Work Done As Per 28-June 2023
Work Done As Per 28-June 2023
Tanah 1 - based on lorry load Tanah 2 - based on as-built drawing Excess earth in between tanah 1 and tanah 3 - based on lorry load
10 tyre lorry with 10 tyre lorry without 10 tyre lorry with 10 tyre lorry without
12 tyre lorry
compaction/ bigger bucket compaction/ smaller bucket compaction/ bigger bucket compaction/ smaller bucket
19/6/2023 3 load 0 load 26/6/2023 3 load 4 load 0 load
20/6/2023 7 load 8 load 27/6/2023 6 load 10 load 0 load
21/6/2023 9 load 0 load 28/6/2023 3 load 9 load 2 load
22/6/2023 11 load 0 load
23/6/2023 11 load 1 load
24/6/2023 11 load 0 load
52 load 9 load 12 load 23 load 2 load
Total 3783.56 m3