PL RENOVATION WORK

QUOTATION
Attn: Hi Tech Construction & Engineering Works
Project: Renavation Work For MCC Main Office Date: 18/3/2024
Item Description QTY UNIT RATE Price
(RM)
1 Demolish Works C/W Clear Rubbish From Site
1.1 To demolish existing gypsum board & glass L/S L/S L/S 4,500.00
1.2 To demolish existing 2'x4' suspended ceiling L/S L/S L/S 4,200.00
1.3 To demolish existing vinyl tiles L/S L/S L/S 4,200.00
1.4 To demolish eixsting wall mounted air-con for meeting room L/S L/S L/S 300.00
1.5 To demolish meeting room glass door L/S L/S L/S 300.00
1.6 To demolish meeting room wall partation L/S L/S L/S 300.00
1.7 To touch-up meeting room partation & close-up existing doorway L/S L/S L/S 400.00
1.8 To repaint meeting room partation L/S L/S L/S 400.00
1.9 To touch-up meeting room vinyl tiles L/S L/S L/S 200.00
1.10 To demolish entrance area vinyl tiles L/S L/S L/S 200.00
1.11 To demolish entrance area glass panel L/S L/S L/S 400.00
1.12 To demolish entrance area 2'x4' suspended ceiling 1400 SQFT 1.00 1,400.00
1.13 To supply & lay plastic sheet to protct exisiting vinyl tiles for entrance area L/S L/S L/S 600.00
2 Plaster Ceiling Wokrs
2.1 To supply & install plan plaster ceiling for main office 4700 SQFT 4.50 21,150.00
2.2 To supply & install plan plaster ceiling for entrance area 1400 SQFT 4.50 6,300.00
2.3 To supply & install service manhole 10 SET 180.00 1,800.00
2.4 To open lighting hole 240 NO 6.00 1,440.00
2.5 To open air-con hole 7 NO 50.00 350.00
3 Gypsum Board & Tempered Glass Works
3.1 To supply & install gypsum board partation 1800 SQFT 8.00 14,400.00
3.2 To supply & install 12mm tempered glass wall 1550 SQFT 26.00 40,300.00
4 Door Works
4.1 To supply & intsall 3'L x 7'6"H 12mm tempered glass door c/w 3'L s/steel handle & cks floor spr 11 SET 1,800.00 19,800.00
4.2 To supply & intsall 3'L x 7'6"H 12mm laminated plywood glass door c/w door frame for store roo 2 SET 1,800.00 3,600.00
5 Flooring Works
5.1 To supply & install SPC vinyl tiles c/w underlay foam for main office 4200 SQFT 6.80 28,560.00
5.2 To supply & install SPC vinyl tiles c/w underlay foam for entrance area 500 SQFT 6.80 3,400.00
5.3 To supply & install PVC skirting 700 FR 4.00 2,800.00
6 Painting Works -
6.1 To supply & apply gypsum board partation skim coats 3600 SQFT 0.80 2,880.00
6.2 To supply & apply ICI emusion paint for gypsum board partaion wall & brick wall 6700 SQFT 2.00 13,400.00
6.3 To supply & apply ICI maxlite paint for plaster ceiling 6100 SQFT 1.00 6,100.00

Total 183,680.00
.

Payment: Confirmed By
50% after confirmation
50% progressive claimed