Professional Documents
Culture Documents
6 Months Up To Sep'20
6 Months Up To Sep'20
scope target
Key Equipments:
U/S Surge Shaft 3 m 140 37.5 102.5 7m/month as Pilot hole 14 m + 89 m 2-EOT Gantry,
choked 2 - Surface Drill (DQ-500), .
1- Shotcrete Machine (Robo Slipforms-2nos as
arm), clashing with USSS Slipform requirement of
2- Excavator (PC-130), DSSS and USSS may clash
7m/month as pilot hole is 2 -Grout pump.
U/S Surge Shaft 4 m 140 46 94 10 m + 84 m Dumper, Loader, Transit mixer
open.
in common
Benching Equipments
Upper Horizontal m 310 0 310 15 m/month 84 m To be start from Apr'20- will be utilized for the To be start from Apr'20
Penstock-5,6,7,8 Dec'21 front
Methodology for
Concreting works will be
required.
Ventilation Tunnel m 581 503 78 10 m/month 30 m +48 m Will be progressing with Gantry for VT. Excavation to Complete in
Rockbolts and Shotcrete. 1 JCB with breaker Jul'20
against replacement of
Surplus.
Ferrule ereccrtion to be
Draft tube (Excavation) m 168 134 34 21 m/ month 34 m DT-6 and DT-8 remaining 17m completed before Orifice
each will be done after DSSS . slab of DSSS
Control Building Slabs No.s 9 4 5 Avg. 2 months /slab 2 slab + 3 slab Structural Completion by Separate Agency for
Oct'20 Architecture works.
Lower Horz. Busbar m 226 52.4 173.6 Avg. 13 m 65 m + 132 m Manual concreting works with Parallel Shuttering
Concrete-5,6,7 & 8 shuttering and staging works Material to be available.
Key Equipments:
Shotcrete Machine-1nos. 1 nos. Excavator on
TRT Outlet 99 nos. + 288 Excavator (PC-130)-1nos, Hire/Subcon in
cum 182896 78169 104727 Avg. 2700 m3 Grout pump-1nos.,
(Excavation) nos. C/A replacement of M/s
Dumper, Loader, Transit mixer Pawar Construction.
in common .
-
TEHRI PSP - Linear work plan for balance work till completion - Budget FY 2020-2021
Status as on
May/20
Aug/20
Sep/20
Jun/20
Apr/20
Jul/20
Total 31st March-20
Work Front Activity
Scope
Completed Balance
Linear (m) 16 17 14 20 18 16
Drainage Gallery around U/S Surge Shaft Exc & Supports 350 247 103.0 0 8 8 8 8 8
Drainage Gallery around U/S Surge Shaft Invert Lining 350 0 350
PAC Slashing 83 83 0
BVC Slashing 78 78 0
Concrete at BVC
Concrete at PAC
Penstocks
Lining
HRT 3 extended lining 32m length Breaking
HRT-3
Plugging 1A
Plugging 1A and
and 1B upto
Plugging of existing 1A & 1B Access Adit 30m length 1B upto
Bifurcation
Bifurcation 30m
30m
Plugging
Vertical Penstock -6 (Pilot) 135 135 0
Vertical Penstock -6 - Slashing 135 0 135
Interface Penstock -6
Plugging
Page 7 of 16
TEHRI PSP - Linear work plan for balance work till completion - Budget FY 2020-2021
Status as on
May/20
Aug/20
Sep/20
Jun/20
Apr/20
Jul/20
Total 31st March-20
Work Front Activity
Scope
Completed Balance
Linear (m) 16 17 14 20 18 16
Plugging
Interface Penstock -8
Plugging & LPAC Adit Plugging & AA-7 Lining (407 mt)
Page 8 of 16
TEHRI PSP - Linear work plan for balance work till completion - Budget FY 2020-2021
Status as on
May/20
Aug/20
Sep/20
Jun/20
Apr/20
Jul/20
Total 31st March-20
Work Front Activity
Scope
Completed Balance
Linear (m) 16 17 14 20 18 16
Draft Tube- 5,6,7,8 Concrete Works 168.00 0.00 168.00 4.36 4.36 4.36
Power House Units Concrete from bottom Raft El.552 to top Slab
30 7 23 El. 552 to 562.3 (MIV floor)
El. 582 m
Architectural works at PH
Busbar Upper Hor Tunnel-6 (Exc & Supports) 103.00 103.00 0.00
Busbar Upper Hor Tunnel-7 (Exc & Supports) 104.00 104.00 0.00
Busbar Upper Hor Tunnel-8 (Exc & Supports) 113.00 113.00 0.00
Busbar Lower Hor Tunnel-5 (Concrete) 68.20 0.00 68.20 0.00 13.00 13.00 13.00 13.00 16.00
Busbar Lower Hor Tunnel-6 (Exc & Supports) 52.49 52.00 0.49
Busbar Lower Hor Tunnel-6 (Concrete) 52.49 0.00 52.49 0.00 0.00 13.00 13.00 13.00 13.00
Busbar Lower Hor Tunnel-7 (Exc & Supports) 52.49 52.00 0.49
Busbar Lower Hor Tunnel-8 (Exc & Supports) 52.49 52.49 0.00
EM & HM Activity
Page 9 of 16
TEHRI PSP - Linear work plan for balance work till completion - Budget FY 2020-2021
Status as on
May/20
Aug/20
Sep/20
Jun/20
Apr/20
Jul/20
Total 31st March-20
Work Front Activity
Scope
Completed Balance
Linear (m) 16 17 14 20 18 16
DSS-EA7 Grouting
EA7-EA8 Grouting
EA8-Outfall Grouting
EA7-EA8 Grouting
EA8-Outfall Grouting
TRT Outlet Excavation & Supports (El. 623.12 Cable anchor top to
488 105 383 5 25 25 25 25 25
EL. 608 Cable anchor bottom) (436 Cable anchor)
Drilling of holes and creating Curtain barrier from El. 602 at toe of
flood protection wall
Page 10 of 16
)
Monthwise TO Projection
BOQ
Description Unit
Rate (Rs)
Apr/20 May/20 Jun/20 Jul/20 Aug/20 Sep/20
Group Code
2.e UG Excavation in d/s Surge Shaft 28 CUM 2,357 970 3882 3882 4205 2588 0
BOQ
Description Unit
Rate (Rs)
Apr/20 May/20 Jun/20 Jul/20 Aug/20 Sep/20
BOQ
Description Unit
Rate (Rs)
Apr/20 May/20 Jun/20 Jul/20 Aug/20 Sep/20
9.e.i Concrete works in Bus bar cavern 89 CUM 8,073 35 - - 249 249 249 CONC-M25A20
9.e.ii Concrete works in upper hor gallery in 268 57 143 143 181 -
90 CUM 8,073
Bus bar
9.e.iii Concrete works in Bus bar vertical 0 0 0 55 55 0
91 CUM 8,073
shaft
9.e.iv Concrete works in lower horz gallery 82 196 392 392 392 437
92 CUM 8,073
in Bus bar
1.a.iii Common excavation in Ventilation ###
94 CUM 210
Chamber
1.b.iii Rock excavation in Ventilation tunnel 95 CUM 477 430 430
###
1.b.ii Rock excavation 101 CUM 477 3,687 1,500 1,500 1,500 1,500 1,500
###
2.n.i UG Excavation in TRT-3 103 CUM 1,641 530 670 670 670 670 1,005 Adjusted PH excavation qty to avoid -ve factor for Exp BOQ (in Dec'17 qty)
2.n.ii UG Excavation in TRT-4 104 CUM 1,641 268 670 670 670 670 670
9.n.i Concrete works in TRT-3 105 CUM 7,913 - 720 720 720 691 691 CONC-M25A20
9.n.ii Concrete works in TRT-4 106 CUM 7,913 400 116 233 243 - -
9.r Concrete works in backfill 119 CUM 6,414 216 77 77 178 178 199 CONC-M15A20
4 Shotcrete on walls and roof 120 BAGS 2,247 1284 4612 4796 6120 5348 4154
###
5.a Rock bolts / perfo anchors type- dia-1 0 517 517 517 517 517
###
121 RM 465
for adits & drainage gal
5.a Rock bolts / perfo anchors type- dia-1 19 36 40 40 40 40
122 RM 465
for u/s SS & Penstock
5.a Rock bolts / perfo anchors type- dia-1
123 RM 465
for PHC
5.a Rock bolts / perfo anchors type- dia-1 - 24 24 26 16 -
124 RM 465
for d/s SS
5.a Rock bolts / perfo anchors type- dia-1 -
125 RM 465
for TRT
5.b Rock bolts / perfo anchors type- dia-2 4,344 8,663 9,075 12,650 9,900 6,875
###
126 RM 512
for SS/BVC/PAC cavern
5.b Rock bolts / perfo anchors type- dia-2
127 RM 512
for PHC cavern
5.c Rock bolts / perfo anchors type- dia-3 900 RB3
128 RM 559
(+SDR)
6.a.i Rock bolts / perfo anchors type- dia-1 0.0 517.0 517.0 517.0 517.0 517.0
###
129 RM 977
for adits & drainage gal
6.b.i Rock bolts / perfo anchors type- dia-1 29 36 40 40 40 40
130 RM 977
for u/s SS & Penstock
6.b.i Rock bolts / perfo anchors type- dia-1 - - - - - -
131 RM 977
for PHC
Monthwise TO Projection
BOQ
Description Unit
Rate (Rs)
Apr/20 May/20 Jun/20 Jul/20 Aug/20 Sep/20
8.b.i Furnishing & installing of cable 100 500 500 500 500 500
###
139 RM 20,442
anchors
Monthwise TO Projection
BOQ
Description Unit
Rate (Rs)
Apr/20 May/20 Jun/20 Jul/20 Aug/20 Sep/20
10.i Furnishing and placing of 0.0 0.0 0.0 0.0 0.0 0.0
144 MT 78,930
Reinforcement steel in BVC, PAC
10.i Furnishing and placing of 22.50 70.61 62.51 70.61 62.51 70.61
146 MT 78,930
Reinforcement steel in u/s PHC
11.a.i Drilling holes for open works 152 RM 2,688 175.00 - - - - ###
-
11.a.i Drilling holes at adits and drainage gal 153 RM 2,688 113 1,179 1,179 1,179 1,179 1,179
11.a.i Drilling holes at TRT 158 RM 2,688 - 192 192 192 192 192
11.c Contact grouting 159 BAGS 616 0 231 231 231 231 231
###
11.b In adits and drainage gal 160 BAGS 616 71 1,198 1,198 1,198 1,198 1,198
11.b Grouting in TRT 164 BAGS 616 867 867 867 867 867
16.l.i Grouting material sand 165 MT 378 263.34 263.34 263.34 263.34 263.34
###
11.d Furnishing and installation of drainage 459 124 113 113 113 108
###
167 RM 193
pipes
16.d Removal of material arising from over - - - - - ###
-
169 CUM 328
break
16.k Non shrink cement base epoxy - ###
171 KG 51
grouting
16.q.i.a Wire crate 172 SQM 1,880
BOQ
Description Unit
Rate (Rs)
Apr/20 May/20 Jun/20 Jul/20 Aug/20 Sep/20