipes
• Wall Thickness‐. It is the responsibility of the Manufacturer to select the
starting pipe with a wall thickness that does not result in the thickness of the
completed bend being less that specified by the DEC against the respective
PMS’s for the project.
• Prior to bending, the thickness of each starter pipe shall be measured and
the thickest side shall form the extrados.
• Tangents‐ A Tangent length of 463 mm over and above 1.5D radius is
required as a holding length for Induction bending.
• Pipe Matcode & Heat Number ‐ To ensure easy identification, the bendable
pipes that are selected shall have the Reliance Pipe Matcode & heat number
punched/marked (in accordance to the purchase order & MTC against which
the pipe had been procured) on outer surface of all carbon steel and alloy
steel pipes issued from warehouse and Inner surface near the open end for
pipes going to sand blasting yard prior to bending. In case of low alloy steel
pipes, color band of the respective material shall be applied on the pipe as
per the applicable project specification / customer specification.

8.3.2 MPS Qualification Bend


Prior to the start of production bending, a qualification bend shall be made, tested
from each grade of bend of starting material based on the “P No” and “Group No.”
classification and where the process variables differ from previously qualified bends.
Production bending shall not commence until the qualified MPS is approved in
writing by the Project Construction Manager.

If, in the opinion of the Project Engineering Manager, previous manufacture of bends
are satisfactory and have been proved by operational experience, then an MPS may
be approved without additional testing.

The qualification bend, of sufficient arc length to allow the extraction of the
necessary test specimens, shall be manufactured in accordance with each preliminary
MPS.

The MPS to be used for production shall, for each of the essential variables in Table
1, specify
• The values recorded during the manufacturing of the test bend;

Page 11 of 22
• The permissible range during production bending.

The variation in essential variables shall not exceed the permissible limits
shown in Table 1.

To reduce the number of MPSs certain materials may qualify others such as

• ASTM A106 may qualify ASTM A53 material and vice versa.
• Each specification and type of austenitic stainless steel (P‐No 8) shall be
qualified individually with the exception of a higher carbon content shall be
able to qualify a lower carbon content, but not vice versa.
The qualification shall demonstrate the suitability of the bending process to provide
a product that meets the required dimensions and material properties. Records of
qualification tests shall be submitted for approval to the Construction Manager. A
sample form is shown in Attachment-I. A Separate detailed bend qualification record
shall be maintained as per Attachment – IV.

All bends, both qualification and production shall be completed in a continuous


heating cycle, with no starts or stops.
All operators of induction bending equipment shall have completed training
(including safety training) by the bending machine manufacturer and be in
possession of a certificate of competence issued by them.
During the manufacturing process the following requirements shall be maintained
for all bends.
• A continuous record of the forming conditions, in the form of a computer
print‐out or electronic copy shall be maintained for each bend.
• Seamless starting pipe is the preferred option but where bends are
manufactured from welded pipe, the bends shall have the longitudinal weld
seam positioned +/‐ 15 degrees from the neutral axis of bending.
• No girth weld shall be contained in the finished bend.
• The pipe shall be loaded into the machine so that the thickest quadrant will
lie on the extrados of the bend. If the pipe is of a welded construction, the
weld seam shall be located along the neutral axis; for compound bends the
weld seam shall be located between the planes of the bend towards the
intrados.
• Bending temperature shall be monitored from bend start to bend
completion by use of optical pyrometers.
• Pyrometers shall be focused ninety degrees from the top neutral axis with
one to the intrados and one to the extrados of the bend

Page 12 of 22
• Any interruption to the bending process shall result in the rejection of the
bend.
• Water quenching, where used, shall be continuous and the flow conditions
shall be the same as the qualification bend.
• No repair by welding is allowed on any part of the bend.
• Rework of any kind after bending or final heat treatment is not allowed.
• Induction bends intended for sour service shall comply with the
requirements of NACE MR‐01‐03.

8.3.3 Essential Variables


The MPS shall include, as a minimum, a report on all items that are the subject of
the essential variables shown in Table 1. The production bend(s) shall be produced
in accordance and within the tolerances shown in 9.2 to 9.5. If, during production
any one of the parameters shown in Table 1 is varied outside the tolerances given,
then the production bend shall be scrapped and/or that process re‐qualified.
Procedures that are intended to be used for remedial work to correct bend angles
shall be submitted to the Construction Manager for approval along with the
applicable MPS.
Table‐1
Material Type
Sl
Variable NAS,
no CS LTCS SS LAS
Ni‐Fe‐Cr.
+/‐ 65 (at
Bending intrados)
1 +/‐ 40 +/‐ 25 +/‐ 25 +/‐ 25
Temperature (o C) ±40 (at
extrados)
Cooling media No Change No Change No Change No Change No Change
2
type or no quench Allowed Allowed Allowed Allowed Allowed
Speed mm/min
3 Applicable Applicable Applicable Applicable Applicable
See Note 5

Addition or N/A N/A N/A N/A N/A


4
deletion of PBHT See Note 4 See Note 4 See Note 4 See Note 4 See Note 4
N/A N/A
5 PBHT ( o C) N/A ± 10 N/A
See Note 4 See Note 4
6 PBHT N/A N/A N/A Applicable N/A

Page 13 of 22
See Note 4 See Note 4
Change in NPS
7 One Size up or Applicable Applicable Applicable Applicable Applicable
Down See Note 6

Change in Wall ≤19= ±4.8 ≤19= ±4.8 ≤19= ±4.8 ≤19= ±4.8 ≤19= ±4.8
8 >19= ± 6 >19= ± 6 >19= ± 6 >19= ± 6 >19= ± 6
Thickness (mm)

Small radius Small radius Small radius Small radius Small radius
Change in Bend qualifies a qualifies a qualifies a qualifies a qualifies a
9
Radius (mm) larger larger larger larger larger
radius radius radius radius radius

Change in No Change No Change No Change No Change No Change


electrical Allowed Allowed Allowed Allowed Allowed
10
characteristics of
Inductor Ring
Macro/Micro
Specimen Required Required Required Required Required
11
(Qualification Note 1 Note 1 Note 1& 2 Note 1 Note 1 & 3.
bends only)
Note 1. A micro specimen shall be prepared to ASTM E3 at 250X to 400X from a
sample taken from the location shown in Figure 1 (and shall include the weld, where
present). Any indication of a damaged structure or lack of homogeneity shall be a
cause for rejection. Where welds are included a macro specimen (x30) shall be
taken as well as the micro specimen.
Note 2. Testing shall be carried out in accordance with ASTM A262. The micro shall
show the grain structure, form and size and reveal any intermetallic phases in
materials where these structures would cause a diminution in corrosion resistance.
Any indication of susceptibility to intergranular corrosion or other forms of
corrosion or damaged structure or lack of homogeneity shall be a cause for
rejection.
Note 3. Testing shall be carried out in accordance with ASTM G28 Method A, to
prove resistance to intergranular corrosion and the results compared with material
from the starting pipe prior to any bending process being commenced. Any
evidence of “ditching” around grain boundaries shall be cause for rejection. The
sample material shall be taken from the bend transition zone and shall include
welds where used as shown in Figure 1.

Page 14 of 22
Note 4. PBHT shall be carried out in accordance with the applicable code and to
achieve the required hardness value as specified by the particular piping class
specification. Special attention shall be given to class specifications in sour service.
Note 5. The speed of bending expressed a +/‐ % tolerance of the qualification bend
NPS + 42
shall not vary more than in production bending.
4.57
Note 6. For the purpose of Induction bending qualification, pipe sizes (NPS in
inches) shall be ‐ 4, 6, 8, 10, 12, 14, 16, 18, 20, 24, 30, 36, 42, and 48.
Note 7. A satisfactory MPS on a 42” pipe will qualify for a 36” and 48” providing all
other parameters are as Table 1.

Figure‐1

T = Transverse tensile test.


CVN = Charpy V Notch (3 test pieces)

Page 15 of 22
H = Hardness Test
M= Micro/Macro

8.3.4 Marking on the Bends for Identification


Low stress punches shall be used for marking the bend no. and the spool no. on the
bend immediately after dismantling the bend from the bending machine. In case
hard punches are used, the punching shall be done 150mm beyond the transition
zone as indicated in Figure‐1.
8.3.5 Post‐Bend Treatment & Testing
After induction bending , the bend shall be visually inspected & checked for
ovality, hardness and wall thickness at its bend portion and results shall be
recorded in the applicable project format. Post‐Bend Heat treatment shall be
carried out as required by Table 1 and Table 2.

Alloy steel pipe bends shall be stress relieved in furnace and hardness & MT shall be
carried on the bend after PBHT. Stainless steel and non‐ferrous material bends shall
be checked by PT at the entire extrados surface of the bend area to confirm the
freedom from any defects/flaws. Stainless Steel bends made from the un‐stabilized
grades i.e. those grades other than TP 321 and TP 347 and processed above the
solution annealing temperature, specified by Table 2 of ASTM A312 and if the micro
sample meets the requirements of Note 2 of Table 1 above, then PBHT is not
required. SS bends formed from TP321 and TP 347 shall be solution annealed after
bending. Material to P No’s 43 and 45 shall be treated the in the same way as SS
covered in clause 9.4.2 above except the annealing temperatures shall be as ASTM
B366 Table 3. If PBHT for any materials are proposed then these shall be submitted
to the Construction Manager for written approval, and shall contain details of
cleaning procedures, temperature range and time at temperature, type and
location of thermocouples.
TABLE 2
Material Post Bending Heat Treatment
P‐Number ASME B31.1 ASME B31.3
Table 132
P‐No 1 Table 331.1.1
Note 4 to Table1
applies. Note 4 to Table1 applies.

Page 16 of 22
Solution Heat Treat if Solution Heat Treat if
P‐No 8 hardness > 100 HRB hardness > 100 HRB after
after bending. bending.
P‐Nos 3,4,5,6 & Table 331.1.1 or Normalize
10A Table 132 & Temper
P‐Nos 43 N/A See Note 4 to Table1
P‐Nos 44 N/A See Note 4 to Table1

9. Inspection and Testing:


9.1 Visual Inspection
Visual inspection shall be performed after cleaning but prior to painting. The surface
of each completed bend shall be smooth, free of cracks, seams, gouges, notches
and free of ripples or buckles.
Waving as shown in Figure 2, is acceptable provided the following requirements are
met:
a. Wave shapes blend into the pipe surface in a gradual manner with a
maximum CVD of 3% of the actual outside diameter of the bend.
b. The ratio of the distance between adjacent crests, l, to the CVD is
minimum of 12
CVD shall be determined as:

D2 + D4
CVD = − D3
2

Figure-2

Page 17 of 22
D3

D4
D2 l

9.2 Dimensional Control

a. Angle of Bend ± 1 degree


b. Radius of Bend ±1%
c. Linear Distances. ± 3mm for 10 inch NB & under.
± 4.5mm over 12 inch and over
d. Plane of Bend. ±1 degree.
e. Minimum thickness required after bending at the Intrados, Extrados and
Sidewall on CLR shall be specified by the piping specifications of the particular
project for which the Induction bends are being made.

9.3. Ovality
Ovality shall be taken by a suitable caliper or C –gauge. Ovality shall not exceed 8%
for bends subject to internal pressure where Ovality%= (Dmax.‐Dmin.)*100/Dnom.
If after 5 consecutively successful bends whose Ovality is within that specified then
only ½ midpoint needs be verified on the remaining batch providing all other
process variables are the same.

Page 18 of 22
9.4 Wall Thickness
At the start of shift the wall thickness at the extrados shall be inspected using
calibrated ultrasonic measurement gauges at, start, finish, ¼ mid point ½ mid point
and ¾ mid point. If after 5 consecutively successful bends whose wall thickness is
within that specified then only ½ mid point needs be verified on the rest of the batch
providing all other process variables are the same. Wall thinning for 1.5D carbon
steel bends shall be less than 12.5 %

9.5 Hardness
All hardness measurements shall be taken after final heat treatment, as applicable.
Hardness tests on production bends shall be performed using a Telebrineller or
ultrasonic hardness tester in conformance with the appropriate ASTM standard.
Hardness measurements shall be taken along the extrados and intrados at start,
finish, ¼ mid point ½ mid point and ¾ mid point. Only after 5 consecutively
successful bends whose hardness is within that specified; ½ mid point needs to be
verified on the rest of the batch providing all other process variables are the same.

10. Vendor Data Requirement:


10.1 The documentation of the manufacturing details of each bend shall be
recorded as per attachment‐1.
10.2 The inspection report of each bend shall be recorded as per attachment‐2.
10.3 Inspection and Test Plan shall be as per attachment ‐ 3
10.4 Bend Qualification report shall be as per attachment ‐ 4

Page 19 of 22
11.Attachments:
Attachment‐ 1: MANUFACTURING PROCEDURE SPECIFICATION RECORD.
Procedure No Date
Pipe Size/Wall Job No
Radius Bend No
Bend Speed Spool No
Inductor Type Material
Quench Type Heat Number
Spray Nozzle Temp Int.
Inductor Temp Ext.
Quench Centre Bend Length
Quench Inside Push Force
Dia.
Ratio Bend Moment
Tap H2 O Int.
Start length H2 O Ext.
Trans Length H2 O Nozzle.
Power (Kw) Air Int
Frequency Air ext.
Bend Position Thinning
Extrados
Angle Ovality
Over bend BHN max.
Radius (Corr) AMPs
DBB (Corr) Volts
FT Tang. Corr Test Report No
Pivot Operator

Page 20 of 22
Attachment‐2 : BEND INSPECTION REPORT

Job NPS & Bend


Material MPS No. Date Remarks
No Wall Angle

Inspected By……………………………………...

Page 21 of 22
Attachment-5: Scope of Induction Bending for J3 Program

Induction_Bend_pi
pe_class_summary_R

Attachment -6: Minimum required thickness (MM) after Final Bending

Min_required_thick
_Chart_for_induction

Page 22 of 22

You might also like