GM 1927 16b Stamping Process Audit-GM Confidential
GM 1927 16b Stamping Process Audit-GM Confidential
Were tailor welded / tailor rolled blanks are used, is GM SQE to verify error Ask supplier to demonstrate error proofing. Re-orientate
3 error proofing in place to assure proper orientation proofing in place and blank to incorrect possitions and verify system stops R
of the TWB throughout the process functional. process.
Were tailor welded blanks are used, is error GM SQE to verify error Ask supplier to demonstrate error proofing. Re-orientate
4 proofing in place to assure material offset from thin proofing in place and blank to incorrect possitions and verify system stops R
to thick is on correct side of part? functional. process.
Review supplier Parts identified as a severity 10/9 must be free from burrs
Preventative Maintenance
6 Part free of burrs and sharp corners Procedure and inspect
and sharp corners. Burrs on parts with no severity criteria R
parts (Attribute Inspection) must be within 10% of material thickness (industry std).
Total
Prior to production, review After forming; part should be free of wrinkling and folded
Part free of un-acceptable wrinkles and folded over forming diagrams. During over metal. Approved Master sample must be available
9 production run, review parts R
metal. and subject to attribute for comparison. The Process Control Plan and PFMEA
inspection. need to make reference to wrinkling.
Prior to production, review After forming part must be free of splits and edge
forming diagrams. During
cracking. Master sample to be available for comparison.
10 Part free of splits and edge cracking. production run, review parts R
and subject to attribute Review the Process Control Plan and PFMEA and ensure
inspection. controls are in place
Check for part no./ frequency wise program log. Check for
Method for confirming correct selection of program Review Die Set Up control on program accessibility.
26 R
in cases of automated press lines Procedures Refer to Process Control Plan and PFMEA to ensure the
necessary controls are in place
Total
Visual review of gauge The operator must be able to understand the Standard
37 Gauges usage instruction to be available. instructions to assure they Operating Procedures and must be available to the R
are clear and concise. operator while checking the part.
Visual Review of where If datum pads are damaged on the gauge, the parts may
Datums to be clearly identifiable and free of how does suppler store be incorrectly identified as rejects. Refer to the
38 R
damaged. gauge when not in use to preventative maintenance schedule for calibration
prevent potential damage records.
Gauge to be kept updated to the latest engineering Verify Math and review The gauge must be identified with the latest part number
39 suppliers documentation for R
change level. gauge changes and Engineering design level.
Total
Review warehouse work Some parts have a shelf life does the Process Control
43 Supplier to follow FIFO? instructions and process
R
Plan / PFMEA capture this and is it being followed.
Labels should only be Stampings may have Left and Right and suppliers often
printed when container part
Supplier to have an error proofing process for supply parts with incorrect labelling. Follow the Process
44 bin is ready for shipment. R
labelling. No labels printed in Control Plan / PFMEA is there an opportunity for the
advance supplier to implement error proofing.
If any of the single sections is rated RED, overall audit result is RED with 0% score
1
2
3
4
5
6
7
8
9
10
C5: Person at supplier that prepared the form for the GM SQE. (If applicable)
2- High priority
3- Highest priority
D16: ACTION ITEM: The item that requires action to improve the process or quality of the product being produced.
E16: ACTION LEADER: The person that leads the team to make the improvements. This should be the suppliers person but may be a GM Management person.
F16: START DATE: The date the action item was identified and listed in the action item column
G16: TARGET CLOSE DATE: The date the supplier will complete the action item.
This date may change. If the date changes, you are required to entry the correct color code in the pass status and present status columns.
A comment on why the change to be entered in the comment field
H16: ACTUALCLOSE DATE: The date the action item was closed TO INCLUDE VALIDATION.
The SQE should validate the action item as being closed and RESOLVED.
I16: LAST UPDATE: The date the SQE reviewed the action item.
J13: PAST STATUS: The cell is filled in when the status changes. Oldest status to the left
If status is WHITE put a "W" in the cell. Do not leave blank.
Copy the cell for the correct color.
COLOR CODE:
GREEN: Task Completed on Time
YELLOW: Action item is in trouble and may affect target date.
RED: Action item has missed target date.
WHITE: Task Re-Timed, No Status
BLUE: Task Status is incorrect / Not Updated
P16: COUNTER MEASURES: