Method Statementfor Mechanical Works Underground Rain Water Sewer Drainage System
Method Statementfor Mechanical Works Underground Rain Water Sewer Drainage System
Method Statementfor Mechanical Works Underground Rain Water Sewer Drainage System
net/publication/370658104
CITATIONS READS
0 792
1 author:
Sherin Akter
Independent University, Bangladesh
249 PUBLICATIONS 1 CITATION
SEE PROFILE
All content following this page was uploaded by Sherin Akter on 11 May 2023.
METHOD STATEMENT
FOR UNDERGROUND RAIN WATER & SEWER
DRAINAGE SYSTEM WORKS OF DEPOT
BUILDING CONSTRUCTION
Document No. ITD-SINOHYDRO JV/CP02/MS/ME001, Rev. 01
MARCH 2019
Employer
Dhaka Mass Transit Company Limited
A Government Owned Company
Level-14, Probashi Kalyan Bhaban
71-72, Old Elephant Road
Eskaton Gardens, Dhaka-1000, Bangladesh
PREPARED BY
Method Statement for underground rain waler and sewer drainage system works
ITD-SINOHYDRO JV
DHAKA MASS RAPID TRANSIT DEVELOPMENT PROJECT
CONSTRUCTION OF CIVIL AND BUILDING WORKS
IN UTTARA DEPOT FOR MRT LINE 6
CONTRACT NO. CP-02
ITD-SINOHYDRO JV
ITD-SINOHYDRO JV/CP02/MS/ME001
DOCUMENT NO.:
REVISION: 01
TITLE: METHOD STATEMENT FOR UNDERGROUND RAIN WATER,
SEWER DRAINAGE SYSTEM WORKS OF DEPOT BUILDING
CONSTRUCTION
AUTHORISATION
Prepared by: Reviewed by: Approved by:
.�,
. .... t..J ................... -�-· .......
Engr.Sherin Akter (Mr. Wang Wenliang) (Mr. Thitinan Panpila)
.......... ..........
Quality Control QA Engineer Project Manager
Engineer
Date: 16.03.2019 Date: (b - 0 \
Date: I b /o 1> /zotq
Th1!11!1 a r.ontrollP.d ,1ocumenl wl111;h !lhllll nut""' cuµ1l'LI wllhuul lhe permlnlon or the Document Controller.
Note: A CONTROLLED copy is valid only if stamped "C" in red
AMENDMENT/RELEASE RECORD
Revision Issue Description of Amendment/Release Effective Date
No. Type
ype of "A" For Acknowledgement & Information & Reference "R" For Internal Review & Comment
Issuing: "C" For Employer's Representative's Approval "U" For Internal Using and/or replacing the existing one.
CONTENTS
1.0 PURPOSE
This method statement describes the construction method, sequence and procedure to be
deployed of installation pipe for underground rain water & sewer drainage system construction
including relevant materials, tools and equipment In Dhaka Mass Rapid Transit Development
Project, Contract No. CP-02.
2.0 GENERAL/SCOPE
Work shall be done according to this method statement and the use of materials, tools and
equipment stated herein in order to achieve a quality of work pursuant to relevant specification
and working procedure.
Relevant operatives and staff/engineers shall be thoroughly trained in the methods and skills
required prior to performing their tasks.
Abbreviations Title
Relevant specifications are contained in Work Requirement, Volume 3-2 Specification (2/2) –
Particular Specifications, Part 02 – Civil Works, as follows:
Relevant specifications are contained in Work Requirement, Volume 3-2 Specification (2/2) –
Particular Specifications, Part 05 – Mechanical Works, as follows:
a. Section 1: Plumbing works
b. Approved Shop drawing of each area / zone / station.
c. BNBC 2006; Chapter 7- Drainage & Sanitation, Section 7.14
Plumbing works construction team roles & responsibilities are listed as below:
6.1 Materials
All materials shall conform to the requirements of Contract and relevant specifications
and standards. This method statement shall apply in conjunction with the material
submission as follows.
a. uPVC Pipe Garde / Class shall be as per Project Specification mentioned.
approved by the Engineer
b. If Project Specification mentioned Grade / Class PVC fitting is not produced by
the manufacturer, then Grade / Class can be replaced with prior approval of the
Engineer.
c. PVC Cement (PVC Solvent)
d. PVC Flexible pipe, as per specification and manufacturing standard
e. PVC Support
f. Timber / wood plank for formworks
g. Cementitious grout
h. Approved Sealing materials (If required)
c. Grinding Machine
d. Drilling Machine
e. Measuring Tape
f. Spirit Level
g. Laser level alignment tools
h. Wrench, Screwdriver and Hammer
i. Chain block
j. Scaffolding (If required), Ladder accessories
k. Wooden / steel formwork
l. Steel plate compactor
m. Survey Instruments; Leveling & Total station etc.
n. Hard barrier materials for prevent falling
7.0 EQUIPMENT
7.1 Excavator
7.2 Generator
One Diesel Generator of appropriate capacity will be presented for emergency support during
commercial power failure.
7.3 PPE
Relevant Personal Protective Equipment is Helmets, Safety Shoes, Goggles, Reflective vest
and Masks.
Survey and setting out shall be conducted to provide the guide on levels and alignment
for the construction in accordance with shop drawings. Measure the length of routing for
cutting the pipe.
8.2 Mark support at each installation range and install hanger / support with approved
material
a. The PVC pipe routing and location marked to comply with the details stipulated in
the approved shop drawings.
b. Determined wish excavation area nearly public area shall be installation sheet
pile and steel plate for Protection soil collapsing before start Excavation.
d. The ground water will be collected by sump pit located nearest and divert into
existing drainage trench or pump by relevant equipment tools if required.
e. If the PVC pipe is "required to be installed on the concrete slabs and walls, the
steel supports shall be installed in accordance with the approved shop drawings.
However, prior to the installation of the steel supports, the corresponding
expansion bolts shall be installed. The holes to be drilled for installation of
supports shall be properly marked. The holes shall be drilled using an electrical
drill. The hole-size and correct depth as well as cleaning or re-boring shall be
carried out prior to embedding expansion bolts.
f. The clamp / supports shall then be installed and fixed with the corresponding
expansion bolts. The spacing of supports and installation details are shown in
approved shop drawings. The length of the pipe supports shall be sufficient to
adjust the level of PVC pipes to be installed.
- Ensure that the concrete surface at the bottom of first layer of brick is properly
chipped.
a. Visual check the pipe and fittings fracture, straight, rust.
b. Square cut the pipe as required length by hacksaw
c. File off the inner burrs with sandpaper. Hold the sandpaper at pipe end and sand
or use file until the edges of pipe are beveled
d. Clean end of pipe and fitting to remove any dirt, grease, shavings or moisture.
e. Check pipe and fittings for dry fit before cementing
f. Apply PVC cement for inside surface of fitting first, then apply to outside surface
of pipe.
g. Immediately, while cement is still wet, assemble the pipe and fittings. Insert pipe
until reaching pipe stop (socket bottom) and/or erasable depth mark on pipe
outer surface. Hold the pipe and fitting together for 15 seconds.
h. Clean around connecting joint. The joint shall be dry for 10 minutes.
Document No. Revision Page No.
ITD-SINOHYDRO JV/CP02/MS/ME001 No. 01 Date: March 12, 2019 6 of 10
ITD-SINOHYDRO JV Dhaka Mass Rapid Transit Development Project
Contract No. CP-02
Method Statement for underground rain water and sewer drainage system works
i. PVC connect to flexible will not apply cement for connecting surface. After
assemble the pipe to flexible, tight by pipe belt.
Upon completion of the piping works, leave it to cured solvent cement for proper bonding
before proceed with the leak test.
Drainage and venting system: After installation of piping the drainage and venting
system shall be tested with water to ensure installed system is leak proof. The leak test
shall be performed as described below:
The water test shall be applied to the drainage and venting system either for the whole
system part (section) therefore. For the entire system, all openings in the piping expect
the highest opening shall be closed, and the system filled with water to the point of
overflow. For the system to be tested in section, each opening shall be tightly plugged
except the highest opening of the section under test and each section filled with water
but no section shall be tested with less than a 3m head of water. In testing successive
section, at least the upper 3m of the next preceding section shall be tested so that no
joint or pipe in the building (except the top most 3 m of the system) shall have been
submitted to a test of less than a 3 m head of water. The water shall be kept in the
system or in the portion under the test for at least 15 minutes before the inspection
starts. The system or the part of the system under test shall be water tight at all point.
All joint connections shall be inspected to ensure that they are completely plugged and
wrapped prior to concrete being placed.
Installed formwork shall be leak free with sufficient support to withstand pressure
resulting from placement of grout / concrete and sufficient rigidity and shall be tightened
to maintain specified dimensions and shape and to prevent loss of grout materials.
Form surfaces shall be well prepared and covered with coating material such as form oil
to prevent absorption of moisture and prevent bond with concrete. Incase installation the
formwork of Wall before installation 2 side shall be inspection of reinforcement rebar
completed by NKDM
Grout shall be placed continuously in one single operation without cold joint. After
placement, grout shall be protected from premature drying and excessively hot
temperature. Grout materials shall be approved by the Engineer prior to use at site.
Sewer drainage formwork shall be removed after 24 hours or as soon as concrete has
proven hardness and sufficient to resist damage from removal operations, but not until
the concrete has sufficient strength to support itself. Remove the formwork keep curing
for 03 days. The curing methodology is the following with hessian cloths, fabrics, or
similar material kept continuously wet - to protect moisture loss PE sheet will use.
Backfilling work shall be not more than 300mm thick and shall be properly compacted by
steel plate compactor before laying of subsequence layer of backfill. This process is
repeated until the whole height of the sewer system drainage and surrounded manhole
is filled. Backfilling activities will commence as soon as the fully completed section of the
excavated area is ready to received backfill material and also practically safe for the
other on-going construction activities for remaining sewer drainage system and
manholes.
- Pipe & fittings installation location will be marked by survey setting out.
- Inspection with the engineer’s representative will be carried out while work is in
progress.
- Sample of uPVC pipe will be submitted to the engineer for necessary approval.
- Movement of heavy equipment shall be done under close supervision of highly skill
person when working close to near-by traffic.
- Inspect machines & tools in advance of this use. Handle electrical machinery &
hazardous materials with care established operational.
- All trailers, truck mixer and cranes used for the work must be driven carefully.
- All persons entering the construction areas must be induced in accordance with the
safety plan procedure.
- All operatives must wear & hooked safety belts / body harness during working at
height.
- All operatives being outdoors must stop working during heavy raining and lightning
periods.
- All workers and staff are required to follow the safety regulations as part of the Site
Safety Plan.
This method statement is used for the general installation work. No toxic material is
involved. The General Technical Specification Environmental Management and Fire
Controls, shall be used in order to protect the environment from the installation activities.
Control for material scrap and industrial waste for all of work. All scrap at site work area
shall be moved to the specified area after completion of work every day
15.0 SECURITY
16.0 ATTACHMENTS
Attachment 1
Inspection and Testing Plan
INSPECTION AND TEST PLAN
Project : The Dhaka Mass Rapid Transit Development Project OF
Contract: CP-02 Quality System : ISO 9001 : 2008
Item Description: Installation of uPVC Pipe for Sewer Drainage system METHOD STATEMENT FOR UNDERGROUND RAIN Document Type : Controlled
Location: N/A WATER, SEWER DRAINAGE SYSTEM WORKS OF Date : March 13, 2019
Specification No: Work Requirement, Volume 3-2: Specification – Particular Specifications, Part 5 DEPOT BUILDING CONSTRUCTION Prepared by : Mr. Wang Wenliang
Mechanical Works Approved by : Mr. Thitinan Panpila
ER Approved : N/A
1 Submission - Material, Shop Drawing, Method Statement N/A R R/D N/A N/A Refer to relevant specification
- Mock up Inspection N/A H R Record/report inspection Record/report inspection Refer to relevant specification
ITD-SINOHYDRO
2 Materials - Approved uPVC and its accessories X H W/O Engineer Refer to material submission
JV/CP02/PR006/01
ITD-SINOHYDRO
3 Equipment - Its equipment and related equipment X S R, W/O Engineer Refer to relevant specification
JV/CP02/PR006/01
5 In-process Inspection
ITD-SINOHYDRO
7 Quality Record Submission - Completion of documents. D D R Engineer As shown in Method Statement
JV/CP02/MS/ME001/01
Symbol Legend Symbol Legend
H Mandatory Hold Point-Hold Until Approved D Document or Record Required
W/O Witness Point-Optional X Subcontract Inspection
W Witness Point R Review Point
S/......... Surveillance Point - Random ITP/Each Quantity N/A Not Applicable
N Notify E (Request for Inspection)
Attachment 2
Inspection Checklist for UPVC Pipe installation
Works
ITD-SINOHYDRO JV Dhaka Mass Rapid Transit Development Project
Contract No. CP-02
Method Statement for underground rain water and sewer drainage system works
Inspection Sheet for Installation of UPVC pipe for Rain & Sewer Drainage
System
Sign Acceptance
Item Description Acceptance Criteria Inspected by Remarks
Yes No
1 Preparation Work
2 In-process Inspection
Follow to drawings/relevant
3.1 Anchoring Installation (QC/FM)
specifications
Follow to drawings/relevant
4 Leak test
specifications
Follow to drawings/relevant
4.1 Joint leakage (EN)
specifications
Relevant
5 Manholes Grouting works (QC/FM)
Specification/Drawing
Relevant
6 Final Inspection (EN)
Specification/Drawing
Note:
Date : Date :
ITD SINHYDRO JV QC / MEP Engineer NKDM QC Engineer
Attachment 3
Task Risk Analysis
ITD-SINOHYDRO JV Dhaka Mass Rapid Transit Development Project
Contract No. CP-02
Method Statement for UPVC pipe installation for Sewer drainage system
SL
Task Name Risk Factors Mitigation Plan
No
1. Proper way to operating tools
shall be reviewed.
2. Operation manual shall be
followed properly.
3. Removal of safety guards or
other safety features of rotating
Being struck by hand or
blade or saw shall be prohibited.
power tools.
4. Damaged and unsafe tools
shall be removed or repaired.
5. Wearing loose clothes e.g.
Use of power tools and
01. lungi, towel, panjabi shall be
cement mixers
avoided to be safe from being
stuck to equipment and tools.
1. Operators shall be alerted to
hazards electricity.
2. Proper grounding of tools shall
Shock or electrocution be ensured.
from power tools 3. Unnecessary cords shall be
removed.
4. Standing or working in wet
area shall be avoided.
1. PPE shall be used.
2. Scaffolds shall be
manufactured as per safety plan.
3. Scaffoldings, which will be
used shall be in good condition
Working on heights, and have adequate capacity for
02. Falls from platform
decks or scaffolds the load.
4. Body harness shall be used for
works on elevated surfaces.
5. Necessary measures shall be
taken as per safety personnel’s
instruction.
Imbalance, stretching and excess
reaching shall be avoided using
03. Placing liquid grout Muscle Strain tools and maneuvering around
forms.
SL
Task Name Risk Factors Mitigation Plan
No
Fingers and hands shall be
Finger Injury protected from cutting by saw or
hammer.
Pulling or lifting of heavy objects
Muscle Strain without precaution shall be
avoided.
05. Placing Pipes 1. Measures shall be taken to
prevent dropping of bricks.
Injury from blocks
2. Unnecessary broken parts
shall be removed
1. Rotation between activities is
recommended.
Excavation & Muscle strain due to 2. Stretching and strengthening
06.
Backfilling works repetitive works exercises for the hand and wrist
are recommended after the pain
improves.
Protection around elevated
Falling of objects from platforms shall be taken to
elevated platform prevent falling of objects on
07. General somebody below the platforms.
Removal of PPE while working
Not wearing PPE all time with material and tools shall be
prohibited.