Professional Documents
Culture Documents
Ir Report FINAL
Ir Report FINAL
Project-I
BATCH 2019
Section (CV-B2)
Submitted By:
1|P a g e
2|P a g e
Acknowledgment:
We have put our efforts in this project. Indeed, it would not have been achievable without support
and help from the university and many individuals. We would like to say heartfelt thanks to all of
them.
We would also like to express our gratitude towards our parents & Engr. Fahad Haseeb for her
kind co-operation and encouragement which helped us in completion of this project.
3|P a g e
Declaration:
I declare that the work presented in this report belongs to us completely. In case any of the
information provided is found plagiarized or copied from any source, we are aware that we may
be held liable for it and serious actions can be taken against us.
Signature: -----------------------
4|P a g e
5|P a g e
Table of Contents:
6|P a g e
Table of Figures:
FIGURE 1: PLAN VIEW OF A BARRAGE ............................................................................................................................................................... 10
FIGURE 2: CROSS SECTION OF A BARRAGE ......................................................................................................................................................... 11
FIGURE 3: LONGITUDINAL VIEW OF THE BARRAGE ........................................................................................................................................ 11
FIGURE 4: SCOUR DEPTH CALCULATION USING LACEY FACTOR............................................................................................................ 13
FIGURE 5: DISCHARGE CALCULATION FORMULA .......................................................................................................................................... 13
FIGURE 6: RATING CURVE FOR DSWL ................................................................................................................... 14
7|P a g e
1. Problem Statement:
It is required to take off three canals one from left and two right side of a river, all the three canals are
required to carry a maximum discharge of 3500 cusecs. We are required to design a head work (Barrage)
that will be capable of raise the water level in the river and to divert it into these canals. Following are the
properties of river that will be used in designing the barrage.
2. Introduction:
Barrages are typically constructed in flat areas and involve the use of gates to control water levels
in a river. The top of the solid obstruction is kept low, and during floods, the gates are raised to
prevent floodwaters from rising too high. By doing this, there is less silting and the weir can better
manage and control the water. These structures are typically built on permeable soil like alluvium,
silt or sand, allowing for seepage under the floor and giving uplift pressure. It is important that a
barrage is designed to be safe against subsoil flow and overflowing water.
8|P a g e
d. Upstream glacis of suitable slope and shape. This joins the crest to the downstream floor
level. The hydraulic jump forms on the glacis since it is more stable than on the
horizontal floor, this reduces length of concrete work on downstream side.
e. Downstream floor is built of concrete and is constructed so as to contain the hydraulic
jump. Thus it takes care of turbulence which would otherwise cause erosion. It is also
provided with friction blocks of suitable shape and at a distance determined through the
hydraulic model experiment in order to increase friction and destroy the residual kinetic
energy.
Divide Wall:
A wall constructed at right angle to the axis of the weir separating the weir proper from
the under sluices (to keep heavy turbulence at the nose of the wall, well away from
upstream protection of the sluices)
It extends upstream beyond the beginning of canal HR. Downstream it extends up to the
end of loose protection of under sluices launching apron)
This is to cover the hydraulic jump and the resulting turbulence.
The divide walls are costly structures
These walls are likely to be subjected to maximum differential pressure when the full
discharge of the river is passing through the weir, (there will be difference in water level
on the two sides ).
Also there may exit difference in silt pressure on the two side . The values of differential
pressure are taken arbitrarily say 1.0 m for water heads and about 2.0 m for silt pressure
Fish Ladder:
Fish ladder or fish passes are generally provided to enable the fish to ascend the head
waters of the river and thus reach their spawning grounds for propagation or to follow
their migratory habits in search of food.
For movement of fish (negotiate the artificial barrier in either direction)
Difference of level on the upstream and downstream sides on the weir is split up into
water steps by means of baffle walls constructed across the inclined chute of fish ladder.
Velocity in chute must not be more than 3 m/s
Grooved gate at upstream and downstream - for effective control.
Optimum velocity 6-8 ft/s
Plenty of light should be admitted in the fish-way
The water supply should be ample at all times.
Sheet Piles:
Made of mild steel, each portion being 1/2' to 2' in width and 1/2" thick and of the required length,having
groove to link with other sheet piles.
9|P a g e
Upstream Piles:
Situated at the upstream end of the upstream concrete floor driven into the soil beyond the
maximum possible scour that may occur.
Inverted Filters:
Provided between the downstream sheet piles and the flexible protection. Typically 6"
sand, 9" coarse sand and 9" gravel. Filter may vary with size of particles forming the
river bed. It is protected by placing over it concrete blocks of sufficient weight and size.
Slits are left between the blocks to allow the water to escape.
Length should be 2 x downstream depth of sheet.
Flexible Apron:
1. As the bed of under sluice is not lower level than rest of the weir, most of the day,
whether flow unit will flow toward this pocket => easy diversion to channel through
Head regulator
2. Control sil entry into channel
3. Scour the silt (silt excavated and removed)
4. High velocity currents due to high differential head.
5. Pass the low floods without dropping
6. The shutter of the main weir, the raising of which entails good deal of labor and time.
7. Capacity of under sluices:
10 | P a g e
8. For sufficient scouring capacity, its discharging capacity should be at least double the
canal discharge.S
9. Should be able to pass the dry weather flow and low flood, without dropping the weir
shutter.
10. Capable of discharging 10 to 15% of high flood discharge
Guide Banks:
Force the river into restricted channel, to ensure almost axial flow near the weir site.
(Embankments in continuation of G-Banks. To contain flood within flood plains)
Marginal Bunds:
Provided on the upstream in order to protect the area from submergence due to rise in HFL,
caused by afflux.
Embankment type structures constructed transverse to river flood, extending from the
banks into the river (also transverse dykes)
Protect the bank from which they are extended by deflecting the current away from the
bank.
4. Design Considerations:
There are two aspects to the design of a barrage.
Subsoil flow:
11 | P a g e
Uplift pressure Barrages or diversion dams are normally built on the porous subsoil, normally
occurring 'in river beds such as silt, fine sand or gravel. These are low head structures not
requiring rock foundations and they can be built on porous soil, with the provision of necessary
safeguards against uplift pressure. This is defined as the residual pressure of the seeping water
acting vertically with the effect of trying to lift up the body of the barrage. Therefore, in the case
of gravity floors, the thickness of the aprons or the glacis must be of greater weight than the
uplift pressure.
There is another way in which the seepage flow underneath the structure may endanger its
stability and is called piping phenomenon. When the seepage velocity in the microscopic flow
channels in the subsoil under the apron is such that the seepage force at the exit point becomes
greater than the submerged weight and friction of soil, very fine soil particles become displaced.
His can be observed as muddy water emerging from the soil surface continuing process and a
subsoil consisting of fine particles surrounding larger particles, the removal of the fine particles
causes unequal settlement of the subsoil and ultimately the collapse of the structure due to
piping. The river discharge over, the barrage further aggravates the situation by washing away
the loosened soil due to the excessive exit gradient. The problem consists therefore in controlling
the seepage force so that it cannot carry away the foundation material.
12 | P a g e
Figure 2: Cross Section of a Barrage
6. Given Data:
13 | P a g e
Number of canals on right bank 2
Number of canals on left bank 1
Maximum discharge of one canal 3,500 cusecs
Slope of river 1 ft / mile
Soil type in riverbed is medium coarse sand
7. Assumptions Taken:
Number of Bays 49
Width of the 1 Bay 60 ft
Width of Fish Ladder 26 ft
Number of Fish Ladders 1
Number of Divide Walls 2
Width of one Pier 7 ft
Afflux Assumed as 3 ft
Height of crest above river bed, P (Weir Height) Assumed 6 ft
Width between abutments 3318 ft
Crest Level of under sluice = 3ft below main weir
14 | P a g e
15 | P a g e
Figure 4: Scour depth Calculation using Lacey Factor
From the rating curve we have computed DSFL for main weir and under sluices respectively for
3 different states.
16 | P a g e
Figure 6: Rating Curve for DSWL
Retrogressed State
Normal
Accreted State
17 | P a g e
10. Methods for fixing D/S floor level:
For three different stages we should consider take discharges with maximum flood with 20 %
concentration, maximum flood and 50 % of the Maximum discharge.
The DSFL that satisfies the worst-conditions for the formation of the jump, i.e., the lowest
floor level, will be finally selected. Further Details are attached in the excel sheet and the
summary of the report
18 | P a g e
14. Calculation of uplift pressure after applying correction:
Discussed in Summary for further details refer to Excel Sheet.
Description Value
Minimum stable wetted perimeter 1842ft
19 | P a g e
Length of d/s stone apron in horizontal position 33 ft
ФA 69 %
ФB 66 %
ФK 66 %
ФL 36 %
ФM 35 %
ФN 39 %
ФP 32 %
ФQ 24 %
ФR 6 %
20. Calculations:
Following are the Results of excel sheet shown below.
20 | P a g e
Trial:
Number of Bays 49 ft
Width of the 1 Bay 60 ft
Width of Fish Ladder 26 ft
Number of Fish Ladders 1
Number of Divide Walls 2
Width of one Divide Wall 15 ft
Width of one Pier 7 ft
Total number of Piers 46
Total Width of Bays 2940 ft
Total Width of Piers 322 ft
21 | P a g e
From Gibson Curve
C'/C 0.84 Approx
C'= C*C'/C 3.8
Q = C' x W clear(Bays) x Eo^1.5 518888.9 cusecs
6
Check : OK
Check : OK
Step 5: Determination of Water Levels and Energy Levels:
Main weir
575,567 601.6 3 604.6 22.60 195.77 8.66 1.17 15.28 16.44 12.28 0.747 0.82 3.12 66.66 207.72 610692.3
479,639 600.1 3 603.1 21.10 163.14 7.73 0.93 13.78 14.70 10.78 0.733 0.83 3.15 56.38 177.83 522818
239,820 597.2 1.4 598.6 16.60 81.57 4.91 0.37 9.28 9.65 7.88 0.816 0.78 2.96 29.98 88.86 261242.1
119,910 592.2 2.3 594.5 12.50 40.79 3.26 0.17 5.18 5.34 2.88 0.538 0.93 3.53 12.34 43.62 128238.5
For
retrogressed
state
575,567 595 7 602 20.00 195.77 9.79 1.49 12.68 14.16 5.68 0.401 0.96 3.65 53.30 194.45 571672.6
479,639 596 5 601 19.00 163.14 8.59 1.14 11.68 12.82 6.68 0.521 0.93 3.53 45.90 162.22 476935.8
239,820 591 6 597 15.00 81.57 5.44 0.46 7.68 8.13 1.68 0.206 0.97 3.69 23.20 85.52 251426.5
For accreted
state
575,567 604 2 606 24.00 195.77 8.16 1.03 16.68 17.71 14.68 0.829 0.75 2.85 74.52 212.38 624411
479,639 602.5 1.5 604 22.00 163.14 7.42 0.85 14.68 15.53 13.18 0.848 0.71 2.70 61.20 165.11 485421.2
239,820 601.5 0.6 602.1 20.10 81.57 4.06 0.26 12.78 13.03 12.18 0.934 0.5 1.90 47.04 89.38 262770.6
154,861 601.6 3 604.6 22.60 258.10 11.42 2.03 18.28 20.30 15.28 0.752 0.8 3.04 91.47 278.06 166836.7
For
retrogressed
state
154,861 595 6 601 19.00 258.10 13.58 2.87 14.68 17.54 8.68 0.495 0.94 3.57 73.46 262.41 771499.7
For accreted
state
154,861 604 1.5 605.5 23.50 258.10 10.98 1.87 19.18 21.05 17.68 0.840 0.75 2.85 96.57 275.22 809143.3
Undersluices
qweir USEL DSEL hL E2 DSFL
USWL + ho DSWL + ho USEL-DSEL Blench Cr. DSEL - E2
Normal
278.06 606.63 603.63 3.00 22.6 581.03
Retrogressed
262.41 603.87 597.87 6.00 26.8 571.07
Accreted
275.22 607.37 605.87 1.50 23.1 582.77
7) Fixation of DSFL for normal barrage sectionusing Crumps approach
max: DSWL min DSWL
Q
= 479,639.00 479,639.00
DSWL (Corresponding to Q) = 602.5 596
USWL = 604.00 601
USEL = 604.85 602.14
RBL =
582.00 582.00
Crest level =
589.32 589.32
DSFL = 576 576
Dpool DSWL - DSFL = 26.5 20
d/s V Q/(Wabt*Dpool) = 5.45 7.23
d/s V head = 0.46 0.81
DSEL = 602.96 596.81
K =
USEL - CL 15.53 12.82
L =
USEL - DSEL 1.89 5.33
qweir =
Q/Wweir 163.14 163.14
Dc Critical flow depth = 9.38 9.38
Hl/Dc =
0.20 0.57
K+F/Dc Crumps curve = 1.94 2.48
F =
2.68 10.45
Location of
=
HJ CL - F 586.65 578.87
E2 =
DSEL - Loc HJ 16.31 17.94
Submergency of HJ =
Loc HJ - DSFL 10.65 2.87
Length of glasis d/s of jump =
sub. Of HJ * slope 31.94 8.61
Length of d/s floor(4.5 E2 - (Submergency * slope of
glasis)= 41.47 72.12 -
d/s floor length Say 80 ft
26 | P a g e
8) Fixation of DSFL for undersluices using Crumps approach
max: DSWL min: DSWL
154861 154861
604 595
605.50 601.00
607.37 603.87
582.00 582.00
586.32 586.32
572 572
32 23
8.07 11.22
1.01 1.96
605.01 596.96
21.05 17.54
2.36 6.91
258.10 258.10
12.74 12.74
0.19 0.54
1.92 2.33
3.42 12.15
582.91 574.18
22.10 22.78
10.91 2.18
32.72 6.53
66.73 95.98
110 ft
27 | P a g e
9) Ceck aqequacy of
DSFL using conugate
depth method
φ = 1 φ= 1
DSFL = 576 Design Discharge 50% of Design Discharge DSFL = 572
80 % Q 383,711.2 191,855.6
Maximum Minimum Maximum Minimum Maximum Minimum
DSWL 602.5 596 601.5 591 604 595
USWL 604 601 602.1 597 605.5 601
USEL 604.85 602.14 602.36 597.46 607.37 603.87
E USEL - DSFL 28.85 26.14 26.36 21.46 35.37 31.87
Q/(Wweir-
q Wunderslice) 163.98 163.98 81.99 81.99 258.10 258.10
Dpool DSWL-DSFL 26.5 20 25.5 15 32 23
E^(3/2) 155.0 133.7 135.3 99.4 210.4 179.9
f(z) q/E3^2 1.058 1.227 0.606 0.825 1.227 1.435
Conugate c.e s'
(from tables) z 0.15 0.17 0.08 0.11 0.17 0.2
z' 0.6432 0.671 0.5041 0.5732 0.671 0.7062
Conjugate
depths d1=z*E 4.33 4.44 2.11 2.36 6.01 6.37
d2=z'*E 18.56 17.54 13.29 12.30 23.74 22.50
Jump
submergency Dpool - d2 7.94 2.46 12.21 2.70 8.26 0.50
Jump is
submerged Jump is submerged is
is all cases all cases
28 | P a g e
10) Scour protection
Thickness of apron
29 | P a g e
Summary
Total length of d/s apron = 50.03
4' thick block apron (1/3 of total length) = 16.68
4.96 ft thick apron of length = 33.35
Total length of u/s apron = 25.08
4' thick block apron (1/3 of total length) = 8.36
4.96 ft thick apron of length = 16.72
30 | P a g e
11) Inverted flter design
Provide 4'*4'*4' thick concrete blocks
9'' thick shingle (3'' t0 6'')
9'' thick shingle (3/4'' to 3'')
6'' thick shingle (3/16'' to 3/4'')
31 | P a g e
32 | P a g e
33 | P a g e
34 | P a g e
15) Fiation of depth of sheet piles
provide = 30.00
H/d = 1.03
Concrete floor length; b = 205.27
α=(b/d) = 6.62
1/nλ (Khoslas curves) = 0.18
Exit gradient; should be b/w 1/7 to 1/5 for 1:1 flotation
(h/d)*(1/nλ0.5) = 0.19 gradient
35 | P a g e
17) Thickness of floor
36 | P a g e
37 | P a g e
38 | P a g e