SAATVIK VIHAR PHASE II, PLOTTED DEVELOPEMENT PROJECT ON KH. NOS.

110, 111, 112/1, 112/2, 165/1, 165/2, 165/3, 165/4, 172 AT VILLAGE MANGLIYA, TEHSIL SANWER,
DISTT. INDORE. DEVELOPER : M/s RUCHI REALTY PRIVATE LIMITED
PROJECT SCHEDULE INDICATING ITEMWISE START AND COMPLETION DATES OF ACTIVITIES
01.03.2021 TO 28.02.2022 (YEAR-1) 01.03.2022 TO 28.02.2023 (YEAR-2) 01.03.2023 TO 29.02.2024 (YEAR-3)
01.03.2021 to 01.06.2021 to 01.09.2021 to 01.12.2021 to 01.03.2022 to 01.06.2022 to 01.09.2022 to 01.12.2022 to 01.03.2023 to 01.06.2023 to 01.09.2023 to 01.12.2023 to
S No. Item 31.05.2021 31.08.2021 30.11.2021 28.02.2022 31.05.2022 31.08.2022 30.11.2022 28.02.2023 31.05.2023 31.08.2023 30.11.2023 28.02.2024

1 Layout & levelling

2 Excavation

3 Murrom filling

4 GSB

5 DLC

6 PQC

7 Drainage

8 Storm water

9 Waterline

10 Garden

11 STP

12 Electric line

13 Foot Path

14 SUMP WELL

15 Testing & Charging