INFINITY LIFT Plan
INFINITY LIFT Plan
All lifting operations require to be considered but this list is not exhaustive:
Every Lift every time Specify Yes/No
TBT at site with all involved personnel: Working under suspended loads
Crane operator, riggers, banksman, Route adjacent to or over live plant
truck driver Conflicting tasks in area/adjacent worksites
Pre-use equipment checks by Trial lift required
competent person Risk of overturning
All lifting equipment should have SWL Standard methods of slinging/ attaching/ detaching the loads
identified to be used
Weight, Size, Shape, certification and Availability of certified lifting points
center of gravity Check that lift is within crane radius
Proximity hazards, obstructions, path Ensure any slinging at height has safe access
of load laydown area load bearing Safety Harness required
capacity Diameter/Dimension of load known
Environmental conditions including Length of load known
weather Confirm No of Tag lines require
Responsibilities clearly defined e.g., Confirm Number of personnel required for task
Rigger/Slinger /Banksman
Competent crane operators, ! x riggers
Check lift radius achievable for the
Trained Riggers
load
Lifting area is barricaded off
Experience, competence and training
Personal Protective equipment
of personnel.
All lifts must be checked for loose
objects
No unauthorized persons in the
vicinity of the lift
Should changes render this lift plan no
longer applicable, stop the job.
Methods of communication to be used
Certified lifting equipment and accessories to be used (Specify Type, SWL and Color Coded)