Schedule - TSC Shiploader - 240311 Prelim

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Task Name Duration Start Finish Predecessors Successors Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024

Mode Jan Feb Mar Apr May Jun Jul Aug


1 Ship Loader @ Luffing & Shuttling Winch, A frame
133 days Wed 14/2/24 Thu 18/7/24
2 Manufacturing (Panel & Winch) 34 days Wed 14/2/24 Sat 23/3/24
3 Electrical Panel 0 days Wed 14/2/24 Wed 14/2/24 10FS+2 days 14/2

4 Winch Final Assembly 3 days Fri 23/2/24 Mon 26/2/24 12FS+1 day 5FS+7 days
5 Winch Pre FAT, Wiring, Testing 3 days Wed 6/3/24 Fri 8/3/24 4FS+7 days 6
6 Finalised Testing Tower 2 days Sat 9/3/24 Mon 11/3/24 5
7 Winch FAT with Client 2 days Thu 14/3/24 Fri 15/3/24 8FS+2 days
8 Winch packing 5 days Tue 19/3/24 Sat 23/3/24 7FS+2 days 13FS+19 days
9 Shipment & Delivery (Panel & Winch) 54 days Thu 15/2/24 Thu 25/4/24
10 Electrical Panel ETD JKT 0 days Thu 15/2/24 Thu 15/2/24 3FS+2 days 11FS+2 days 15/2

11 Electrical Panel ETA SYD, BRISBANE 0 days Sat 17/2/24 Sat 17/2/24 10FS+2 days 12FS+3 days 17/2

12 Electrical Panel ETA ACW with clearance 0 days Wed 21/2/24 Wed 21/2/24 11FS+3 days 4FS+1 day 21/2

13 Winch ETA - MY PKG (Sea Shipping) 0 days Mon 22/4/24 Mon 22/4/24 8FS+19 days 14FS+3 days 22/4

14 Winch ETA TSC Setiu 0 days Thu 25/4/24 Thu 25/4/24 13FS+3 days 25/4

15 New A-Frame (Engineering & Fabrication) 81 days Thu 22/2/24 Mon 3/6/24
16 STAAD preparation 7 days Thu 22/2/24 Thu 29/2/24 17
17 Detail Engineering 14 days Fri 1/3/24 Sat 16/3/24 16 18SS+7 days
18 Steel fabrication 60 days Sat 9/3/24 Sat 25/5/24 17SS+7 days 19FS+7 days
19 Delivery to site 0 days Mon 3/6/24 Mon 3/6/24 18FS+7 days 22 3/6

20 Site Construction 45 days Tue 4/6/24 Thu 18/7/24


21 Site Preliminary 10 days Tue 4/6/24 Thu 13/6/24
22 Prelim & Preparation 10 days Tue 4/6/24 Thu 13/6/24 19 24
23 Site Activity 32 days Thu 13/6/24 Mon 15/7/24
24 Crane on barge reach site 0 days Thu 13/6/24 Thu 13/6/24 22 25 13/6

25 Electrical De-Termination & Dismantling 4 days Fri 14/6/24 Mon 17/6/24 24 26


26 Remove old platform and winch 4 days Tue 18/6/24 Fri 21/6/24 25 27
27 Remove existing A-Frame 7 days Sat 22/6/24 Fri 28/6/24 26 28
28 New A Frame installation 10 days Sat 29/6/24 Mon 8/7/24 27 29
29 New Shutling & Luffing winch installation 7 days Tue 9/7/24 Mon 15/7/24 28 31
with Electrical

30 Testing& Commissioning 3 days Tue 16/7/24 Thu 18/7/24


31 T&C 3 days Tue 16/7/24 Thu 18/7/24 29

Task Project Summary Manual Task Start-only Deadline

Project: TSC Shiploader Split Inactive Task Duration-only Finish-only Progress


Date: Mon 11/3/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1